0 ratings0% found this document useful (0 votes) 53 views12 pagesAttachment-3A - General Electrical Requirement
MEW General Electrical Requirement
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
5.2E ELECTRICAL EQUIPMENT AND WORK
5.2E.1 GENERAL ELECTRICAL REQUIREMENTS
5.2614 EXTENT AND VALIDITY
All electrical equipment forming an integral part of the power plant, whether specifically mentioned or
not shall be designed, manufactured, supplied, erected, tested and commissioned in compliance with
the general and specific requirements of this contract,
Basic configuration of the supplied SCCGT-2 Plant i.e. Conversion of EXISTING Open Cycle Gas
‘Turbines to Combined Cycle Plant and their auxiliaries shall fulfil the basic requirement as outlined in
the indicative tender single line diagram SCCGT-2/E/3001 as a minimum. However, tenderer may
develop their own single line diagram and power flow configuration fuliling the basic requirements as
‘mentioned in the indicative tender single diagram and tender specification
Power export of the supplied SCCGT-2 Plant i.e, Conversion of the existing Open Cycle Gas Turbines
to Combined Cycle shall be achieved by the tenderer while connecting the generator step-up
transformer with 400kV high voltage XLPE cable which shall be further connected to the available
spare feeder (C-16) in the existing 400kV Switchgear (SWPS-2) Mfd: M/s. Siemens located at a
distance of approx. 500 m in West away from assigned location of SCCGT-2 Plant as shown in site
layout drawing,
‘As described above and indicated clearly in the Tender Single Line Diagram, plant is connected with
aforesaid 400KV SWGR for the dual purpose of power export to the Grid and also for power import to
back energize transformer/SWGR of the plant for commissioning purpose. No other separate power
source shall be made available for commissioning purpose from MEW.
Indicative single line diagram of the plant as well as basic protection and monitoring diagram of
generator, unit transformer, generator step-up transformer & 400kV HV cable, integrated with the
spare feeder C16 of existing 400 kV Switchgear (SWPS-2) to achieve reliable power export, is
attached in Tender document for Tenderer compliance.
The scope of work in general is indicated in Section §.1 of Tender document, however any electrical
work and equipment as needed for the requirement of Mechanical, Instrumentation & Civil works
mentioned elsewhere in the tender document shall be considered within the contract
5.26.1.2 BASIC DESIGN CRITERIA
5.2E.1.2.1. GENERAL DESIGN PHILOSOPHY
‘All electrical equipment except packages of original equipment manufacturer for steam turbine
generator shall be designed to include an additional margin of 10% of the full load capacity, when
considering the worst case to be met in service. The duty and rating shall be indicated on the relevant
documents submitted for approval
‘Specifigation No, MEW / SCCGT -2 1 Contractor's
Initial and StampAl electrical equipment shall be designed to withstand the maximum stresses imposed on them for
the fault levels and durations obtained under the worst possible conditions. Short circuit calculations
shall be carried out as part of the contract to verify the ratings of the proposed equipment and shall be
submitted for approval by the Owner/Engineer.
The calculations shall assume ‘worst case’ values of all parameters, including upper and lower
tolerance limits as well as lowest values of transformer tapping ranges. The fault level shall be
‘considered as 80KA, 3 seconds for the 400kV system, the Contractor shall confirm and consider the
‘actual fault levels during the design phase through coordination with NCC.
MV switchgear shall have a minimum rating of SC level as 40KA, 1 Sec. whereas all LV main
‘switchgear and MCCs shall have a minimum rating of SC level as SOKA, 1 Sec. However, based on
calculation during detail design stage, if it is found that a higher level of SC levels are needed for
‘above switchgears/MCC, they shall be provided accordingly within the scope of contract with no
additional cost to the contract.
SC level of other AC & DC boards such as but not limited to AC distribution board, DC & safe AC
switchgear / distribution boards AC/DC sub-distribution boards, lighting boards.....ete shall be decided
based on calculation during detail design stage.
