J 2015 SCC OnLine APTEL 48 2310 Cnluacin 20240808 145003 1 14
J 2015 SCC OnLine APTEL 48 2310 Cnluacin 20240808 145003 1 14
(GIS)-New
(b) 50% series compensation at existing Sub-station of POWERGRID at Meerut
(Extension) on Tehri Pooling Point (Koteshwar)-Meerut 765 kV 2* S/C lines
(charged at 400 kV level)
(ii) That on 01.06.2005, the Board of Directors of the appellant approved the
Investment for the Koteshwar Transmission System at an estimated cost
of Rs. 26034 lakh including Interest During Construction of Rs. 1334 Lakh
th
based on the 4 quarter 2004 price level.
(iii) That on 11.09.2006 Global Competitive Bids were invited by the appellant
for the 765 kV installation at Meerut. However, the bidding process was
annulled as two out of three bidders did not have the technical qualifications.
(iv) That on 27.09.2007 the bids were again invited after incorporation of revised
qualifying requirements.
(v) That on 14.12.2007 the bids were opened. However, the bidding process was
again annulled as the bidders had deviated from the design in the bidding
documents.
(vi) That on 25.07.2008, the appellant reviewed the technical specifications and
after necessary modifications, re-invited the bids. The bids were opened.
(vii) That on 17.06.2009 the Letter of Award was issued to the successful bidder
i.e. M/s SIEMENS.
(viii) That as per the Investment Approval (IA) the above transmission assets
were scheduled to be commissioned within 27 months from the date of letter
of award for Gas Insulated Substation (GIS) package i.e. 27 months from
17.06.2006. Accordingly, the scheduled completion date was 01.10.2008.
Transmission assets were commissioned on 01.02.2012.
(ix) That on 25.02.2012, the appellant filed petition, being Petition No.
80/TT/2012 before the Central Commission for determination of transmission
tariff for the Transmission Assets on the basis of capital expenditure incurred
or to be incurred up to the anticipated date of commercial operation and
estimated additional capital expenditure projected to be incurred from the
anticipated date of commercial operation i.e. on 01.01.2012 till 31.03.2014.
(x) That on 03.07.2014, the appellant vide Affidavit submitted the actual date of
commercial operation of transmission assets i.e. 01.02.2012.
(xi) That during the proceedings in Petition No. 80 of 2012, the Central
Commission from time to time sought for various information, detail
justification, clarifications etc. from the appellant regarding the delay, which
details were provided by the appellant to the Central Commission vide
Affidavits dated 07.01.2013 and 10.12.2014. Thus the appellant submitted
the requisite details regarding the delay in commissioning of Transmission
Asset.
(xii) That the appellant stated before the Central Commission that 765 kV Fixed
Series Compensation (FSC) to be installed at Meerut end on Tehri Pooling
Point (Koteshwar)-Meerut 765 kV 2* to single circuit line is the first 765 kV
level installation in the country and there are very few such 765 kV level
installation worldwide. Due to the specific design, 765 kV Bypass Switch
exclusively used for 765 kV FSC installation is very rare and not commonly
available. During global competitive bidding in 2006 very few vendors like
SIEMENS, NOKIA & ABB were understood to have the technology and
capability of FSC at level 765 kV. Accordingly, with this backdrop and in line
with the procurement policy and procedure in vogue, for transparency fairness
and competitiveness in process, Global Competitive Bids for the subject
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 4 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
package were invited in September, 2006. However, two out of three firms fell
short of meeting the qualification criteria stipulated in the Bidding Documents
and therefore the bidding process was annulled.
(xiii) That bid had to be invited thrice after they failed twice only because
of the uniqueness of the works to be carried out. This was due to the
fact that it was the first 765 kV FSC installation in the country. There
were constraints in the availability of experienced manufacturers
worldwide which forced the bidding process to be delayed by about 34
months with respect to the investment approval date.
(xiv) That the period of execution of the project of 27 months was indicated
to begin along with the award of Tehri Pooling Station GIS. This was
mainly due to the reason that both the projects were required at the
same time and as per Feasibility Report, both were expected to be
awarded simultaneously. However, in actuality, though the contract for
Tehri Pooling Point (GIS) substation got awarded on 17.06.2006, the
contract for 765 kV FSC could not be awarded due to the aforesaid
reasons which involved a delay of nearly 3 years. Further the project also
got delayed during the execution stage since the by-pass switch was not
meeting the technical requirements stipulated by the appellant.
(xv) That the finer aspects of design of FSC which was being done for the first time
could not be known in completeness at the stage of selecting a bidder. After the
contracting stage is completed, the detailed engineering is normally done to
determine the final parameter of the equipment based on which the type test is
carried out. This being a unique project, on account of technical complexities
involved and the fact that it was the first 765 kV level installation in the country,
it required a detailed set of calculation based on which the series of type - test
were carried out at CERDA, France and completed in January 2012 and
accordingly the FSC was commissioned in February 2012. Thus the FSC was
commissioned with a delay of 40 months from the date of scheduled
commissioning. This delay in procurement and subsequent execution of this work
was entirely beyond the control of the appellant.
(xvi) That after hearing the parties and considering the material on record the
learned Central Commission vide Impugned Order dated 09.01.2005 has
disposed of the said Petition No. 80/TT/2012.
6. We have heard Mr. M. G. Ramachandran, assisted by Ms. Ranjitha
Ramachandran, learned counsel for the appellant, Mr. Pradeep Misra, Mr. Suraj Singh
and Mr. R.B. Sharma, learned counsel for the respondents. We have also gone through
the written submissions submitted by the parties and also gone through the material
on record including the Impugned Order passed by the Central Commission.
7. The only following issue arises for our consideration in this appeal:
Whether the Central Commission is legally justified in rejecting the claim
of time over run of the appellant in respect of transmission asset and in
holding that the said delay of 40 months was caused by the inefficiency of
the appellant?
8. The following submissions have been made by the appellant on this issue:
(i) That the Investment Approval provided for a common Schedule Date for all the
Assets being 27 months from the Letter of Award for Gas Insulated Substation
Package. The period of 27 months is less than the time scheduled under Tariff
Regulations 2009 for completion of transmission schemes for 765 kV
transmission lines and sub-stations. Thus it is incorrect to say that any time
cushion was granted to the appellant in view of the time taken from the date of
Letter of Award as opposed to the date of Investment Approval.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 5 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
(ii) That the scheduled date for the transmission system was computed based on
the Letter of Award of the Gas Insulated Substation package on the expectation
that the letter of Award for both the Gas Insulated Substation and the 765 kV
FSC installation would be awarded simultaneously. Further 765 kV FSC
installation was connected to the construction of the Loop In Loop Out (LILO) of
Tehri Meerut line at Tehri Pooling Point and the sub-station of the Tehri Pooling
point. Thus the installation was to be constructed in accordance with the
implementation schedule of the LILO and the sub-station. The Commissioning
of FSC installation would not serve any purpose if the LILO and sub-
station were not ready and not commissioned. Both projects were
required at the same time and as per the feasibility report both were
expected to be awarded simultaneously. Therefore, scheduled date of
commissioning of FSC installation was connected to the letter of award
of the gas insulated sub-station package.
(iii) That the selection of the manufacturer for the 765 kV installation and the 765
kV bypass switch was under the global bidding process in line with the
procurement policy and procedure in vogue, for transparency, fairness and
competitiveness in process. The competitive bidding process had to be
conducted three times for issuance of letter of award to the successful bidder.
This was because of the uniqueness of the work to be carried out being the first
765 kV FSC installation in the country and even globally, there were very few
such installations. The appellant had no previous experience of such installation
and could not have known all the finer aspects of the design and the technical
specifications prior to the procurement process. Further there were also
constraints in the availability of the experienced manufacturers worldwide which
forced the bidding process to be delayed by about 34 months with respect to the
investment approval date.
(iv) That the first bid was undertaken in 2006. There were few vendors like
SIEMENS, NOKIA and ABB which were understood to be having technology and
capability of FSC at level of 765 kV. Only three firms participated in the bid and
two out of three firms fell short of meeting the qualification criteria. Since only
one firm was technically qualified, the bidding process was annulled. This was
beyond the control of the appellant as the bidding process could not be held with
only one qualified bidder.
(v) That another bidding process was conducted in 2007. The qualification
requirements were revised and the bids were invited. The bids were opened on
14.12.2007. Since some bidders deviated on the design of the Metal Oxide
Varistor (MOV) for high order of contingency stipulated in the bidding
documents, the bidding process on second time had to be annulled.
(vi) That in view of the technical complexity involved and the lack of experience, it
was considered prudent to review the technical specifications by suitably
adjusting the contingency levels which inter alia had no impact on the
performance of the appellant. The necessary modifications were carried out
before the bids were re-invited. In May, 2008 fresh bids were invited on global
basis for the third time and were opened on 25.07.2008. The letter of award was
issued to the successful bidder M/s SIEMENS on 17.06.2009 on turnkey contract
basis for 765 kV FSC installation.
