Week 6 - Assignment - PM - 2024 - Solution
Week 6 - Assignment - PM - 2024 - Solution
QUESTION 1:
The most common method for shortening activity durations involves the decision to:
a. Eliminate bureaucracy.
b. Alter the technology used in the activity.
c. Assign more senior personnel to the activity.
d. Increase project resources.
Correct Answer: d
Justification: The most common method for shortening activity durations is to increase project
resources. By adding more resources to an activity, you can often complete it more quickly,
assuming the additional resources can be effectively utilized.
______________________________________________________________________________
QUESTION 2:
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.
Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor
informs you that the activity can be completed in 16 weeks for $200,000, what is the slope for the
activity?
Correct Answer: c
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Justification:
To find the slope for the activity, you need to determine the additional cost per week saved. The
slope is calculated as:
Determine the additional cost for reducing the activity duration from 20 weeks to 16 weeks:
QUESTION 3:
Use the information in the table (all times are in days) to determine the lowest cost minimum completion
time if the base cost for each activity finished in normal time is $1,000.
a. $7,120
b. $6,910
c. $6,790
d. $6,830
Correct Answer: c
Justification:
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Calculate the base cost for each activity if they are completed in normal time.
Each activity costs $1,000 if finished in normal time.
Total base cost = Number of activities × $1,000
Total base cost = 6 × $1,000 = $6,000
Draw the network, compute critical path, and crash critical activity with least cost slope as
shown below:
_____________________________________________________________________________
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Crashing Cost
(in '000)
Normal Time Subsequent
Activity Succeeds 1st Week
(wks) Week
Start A, B - - -
A C, D 6 8 -
B G 4 5 6
C E 4 - -
D F 5 6 6
E H 6 8 8
F H 6 7 10
G I 8 3 5
H End 5 12 15
I End 6 5 -
QUESTION 4:
a. A
b. B
c. D
d. E
e. F
Correct Answer: c
Justification:
D is the most economical critical path activity to crash, as A costs $8,000, D costs $6,000, F
costs $7,000, and H costs $12,000.
(Further see below)
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
_________________________________________________________________________
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
QUESTION 5:
What is the total cost of reducing this project by two weeks?
a. 10,000
b. 12,000
c. 14,000
d. 16,000
e. 18,000
Correct Answer: c
_____________________________________________________________________________
QUESTION 6:
a. 28,000
b. 30,000
c. 35,000
d. 40,000
e. 45,000
Correct Answer: d
QUESTION 7:
Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000,
EAC = 1333. How is the project doing in terms of schedule?
a. More work has been done than planned
b. Less work has been done than planned
c. The same amount of work has been done than planned
d. The project has cost less than planned
e. There is not enough information to draw a conclusion
Correct Answer: a
Justification:
To assess how the project is doing in terms of schedule, compare the Planned Value (PV) and
Earned Value (EV):
QUESTION 8:
Determine the earned value at week 49 (Consider the nearest value)
a. $4,950
b. $6,050
c. $4,155
d. $5,250
Correct Answer: c
Justification:
___________________________________________________________________________
QUESTION 9:
Determine the schedule variance (SV) at the end of 49 weeks (Consider the nearest value)
a. -$1,896
b. -$1,096
c. -$800
d. -$206
Correct Answer: b
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Justification:
To determine the schedule variance (SV) at the end of 49 weeks, follow these steps:
Calculate the Planned Value (PV) at week 49:
PV is the cumulative planned value of work scheduled up to week 49.
From the monthly plan: $325 + $800 + $435 + $1,475 + $1,440 + $425 + $350 = $5,250
Calculate the Earned Value (EV) at week 49:
From the previous calculation, EV at week 49 is $4,155.
Calculate the Schedule Variance (SV):
SV = EV - PV
SV = $4,155 - $5,250 = -$1,095
______________________________________________________________________________
QUESTION 10:
Determine the schedule performance index(SPI) at the end of 49 weeks (Consider the nearest value)
a. 1.46
b. 0.68
c. 0.79
d. 1.26
Correct Answer: c
Justification:
To determine the Schedule Performance Index (SPI) at the end of 49 weeks, follow these steps:
Calculate the Planned Value (PV) at week 49:
From the monthly plan: $325 + $800 + $435 + $1,475 + $1,440 + $425 + $350 = $5,250
Calculate the Earned Value (EV) at week 49:
From the previous calculation: EV = $4,155
Calculate the Schedule Performance Index (SPI):
SPI = EV / PV
SPI = $4,155 / $5,250 = 0.790
_____________________________________________________________________________________________________________________
QUESTION 11:
Determine the estimated cost to completion at the end of 49 weeks (Consider the nearest value)
a. $4,285
b. $5,250
c. $6,050
d. $7,645
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Correct Answer: d
Justification:
Estimated cost at completion (EAC) = Budgeted cost of completion (BAC) / Cost performance
index (CPI)
CPI = Earned value (EV)/Actual cost (AC)
EAC = 5250/0.6866 = $7,645
______________________________________________________________________________
QUESTION 12:
Determine the estimated cost variance at the end of 49 weeks (Consider the nearest value)
a. -2395
b. -2746
c. -1875
d. -2186
Correct Answer: a
Justification:
QUESTION 13:
Determine the cost performance index at the end of 49 weeks (Consider the nearest value)
a. 0.597
b. 0.686
c. 0.744
d. 0.974
Correct Answer: b
Justification:
Cost performance index (CPI) = Earned value (EV)/Actual cost (AC) = 4155/6050 = 0.686
_____________________________________________________________________________________________________________________
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
QUESTION 14:
Determine the estimated time of completion of the project at the end of 49 weeks (Consider the nearest
value)
a. 56.5
b. 61.9
c. 64.4
d. 67.6
Correct Answer: b
Justification: