Estimating Bench Design Parameters For Open-Cut Excavation
Estimating Bench Design Parameters For Open-Cut Excavation
1964
Recommended Citation
Gandhi, Rajni K., "Estimating bench design parameters for open-cut excavation" (1964). Masters Theses.
5639.
https://scholarsmine.mst.edu/masters_theses/5639
This thesis is brought to you by Scholars' Mine, a service of the Missouri S&T Library and Learning Resources. This
work is protected by U. S. Copyright Law. Unauthorized use including reproduction for redistribution requires the
permission of the copyright holder. For more information, please contact [email protected].
ESTIMATING BENCH DESIGN PARAMETERS FOR
OPEN-CUT EXCAVATION
BY
RAJId K. GANDHI
THESIS
Degree of
MASTER OF SCIENCE
IN
MINING ENGINEERING
Rolla, Missouri
1964
i
ABSTRACT
efficient operation.
ii
ACKNOWLEDGEMENTS
manuscript.
ill
TABLE OF CONTENTS
Pag*
ABSTRACT ..................................................... i
ACKNOWLEDGEMENTS ............................................. ii
CHAPTER
I. INTRODUCTION ......................................... 1
ANGLE, |p ...................................... 7
OPERATION ......................................... 20
Pag*
PRODUCTION ..................................... 32
Production .............. 32
Production ............. 35
Production .......................... J6
IV/* BANK PREPARATION DESIGN .............................. 38
A* BLASTING RELATIONSHIPS ............................ 38
P age
Length, .................................. 63
8. Stannary ....... . 70
Pag*
APPENDICES
BIBLIOGRAPHY ................................................. 87
LIST. OF ILLUSTRATIONS
Figure Peg®
Collapse ........................... 21
Height .......................................... 53
viii
Figure ?»«•
LIST OF TABLES
Table Pago
Materials ...................................... 12
Rocks ................................ 16
CHAPTER I
INTRODUCTION,
materials removed from the earth (1, 2)* Competition in the world
economic conditions#
(3, 4)* As for the selection of specific types of equipment and the
literature does not indicate that work is being done toward that
CHAPTER II
the area in which the work is done, Ctice established, the normal
tion is made.
the project size varies, but the unit capital equipment cost
economically*
the required bench width, the height of bench working faces, and
tion* It must not exceed the critical height calculated from the
ting requirements*
control*
working days per year will be available for production* The annual
B. BANK FAILURES.
tho fall of loose blocks when the slope angle is greater than the
of joints that divides the mass into a system of blocks, which may
Bonch Failure.
Figure 1* Modes of Failure in Open-Cut Excavations (7)*
o\
7
within a rock bank depart o.. the stress history* When an excava
the bench and the height of the working face, as shown in Figure 2
(9)*
The stripping ratio (9) and bench geometry depend upon the
the horizontal plane at which the slope can be cut and yet stand
excavation*
Providing that single bench damage does not measurably affect the
tion, moisture conditions, seepage, etc#, can greatly can pound the
<5** is the unit stress applied normal to the sliding surface, and
Figure 3#
given by Tables I and II# It should be noted fran the data that
o
TABLE I . S tren g th Data For Some Competent Rocks ( 13) .
C - Cohesion
£ - Angle of Internal Friction
12
the factor should not be less than 2*0 for soils and similar non-
ccmpstent materials*
(1 )
that will stand before shear failure are given by Table I H , calcu
that Q becomes very high when the cohesion and angle of internal
other hand* Trollope (19) suggested from his work that the
solution*
ted that when ^ was larger than 60 degrees, bank failures at the
toe or above were possible* When was &7 degrees or less* all
would lie below the slope toe and not pass through it*
Physical Granite Marble Salt-Rock Sand Stone Shale Soft Lime Altered Altered Dense
Properties Stone Quartzite Schist Sand and
of Rocks Gravel
NJ'X
!\5
ON
1720 210 900 1420 6 10
O
C - psi. 7 5
dr - tons/cu. ft. 0 .0 7 0 0.080 0.080 0.073 0 .0 6 0 0 .0 7 2 0.082 0 .0 7 2 0 .0 5 8
Q Q Q Q Q Q Q Q Q
P
90 * * * * * 29 38 46 90
80 * * * * * 36 44 70 125
70 * * £ £ * 56 68 98 189
60 * * * * * 76 120 240 303
* * * * * 117 2 68 635 620
50
4o * * * >r * 208 880 *
* * * * 580 * * *
30
H
On
17
tho other hand* for deop pits in reasonably strong rocks and for
ore slope was kept near 4-5 degrees* The Pima operation in Arizona
(22)* the Marquesado iron mine in Spain (23)* and some of the iron
to 1).
may be one relationship between the and Q values for above the
ranging from days to years* But in time* banks will tend to fail*
that the ratio of bench height to width must not exceed tan jji ,
followst
19
L / Wh = tan Y (2)
where "V is tho angle which tho lino connecting tho toos of all
dimensions of the equipment used for both loading and haulage, and
ascertain that the designed L/W^ ratio does not exceed the slope
CHAPTER III
A. DIMENSIONAL LIMITATIONS.
1* Swell Effects.
sents a block of solid material and the new volume after blasting*
ted by Figure 6.
One can assume that the depth of bench blasted, y, and its
V # = abL3 / Sf %
21
Also, L * L* S^ 3 , y « y 9 S^ 3 , and 1 « 1* S^ 3 .
For convenience in analysis, no vertical rise of broken
bo as follows*
l/3
which gives a X / Sf' * 0*5(y,,t - y ,# 4 2 y 99)*
Thus.
Since
than the original bench height$ the part of the bench width required
length, it follows that the part of the length required for swell, u,
would be similar to z, or
could be assumed for haulage as follows! one truck width each for
the loaded unit and for a returning empty unit that may need to
pass at the shovel rear, one width for passing clearance between
units, and two or more widths from the outside edge of the bench
s, must also be included* The total minimum bench width would then
be as followsl
(6 )
shovel crowds directly into the broken pile until it has dug a
scmi .-circular path* The method has the advantage in that trucks
room exists, which greatly reduces loading time losses from truck
spotting.
the total distance of the sum of the dumping radius of the shovel*,
R„j and a minimum distance of atleast two truck widths, W^, for
would be as follows t
2(RS ♦ 2 tft ) • u ♦ ^ ,
optimum production* It has been shown that the optimum height can
cut the pile of broken material* Rock fragments in the top portion
and possible injuries* On the other hand, bench heights that are too
determined for the minimum bench width, the optimum bench height,
istics for presently available machines occurs when the bucket capa
city is about 18 cu* yd*, or those sizes available only for stripping
shovels* The latter are designed for a long reach and large capacity,
while loading shovels, with 12 ou* yd* capacities or less, have short
er reach but greater speed and digging power for close-in work* Since
the latter condition is required for this study, only shovels with
follows l
(8)
Figure 7* Relationship Between Optimum Height of Out and Bucket Size for Shovels (30)
30
2. Cycle Time.
basic phasesS crowd* hoist* swing* and dump 0 Total cycle time is
the time required to dig* swing* dump into haulage units* and swing
from blasting* the weight and hardness of the material loaded, the
If the optimum depth of cut and the normal 90-degree swing angle
maximum dumping and clean-up radii are related to the bucket capa
( 10 )
33
(11)
width.
37
then,
Regrouping,
CHAPTER IV
A. BLASTING RELATIONSHIPS.
charge configurations (34, 35» 36, 37j 38* 39)* Of these relation
dons (36, 41* 45)* analyses show that the true burden does not
1* Burden Calculation*
Aah (41) is the most convenient for estimating the true burden
dimension, or
being defined as (S G )
o 0 • Since it has been generally accepted
that the pressures developed by explosives would be a diroot func
the average Kg ratio for the standard explosive when used to blast
sive in normal rock requires that the density and velocity of the
b o as follows t
42
h m \ (“ 2 / “ i )1/3 »
standard explosive and average rock, one can approximate tho true
follows that I
or B*
Providing that the true burden has been determined for any explo
sive charge* one can approximate the necessary adjusted true burden
ratios that may exist when blasting in the same rock with difforent
explosives.