The installation shall be designed for operation, where continuity of power supply is the prime
consideration. All plant and equipment shall be designed to ensure satisfactory operation under
sudden variations of load and voltage as may be met under all operating conditions, including those
due to starting loads, transient short circuit and other internal and external fault conditions,
The design shall incorporate every reasonable safeguard and provision for the safety of all personnel
concemed in the commissioning, operation and maintenance of the installation
‘The plant and equipment shall be capable of being controlled under normal operation from the Central
Control Room. Description of Central Control Room is indicated elsewhere in the tender document.
Local contro! facilities shall be provided for testing and maintenance purposes.
‘The installation shall have the maximum possible levels of reliability and availabilty in service. To this
end tried and proven equipment shall be used in the installation; prototype equipment shall be
excluded.
‘The design and installation shall be such as to minimize the risk of outbreak of fire and consequential
damage. Materials used shall not support combustion and shall preferably be fire retardant.
Emergency diesel generators shall be provided to supply essential auxiliaries in the event of loss of
connection to the grid, as well as to provide an independent supply to ensure safe shutdown of the
plant and ensure the operation of all essential equipment during periods of stendstil, including fire-
fighting requirement ofthe plant
Specification No, MEW / SCCGT-2 2 Contractor's
z Initial and Stamp§.2E.1.2.2 DESIGN OF ELECTRICAL POWER SYSTEMS
Where any electrical equipment is essential for the continuous operation of the plant, the associated
auxiliary systems shall be arranged to be fed from an alternative supply, so 2s to allow recovery from
fault conditions and also to permit inspection and maintenance of equipment without interference with
the normal operation of the plant. A suitable fast transfer scheme, with automatic and manual control
facilities for MV system (if applicable) shall be provided to ensure smooth changeover to alternative
supplies. A momentary paralleling of the MV system shall be (if applicable) envisaged in design. A
suitable transfer scheme shall be provided for LV system so that changeover between incoming and
coupler is achieved without tripping of any associated load while plant is running at its full continuous
rated output
The essential supplies systems shall be capable of maintaining the supply to all instruments, controls
and auxiliaries required for the safe and reliable operation of the plant and equipment under all normal
and abnormal operating conditions and also for safe shutdown and placing of the turbine onto turning
gear following the total loss of the grid connection to the station,
‘The design shall require only minimal operator intervention to reconfigure the auxiliary systems upon
restoration of normal supplies.
‘The electrical plant and equipment shall be provided with suitable means for electrical disconnection,
isolation and earthing of connections to facilitate maintenance and reconfiguration of the electrical
power system in the normal operation of the power station.
§.2E.1.2.3 REQUIREMENTS DUE TO THE ENVIRONMENT
All electrical equipment shall be of tropical design and entirely suitable for use under the prevailing
Kuwait site conditions specified elsewhere in this specification
‘An ambient temperature of 50°C for indoor equipment and 55°C for outdoor equipment shall be taken
as design reference. 85°C shall be considered for equipment subject to direct sun radiation. Ratings
of all electrical equipment, whenever specifically mentioned or not shall be based on these
conditions. However, if the equipment is located in pre-designed capsules/modules with continuous
redundant HVAC arrangement having reduced continuous temperature in modulesicapsules,
‘equipment may be rated accordingly for reduced temperature as per manufacturer standard, whereas
all other electrical equipment whether located in room with forced ventilation or HVAC shall be rated
for 50°C.
All bushings of transformers (neutral bushing, surge arrestor, neutral circuit breaker, etc.) which are
exposed to the outdoor environment shall have increased creepage distances of 55 mmikV as a
minimum due to the environmental conditions of the site, In order to establish design and length of the
exposed bushing, value of voltage shall be based on actual worst fault condition which is
substantiated with calculation during design stage in accordance with relevant IEC standards and
approved by MEW,
Specification No. MEW / SCCGT-2 3 Contractor's
Initial and Stamp5.26,
4 HAZARDOUS AREAS, AREA CLASSIFICATION AND ELECTRICAL
EQUIPMENT
All areas of the plant where concentrations of gas or other hazardous substances may occur due to
normal leakage or process fault or ventilation system fallure shall be classified as hazardous
locations.
