100% found this document useful (1 vote)
650 views2 pages

Highway Survey CEL6 (S23 & S24) - October

Highway Survey assesment tools

Uploaded by

Vincent Joseph
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
650 views2 pages

Highway Survey CEL6 (S23 & S24) - October

Highway Survey assesment tools

Uploaded by

Vincent Joseph
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

CIVIL ENGINEERING TECHNICIAN LEVEL 6

CON/CU/CET/CR/02/6/A
Highway Survey
October 2024
Time: 3 Hours

WRITTEN ASSESSMENT
3 HOURS

INSTRUCTIONS TO CANDIDATES:
i. This paper consists of sections A and B
ii. Do not write on the question paper
iii. You will be provided with a separate answer booklet

This paper consists of TWO printed pages.


Candidate should check the question paper to ascertain that all pages are printed as
indicated and that no questions are missing.

Page 1 of 2
SECTION A: (40 MARKS)
Answer All Questions
1. Define the following terms

i. Back Sight
ii. Bench Mark
iii. Leveling
iv. Change point
v. Height of Instrument 10 marks

2. State Major tools and equipment used in levelling in highway survey 5marks

3. Briefly explain the types of levelling 5marks

4. With the aid of neatly drawn sketch show the parts of field survey book for;

i. Height of collimation……………………………………………………………………………………………5 marks


ii. Rise and Fall 5 marks

5. Briefly explain the activities undertaken in preliminary survey 10marks

SECTION B: (60 MARKS)


Attempt Any Three Questions

6. Describe the procedure for setting a dumpy level 20 marks

12. With the aid of neat sketches explain the procedure of differential levelling (20mks)

13.

a) Briefly explain the types of errors encountered in levelling (10mks)


b) Briefly explain the procedures of carrying out temporary adjustment on a levelling
machine (10mks)

14.

a) Sketch the Dumpy Level and name its components


(10mks)
b) Describe functions of the parts of dumpy level (10mks)

Page 2 of 2