2020 GPIC Introduction To Process Safety Management
2020 GPIC Introduction To Process Safety Management
2
2 Purpose................................................................................................. 2
3 Are focus areas for OH&S and Process Safety the same............................... 2
4 Why do we need PSM........................................................................... 3
5 Statistics................................................................................................ 5
6 PSM Challenge...................................................................................... 6
7 Process Safety Management (PSM)...................................................... 6
8 PSM at GPIC......................................................................................... 7
9 How we measure our PSM Performance............................................ 26
10 Inadequate PSM impacts all stakeholders.......................................... 28
Process Safety Management
1.0 DESCRIPTION
1.1 What is Process Safety?
• A management system to help prevent major incidents
• Essential for managing complex chemical operations
• Process Safety focuses on:
-- Technology
-- Facilities
-- Personnel
1.2 Process Safety Management (PSM)
Is the proactive identification, evaluation and mitigation or prevention of chemical releases that could occur as a
result of failures in processes, procedures, or equipment?
2.0 PURPOSE
• Prevent Catastrophic Releases of Highly Hazardous Chemicals
• Minimize Consequences of Such Releases to Employees and the Community
3.0 Are focus areas for OH&S and Process Safety the same?
• OH&S codes and standards do not specifically address issues related to Process Safety. In part, this is because OH&S
risks are typically of higher frequency and lower consequence than process risks. Indeed, their focus is different.
• Occupational Health & Safety • Process Safety Management
-- Focus: Eliminate harm to people, assets and the environment -- Focus: Eliminate process related incidents
2
Process Safety Management
• March 6, 2007
Explosion and Fire at Formosa Plastics Illinois, USA
3
Process Safety Management
5.0 STATISTICS
Other 32%
Mechanical
Integrity 44%
5
Process Safety Management
• PSM should form an integral part of an organization’s safety culture, but the tendency in a large number of
companies is to focus on personal safety.
• Near Miss reports, more often than not, highlight slips, trips and falls, rather than hydrocarbon releases, fires,
overdue inspections/maintenance and close out of HAZOP action items.
Plants with limited personnel accidents become considered “safe”.
6
Process Safety Management
Identifying the equipments which involves storage and handling of Highly Hazardos Chemicals
(HHC) or flammable liqids and gases above a specified quantity.
PSM Elements
1. Employee Participation (EP) 8. Mechanical Integrity (MI)
2. Process Safety Information (PSI) 9. Hot Work Permit (HWP)
3. Process Hazard Analysis (PHA) 10. Management of Change (MOC)
4. Operating Procedures (OP) 11. Incident Investigation (II)
5. Employee Training (ET) 12. Emergency Planning and Response (EPR)
6. Contractors (CO) 13. Compliance Audit (CA)
7. Pre-Startup Safety Review (PSSR)
7
Process Safety Management
Employee
Competence Audit
Participation
Incident
Investigation PSM Process Hazard
Management
Elements Analysis
Of Change
Operating
Procedures
Hot Work Permit
Employee Training
Mechanical
Integrity
Pre-Startup Contractors
Safety Review
8
Process Safety Management
9
Process Safety Management
10
Process Safety Management
• Controling Documents
-- Standard Operating Procedures -- Complex Emergency Procedure
-- Standing Instructions -- Material Safety Data Sheets
-- Plant Trip Logic Diagrams -- Relevant P&IDs
-- Permit to Work Procedure -- Relevant Vendor Manuals
INDEX
S No. Topic
1 Purpose.
2 Scope.
3 Description.
4 Safety, Health and Environment related Information.
5 Requirements.
6 Preparations to Start
7 Start-up.
8 Shutdown.
9 Operating Limits, Deviations, & Corrective Actions.
10 Equipment & Instruments in the section.
11
Process Safety Management
8.2.6 Contractors
The element requires that contractors performing maintenance, repairs,
turnaround activities, major renovation work or specialty work on the
process or adjacent to the process shall be well trained in carrying out the
intended work and shall be informed about the known potential hazards
related to the work and/or the process involved.
• GPIC Compliance
GPIC’s direct hire and/or lump sum contractors go through a selection
process that starts from contractor pre-qualification assessment, trade
testing, rental equipment physical verification, and safety induction
12
Process Safety Management
training, on the job assessment, weekly contractor safety meetings and post service evaluation.