Unless otherwise specified, the design of all electrical installations in such areas shall be explosion
proof in compliance with the latest issue of IEC 60079 or equivalent international standard and
‘electrical equipment shall be suitable for use in these areas,
‘All explosion proof equipment shall be of approved design and must have undergone type tests
‘according to the appropriate standards by neutral international inspection authority. Type test report
shall be submitted for information as an essential pre-requisite for equipment approval.
‘The Contractor shall produce area classification drawings and documentation for the whole site area.
‘The classified area shall be as defined under IEC 60079 or equivalent standard.
All gas groups, electrical equipment maximum surface temperature, (T ratings), and equipment types
shall be approved by the Engineer.
All equipment that Is located in hazardous areas shall be manufactured, certified and installed in
accordance with IEC 60079 or equivalent standard,
‘A consistent approach to the design of the hazardous area electrical systems shall be adopted
throughout the contract.
§.2E.1.2.6 POWER SUPPLY AND DISTRIBUTION SYSTEM
‘The system shall have the following voltage levels,
8) HV transmission - 400 kV
b) MV distribution — 11 or 6.6 KV (based on Tenderer’s discretion)
©) LV distribution (3 phase) - 415 V
4) LV distribution (single phase) - 240 V
©) DC system - 220V,110 V and 48V (as required)
) UPS system-240V
Ail electrical equipment shall be designed to withstand the following voltage
variations,
Specification No. MEW / SCCGT -2 4 Contractor's
r Initial and Stamp
\\|. 400kV system continuous operation with 46% rated voltage variation L.e. between
380KV ~ 420kV.
|. AC systems ~ Continuous operation between 90-1 10% rated voltage, operation at
80% voltage for short durations (<30s)
lll, Secure AC systems ~ continuous operation between 90-110% voltage, maximum
frequency variation of + 0.5%.
IV. DC systems — continuous operation between 90 -110% voltage
‘While establishing the capacity of the continuous current rating of electrical equipment such as but not
limited to generator, transformers, motors, IPB, MV/LV bus duct, power cables, inverter rectifier..etc,
negative voltage variationsitolerance as described here and specification clause 5.2.2 shall be
considered besides other factors specified in Tender document,
5.2E.1.3 GENERAL REQUIREMENTS FOR ELECTRICAL EQUIPMENT
This part of the Specification details the requirements for ancillary electrical equipment such as wiring,
terminals, switches, panels and cubicles common to all items of plant. The equipment shall comply
with the requirements of IEC 60947 and other relevant IEC standard,
5.26.
4 SWITCHBOARDS, CUBICLES AND ENCLOSURES
All switchboards, cubicles and enclosures shall be manufactured from sheet steel. The cubicles shall
be protected against corrosion by immersion in phosphate solution or by spray galvanising,
Fixing screws and bolts for metal enclosures shall be of non-corrosive material (e.g, stainless steel or
brass). All other bolts and screws shall be chrome or cadmium plated.
‘The overall height of switchboards, cubicles and enclosures for electrical apparatus shall not exceed
2.5 m above floor level.
Maintenance access, as applicable, shall be provided at the front and rear of all switchboards and
relay cubicles.
‘The design of the equipment shall be such as to prevent accidental contact with live parts and to avoid
the spread of fire or damage from short circuits or other causes.
Equipment to be installed indoors shall have degree of protection IP 42
Equipment and panels which are located outdoors shall be completely weatherproof with degree of
protection IP 65.
‘Specification No, MEW / SCCGT -2 5 Contractor's
Initial and StampHowever, if pre-designed capsulesimodules are used for housing of switchgear/panel, suitable IP
class for equipment, as per the manufacturer standard, shall be used provided the capsule/module
housing themselves are having higher IP class not less than IP65.