(vii) That since the letter of award was made three years after the letter of
award to the Tehri Pooling Station, the implementation schedule of the
appellant for the FSC installation should be considered from the date of
letter of award for the FSC installation and not the letter of award for
Tehri Pooling Station.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 6 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
(viii) That the delay in issuance of letter of award was not attributable to the
appellant. The circumstances have to be considered in a proper and pragmatic
manner. Since the project was being undertaken for the first time by the
appellant having no prior experience, the installation of any system for the first
time would involve challenges which are not possible to forsee and plan.
Therefore, the time schedule expected may not be accurate and there may be
delays in actual implementation of the new system. The appellant had finalized
the technical specifications to the best of its ability. This has to be considered
while considering the time over run for a new project.
(ix) That this stand that the appellant should have held the pre-bid conference is
erroneous, because the appellant cannot hold a pre-bid conference with potential
bidders for discussions on qualifying criteria and technical specifications in the
bidding documents. It cannot be expected that the potential bidders would
disclose their designs and technical specifications at the pre-bid conferences
when other potential bidders are present.
(x) That the appellant had finalized the technical specifications to the best of its
ability, the appellant cannot be faulted that the technical specifications had to be
revised, particularly when the project was technically complex and rare.
(xi) That after the contract for the 765 kV FSC installation was awarded, the
project was delayed in the execution stage by six months. Since the FSC
installation was technically complex, detailed calculations were required to be
done for finalization of the final parameters. The finer aspects of the design of
FSC could not be known at the time of selecting the bidder and it is only after
the contracting stage that detailed engineering is normally done to determine
the parameter of the equipment based on which type test is carried out. The FSC
installation required detailed set of calculations based on which the series of type
test were carried out at CERDA, France which was completed in January 2012
and commissioned in February, 2012.
(xii) That the bypass switch supplied by the manufacturer did not meet the
technical requirements stipulated by the appellant and the same was beyond the
control of the appellant. The delay due to any default or failure on part of the
contractor/supplier is to be compensated by liquidated damages to be recovered
from the contractor/supplier to the extent of the contract and to be adjudicated
under the adjudication process provided in the contract. Such adjudication can
be done only after completion of the contract. The details of liquidated damages
recoverable were not available with the appellant at the time of filing the tariff
petition. The appellant had undertaken to file the liquidated damages after
closing of the contract. Thus any liquidated damages recovered by the appellant
from the contractor/supplier would be adjusted at such time. However, at
present, the appellant has not recovered the liquidated damages. The delay in
the project is to be condoned and the appellant should be allowed to recover IDC
and IEDC at this stage. Any amount received as liquidated damages after
adjudication would be adjusted subsequently.
(xiii) That in the present case, the learned Central Commission has committed an
error by not considering the relevant material available on record or otherwise
drawing an inference on the basis of mere assumption and presumption without
any analysis of the documents available on record. Thus the Central Commission
should be directed to allow the IDC and IEDC for Rs. 5.53 crores and re-
determine the approval capital cost.
9. Per contra, the following submissions have been made on behalf of the
respondents on this issue:
(i) That the learned Central Commission has legally and correctly disallowed the
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 7 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
the Central Commission for his own omission and commission because it is a
case of clear impudence on the part of the appellant.
10. Our consideration and conclusion on the issue relating to time over run
of 40 months:
(a) We have cited above the detailed facts of the matter and rival contentions of the
parties hence repetition of the same is not necessary here. To arrive at our own
independent conclusion and to test the legality and validity of the Impugned
Order, we deem it proper to quote the relevant part of the Impugned Order,
which is produced as under:
“Time over-run
11. Against the scheduled date of commercial operation of 1.10.2008, the
transmission asset has been declared under commercial operation on 1.2.2012, with
delay of 40 months. During technical validation, the Commission under letter dated
6.7.2012 sought the following information from the petitioner:-
(a) Justification along with documentary evidence for condoning the delay which
was stated to be on account of delay in supply of the equipment by the supplier.
(b) Details of liquidated damages leviable on contractor in accordance with
provisions of contract, along with documentary evidence.
