Roll No 13 Estimate and Costing Micro Project - Excel-Sheet

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
502 views16 pages

Roll No 13 Estimate and Costing Micro Project - Excel-Sheet

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 16

Widht/

Length
Sr. No. Item Description No. Breadth
(m)
(m)

1
Earthwork in Excavation in
Foundation:

Footing (1m x 1m) 15 1.30 1.30


L \ W = 1 + 0.15 + 0.15 = 1.3
Depth From GL = 2.19 m

2 PCC in Foundation

L / W = 1.3 m H = 40 mm (0.040 m) 15 1.3 1.3

3 Footing
L / W = 1 m H = 150 mm (0.150 m) 15 1 1

4 RCC Column

Size = 230 mm x 230 mm 15 0.23 0.23


H = 2.93 m (up to Plinth)

5 RCC Beam at Ground Level

Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23


Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23

6 DPC at Plinth Level

Beam - 1 w = 0.23, L = 3.12 m 5 3.12 0.23

Beam - 2 w = 0.23, L = 3.80 m 5 3.8 0.23

Beam - 3 w = 0.23, L = 1.96 m 3 1.93 0.23

Beam - 4 w = 0.23, L = 3.52 m 3 3.52 0.23


Beam - 5 w = 0.23, L = 3.79 m 3 3.79 0.23

Beam - 6 w = 0.23, L = 3.28 m 3 3.28 0.23

7 RCC Column in Superstructure

Column (230 mm x 230 mm) 15 0.23 0.23

H = 3.98

8 RCC Beam at Slab Level

Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23


Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23
Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23
Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23
Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23
Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23
9 RCC Slab (1:1.5:3)

L = 13.26 m, W = 7.16 m 1 13.26 7.16


Thickness = 150 mm

Deduction
Column (230 mm x 230 mm) 3 0.23 0.23
H= 0.125 m

Beam
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23
Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23
Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23
Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23
Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23
Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23

Total Deduction

Slab Qty after Deduction =


11.87 - 1.17 = 10.70 cu. m

10 Earthfilling up to plinth

L = 13.26 m W = 7.16 m 1 13.26 7.16

Deduction:
Beam and Wall
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23
Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23
Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23
Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23
Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23
Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23

Actal Earthwork =
88.68 - 7.53 = 81.14 m

11 Brick Wall GL to PL

Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23


Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23
Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23
Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23
Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23
Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23

11 Brick Work in Superstructure

Wall - 1 6 3.12 0.23


L = 3.12 m, W = 0.23 m, H = 3m
Wall - 2
L = 3.80 m, W = 0.23 m, H = 3m 4 3.8 0.23
Wall - 4
L = 1.96 m, W = 0.23 m, H = 3m 2 1.96 0.23
Wall - 4
L = 3.52 m, W = 0.23 m, H = 3m 3 3.52 0.23
Wall - 5
L = 3.79 m, W = 0.23 m, H = 3m 3 3.79 0.23
Wall - 6
L = 3.28 m, W = 0.23 m, H = 3m 3 3.28 0.23
Wall - 7
L = 3.12 m, W = 0.23 m, H = 3m 3 3.12 0.23
Extra Wall
L = 2.29 m, W = 0.23 m, H = 3m 1 2.29 0.23

Deduction of Door & Window:


Door :
D = (1.2 x 2.1 m) 2 1.2 0.23
L = 1.2 m,W = 0.23 m, H = 2.1 m
D2 = (1.0 x 2.1 m) 2 1 0.23
L = 1.0 m,W = 0.23 m, H = 2.1 m
D3 = (0.82 x 2.1 m) 3 0.82 0.23
L = 0.82 m,W = 0.23 m, H = 2.1 m

Window:
W1 = ( 1.5 x 1.05 m) 1 1.5 0.23
L = 1.5 m, W = 0.23 m, H = 1.05 m

Ventilation 2 0.6 0.6


L = 0.60 m, W = 0.23, H = 0.60

Parking Opening 1 3.17 0.23


L = 3.17 W = 0.23 H= 3

Actual Qty= 52.27 - 5.92 = 49.87 cu. m


13 Parapet Wall

Long wall, L = 13.72 m, W =0.15 2 13.72 0.15


Height = 0.90 m

Short Wall, L = 7.62 m, W = 0.15 2 7.62 0.15


Height = 0.90

Deduction:
Column:
L = 0.23 W= 0.15 m, H = 0.98 m 15 0.23 0.15

Atual Brick work = 6.27 - 0.47 = 5.81m


Height/
Depth Quantity
(m)

2.19 55.52 cu m

0.04 1.01 cu m

0.15 2.25 cu m

2.93 2.32 cu m

0.23 0.83 cu.m


0.23 1.01 cu.m

0.23 0.31 cu.m

0.23 0.56 cu.m

0.23 0.60 cu.m

0.23 0.52 cu.m

Total 3.82 cu.m

3.59 sq.m

4.37 sq.m

1.33 sq.m

2.43 sq.m
2.62 sq.m

2.26 sq.m

Total 16.60 sq .m

3.98 3.16 cu.m

0.23 0.83 cu.m

0.23 1.01 cu.m

0.23 0.31 cu.m

0.23 0.56 cu.m

0.23 0.60 cu.m

0.23 0.52 cu.m

Total 3.82 cu.m


0.125 11.87 cu.m

0.125 0.02 cu.m

0.15 0.32 cu.m

0.15 0.39 cu.m

0.15 0.07 cu.m

0.15 0.12 cu.m

0.15 0.13 cu.m

0.15 0.11 cu.m

Total 1.15 cu.m

al Deduction 1.17 cu.m

10.70 cu.m

0.934 88.68 cu.m

0.984 2.12 cu.m

0.984 2.58 cu.m

0.984 0.44 cu.m


0.984 0.80 cu.m

0.984 0.86 cu.m

0.984 0.74 cu.m

7.53 cu.m

81.14 cu.m

0.704 2.53 cu.m

0.704 3.08 cu.m

0.704 0.94 cu.m

0.704 1.71 cu.m

0.704 1.84 cu.m

0.704 1.59 cu.m

11.68 cu.m

2.85 12.27 cu.m

2.85 9.96 cu.m

2.85 2.57 cu.m

2.85 6.92 cu.m


2.85 7.45 cu.m

2.85 6.45 cu.m

2.85 6.14 cu.m

2.85 1.50 cu.m

53.27 cu.m

2.1 1.16 cu.m

2.1 0.97 cu.m

2.1 1.19 cu.m

1.05 0.36 cu.m

0.23 0.17 cu.m

2.85 2.08 cu.m

Total 5.92 cu.m

47.35 cu.m
0.98 4.03 cu.m

0.98 2.24 cu.m

Total 6.27 cu.m

0.9 0.47 cu.m

5.81 cu.m