43
solid rock Indicate that the T value may be from 0*5 to 1*0 times
« J / B* - 0.3 (17)
be assumed that the minimum hole depth, H*, should not b e less
H® * L ♦ 0*3 B* , ft.
the minimum bonch height, L* s should not be less than the 3® value.
If this condition does not exist, cratering in tho horisontal face
floor level. Studies by Pearse (48) of many field blasts show that
dopth would be
The exact value for the minimum required hole depth had been
value for the Ky ratio varies between 0.8 and 1.5* Extremes could
is that once the bench height exceeds the burden, stressing and
top priming would give high piles of broken material, while floor
rial being blasted (49, 50, 51* 52, 53)* The relationship, termed
as shown in Figure 15* In this case, the apparent burden and spac
burden and spacing would thereby be greater than the true burden, or
(19)
48
4>
vo
50
1. Basic Assumptions.
effect on the yield (41). Fbr this investigation and for simplifi
in tons/ cu. ft. for any rock could be expressed as follows (41):
Cy ■ 0.03125 (S G p ) , tons , (2 0 )
dU « 0.34 D? ( S G )
9 0 , lb./ft. (21 )
If square patterns are used, it was shown earlier that the apparent
burden and spacing for a blasthole would be equal. Thus, the tonnage
W « 0.03125 B 2 L (S Gy ) , tons •
W « 0.000434 k | D 2 L (S G r ) , tons .
9
(22)
(Figure 11). But from Equations 16 and 17, the PC value could be
PC ■ H - T « L - 0.4 B».
for the PC and Equation 21, the total blasthole oharge can be then
yield is largest, occurs where the bench height equals the true
height, cratering with upward throw, back break, and violence all
ui
04
5*
agents, the cost for drilling constitutes the largest share of bank
in the rock by the drill, (2) the time spent for adding extra drill
hole completion, and (4) time for moving and setting up to drill
the next blast hole. For relatively short holes, the penetration
phase constitutes most of the oyole time, while moving and removing
steel section length was 10 ft. Even though the data covered studies
VJl
ui
56
most conditions*
indicative for most other equipment when drilling the same material,
with the relationship between hole diameter and that for the steel
ately with increasing hole diameters for any particular drill and
powerful and rugged for drilling the larger diameter holes* The net
result is that penetration rates for large holes are only slightly
U)
->3
58
high footages, costs per unit yield (ton or cubic yard) have
the Increased drill pattern proportions (21, 5^* 55* 56)• It would
seen logical, then, that maximum drill footage per unit of time
bench height®
59
CHAPTER V
A. GENERAL CONSIDERATIONS.
moved but also the economic time limit available to amortize the
tion work, the quantity and total working time for completion would
a value normally is estimated that would take into account the total
(a) Ultimate size* 4000 ft* along the strike, 1500 ft, wide,
ore;
61
average footage;
V * 12,000 fps.
©
B. ESTIMATING PROCEDURE.
live limiting slope angles for various depths first should be deter
Q dy / 4 o (cos J ),
as follows:
90 80 70 60 50 40 30 20
Thus, the limiting slope angle, ja , for all benches to full exca
vation depth and the angle whose tangent equals the ratio of each
noted that the bench faces themselves could vary from vertical to
or Lq = 30 ft.
The value calculated, however, does not mean that the bench height
30 ft. bench*
63
cd * Ps / (2700 Sf c^) ,
♦ 2 s f (23 + 2 W t ) - 9 cot V ,
or 1^ * 130 ft.
With the minimum bench operating width and optimum bench height
1000 - y (130)(30)(0.084) ,
or y * 30.5 ft.
any even multiples of their minimum values to suit the daily produc
4.3 to 1,
♦ 9 S-1/3 (cot ♦ 2 a) ♦ 38 18 a + 5 W t ,
f
Because both y and LQ are known, the constant “a* would be approxi
or * 184 ft.