5.2E.1.3.2 WIRING
All secondary wiring in panels, cubicles and equipment racks shall be carried out using 600/1,000 V
grade multi-stranded copper wire to BS 6231. The primary insulation of all wiring shall be PVC for
installations with internal temperatures below 60°C and silicon rubber or similar material for
installations with internal temperatures above 60°C.
All wiring shall consist of stranded copper wires of not less than 0.5mm’ cross-section except for
wiring associated directly with switchgear control and protection shall not be less than 2.5 mm*
whereas CT and VT secondary circuits shall be not less than 4mm’,
Wires shall not be jointed or teed between termination points. Only one wire shall be connected to
one terminal, The ‘terminal’ is the fixing device on the apparatus and the ‘termination’ is the device
fitted to the wire,
All wires shall have an identification marking at each end numbered in accordance with
manufacturer's standard.
5.2E.1.3.3 TERMINALS AND TERMINATIONS
Terminal blocks shall have separate terminals for incoming and outgoing connections.
‘Terminal blocks shall be either of the stud or insertion type as per manufacturer's standard
A provision for spare terminals shall be made to cater for possible future modifications, such @
provision shall not be less than four in number or 20 percent of the total whichever is greater.
Terminals shall be numbered and terminal blocks shall be grouped according to function.
5.2E.1.3.4 | ACCESSORIES
All enclosures containing electrical equipment shall be provided with thermostatically controlled anti-
condensation heaters arranged to operate at 240 V ac if the panel is not located in permanently
available HVAC rooms/prefabricated modules ....etc.,.. Local indication of ON/OFF status of heaters
shall be provided
Panels, boards, cubicles etc., shall be provided with suitable LED lamps having 6500K LED bar and
13.A power socket outlets if not located inside pre-fabricated modules/capsules.
SpeciigaligniRioc MEW /SCCGT-2 6 Contractor's
\ Initial and Stamp.
J5.26.
3.8 LABELS, TAGS AND NAMEPLATES,
Every electrical device or component shall be provided with suitable nameplates, tags and
identification labels to identify their ratings, purpose and any specific information required to allow
efficient maintenance and operation.
All nameplates and tags installed outdoors shall be manufactured from stainless steel or installed
indoors shall be of laminated plastic and shall be engraved in both English and Arabic (with the
exception of standard equipment nameplates which shall be in English only)
All plates and tags shall be permanently fixed to the equipment by screws (stainless steel screw for
name plates located outdoor and brass screws for name plates located indoor)
5.2E.1.3.6 LOCKS, KEYS AND CABINETS
Al hinged doors in switchboards, panels, cubicles etc as well as withdrawable switchgear chassis
shall be secured by means of a suitable lock.
Key cabinets shall be provided in the Central Control Room for storing all keys in use. Each key shall
be provided with an attached identification label and a further identification label fixed above the
hanging hook inside the cabinet.
‘The contractor shall prepare a comprehensive key system proposing the individual groups and master
keys. A minimum of three keys shall be provided for each lock as well as a master key for each zone.
‘The complete key system shall be subject to approval of the Owner/Engineer,
Specification No. MEW / SCCGT -2 7 Contractor's
Initial and Stamp5.2E.10 EARTHING & LIGHTNING PROTEGTION SYSTEM
5.2E.10.1 GENERAL
‘The earthing system shall conform to the relevant sections of BS 7430, IEC 60364, IEEE 80 and
IEEE 665, The Contractor shall present calculations for approval to show that the proposed system
complies with IEEE 80 and Is safe in terms of touch, step and transferred potential
Earthing point distribution bars shall be strategically located within an area in which items of plant are
to be located. A minimum of two earthing point distribution bars shall be provided in all main plant
areas, The bars shall have pre-drilled holes complete with screw or nut and bolt type fastenings for
the attachment of lug type cable connections. The bars shall also have disconnecting links to enable
testing of the connections to the main earthing system. All electrical equipment shall be earthed at a
‘minimum of two points.
