Liu - 2018 - IOP - Conf. - Ser. - Mater. - Sci. - Eng. - 423 - 012026
Liu - 2018 - IOP - Conf. - Ser. - Mater. - Sci. - Eng. - 423 - 012026
LIU Chen yang1, a, LIU Jun yan1, 2, b, WU Yong zhen3, c,LIU Yong4, d
1
School of Civil Engineering and Architecture, University of Jinan, Jinan 250022,
China
2
The engineering technology research center for urban underground engineering
supporting and risk monitoring of Shandong Province
3
China Railway NO.3 Engineering Group Co., Ltd.The Fifth Engineering Co., Ltd
4
Ji'nan Ding Hui Civil Engineering Technology Co., Ltd
a
[email protected], b [email protected], c [email protected],
d
[email protected]
1. Introduction
According to statistics, as of December 31, 2017, the total length of subway lines in China has reached
3894.2 km, and China has become the largest urban rail transit construction market in the world [1].
The underground space is becoming "congested", there are many adjacent excavation projects around
the subway tunnel. The excavation unloading is bound to cause the change of the stress field and
displacement field of the subway tunnel, which causes the additional internal force and deformation of
Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
ICAMMT 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 423 (2018) 012026 doi:10.1088/1757-899X/423/1/012026
1234567890‘’“”
the tunnel structure, and seriously threatens the safety of the subway, Burford[2] first reported the
engineering case of tunnel excavation over 27 years' cumulative uplift 50mm above the subway tunnel;
Chang[3] and so on analyzed the damage of the tunnel structure caused by a subway tunnel in Taipei
due to the excavation of the adjacent foundation pit. So it is very important to understand the
deformation characteristics and internal force distribution of existing subway tunnel during
excavation[4].
For the deformation of existing tunnels caused by excavation,many experts and scholars have
carried out a lot of research work. Zhang Junfeng et al. [5]used Boussinesq solution to analyze soil
deformation caused by excavation unloading of foundation pits,considered the space-time effect of
soft soil deformation and proposed a calculation method for predicting tunnel uplift volume;Huang
Hongwei et al [6] combined with the foundation pit engineering of the Shanghai Bund, adopted the
finite element software PLAXIS-GID for numerical simulation and analyzed the tunnel deformation
law under different reinforcement measures. The above research results mainly take the typical soft
soil area such as Shanghai as the engineering background, but the similar problems under other
geological conditions are not enough. In this paper, based on the construction of the close pit
excavation above the subway tunnel, the deformation law of the tunnel under typical excavation
conditions is studied, and the control effect of the reinforcement measures is analyzed. At the same
time, the reinforcement effect is verified through the data of field monitoring.
2. Background
The total length of an entrance/exit line at R3 line of Jinan rail transit is 1033.5m, and the depth of the
foundation pit is 3.8~103.1m. At the bottom of the foundation pit is the subway shield tunnel
completed in advance. The southern section of the pit crosses with the left line of the existing tunnel.
The angle between the direction of the foundation pit and the tunnel is 15°, and the minimum distance
from the bottom of the tunnel to the tunnel is only 1.8m. The project is located in the landform area of
low hills and hills and the strata from top to bottom involve 1-1 prime fill, 17-1 gravel soil and 21- 2
weathered limestone. The depth of foundation pit excavation is about 9.4m, and the width is about
12.85m. Slope and anchor are selected for supporting. The slope rate is 1:0.5. The length of the anchor
is 5m~8m, the horizontal distance is 1.5m, vertical distance is 2m.The plane position of foundation pit
and subway tunnel is shown in figure 2-1, and the position of section is shown in figure 2-2. The main
physical and mechanical parameters of the formation are shown in Tab.2-1.
Fig. 2-1 Plane position relation diagram Fig.2-2 Profile position relation diagram
Tab. 2-1 Formation parameter value
Internal
Serial Compression Poisson
Thickness Bulk density Cohesive friction
number Item modulus ratio
(m) γ(kN/m3) forceϲ(kPa) angle
Es (MPa) υ
φk(°)
Prime fill
1 11 18.9 - - 26 16.3
(1-1)
Gravel
2 7.9 21.0 4.8 0.18# 27 15
soil(17-1)
Weathered
3 limestone 17.5 26.9 7.5 0.21# 48 20
(21-2)
(Notice:“#” Indicates that the value takes empirical value.)
2
ICAMMT 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 423 (2018) 012026 doi:10.1088/1757-899X/423/1/012026
1234567890‘’“”
Fig. 3-1(a) Stress balance state before excavation Fig. 3-1(b) Stress imbalance after excavation
4. Numerical analysis
3
ICAMMT 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 423 (2018) 012026 doi:10.1088/1757-899X/423/1/012026
1234567890‘’“”
Fig. 4-2 Vertical displacement of the foundation Fig.4-3 Vertical displacement cloud of the tunnel
pit
E
x
c
a
v
a
t
e
1
s
u
p
p
o
r
t
1
2
5
E
x
c
a
v
a
t
e
2
s
u
p
p
o
r
t
2
E
x
c
a
v
a
t
e
3
s
u
p
p
o
r
t
3
2
0
E
x
c
a
v
a
t
e
4
s
u
p
p
o
r
t
4
P
i
t
b
o
t
t
o
m
1
5
m
m
コ
」
t
i
5
1
0
n
U
0
-
1
0
0
-
8
0
-
6
0
-
4
0
-
2
0
0i
2
0
4
0
6
0
8
0
1
0
0
U
n
t
:
m
Fig.4-4 shows the comparison between before and after deformation of the tunnel and Fig.4-5
shows the tunnel vertical uplift changes diagram at different stages of foundation pit excavation. It can
be seen from the diagram that with the increase of excavation depth, the uplift of the tunnel under the
foundation pit increases gradually, and the maximum uplift is located directly below the foundation pit
4
ICAMMT 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 423 (2018) 012026 doi:10.1088/1757-899X/423/1/012026
1234567890‘’“”
in the cross span section. Taking the location as the axis center, the uplift of the tunnel gradually
decreases to both sides, and is approximately symmetrical about the axis. When the foundation pit is
excavated to the bottom at the last step, the vertical displacement of the tunnel exceeds the control value.