12. The petitioner vide affidavit dated 7.1.2013 has submitted as under:
“Reply to point-(a)
It is submitted that 765 kV FSC to be installed at Meerut end on Tehri Pooling
Point (Koteshwar) - Meerut 765 kV 2* S/C line, is first 765 kV level installation in
the country and there are very few such 765 kV level installation worldwide. Due to
specific design, 765 kV Bypass Switch exclusively used for 765 kV FSC installation
is very rare and not commonly available. During global competitive bidding in 2006,
hardly few vendors like SIEMENS, NOKIAN & ABB were understood to have the
technology and capability of 765 kV FSC. Accordingly, with this backdrop and in line
with the procurement policy and procedure in vogue, for transparency, fairness and
competitiveness in process, Global Competitive Bids for the subject package were
invited in September, 2006. As two out of three firms were falling short of meeting
the qualification criteria stipulated in the Bidding Documents, the bidding process
was annulled.
The bids under re-bidding were invited on 27/09/2007 after incorporation of
revised Qualifying Requirements (QR) in the Bidding Documents and were opened
on 14/12/2007. Again the bidding process against the said invitation was annulled
due to deviation taken by the bidders on design of the MOV for high order of
contingency stipulated in the Bidding Documents.
In view of the technical complexity involved and the fact that POWERGRID had
no previous experience with 765 kV FSC and also the experience across the global
for such supply was rare, it was considered prudent to review the technical
specification by suitably adjusting the contingency level which inter-alia had no
impact on performance requirement of petitioner, bids were re-invited after
necessary modifications.
Subsequently, fresh bids were invited in May, 2008 on global basis and were
opened on 25.07.2008. Finally LOA was issued to the successful bidder i.e. M/S
SIEMENS on 17.06.2009 on turnkey contract basis for 765 kV FSC installation at
Meerut. It is therefore to be clarified that the Bids had to be invited three times
(after they failed twice) only because of the uniqueness of work to be carried out. It
is to be emphasized that this being the first 765 kV FSC installation in the country
and constraints in availability of experienced manufacturers worldwide, forced the
bidding process to be delayed by about 34 months w.r.t investment approval date.
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 9 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
works to be carried out and this was due to the fact that it was the first 765 kV
Fixed Series Compensation installation in the country and there were constraints
in the availability of the experienced manufacturers worldwide which forced the
bid process to be delayed by about 34 months with respect to the Investment
Approval date. Further contention of the appellant is that the period of execution
of the project of 27 months was indicated to begin along with award of Tehri
Pooling Point Gas Insulated Substation and this was mainly due to the reason
that both projects were required at the same time and as per Investment
Approval both were expected to be awarded simultaneously. However, in
actuality, though the contract for Tehri Pooling Point Substation GIS got awarded
on 17.06.2006, the contract for 765 kV FSC installation could not be awarded
due to the thrice bidding process which involved a delay of nearly three years.
Further, the project also got delayed during the execution stage since the bypass
switch was not meeting the technical requirement stipulated by the appellant.
Further contention of the appellant is that the nature of the transmission work
being a unique project, on account of technical complexities involved and the
said work being first 765 kV installation in the country, it required a detailed set
of calculation based on which the series of type test were carried out at CERDA,
France which completed in January 2012 and accordingly, the FSC was
commissioned in February, 2012. A justification is being argued by the appellant
for this delay of 40 months from the date of scheduled commissioning stating
the aforesaid grounds/reasons, which we are unable to accept after considering
the facts and circumstances and the factors connected there with. All these
reasons were entirely within the control of the appellant and the appellant was
well aware of the uniqueness/complexity and the nature of 765 kV installations
in the country. If the reasonable and prudent precautions and care had been
taken by the appellant/petitioner the said situation would not have arisen.
(e) We are totally unable to accept or countenance the said contentions of the
appellant because there was a clear stipulation in the Investment Approval that
the said assets were to be commissioned within 27 months from the date of
Letter of Award for Gas Insulated Substation package. The Letter of Award for
Gas Insulated Substation package was made on 17.06.2006 and accordingly, the
scheduled completion date was 01.10.2008. There is no indication at all to the
effect that the period of execution of the project of 27 months would begin along
with award of Tehri Pooling Point GIS. If the appellant expected that both
projects were expected to be awarded simultaneously, it was a mistake on the
part of the appellant. In the present case, the contract for Tehri Pooling Point GIS
was awarded on 17.06.2006 whereas the contract for 765 kV installation was
awarded after nearly three years, there remained no question to contemplate
that both the projects would be awarded simultaneously. It appears from the
record that there was no proper and careful planning about the said transmission
project which resulted in the said project having been commissioned with a delay
of 40 months. We conclude from the facts and circumstances in the matter in
hand, that the said delay of 40 months was absolutely within the control of the
appellant and by the exercise of due and reasonable prudence, the said
transmission system could have been commissioned within the stipulated time
but because of the slackness and improper coordination the said delay had
occurred. Hence, we conclude that the delay in issuance of letter of award was
completely attributable to the appellant/petitioner because had the appellant
finalized the technical specifications to the best of its ability at an appropriate
time, the said extra ordinary unexplained delay could not have occurred. We are
of the firm view that in such situation the appellant should have held the pre-bid
conference and we are unable to accept the contention of the appellant that such
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 13 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
pre-bid conference with potential bidders for discussion of qualifying criteria and
technical specifications in the bidding documents could not be held.