‘The earthing and bonding system shall fulfil te following requirements:
a. Maintain a low overall resistance to the ground mass so as to limit the plant potential
rise and ensure protective relay operation in the event of an external fault.
b. Provide ground connections to all electrical equipment enclosures and structural
steelwork, which are adequate to carry prospective ground fault currents without
overheating.
Limit potential differences within the power station in the event of ground current
originating from within or outside the station and so ensure the safety of personnel
and eliminate interference or damage to electronic circuits,
DESIGN AND ARRANGEMENT OF EARTHING AND BONDING
POWER TRANSFORMERS
Power transformer shall be earthed at two points diagonally opposité each other. These
connections shall be madé Tray two different points of the earth grid, Where the neutral conductor is
carried directly from the neutral Bushing to earth, an additional cerinection between bushing and tank
shall be provided to ensure a straight ‘between tank and the neutral leg. The
neutral conductor shall be brought directly at f st distance to an earth electrode.
‘Specification No, MEW / SCCGT -2 6 Contractor's
Initial and Stamp5.2E.10.2.3 BUILDINGS AND STRUCTURES
‘The design of the earthing system within buildings shall comply with the requirements
of IEC 60364. Structural steel shall be connected to the earthing grid at @ minimum of two points of
Re-enforcement bars of each foundation of building/structure and shall have adequate earthing in line
with international standard and also shall be connected with sub-grade earthing,
5.2E.10.2.4 MOTORS
‘The body of the MV Motor shall be earthed at two points diagonally opposite each other whereas body
of LV motors can be earthed at one point only. Each motor shall be connected to the earthing grid or
with the earth bus by the shortest route,
Each motor shall have earthing for the motor body and the terminal boxes.
5.2E.10.2.5 SWITCHGEAR AND SWITCHBOARDS
All switchboards, metal enclosures and conductive structures of circuit breakers, isolating switches,
measuring transformers..etc., shall be connected to the earthing grid. The housings of the operating
mechanisms shall be earthed at a point as near to the operating handle as possible,
All panels, desks and switchgear located in a room shalll be connected to a common earth bus.
SURGE ARRESTERS
arrester is mounted.
5.2E.10.2.7 PIPELINES
A shall be connected to the main
‘lating flanges. The two outer flanges of
Motor operated valves in pipelines fit
earthing grid and insulated from the pipeline
the pipelines shall be bonded together.
the occurrence of dangerous potential id both within and outside the site.
5.2E.10.2,8 FENC!
Specification No. MEW / SCCGT -2 70 Contractor's
. Initial and Stamp2.9 ELECTRONIC EARTHING
Earthing of electronic &%
section of this document.
juirements specified in the 1&C
5.2E.10.2.10 FOUNDATION
(6F the re-enforcement bar of foundation of each building/structa
Televant standard, which will be connected with sub-grad earthing system.
5.2E.10.3 - METHODS OF INSTALLATION
5.2E.10.3.1 GENERAL
In the main areas of the plant the earthing system shall comprise a buried bare copper conductor grid.
To minimize the effects of corrosion, all above grade conductor pigtails shall be PVC covered or
tinned stranded copper conductor, but this length shall not be considered as forming part of the earth
grid resistance,
‘The system shall be designed to withstand an earth fault current of 80 kA for 1 second. The mesh
size shall depend on the ground resistivity and may vary in different parts of the site. To this main
atid, ground rods shall be bonded at intervals and in particular at the base of lightning conductors.
‘The approximate average soil resistivity is 15 Om at a depth of 0.5 m and 3 Om at a depth of 2.5 m,
however these figures are indicative only. The Contractor shall be responsible for determining the
actual soil resistivity
Where the ground conditions are such that a borehole is necessary then this shall be backfilled with
bentonite after installation of the ground rod
The system shall cover the entire plant area up to the site boundaries. A sufficient number of earth
electrodes of sufficient length shall be distributed around the site to achieve an overall earth
dissipation resistance of 0.1 Ohm or less.
