FABTECH PROJECTS AND ENGINEERS LTD
RECORD OF CLEARENCE FOR HYDROTESTING
Report No.:FPEL/CFH/R-02 Date.:
Name of Project.: BIO REFINERY PROJECT
Client.: M/s ASSAM BIO REFINERY PVT LTD.
Consultant.: M/s ARYA ENGINEERS AND CONTRACTORS PVT.LTD.
Contractor.: M/s FABTECH PROJECTS AND ENGINEERS LTD
TANK NO: FERMENTER-125-RB-0001-B TEST PACKAGE NO:
SIGNATURE
S No ACTIVITY DESCRIPTION CHECKS REMARKS
FABTECH TPI/AECPL
A MECHANICAL CLEARENCE
Completeness of Drawing(FPRO-535-DR-125-W-
1 0001-B-0001,REV-7 )
COMPLETED
2 Fit-up OK
3 Installation as per Drawing OK
4 Correctness of installation of Shell OK
a Valves NA
b Strainer NA
c Flange joints COMPLETED
d Level guages NA
5 Supports OK
6 Vents/Drains NA
7 Tapping for instruments OK
8 Expension bellows NA
9 Earthing OK
10 Rf Pad Pneumatic Test OK
11 seal welding of screwed connection OK
12 Cold pull,if any NA
13 Flange box-up OK
14 Liquidation of checklist point OK
15 Pre-hydro test punch list DONE
B WELDING/NDT CLEARENCE
1 Weld Visual OK
2 PWHT/Hardness NA
3 DPT/MPT OK
4 Radiography OK
5 Positive Material Identification OK
6 Tank joint History sheet OK
C WATER FILLING CLEARENCE
1 Liquidation of Pre hydrotest point OK
Removal of NRV/CV/Instrument/ Rupture
2 OK
disc/Strainer mess
3 Location of Test Pump OK
4 Post hydrotest punch list(note-1) NA
FABTECH TPI/AECPL
Sign: Sign:
Date: Date:
Name: Name: