Opme003 Merged
Opme003 Merged
OPME003
a—Ratio/range analysis
b—Decision tree
c—Pert simulation
d—Pert
4: People working on prototype development needing time to interact with the design engineers after
the design is completed is a good example of
5: A list of questions that address traditional areas of uncertainty on a project is termed a risk.
a--Profile
b--Questionnaire
c--Research
d--Query
6: Learning curves are more likely to apply in situations where most of the costs are
a-- Materials
b-- Labor
c--Overhead
7: Detailing all identified risks, including descriptions, category, and probability of occurring, impact,
responses, contingency plans, owners and current status is called
a---Management reserves
b—Change control
c---Contingency reserves
d—Risk register
8: ______ begins with a review of the strategic intent of the project, selection
criteria, project charter, project objectives, project scope, and acceptance criteria
a—Process review
b—Project overview
c—Analysis
d—Recommendation
9: which of the following is the most common method for shortening project time?
b—Subcontract of work
c—Schedule overtime
10: which of the following is not one of the steps in the risk management process?
b—Risk assessment
c—Risk identification
d—Risk tracking
12: which of the following statement best describes the use of an issue log
b-- A summary of all the project issues, their analysis and status
c—A tool to ensure that a process is in place for capturing all issues
13: The amount of time an activity can be delayed and yet not delay the project is termed
a--Total slack
b--Free slack
c--Critical float
d--Float pad
a-- An arrow
b-- A line
c-- A node
a-- Materials
b-- People
c-- Equipment
d—Information
a--Personality
b--Hierarchy
d-- Background
18: Under which heading of the Wrap-up closure checklist should the question "Have project accounts
been finalized and all billing closed?" be answered
a—Team
b—Vendors/contractors
c—Customers/users
a-- A technique to establish the best approach for obtaining the resources for the project.
b--A group of interrelated resources and activities that transform inputs into outputs.
c--The description of the purpose, form and components to support delivery of a product.
d-The process by which products and services required for the project are acquired
a-- Management
b--Leadership
c--Monitoring
d--Corrective action
b—A party with an interest or role in the project or is impacted by the project
c—A party who has a vested interest in the outcome of the project
d—A party who has a financial stake in the organization managing the project
a—Often the kind that can cause the project to be shut down
b—Problematic
23: Mega Computers, Inc. has assigned a project manager for each of the five new-product teams. The
managers as well as the project team members work on the projects on a full-time basis. The structure
a--Functional
b--Balanced matrix
d—Project
24: In monitoring project time (schedule) performance actual performance should be compared to:
25: Information on the project type, size, number of staffs, and technology level would be included in
which section of the audit report?
a—Analysis
b—Recommendations
c—Classification of project
d—Lessons learned
26: the assessment of the external and internal environments is called ------- analysis
a—Swot analysis
b—Competitive
c—Industry
d—Market
d--All of these
29: Many projects will fail because of circumstances beyond the control of the project team is called
a--Normal
b--Premature
c--Perpetual
d--Failed Project
30: Once a change has been repeated what is the next step in the change control process?
a--Demands
b--Increases
c--Assumptions
d—Utilization
a--to be the sole source of expertise for estimating techniques on cost and time.
c--to take ultimate accountability for the delivery of the business benefits.
d--to delegate all accountability for managing time, cost and quality to team leaders
34: The president of a software company remarks in a speech that new technologically advanced
software will be available in one year. This is an example of reducing project duration caused by.
b—Time to market
d—High overhead
35: Project mission and objectives, procedures and systems used, and organization resources used
typically appear in the _____ section of the final project report.
a—Analysis
b—Recommendations
c—Classification of project
d—Lessons learned
36: Which of the following illustrates why effective project management is beneficial to an organization
a-- It utilizes resources as and when required under direction of a project manager.
c--It recommends using only highly skilled people in the project team.
d--It ensures that the chief executive is accountable for the achievement of the defined benefits.