The subgrade earthing system shall be connected to the earthing system of the neighbouring Sabiya
power plant at @ minimum of three locations as part of this Contract, however this interconnection
shall not be taken into consideration during the design of the earthing system,
5.2E.10.3.2. JOINTS AND CONNECTIONS
Joints and connections shail normally be made by brazing overlapped ends. Copper to copper joints
shall be tinned using hard silver solder. When surfaces have cooled they shall be protected
immediately using a suitable jointing compound.
For copper to aluminium joints, the copper faces shall frst be tinned. The aluminium faces shall be
leaned using a stainless steel wire brush or non-metallic abrasive pad until surface is bright. After
Specification No, MEW / SCCGT -2 nm Contractor's
_ Initial and Stampbrazing, both surfaces shall be protected immediately with a suitable jointing compound. Copper to
steel joints shall be the same as copper to aluminium joints,
Welding techniques such as Cadweld may be used as an allemative to bracing or bolting. Where
bolted connections and links are necessary these shall be made above ground or in an inspection pit,
Bolted connections shall be complete with one round brass and one phosphor bronze double coil
spring washer. The surfaces shall be cleaned and greased with a suitable jointing compound prior to
assembly to eliminate corrosion. If stranded conductors are used then approved crimp type lugs and
bolts shall be used.
Faulty joints should be cut and a new length of conductor inserted.
‘Where used to prevent ingress of moisture it is important that sufficient jointing compound is used to
fill all voids.
Extreme care shall be taken to prevent electrolytic action when running the copper strip in the vicinity
of aluminium or any other metal.
All items of plant and structures shall be connected to the main earthing grid. This shail include steel
reinforcing. Connections between earth tags and bosses and the station eathing grid shall be by
copper strip, cable or flexible braid. Normally a minimum of two separate connections shall be made.
The rating of these conductors shall be sufficient to withstand the fault currents and duration after
allowing for the parallel paths through the system with any one conductor disconnected.
‘Screwed conduit connections and cable tray shall be electrically continuous and grounded to the main
station earth system. An earth conductor of suitable size shall run on the entire length of the cable
tray and on the top tray in a group of trays with intermittent loop connections,
A separate insulated conductor of the same size of the phase conductor shall run inside the conduit to
all electrical equipment.
5.2E.10.3.3 MATERIALS
Conductors shall be of high conductivity copper in the form of circular conductors stranded to
IEC 60228 or solid rods or bars to BS 1433,
The minimum conductor size for the main sub-grade earth system shall not be less than 150 mm?
Equipment connections shall be designed to withstand the maximum prospective fault current, but
shall not be less than 70 mm? for equipment with ratings in excess of 30 kW.
Conductor sheaths shall be PVC coloured green/yellow to meet the requirements of IEC 60502,
Ground rods shall be of hard drawn high conductivity copper with a diameter of not less than 15 mm
and fitted with hardened steel driving caps and tips.
Specification No. MEW / SCCGT -2 id Contractor's
Initial and Stamp5.2E.10.3.4 FITTINGS
Clips for supporting strip conductors, not buried in the ground, shall be direct contact type. Clips for
circular conductors shall be of cable saddle type.
Disconnecting links shall comprise a high conductivity copper link supported from two insulators on a
galvanized steel base.
Connections to electrical equipment shall be detachable and made at earthing studs or bolts.
For single core cable circuits where the cable armours are bonded at the switchgear end only, the
earth bond shall be a 25 mm x 3mm tinned copper earth bar arranged to provide the shorting strap
‘across all the glands of the circuit and the connections to the switchgear earth bar.
10.4 LIGHTNING AND SURGE PROTECTION
by the Contractor during the desig
approval
% submitted to the Engineer for
Lightning protection may be interconnected wi
recommended by relevant international star
ie plant sub-graded earthing system if it is
(On completion of the installa
termination or section thes
ofall bonds verified
of any modification to it, the Fesigtance to earth of each earth
Chall be measured and the continuity of all Conductors and the efficiency
infirm conformity with design data,
“which shall be adequately drained and labelled
Specification No. MEW / SCCGT -2 73 Contractor's
Initial and Stamp