PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 1/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
PERMIT TO WORK
REVISED AS PER
5 30 DEC 20 H. S. Woo J. S. Ham B.H.Lee Y. B. Lim S.B.Park
MARKED
REVISED AS PER
4 08 NOV 20 H. S. Woo J. S. Ham B.H.Lee Y. B. Lim H.S.Hwang
MARKED
ISSUED FOR
3 06 NOV 19 Allan Cho J. S. Ham Y.S.Kim Y. B. Lim H.S.Hwang
CONSTRUCTION
REVISED FOR
2 03 AUG 19 Allan Cho J. S. Ham Y.S.Kim Y. B. Lim H.S.Hwang
COMMISSIONING
ISSUDED FOR
1 02 DEC 14 D. W. Youn W.S.Ann Y.S.Kim B.H.Shim H.S.Hwang
CONSTRUCTION
ISSUED FOR
0 20 OCT 14 D. W. Youn W.S.Ann Y.S.Kim B.H.Shim H.S.Hwang
CONSTRUCTION
Joint Venture of Hyundai Engineering & Construction Co., Ltd., GS Engineering & Construction Co., Ltd., SK Engineering
Note :
a) Revision bar(vertical line) shall be placed in the right hand margin to indicate where the changes has been made
b) PRPD = Prepared by, CHKD = Checked by, REVD = Reviewed by, APPRD = Approved by, CONFD = Confirmed by
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 2/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
REVISION HISTORY
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 3/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
TABLE OF CONTENTS
1. Purpose ..................................................................................................................................................... 5
2. Scope ......................................................................................................................................................... 5
3. Responsibility ........................................................................................................................................... 5
3.1. HDGSK JV Project Director ........................................................................................................ 5
3.2. HDGSK JV HSE Manager ............................................................................................................ 5
3.3. HDGSK JV Area Construction Managers (Construction Area Authority) .............................. 5
3.4. HDGSK JV Construction Supervisor ......................................................................................... 6
3.5. HDGSK JV Area Commissioning Manager ............................................................................... 6
3.6. HDGSK JV Commissioning Section Engineer or Superintendent (Commissioning Area
Authority) .................................................................................................................................................. 6
3.7. Subcontractor’s Permit Holder .................................................................................................. 6
4. Definition ................................................................................................................................................... 7
4.1. Area Authority (Permit Issuer).................................................................................................... 7
4.2. Permit Holder ............................................................................................................................... 7
4.3. Permit Reviewer ........................................................................................................................... 7
4.4. Competent Person ....................................................................................................................... 7
4.5. Competent Person, Electrical ..................................................................................................... 7
4.6. Competent Person, Mechanical ................................................................................................. 7
4.7. Competent Person, Civil ............................................................................................................. 7
4.8. Competent Person, Lifting .......................................................................................................... 8
4.9. Competent Person, Excavation .................................................................................................. 8
4.10. Confined space ............................................................................................................................ 8
4.11. Gas testing ................................................................................................................................... 8
4.12. Permit To Work System ............................................................................................................... 8
4.13. Permit to Work Hand over........................................................................................................... 8
4.14. Standby Man ................................................................................................................................ 8
4.15. Fire Watcher ................................................................................................................................. 8
4.16. Authorized Gas Tester ................................................................................................................. 8
4.17. Radiation Protection Supervisor ................................................................................................ 9
4.18. First Aider ..................................................................................................................................... 9
4.19. Isolation/DE-Isolation Certificate ............................................................................................... 9
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 4/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
5. Procedure .................................................................................................................................................. 9
5.1. Preliminary ................................................................................................................................... 9
5.2. General ......................................................................................................................................... 9
5.3. PTW Application process ......................................................................................................... 10