Contractors performing maintenance within the process areas are apprised of the hazards during the safety induction
training and regular Tool box talk.
• Controlling Documents
-- Establishing and Managing Approval Suppliers List
-- Contractor Prequalification Requirements
-- Contractor Services Management
-- Contractor / Vendor Performance Evaluation Form
13
Process Safety Management
14
Process Safety Management
Integrity. Section A gives an overall view about Mechanical Integrity and Section B gives the minimum requirement to
ensure the integrity of the identified Critical Equipment List that was derived after adopting the PSM standard at GPIC
The PSM standard applies specifically to processes which involve storage and handling of Highly Hazardous chemicals
(HHC) or flammable liquids and / or gases above a specified threshold quantity as specified in OSHA Standard.
This list has been drawn up based upon the criteria that failure of any listed equipment, along with their associated
safety protection devices, could reasonably cause a catastrophic release of one or more of the following listed
chemicals or gasses:
• Ammonia: Hold up more than 4535.9 kg;
• Ammonia Water Solution (conc >44%): Hold up more than 6808 kg;
• Hydrocarbon fuels-Gasoline/Diesel for vehicle refueling: Hold up exempted from PSM.
Section A:
Scope:
This procedure relates to the mechanical integrity of process equipment, as identified in the Critical Equipment List.
The list contains the following types of equipment:
• Pressure vessels and storage tanks;
• Piping systems (including piping components such as valves);
• Relief and vent systems and devices;
• Emergency shutdown systems
• monitoring devices and sensors, alarms, and trip logic
• Instrument valves including control valves;
• Emergency Response Equipment
15
Process Safety Management
Responsibilities
Given the broad scope of the equipment covered and the requirement of ensuring the mechanical integrity of the
critical equipment listed, it is the responsibility of the Operation, Maintenance, Technical Services, Training and
Development and SHE Superintendents, and any other related superintendent(s) to ensure this procedure is correctly
applied in their areas of responsibility.
Definitions
Owner: The plant superintendent responsible for operating the identify critical equipment
Craft: The maintenance and inspection superintendents responsible for the integrity of the identified critical equipment,
establishing the Preventive maintenance frequency and establishing the stock level requirements.
Reference
Process Safety Management of Highly Hazardous Chemicals – 1910.119 (PSM).
Maintenance Procedures:
Each relevant section head in GPIC is required to develop comprehensive procedures, the purpose of which is to
maintain the ongoing integrity of process equipment within
their area of responsibility. A list of equipment types must be developed in each related section indicating the
applicable procedure numbers for that equipment.
Some maintenance work is undertaken by the operations department. This work, such as oil top up equipment
monitoring etc. is undertaken on routine basis as per the ongoing procedures of each applicable section.
Maintenance work is carried out by the maintenance sections through the work request system (SAP), administered
by the maintenance Planning Section.
All work requests are initiated either manually (corrective maintenance) or automatically (preventive maintenance).
16
Process Safety Management
Work order management is implemented by the maintenance planning section through the application of, Maintenance
Work Order Management.
The preventive maintenance system is implemented by the maintenance planning section through the application of,
Preventive Maintenance Management.
Adequate spare parts are made available for proper maintenance of process equipment. Material Management,
describes the process of setting up and reviewing spare parts
requirements.
Stock Levels Management, describes how maintenance spare parts stock levels are established and maintained.
Training:
Each section head, within his area of responsibility, will ensure that maintenance activities on process equipment are
carried out by suitably competent personnel.
Such personnel will be competent to undertake the technical aspects of the job task. Such personnel will have
undergone training in an overview of the process in which the
equipment is located, along with the hazards and procedures applicable for the safe
performance of the job task. Such refresher training must be undertaken for all relevant personnel at least every
three years, Refresher Training for Staff Involved in Plants Operation & Maintenance.
