PVTRANS SHIP MANAGEMENT SECTION 2 : Additional control measures
STANDARD TASK BASED RISK ASSESSMENT Hazard no. Further action necessary to reduce the Risk of Harm
Work activity being assessed :
AUX. GENERATOR ENGINE: OVERHAUL CYLINDER HEAD, PISTON UNIT 1 To confirm bridge weather forecast to be checked.
SECTION 1 : Hazards 2
Hazard Description of identified hazards 3 Procedures to be discusses among all engineer prior commencement
No. 4 Good communication/co-ordination/job allocation must be without fail
1 Wheather condition 5 The area must be repeatedly cleaned to keep it oil free and dry
2 Possibility of staff getting hurt in absence of PPE 6
3 Possibility damages in case Maker's procedures are not followed 7 E/R lifting block to be only used by responsible engineer
4 Communication/Co-ordinations. Safety notices. Job allocation 8
5 Cleaniness of working areas
6 Hydraulic hoses, jacks, pump and all other associated tool proper functioning
7 Lifting appliances Additional comments:
8 Key items like L.O pump, starting air system isolated All the Engineers & Motormen are aware of Risk Assessment done for the task.
And Risk Assessment is reviewed & monitored regularly depending upon the level of risk.
The job can start.
Existing control measures:
Hazard Control measures Assessement review date
No.
1 Weather forecast to be checked if likely to detenorate additional measures to be taken
2 To ensure all staff allocated for this job has proper PPE
3 To discuss in tool box meeting, photocopy of procedures to hand over to staff
4 Good communication job allocation notice on to be done
5 The area must be maintained clean to void slipping
6 Visual (if possible operational) check on these item to be done prior starting
7 Visual check of wire, chain block, eye bolt
8 Positive isolation procedures to be followed