5.4. Validity of Permits....................................................................................................................... 11
5.5. Revalidation ................................................................................................................................ 11
5.6. Permit Holder Signing Off .......................................................................................................... 11
5.7. Classification of Work Permit. ................................................................................................... 11
5.8. Standard Forms ......................................................................................................................... 17
5.9. Identification of Authorized Personnel & Alternates ............................................................. 17
6. Reference ................................................................................................................................................ 17
6.1. IONE-AA00-PE-HS-0001 Project HSE Plan .............................................................................. 17
6.2. IONE-AA00-PE-HS-0004 Tool Box Meeting ............................................................................. 17
6.3. IONE-AA00-PE-HS-0020 Lock Out Tag Out ............................................................................. 17
6.4. IONE-AA00-PE-HS-0024 Working at Height ............................................................................ 17
6.5. IONE-AA00-PE-HS-0025 Confined Space ................................................................................ 17
6.6. IONE-AA00-PE-HS-0026 Excavation ........................................................................................ 17
6.7. IONE-AA00-PE-HS-0028 Hot Work ........................................................................................... 17
6.8. IONE-AA00-PE-HS-0029 Lifting Safety .................................................................................... 17
6.9. IONE-AA00-PE-HS-0041 Radiography Safety ......................................................................... 18
6.10. IONE-AA00-PE-HS-0050 Pre-commissioning & Commissioning HSE Plan......................... 18
6.11. IONE-AA00-PE-HS-0051_Simultaneous Operations Procedure ........................................... 18
7. Appendices ............................................................................................................................................. 18
7.1. The Permit to Work Flowchart .................................................................................................. 18
7.2. The Standard Permit to Work Forms (For Construction Area) ............................................. 18
7.3. Revalidation sheet (For Construction Area) ........................................................................... 18
7.4. The Standard Permit to Work Forms (For Commissioning Area) ......................................... 18
7.5. Revalidation sheet (For Commissioning Area) ....................................................................... 18
7.6. Identification of Authorized Personnel and Alternates .......................................................... 18
26
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 5/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
1. Purpose
This procedure and guidance information has been developed to establish a uniform system for the
issuance of permits to work in such a way that a hazardous and/ or high risk activities can be carried out
in a safely manner as possible.
2. Scope
This procedure is to be used by members of the HDGSK JV, its Sub-contractors Project Management
Team, Supervisors and Subcontractors who directs, supervises and control hazardous activities where a
permit to work is necessary.
This procedure has been updated for applying to all stages (Construction, Pre-Commissioning,
Commissioning) of this project.
3. Responsibility
3.1.1. The HDGSK JV Project Director has overall responsibilities for ensuring that provisions are
made for the implementation of Safe Systems of Work including planning for Permit to Work
durations.
3.1.2. The implementation of the "Permit to Work (PTW)" scheme shall be the joint responsibility of
the HDGSK JV Project Director and the HDGSK JV HSE Manager, with full assistance from
the HDGSK JV Construction/Commissioning Manager, Delegated personnel and
Subcontractors Permit Holder nominated personnel.
3.3.1. Responsible for the review of permit to work application on construction area.
3.3.2. Ensuring all hazards and risks are adequately addressed in consultation with the
subcontractors Project Manager and/ or construction field supervisors.
3.3.3. Monitoring of the work in progress to ensure compliance with the conditions set forth in the
PTW permit/s.
3.3.4. Suspension of non-compliance activities and withdrawal/ cancellation of non-compliance PTW.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 6/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
Responsible for managing overall PTW system and monitor its implementation in Pre-Commissioning
and Commissioning area.
3.6.1. Responsible for the approval of permit to work application on pre-commissioning and
commissioning area.
3.6.2. Monitoring of the work in progress to ensure compliance with the conditions set forth in the
PTW permits.
3.6.3. Assigning competent electrical and mechanical personnel to perform and certify isolations as
required by the Lock Out / Tag Out Procedure in Commissioning Controlled Areas.
3.6.4. Controlling the issuance of clearance tags for access to Commissioning Controlled Area.
3.6.5. Suspension of non-compliance activities and withdrawal/ cancellation of non-compliance PTW.
3.6.6. Controlling the issuance of isolation/de-isolation certificate when permit is required to check
Lock Out / Tag Out status.
The Permit Holder’s responsibilities include but are not limited to;
3.7.1. Ensuring the proper authorization of designated work such as certain type of work, extent of
job, related hazard and limitations.
3.7.2. Ensuring that adequate precautions are made and maintained throughout the work activities
as stated in the permit to work JHA and Risk Assessment.