17
Process Safety Management
Equipment Deficiencies:
Where equipment deficiencies are identified, such as material out of tolerance, calibration errors etc., actions must
be taken to rectify the deficiency in a time frame and manner dependent upon the potential impact of the deficiency
identified. Such actions will be agreed by the relevant personnel at the operations morning meeting. If the deficiency
is considered to be an immediate risk, then the relevant manager(s) and superintendent(s) are informed and an ad-
hoc meeting convened to determine the appropriate course of action. The equipment owner is responsible to invoke
such emergency response as is deemed adequate.
18
Process Safety Management
Normally, calibration errors / instrument malfunctions are addressed immediately. Where this cannot be achieved,
then the requirements of Standing Instruction, Override
of plant / equipment trip systems / long term overrides / instrument trip system settings, must be followed.
Where deficiencies of a mechanical or electrical nature are identified, the relevant Plant owner/superintendent
(where the equipment failed) is to be advised of the appropriate course of corrective action by the relevant section
head (maintenance, inspection, engineering, SHE etc.). Where the proposed corrective action does not comply with
standard codes and practices, such actions must be approved through the application of Management of change.
Quality Assurance:
All modifications and additions to plant and equipment and capital expenditure (capex) projects must be implemented
through the application and controls of the following procedures:
• Implementation of capital projects.
• Management of change.
• Inspection of new static equipment.
Section B
Mechanical integrity minimum assurance level requirement
As stated above, given the broad scope of the equipment covered, and to ensure the ongoing mechanical integrity
of the identified Critical Equipment, below are the minimum requirement and concepts to ensure the ongoing
mechanical integrity:
1- The identified Critical Equipment List is the most critical from safety and hazardous material release point of view
and therefore; they require most focus and attention during operation and maintenance activities.
19
Process Safety Management
2- Each Plant Owner is responsible to ensure the safe operation of the items under his jurisdiction. Planning Section
have identified the PSM equipment in the SAP system. For any required corrective maintenance (CM), it is the
Owner responsibility to ensure the appropriate and justified priority is logged during raising the said notification
to ensure attending the same on TOP PRIORITY. All Quality documents maintenance procedures associated with
the integrity of the equipment as indicated in section (J-2) above are to be revalidated and reissued (if needed)
to reflect the CM review .
3- The Preventive Maintenance (PM) are set by the Craft and it reflects the level of attention required to ensure the
ongoing integrity of the equipment. The revalidation and review of PM are to be done every 2 years and after
every turnaround for non- turnaround and turnaround equipment respectively.
4- Maintaining the record required to demonstrate that all equipment’s PM/CM are done in accordance with the
established procedures is the responsibility of relevant Craft.
5- The Craft is responsible for ensuring appropriate level of stock (spare parts) are available to conduct the PM and
CM activity in an effective and timely manner. The stock level review should be part of the PM revalidation as
indicated in points 2&3 above. The guidelines to be followed for ensuring the minimum stock levels for spares of
the PSM Critical Equipment List are as below;
20
Process Safety Management
Examples:
We have selected two PSVs from the PSM critical PSV list and have elaborated the spares assessment based on the
above matrix.
5.2 PSM Critical Instrument valves and mechanical isolation valves 100% spare internals are required for every
PSM critical valve
5.3 PSM Critical Analyzers/ detectors
Consumables are required to maintain the analyzers/ detectors.
5.4 PSM Critical Instrument transmitters/ trip switches Minimum one spare for common trip switches/
transmitters.
5.5 PSM Critical Level glasses
Consumables are required to maintain the level glasses.