37: The section of the final project report that new project teams are likely to find most useful is the
a—Analysis
b—Recommendations
c—Classification of project
d—Lessons learned
38: In terms of commonly traded organizational currencies, vision, excellence, and ethical correctness
are part of ______ related currencies
a—Task
b—Position
c—Inspiration
d—Relationship
39: What is a visual representation of a project's planned activities against a calendar called
c—A resource may be moved from one activity to another and then back
d—Both possibility of start up and shutdown costs and resource may be moved from one activity to
41: In which of the following stages are you more likely to find status reports, many changes, and the
creation of forecasts
a--Conceptualizing
b--Defining
c--Planning
d—Executing
42: Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an
example of reducing project duration caused by:
b--Time to market
d-High overhead
45: The risk assesment from contain all of the following except
46: Which of the following is NOT one of the tips for alleviating communication problems of virtual
teams?
b—Keep team members informed on bow well the overall project is going
d—Establish clear norms and protocols for surfacing assumptions and conflicts
48: which one of the following is a valid project key performance indicator (kpi)
a—Staff appraisals
b—Management buy in
c—Milestone achievement
d—Master schedule
b—It is frequently unnoticed until time delays or cost overruns are observed
52: Project closure can fall into all of the following categories except
a—Premature
b—Perpetual
c—Failed
53: A new holistic approach in new commercial product development effect is known as
a—Scrum
d—Prioritized wbs
55: All projects should be aligned with their organizations strategic plan, which includes the
organizations vision goals and objectives. Which of these is the definition of a vision statement?
a—Conveys a large sense of organizational purpose, and is both inspiring and guiding
b—Describes short- and long-term results along with measures to determine if they have been achieved
c—Includes the organization core purpose, core value, beliefs, culture, primary business and primary
customers
d—Is smart specific, measurable, achievable, results based and time specific
c--Critical path
a--the reporting structure and current availability of all individuals in the project.
b-- technical ability and line of communication for all individuals in the project.
c--lines of communication and responsibility for all the individual managers in the project.
d-- the reporting structure and lines of communication for all individuals in the projects.
59: Change management systems are designed to accomplish all of the following except
d--All of these
60: Janet is forecasting how much money her department needs to support a new project. She
estimates that two people and $25,000 in expenses will cover her needs. Because management typically
insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction.
Which of the following factors is illustrated in this situation?
a--Padding estimates
b--Planning horizon
c--Project structure
d--People
61: An earned value system used to monitor project progress includes comparison of
62: Which of the following is not one of the more common problems associated with scheduling multi
project resources?
c—Resource bottlenecks
d—All of these
63: The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
a--Slowly rise
64: When developing a new software package, the software must be designed, the code must be
written, and the code must be tested. This is an example of a ---------constraint
a—Physical
b—Technical
c—Resource
d—Schedule
66: The Risk Management Plan, which is the outcome of the process Plan Risk Management includes all
except
a-- Methodology
c-- Budgeting
d-- Tracking
67: The process of identifying quality requirements and/or standards for the project and its deliverables
and documenting how the project will demonstrate compliance with quality requirements and/or
standards is called:
68: What is the term used for processes that are required to ensure timely and appropriate planning,
collection, creation, distribution, storage, retrieval, management , control monitoring, and the ultimate
disposition of project information?
69: Approximately what percentage of the project manager''s time is spent in some form of
communication, such as: conferences, meetings, writing memos, reading and preparing reports, and
talking with project team members, upper management, and all other stalk holders?
a-- 10-20%
b-- 50-70%
c-- 75-90%
d-- 21-45%
70:- Resource reallocation from non-critical to critical activities is an example of which Project
Scheduling technique:
71: which one of the following is true about for the project management plan
a—The project management plan is developed by the project manager and term and owned by the
sponsor
b—A draft of the project management plan is developed by the sponsor at the same time as the
business case
c—The project management plan is developed by the sponsor and owned by the project manager
d—the Project management plan is developed by the project manager and team owned by the project
manager
72: During project executing, a team member comes to the project manager because he is not sure of
what work he needs to accomplish on the project. Which of the following documents contain detailed
descriptions of work packages?
73: Which of the following is not correct about initial phase of a project?
d-- Customer
77: The process of monitoring the status of the project to update the project costs and managing
changes to the cost baseline is called
78: The project manager is considering contracting some of the work of the project to a service bureau.
The service bureau has been used in the past by this project manager. The manager has several choices
of contracts that can be used to subcontract this work. Which of the following is not a type of contract
that the project manager might choose?