3.7.3. Ensuring that on completion or suspension of work, the site is left in a safe condition and the
Area Authority (Permit Issuer) is adequately informed.
3.7.4. Ensuring that the plant and equipment is left in a safe condition after work is finished.
3.7.5. Ensure PTW is present during toolbox meeting and all conditions of the PTW were
communicated to all members of the team. The PTW must be present at all times during
execution of the activity.
3.7.6. Ensure strict implementation and compliance of the PTW procedures.
3.7.7. Ensure pre-start meeting for sharing JHA & Risk assessment of work which applied by permit
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 7/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
to work system.
4. Definition
A Technical Specialist of the disciplined work with responsibility for defining the control measures to
be put in place to control and manage the work in an area or particular discipline.
Permit issuer should be completed Permit to Work Training course including examination which
providing by HDGSK JV.
The person/s responsible for completing the Permit to Work application, directing and supervising
the work being carried out and ensuring full compliance with all conditions of the permit to work. Also,
safety supervisor should not be permitted to process permit to work as permit holder.
HSE People will only review PTW not sign them on. Permit holder is limited to assigned person by
Task Team Engineer/Supervisor. PTW work holder must be trained by issuing authority and be
foreman / supervisor level appointed by Construction or Commissioning Manger. 5
The person/s responsible for reviewing the Permit to Work processing and monitoring the work being
carried out and reviewing full compliance is fulfilling as per Permit to Work requirement.
4.3.1. In Construction activities, permit reviewer will be assigned by HDGSK JV HSE Team
4.3.2. In a Commissioning activities, permit reviewer will be assigned from HDGSK JV Construction
Manager and HDGSK JV HSE Team.
4.3.3. PTW shall be reviewed at the place of the work activities.
4.4. Competent Person
A competent person is person who has skill, knowledge, training, experience, abilities and authorized
to carry out defined work through internal training and 3rd party training with certificate.
A competent person who is approved by HDGSK JV Electrical Manager to carry out the preparation 5
to isolate/de-isolate electrical appliance and/ or equipment up to a predetermined voltage.
A competent person who is approved by HDGSK JV Mechanical Manager to carry out the preparation
and control of mechanical isolation of process equipment.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 8/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
A competent person who is approved by HDGSK JV Civil Manager to carry out the planning,
preparation and execution of the civil work in a safe manner.
5
4.8. Competent Person, Lifting
A competent person who has been approved to carry out the lifting preparation and perform the lifting
work in safe a manner.
A competent person who has been approved to carry out the excavation preparation and perform
the excavation work in a safe manner.
A space that is large enough and so configured that an employee can bodily enter and perform
assigned work.
A test conducted to measure the existence and/or concentrations of toxic gas or flammable gases,
such as O2, CO2, CO, NO2, H2S secure safe workplace.
The system that allows central control and ongoing monitoring of higher risk activities to ensure that
activities are;
Authorized.
Carried out by qualified personnel using appropriate safety precautions.
Those activities with potentially hazardous interactions do not take place at the same time.
A person who has been briefed and competent on the emergency procedures and equipment
necessary for confined space entries.
A person assigned to the duties of fire suppression and prevention necessitated by hot work activities.
Personnel who are authorized and trained (Authorized Gas Tester Training by 3rd party services) in
the use of gas testing equipment.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 9/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
The person appointed by the N.D.T (or other) company as the classified person responsible for
supervising work with radiation sources on site.
NOTE: The actual job titles as defined may differ depending on Project Management terms specific
to site, however, the job titles used on project must reflect the authorization of the persons concerned.
A person who provide initial care for an illness or injury until definitive medical treatment action, such
as investigating, considering or acting on a safety matter.
5. Procedure
5.1. Preliminary
During construction/commissioning, the activities tabled below shall require both permission and
certification prior to work commencing. Example permit to work forms can be found in the enclosures
to this document.
Prior to conduct activity, each permit shall be analyzed and approved by permit issuer or
commissioning area authority for in case of commissioning area, then approved permit shall be
submitted to permit control room a day before when activity conducted.