21
Process Safety Management
22
Process Safety Management
PHA
Screening Egfineering
Raise Rfc Implementation Implementation
& Processing & Approvel
23
Process Safety Management
Reporting
the incidenth
Minor
Incident
Reviews the
Incident
Serious
Incident
Interim Final
Report Report
Investigating Team
24
Process Safety Management
25
Process Safety Management
26
Process Safety Management
Mechanical A-TO ensure no overdue inspection A-Number of overdue zero INS close follow up and reminders by ins
integrity (MI) items for more than one month inspection
B-TO ensure no system challenges B-The Number of challenges Zero over INS/ Monthly review of the trip override log to
overdue for more than 14 days to automated safety devices , 14 days Haya ensure compliance
such as Number of trip old
HOT WORK To close out Hot Ptw violations within Number of outstanding hot ptw zero ENUS Regular review of the accident / invcident
PERMIT (HWP) 7 days violations data base to ensure compliance
Management of Technical committee to approve all Number of outstanding MOC zero ENS/ Weekly status of capex and RFCS IS Sent
change(Moc) moc request within two months from Related to critical equipment reem al by ENS
receiving the RFC otaibi
Incidents TO Close OUT ALL in cadent The Number of outstanding Zero fsst Regular review of the accident /incident
investigation (II) investigation recommendations PSM within data base to ensure compliance
within 7days incident recommendations 7days
Emergency Number of PSM emergency 4 per year Fsst Issue the annual mock drills schedule
planning & To conduct the annual planned psm mock drills carried out Follow up with consumed fsss the mock drill
response(EPR) Emergency mock DrillS execution
Follow up and address any raised
recommendation/short comes
Raised from the drills
Compliance To close all issues raised in the PSM Number of pending NCRS OR zero MSS Issuing the yearly PSM audit schedule. close
Audits (CA) audits , i.e NCRS OR OAIS WITH IN OAiS follow up with internal auditors to ensure the
30 DAYS audits are conducted as per schedule
Close follow up with audited to ensure al
audits findings are addressed and closed with
30 days of issuing
27
Process Safety Management
• Environment
28
Process Safety Management
29
Standard Operating Procedure
30
Standard Operating Procedure
1.0 Purpose
For the reference and guidance of the Urea Plant Operations personnel in start-up, shut down and normal and
emergency operation of cooling water system. The following operational practices have proven to be appropriate in
start-up and shutdown of such systems.
2.0 Scope
To start up, shutdown and carry out normal operations of the cooling water system in the Urea Plant.
3.0 DESCRIPTION
Parameters recommended for the CW:
pH : 8.5 ~ 10.5
Conductivity : < 6500 mcs
Chloride : < 200 ppm
NO2 : 500 ~ 700 ppm
Iron : < 3.0 ppm
Bacteria level : < 1000 Colonies/ml
Dosing frequency is adjusted according specialists recommendations.
31
Standard Operating Procedure
32
Standard Operating Procedure
33
Standard Operating Procedure
Repeated or prolonged exposure may Get medical attention, Remove to fresh air,
Inhalation
irritate respiratory tract treat symptomatically
34
Standard Operating Procedure
5.0 REQUIREMENTS
1- Sea water is available from Utilities Plant.
2- Desalination water is available from Utilities Plant.
3- Electrical power is available.
4- NALCO.
NOTE
All the high point vents must be ensured to be clear & not blocked as this will cause vapor lock and charging
of circuit will be improper that can cause damage to lines
CAUTION
Special care needs to be taken while lining up the plate exchangers to ensure that CW & SW
sides are pressurized almost simultaneously to avoid one side pressurization that may cause a
failure of the gaskets between the plates in the plate pack
36
Standard Operating Procedure
NOTE
1- Each of these four Plate Heat Exchangers are cleaned by chemical cleaning that is done occasionally
by engaging a specialized external contractor. The major steps involved in such cleaning are typically:
• Water Flushing
• Degreasing
• Acid Pickling
• Neutralisation
• Flushing
• Passivation
Specific procedure given by contractor for such chemical cleaning is agreed & approved by GPIC prior to
its use by the contractor
2- Each of the four Plate Heat exchangers are re-gasketted periodically when it is sent to a specialized
approved vendor where complete plate pack is opened, inspected, cleaned chemically & by hydrojet,
re-gasketted using new set of gaskets, assembled, pressure tested & then put in position for service
NOTE
Nalco 71-D5 dosing to be done as fast as possible for shock dosing effect. If full charge of chemical (5 Kg)
is not available, do not dose to the FCW system
37
Standard Operating Procedure
CAUTION
This check to be performed only during Urea Plant Total Shutdown and upon
instruction from Urea Shift Supervisor.
CAUTION
Check & ensure that the standby pump is kept on Auto mode for auto start in case required.
38
Standard Operating Procedure
39
Standard Operating Procedure
40
Standard Operating Procedure
41
Standard Operating Procedure
Tag No Location
42
Standard Operating Procedure
43
Standard Operating Procedure
44
Standard Operating Procedure
Responsibilities
References
P&ID
MSDS Material safety data sheets
45