66
From Figure 6 it will be seen that the Wffl value allows for
ratio that the slope stability would be still well within safe
limits* The reduced slope would be only 0*21 (30 / 145)» whioh is
If B* - (0.21 De / dy)
B* = 2 .3 IT0 = 2 .3 Dg ,
ratio bo not less than 1 or greater than 3*7 (41, 48), the rang© of
both the ecenemies and drill footages attainable. The tonnage from
the larger hole would greatly exceed that made available by the
If D# = % , W “ 0.000434
2 2
27®6 were used, the tonnage per hole would be 0.000434(27*6) Eg (81),
sizes for Dg , W * 4500 for the 13-in. and W * 326 tons for the
3-1/2 in. hole. Since both drilling machines were assumed to drill
tion* For a single hour's drilling by the 3-1/2 in, machine, however,
possible hole diameter, i,e,, 13-in, On the other hand, the possibil
would be the greatest for tho' very large holes because of the extended
provided per drill hour of operation. The advantage of the one drill-
sub-drilling, each hole would be drilled in 0,7 hour. Thus, 875 tons,
should be provided by each blast hole. The diameter could be estimated
69
2
from the expression W = 26.6 Dg , derived from Equation 22, where
2
8 75 “ 2 6 .6 Dg , t o g i v e Djj = 5»?5 i n c h e s .
The required apparent burden and spacing for each hole in the
If B - S * 1.4 B* and B* * Kg Dg / 12 ,
then F * S » 1*4 Kg Dg / 12 ,
or B ■ S * 18.5 ft*
Substituting,
a total of seven holes in a single row along the bench face would be
relationships need be used, or Equations 14, 15, 19» 22, and 24.
loading rates. The bench height is the single most important design
8. Summary.
L / W = tan 40°.
CHAPTER VI
for any open— out excavation using the benching method* The allow
strongly control the costs and methods utilized for materials load
ing* drilling, and blasting* Since the study was confined to hand
ships, the operating design parameters for benches were then obtain
(3) For the optimum bench height for any production rate,
73
(^) For the optimum bench height for any shovel capacity,
Wm » [ p 8 / (3000 S f d j | [ s j l/ 3 (o o t JT 4 2 a )
■ f 3 8 - 1 8 a 4 5 W t , ft.
(7) F&r the tonnage yield per blasthole for any bench
(8) For the true burden to use for any blasthole, explosive
and tonnage per hole can be equated as a function of the hourly drill
footage rate.
provided the key dimension upon which all other operating paramaters
most likely could be based. It was noted, however, that the larger
diameter. But the optimum bench height did not increase in like pro
TABLE OF SYMBOLS.
Stress, psi.
<5
tan Coefficient of internal friction.
J - Subdrilling» ft*
Kg - Burden ratio*
Kj ~ Sub-drilling ratio.
Kg - Spacing ratio,
Ko - Stemming ratio.
- Swell factor.
77
APPENDIX II
existing slope.
as shown in Figure 19. The rock above the assumed curve is divided
slice by the unit weight of the rock. Usually, the thickness of the
and N^, which are parallel and normal, respectively, to the base.
is the applied shearing force that tends to move the slice down
hill. The algebraic sum of all values gives the resultant shear
S * o 4-3" tan Q «
would be the sum of the total cohesion (unit cohesion times the
total length of the curved surface), the product of the sum of tha
n n
Z_sA » 2 - s »
1 * 1 r
n
where cM tan
n n n n
co
o
81
APPENDIX III
(After Spangler)
For & given material for which the unit weights cohesion*
as follows t
* - h. * h 4 h
n
or (i)
AC passing through the toe of the slope* The shearing force, S^*
on this plane depends on the weight of the rock above* and the
S - W sin ^ . (ii)
a
82
For S,
- 0*5 ( p + § ) • (vii)
Equation (vi),
or o = 0 * 5 ^ Q coseo
Simplifying,
a - d^, a (viii)
84
Therefor®,
(ix)
which gives,
/ (jL - cos ( | b - ^
to shear only*
85
APPENDIX IV
LIST OF EQUATIONS .
86
BIBLIOGRAPHY
Metallurgy.
November.
March.
New York*
Berlin? Ernst#
November#
Bulletin 587.
26# MAC IVERj, B# N# (1961). Eow tho Soil Engineer Can Help the
Arizona, October*
30* — — ——— (1958)* Coal Age, Guide Book* Coal Age, Mid-July*
California.
and Metallurgy.
March.
VITA
Engineering in 1955.