5.2. General
Training shall be provided for qualification to conduct specific tasks such as Hot works, Confined
Spaces, Electrical Work, Working at Height, Excavation and Energy Isolation. Training should be
provided for individual prior to their assignment start.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 10/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
Third party training shall be provided for qualified personnel & equipment such as Lifting works
(Crane lifting, Rigging), Gas testing, Working at Height (Scaffolding Work).
Application shall be made by the Permit Holder who shall supply all information and required
attachment/s relevant to the scope of works on the relevant permit forms.
The Area Authority (Permit Issuer) shall review the precautions necessary to carry out the work safely.
The Area Authority (Permit issuer) must first check that the work method statement and risk
assessment adequate to carry out the activity safely before signing the PTW in a location as close
to the work activity as can be safely achieved to ensure that the Permit is issued in a safe work
location free from hazards.
Provision of "Work Method Statements" may be necessary and shall be attached to the permit.
Preventative measures shall be identified by the Area Authorities (Permit Issuer) in conjunction with
the Permit Holder and reviewed by HSE department.
When the Area Authority (Permit Issuer) is satisfied that all conditions have been met in preparing
the area to be worked on, the Area Authority (Permit Issuer) shall discuss the measures taken and
precautions required to carry out the job safely with the Permit Holder and the HSE department as
required.
When the Permit Holder is satisfied, he shall sign acceptance of the terms and conditions set out in
the permit for doing the work.
*Note
On signing the acceptance, Permit Holder accepts responsibility for the work activity and the
work area.
Both the Issuing authority and the permit holder shall visit the work activity location and check
5
for the compliance of health and safety requirements before any permit is signed off.
The Area Authority (Permit Issuer) shall also sign to indicate approval and share of responsibility to
the Permit Holder.
The PTW is to be sent to the HSE department PTW document controller for recording and tracking.
A copy of the PTW is to be retained at the HSE office record and the original copy posted at the
visible location such as PTW board or box which installed nearby of the workplace (i.e confined 5
space work/entry, NDT, Hazardous substance handing, excavation, lifting, commissioning area, etc).
All team members are to be made aware of its content and requirements for the works.
If there is shift change during designated work, the Permit to Work and detailed information on the
work shall be transferred to other authorized permit holder. In that case, the Area Authority (Permit
Issuer) or his nominee shall regularly monitor whether the work is going as planned.
Permits should be returned to ‘Permit Control Office (HSE Office)’ after closed out by both Area
Authority (Permit Issuer) and Permit Holder.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 11/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
Permits needs to be re-applied after the end of the duration of permit, validity in case the work is
continued.
5.5. Revalidation
The Area Authority (Permit Issuer) shall re-approve the recommencement of work by signing the
date/shift of revalidation (7 days maximum). This must be accomplished after the day’s tool box
meeting before the start of work.
Until permit holder, permit issuer sign on daily revalidation sheet, commissioning area authority also
must do same process in commissioning area, otherwise, permit shall not be activated.
If there is change of conditions and permit condition could not cover it, the permit should be closed-
out and re-issue the permit.
When the Permit Holder is satisfied that the permitted work has been completed or suspended for a
sufficient length of time to warrant the permit closure, the Permit Holder and the Area Authority
(Permit Issuer) shall both sign off the PTW.
Note: Completed Permits will be return to HDGSK JV PTW Reviewer (HSE) for closing of the permit
and kept in a master file to maintain history of the work carried out. These documents in some cases
can be used in litigation and should be treated as Legal documents.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 12/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
When work is generally conducted on the site, general work permit shall be written by permit holder.
However, if work area is considered as the area where commissioning activity is being conducted or
exist any potential hazard due to it, work permit shall be followed according to work permit for
commissioning area.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 13/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
Associated Work permit which shall be prepared on any activity that require to lift with
crane.