(f) We agree to the finding of the Central Commission as recorded in the Impugned
Order that the delay in commercial operation of the transmission asset is on
account of inefficiency of the appellant/petitioner or the failure of the
vendor/supplier to supply the equipment of the agreed technical specifications
and the same could not be condoned. We further approve the finding of the
Central Commission that there is no justification, whatsoever, to burden the
consumers with additional costs for the failure of the vendor/supplier to supply
the proper equipment. We are unable to approve or countenance this contention
of the appellant that the scheduled commissioning of the asset in question being
27 months from the date of letter of award means that the letter of award for
both Tehri Pooling Point GIS and 765 kV FSC installation would be awarded
around the same time. The said technical complexities involved in this asset, as
is emerging from the material on record, were neither brought to the notice of
Standing Committee meeting on Transmission System planning in Northern
Region nor to the Board of Directors of the appellant while granting Investment
Approval. It appears from the record that the appellant had not properly
prepared the technical specifications before undertaking the bidding process. If
the appellant was of the view that the project was unique, a pre-bid conference
could have been held to finalize the specifications and assess the availability of
vendors which is a general practice for such projects. However, in this case, pre-
bid conference was done by the appellant when huge delay had already occurred.
A part of the delay was also caused by the vendor as the vendor could not supply
the bypass switch in accordance with the prescribed specifications under the
contract and is liable for the damages. Thus the whole delay in the
commissioning of the transmission asset was entirely within the control of the
appellant and the same is fully attributable to the appellant/petitioner itself.
(g) The appellant may recover the liquidated damages from the contractor/supplier
to the extent of the contract for any such default or failure of the
contractor/supplier. We are unable to accept this contention of the appellant that
the appellant should be allowed to recover IDC and IEDC at this stage and any
amount receivable as liquidated damages after adjudication from the
contractor/supplier would be adjusted subsequently. There is no question of any
kind of adjustment in this matter if there is really any delay due to default or
failure on the part of the contractor/supplier in supply of the said equipment. The
appellant can always recover the liquidated damages from the said
contractor/supplier.
(h) This Appellate Tribunal, in its judgment dated 27.04.2011 in Appeal No. 72 of
2011 in the matter of MSPGCL v. MERC, while considering the principle for
prudence check of time over run and cost overrun of a project has already settled
a principle of law and clearly held that any delay in execution of any project if
caused due to the factors entirely attributable to any generating company or
utility i.e. imprudence in selecting the contractor/supplier and delay in payment,
mis-management of finance, slackness in project management like improper
coordination, the entire cost due to time over run has to be borne by the
company or the utility and the liquidated damages and insurance proceeds on
account of such delay, if any, receivable by the company or a utility could be
retained by the said company or the utility.
(i) In view of the above discussion, we do not find any merit in the contentions of
the appellant/petitioner. There is no material on record to deviate from the
findings recorded by the Central Commission in the Impugned Order and we
approve the same. The said issue is decided against the appellant. We observe
SCC Online Web Edition, © 2024 EBC Publishing Pvt. Ltd.
Page 14 Thursday, August 08, 2024
Printed For: Amisha Singh, Chanakya National Law University
SCC Online Web Edition: https://www.scconline.com
© 2024 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
that the Central Commission is legally justified in rejecting the claim of time over
run of 40 months in respect of the said transmission assets. The appeal is worthy
of dismissal.
ORDER
20. The instant appeal, Appeal No. 99 of 2015, is hereby dismissed and the
Impugned order dated 09.01.2015, passed by the Central Commission in Petition No.
80/TT/2012 is herby upheld.
21. No costs.
———
Disclaimer: While every effort is made to avoid any mistake or omission, this casenote/ headnote/ judgment/ act/ rule/ regulation/ circular/
notification is being circulated on the condition and understanding that the publisher would not be liable in any manner by reason of any mistake
or omission or for any action taken or omitted to be taken or advice rendered or accepted on the basis of this casenote/ headnote/ judgment/ act/
rule/ regulation/ circular/ notification. All disputes will be subject exclusively to jurisdiction of courts, tribunals and forums at Lucknow only. The
authenticity of this text must be verified from the original source.