P
r
o
t
e
c
t
i
v
e
m
e
a
s
u
r
e
s
2
0
1
5
m
m
コ
」
5
1
0
t
i
n
U
0
Es
xu
c
ap
vo
ar
t
et
11
Es
xu
c
ap
vo
ar
t
et
2 2c
Es
x ua
c
a pi
v n
ao
t
et
3 n
Es
x uo
c
a pn
vo
ar
t
et
44
P
i
t
b
o
t
t
o
m
p
pt
rc
3
p
E
x
a
v
o
o
d
i
t
i
Fig.4-7 Vertical displacement cloud of the tunnel Fig.4-8 Vertical displacement of the tunnel
Fig.4-8 shows the comparison of the maximum vertical displacement of the tunnel after excavation
with or without protective measures. It can be seen from the graph whether tunnel protection measures
are taken or not, the trend of the tunnel uplift is roughly consistent in the excavation process. After the
reinforcement scheme was adopted, the maximum uplift of the tunnel was reduced from the 14.37mm
to 4.86 mm, and the protective effect was obvious, which can greatly reduce the safety risk of the
subway tunnel in the construction process of the foundation pit.
5
ICAMMT 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 423 (2018) 012026 doi:10.1088/1757-899X/423/1/012026
1234567890‘’“”
uniform. When the foundation pit is excavated to the bottom of the pit, the numerical calculation result
of the tunnel dome settlement is 4.86 mm, and the actual field measurement result is 3.04 mm, with a
small difference. The convergence results of both tunnels are relatively small, but the measured data
are in a negative and changing state, and there is no obvious change rule, which is not consistent with
the numerical results.
3
0 .
.
N
u
m
e
r
i
c
a
l
s
i
m
u
l
a
t
i
o
n
5
N
u
m
e
r
i
c
a
l
s
i
m
u
l
a
t
i
o
n
2 2
5 .
M
e
a
s
u
r
e
d
d
a
t
a
M
e
a
s
u
r
e
d
d
a
t
a
4
0 .
1 1
5 .
3
0 .
m
2
m m
:
0 0
5 .
m t
i
n
1
:
t
i U
0 .
n
U
0
-
0 -
5 .
1 -
0 .
1
1
5
-
E
x
c
a
v
a
t
e
1
E
x
c
a
v
a
t
e
3
E
x
c
a
v
a
t
e
2
E
x
c
a
v
a
t
e
4
E
x
c
a
v
a
t
e
1
E
x
c
a
v
a
t
e
1
E
x
c
a
v
a
t
e
1
E
x
c
a
v
a
t
e
1
P
i
t
b
o
t
t
o
m
P
i
t
b
o
t
t
o
m
s
u
p
p
o
r
t
1
s
u
p
p
o
r
t
3
s
u
p
p
o
r
t
2
s
u
p
p
o
r
t
4
s
u
p
p
o
r
t
1
s
u
p
p
o
r
t
1
s
u
p
p
o
r
t
1
s
u
p
p
o
r
t
1
6. Conclusion
(1) The displacement field of the original soil is changed by the influence of the excavation of
foundation pit. The displacement of the existing tunnel below the foundation pit is upward by the
influence of its overall impact. And the largest displacement is located at the bottom of the foundation
crossing the crossing section.
(2) Calculations show that in the process of construction of the foundation pit, protective measures
such as loading at the bottom of the pit and grouting reinforcement of soil around the tunnel can
effectively reduce the amount of tunnel uplift and greatly reduce the safety risk of the existing tunnel.
(3) Compared with the results of numerical simulation and measured data, the horizontal
displacement of tunnel is small, and the excavation of foundation pit has little influence on it. The
horizontal displacement data of tunnel is disorderly, and there is no obvious deformation rule.
(4) For complex geotechnical problems, numerical calculation can effectively predict the actual
engineering deformation problems and provide some reference for field construction.
Acknowledgments
The author would like to thank for the support from the Key R & D project in Shandong
Province(project number 2018GSF120010), Jinan Science and Technology Project(project number
201705015), Planning project of Shandong Provincial Construction Department(project number
KY011).
References
[1] Feng Aijun,Lu fang.Statistics of urban rail transit in mainland China, 2017[J]. Tunnel
Construction(Chinese-English), 2018, 38(3): 514-517.
[2] Burford D.Heave of tunnels beneath the shell center,London,1959-1986[J]Geotechnique,
1938,38(1):135-137.
[3] Chang C T, Sun C W, Duann S W, et al. Response of a taipei rapid transit system (TRTS)
tunnel to adjacent excavation[J]. Tunnelling & Underground Space Technology
Incorporating Trenchless Technology Research, 2001, 16(3): 151-158.
[4] Liu Siqin,Yu Xiaolin, YAN Quansheng. Numerical simulation analysis for influence of overhead
excavation on existing MTR[J]. Guangdong Architecture Civil Engineering, 2009(6): 19-20.
[5] Zhang Junfeng, Wang Jianhua, Wong Qipinf..Nonlinear rheological analysis on tunnel
displacement induced by adjacent excavation in soft clay[J].Journal of
Civil,Architectural&Environmental Engineering, 2012, 34(3): 10-15.
6
ICAMMT 2018 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 423 (2018) 012026 doi:10.1088/1757-899X/423/1/012026
1234567890‘’“”