Crane Lifting Permit should be prepared with documents below but not limited to;
Risk Assessment and JHA
Load chart 5
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 14/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
Safety requirements below should be reviewed while Abrasive Blasting Permit but not
limited to;
Use of correct tools & tackles
5
Temporary Hard Barricades or Cover
Caution sign all sides for preventing unauthorized access
No loose materials on the floor
Life line / Anchorage
Scaffold tag system in place
Sufficient Replacement Clips- Available
Trained Grating Removal Personnel and Supervision
"OPEN HOLE-DANGER, DO NOT REMOVE" caution board in place
5.7.1.9. Radiography
Radiography shall only be carried out by competent persons, following a review of their
local working rules and such activities will be programmed wherever possible after
normal working hours. Notification include marked up plot plan with safety distance,
working time should be noticed to all contractors at least 12hours before commence the 5
work.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 15/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
All pipes which connected to the confined spaces should have blind or air gaps to
prevent unexpected flow of energy source or hazardous atmosphere. 5
Any confined space that may have contained Nitrogen must be opened up and ventilated
72 hours before any planned work or mechanically ventilate to fresh air with ventilator,
then made atmospheric test in the confined space to ensure that sufficient level of the
oxygen or not presences of any hazards.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 16/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 17/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
The "Permit to Work" form/s is designed to cover most eventualities arising on site. Other attachment
necessary and required for the PTW will be included in a part of the permit.
The authorized personnel shall be recorded by “Identification of Authorized Personnel and Alternates”
form. Permit to work and other relevant document shall be signed by authorized personnel &
alternates register.
6. Reference
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 18/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
7. Appendices
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 19/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 20/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 21/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (1) The Standard Permit To Work Forms (For Construction Area)
KARBALA REFINERY PROJECT
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
JV Safety
Comment:
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 22/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (2) The Standard Permit To Work Forms (For Construction Area)
Application Date: Start Date & Time: Completion Date & Time Company: JHA Attached:
YES □ No □
Location : Tools & Equipment to be Used Certificates Checked
Operators: YES □ N/A □
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
Safety Googles □ □ All utilities & line identified before beginning□ □ Required
Face Shield □ □ Spoil piles at least 0.6m from the edge □ □ YES □ No □
Hot Burn Protective Clothing □ □ Qualified person make daily inspections □ □
Appropriate Gloves □ □ No person when Power equipment operating □ □ IF YES Then Gas
Hearing Protection □ □ Adequate sloping and access provided □ □ Test Results to be
Respirotary Protection □ □ Ladder extended 1m above top of excavation □ □ Recorded on PTW
Full Body Harness □ □ Heavy equipment not permitted within 1.5m □ □ "Gas Test Record
Rubber Boots □ □ Equipment Inspection & color coding □ □ form"
□ □ Signs & Barricades Posted □ □
JV Safety
Comment:
I am Aware of the conditions on this Permit, they have been discussed with the JHA and I confirm that the Safety Precautions as attached
to the Work Permit and certificates will be strictly observed. All personnel under My control shall be briefed through TBT accordingly.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 23/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (3) The Standard Permit To Work Forms (For Construction Area)
Application Date: Start Date & Time: Completion Date & Time Company: JHA Attached:
YES □ No □
Location : Tools & Equipment to be Used Certificates Checked
Operators: YES □ N/A □
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
JV Safety
Comment:
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 24/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (4) The Standard Permit To Work Forms (For Construction Area)
Application Date: Start Date & Time: Completion Date & Time Company: JHA Attached:
YES □ No □
Location : Tools & Equipment to be Used Certificates Checked
Operators: YES □ N/A □
Critical Lift Plan required YES □ No □ Trial Lift & LMI Check required YES □ NO □
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
Safety Precaution YES NO Crane Capacity: tons
Ground stablity OK □ □
Weather Conditions OK □ □ A= meters
Outrigger fully extended and Pad in good condition □ □ B= meters
Pick up & Drop Paths identified and Checked □ □ C= tons
Rigging equipment inspected and correctly color coded □ □ D= tons
Lifting area controlled and barricaded properly □ □
Daily Crane Checklist completed by certified operator □ □ Total lifting Weight (C+D) = tons
Certified Rigger assigned □ □ Actual Lifting Capacity at set up (F)= tons
Slings & Shackles inspected & Secured by certified Rigger □ □ Current % Crane Capacity [(C+D)/F]= %
*Refer to the attached detailed lifting plan for critical lifting
