Lesson 8 Line Balancing
Lesson 8 Line Balancing
Line Balancing
6-1
GOAL OF LINE BALANCING
• To obtain task groupings that represent
approximately equal time requirements.
• This minimizes the idle time along the line and
results in a high utilization of labor and
equipment.
• Lines that are perfectly balanced will have a
smooth flow of work as activities along the
line are synchronized to achieve maximum
utilization of labor and equipment
Major obstacles to attaining a
perfectly balanced line
• It may not be feasible to combine
certain activities into the same bundle,
either because of differences in
equipment requirements or because the
activities are not compatible.
• Differences among elemental task
lengths cannot always be overcome by
grouping tasks.
• The required technological sequence
may prohibit otherwise desirable task
combinations.
6-6
Maximum cycle time is given by the summation
of the task times.
OT
Output rate =
CT
OT
CT = cycle time =
6-10
D
A very useful tool in line balancing is a
precedence diagram. A diagram that shows
elemental tasks and their precedence
requirements.
Precedence Diagram
Figure 6.11
c d e
0.7 min. 0.5 min. 0.2 min.
6-12
Determine the Minimum Number
of Workstations Required
( t)
N=
CT
t = 2.5 mins
Example 1: Assembly
Line Balancing
• Arrange tasks shown in Figure 6.11 into
three workstations.
– Use a cycle time of 1.0 minute
– Assign tasks in order of the most number of
followers
6-15
Example 1 Solution
Revised
Time Assign Time Station
Workstation Remaining Eligible Task Remaining Idle Time
1 1.0 a, c a 0.9
0.9 c c 0.2
0.2 none – 0.2
2 1.0 b b 0.0 0.0
3 1.0 d d 0.5
0.5 e e 0.3 0.3
0.3 – – 0.5
6-16
Calculate Percent Idle Time
6-17
0.5
Percent idle time = *100% 16.7%
(3)(1.0)
6-21
Example
A manager wants to assign workstations in such
a manner that hourly output is 4 units.
Working time is 56 minutes per hour. What is
the cycle time?
Numbers above
the circles indicate
task times
Steps:
1) Arrange the task in the decreasing order of positional weights.
2) Find out the number of workstations
11
Percent idle time = *100% 19.64%
(4)(14)
Homework
A shop wants an hourly output of 33.33 units
per hour. The working time is 60 minutes per
hour. Assign the tasks using the rules:
Bottleneck
Theoretically, the line should be able to
produce at 60 units per hour.
6-30