Part 3: Acceptance (To Be Filled By JV HSE or PTW Coordinator)
JV Safety
Comment:
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 25/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (5) The Standard Permit To Work Forms (For Construction Area)
Application Date: Start Date & Time: Completion Date & Time Company: JHA Attached:
YES □ No □
Location : Tools & Equipment to be Used Certificates Checked
Operators: YES □ N/A □
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
Safety Googles □ □ Access and Walk way are Clear and free of obstruction □ □
Face Shield □ □ Scaffolds are completed and tagged properly □ □
Hot Burn Protective Clothing □ □ 100% Fall Protection complied (Toeboard/Toprail/Midrail) □ □
Appropriate Gloves □ □ Adequate number of Fire Extinguisher provided □ □
Hearing Protection □ □ Fire Blanket for welding, cutting/grinding work provided □ □
Respirotary Protection □ □ Open areas/gratings are covered and protected □ □
Full Body Harness □ □ Warning signs in place for preventing unauthorized access □ □
Rubber Boots □ □ Equipment inspected and correctly color coded □ □
□ □ Safety officer designated to the area □ □
Need of using ladder for □ □
working platform
JV Safety
Comment:
I am Aware of the conditions on this Permit, they have been discussed with the JHA and I confirm that the Safety Precautions as attached
to the Work Permit and certificates will be strictly observed. All personnel under My control shall be briefed through TBT accordingly.
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 26/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (6) The Standard Permit To Work Forms (For Construction Area)
I certify that I have inspected the site and check all the safety requirements detailed in this permit are being fully
implemented and I confirmed that the area is safe for Night/Holiday work to start.
Represent Permit
Holder Name: Date/Time: Signature: Tel:
JV Safety
Comment:
I am aware of the conditions on this Permit, they have been discussed with the JHA and I confirm that the Safety Precautions as
attached to the Work Permit and certificates will be strictly observed. All personnel under My control shall be briefed through TBM
accordingly.
Issuer Name: Date/Time: Signature: Tel:
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 27/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (7) The Standard Permit To Work Forms (For Construction Area)
KARBALA REFINERY PROJECT
Application Date: Start Date & Time: Completion Date & Time Company: Layout/Sketch attached
YES □ No □
Location : Reason for the Road Closure:
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
JV Safety
Comment:
I am Aware of the conditions on this Permit, they have been discussed with the JHA and I confirm that the Safety Precautions as attached
to the Work Permit and certificates will be strictly observed. All personnel under My control shall be briefed through TBT accordingly.
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 28/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (8) The Standard Permit To Work Forms (For Construction Area)
KARBALA REFINERY PROJECT
Application Date: Start Date & Time: Completion Date & Time Company: JHA Attached:
YES □ No □
Location : Tools & Equipment to be Used Certificates Checked
Operators: YES □ N/A □
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
Preparation YES NO Safety Precaution YES NO
JV Safety
Comment:
The work is completed and working area has been cleared The site has been checked and working area accepted
from debris and equipment
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 29/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (9) The Standard Permit To Work Forms (For Construction Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 30/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.2] (10) The Standard Permit To Work Forms (For Construction Area)
Application Date: Start Date & Time: Completion Date & Time Company: Layout/Sketch attached
YES □ No □
Describe Exactly
Work to be done:
Part 2: Specific Safety Precaution. (To Be Filled By Subcontractor PTW Holder or Safety)
JV Safety
Comment:
I am Aware of the conditions on this Permit, they have been discussed with the JHA and I confirm that the Safety Precautions as attached
to the Work Permit and certificates will be strictly observed. All personnel under My control shall be briefed through TBM accordingly.
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 31/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 32/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (1) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 33/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (2) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 34/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (3) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 35/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (4) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 36/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (5) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 37/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (6) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 38/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (7) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 39/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
[Appendices 7.4] (8) The Standard Permit To Work Forms (For Commissioning Area)
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 40/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701
PERMIT TO WORK
DOC. NO. : IONE-AA00-PE-HS-0012
KARBALA REFINERY PROJECT Rev. 5 Page 41/41
Ref. FEED DOC. No. : 2342-AA00-JSM-701