79: Which of the following has the greatest effect on product's reliability and maintenance
characteristic?
a-- quality
c-- pricing
d-- a and b
80: The measure along the level of uncertainty or the level of impact at which a stakeholder may have a
specific interest. Below that, the organization will accept the risk, and above this measure the
organization will not accept the risk. It is known as
d-- None
81: The project you are managing has nine stakeholders. How many channel of communications are
there between these stakeholders?
a--9
b-- 8
c-- 45
d-- 36
82: A project manager's main responsibility in a project meant to create a product is: :
a-- Finish-to-Start
b-- Start-to-Finish
c-- Start-to-Start
d-- Finish-to-Finish
84: A planning phase for an engineering component generated 80 engineering drawings. The QA team
randomly selected 8 drawings for inspection. This exercise can BEST be described as example of:
a-- Inspection
c-- Flowcharting
85: Which of the following does NOT generate changes to the Project documents:
87: Omar, a project manager in a construction company is preparing for a meeting with the stakeholders
to update them about the status of the project after the monitoring and controlling of the project work.
For the information, Omar will access automated tools such as performance indicators, databases,
financials, or resourcing tools through:
88: The total amount of risk that is calculated for a project is found by
a-- Multiplying the sum of each the risk times the amount at stake
b-- Calculating the cumulative sum of the probability for each risk and multiplying this value times the
consequence of occurrence of the risk events
89: When checking the calendar of a team member to schedule a meeting, you see she has scheduled a
meeting with a key stakeholder that you were not informed of. The best approach would be to:
a-- avoid mentioning it to the team member but continue to watch her activities.
91: The sum of all budgets established for the work to be performed is known as:
d--Estimate at Completion
92: The inputs used in the process of Perform Qualitative Risk Analysis includes all except
93: The process of developing an approximation of the monetary resources needed to complete project
activities is known as
94: The processes involving planning, estimating, budgeting, financing, funding, managing, and
controlling costs so that the project can be completed within the approved budget fall under
95: The process under Process Risk Management that prioritizes risks for further analysis or action by
assessing and combining their probability of occurrence and impact is called
96: The tools and techniques used in the process of Determine Budget includes all but
97: The name for the tool used in Perform Quality Assurance to represent decomposition hierarchies
such as the WBS (work breakdown structure), RBS (risk breakdown structure), and OBS (organizational
breakdown structure) is:
98: All of the following are the responsibility of a project manager EXCEPT?
c-- Ensure that a conflict of interest does not compromise the legitimate interest of the customer.
c-- Histogram
b-- Scatter
d-- Histogram
102: Work performance data, quality checklists, quality metrics, and the project management plan are:
103: Which of the following process is not included in project communication knowledge area?
106: A schedule activity may begin 10 days before the predecessor activity finishes. This is an example
of:
a-- ADM
b-- PDM
108: Which one of the following is not an input used in the process of Estimate Costs?
109: A risk is defined as ____________ event or condition that, if it occurs, has a positive or negative
effect on one or more project______________.
110: When is the risk and uncertainty in a project's life cycle at the highest?
a-- start
b-- design
c-- closing
d-- implementation
111: A project team has completed, and the customer has accepted, the completed project scope.
However, the lessons learned required by the project management office have not been completed.
What is the status of the project?
b-- The project is incomplete until all the activities required for closing a project are completed.
c-- The project is complete because the customer has accepted the deliverables.
d-- The project is complete because the project has reached the due date.
d-- determining the amount of time the activity can be delayed before it delays the critical path.
114: A new project that was initiated, involved new technology and had never been done before. What
type of contract would the owner want to issue to reduce or eliminate as much risk as possible?
115: The results of the Plan Communications Management Process should be reviewed regularly
throughout the project and revised as needed to ensure continued applicability. The statement is
a-- TRUE
b-- FALSE
d-- Not completely true as it is not possible to review the plan frequently
a-- Scope
b-- Resources
c-- Team
d-- Budget
118: A Project Manager is preparing a Project Schedule network diagram. During the diagram
development, she removes a dependency between two tasks that was defined in an earlier stage. After
the network diagram is completed, she updates activity attributes for the two tasks. This is an example
of:
119: You just found out that a major subcontractor for your project consistently provides deliverables
late. The subcontractor approaches you and asks you to continue accepting late deliverables in
exchange for a decrease in project costs. This offer is an example of:
a-- confronting.
b—compromise
c-- smoothing.
d-- forcing.
1 C 21 B 41 D 61 D 81 D 101 B
2 C 22 A 42 C 62 D 82 B 102 A
3 A 23 D 43 B 63 A 83 B 103 D
4 A 24 C 44 A 64 B 84 B 104 A
5 A 25 C 45 C 65 A 85 A 105 B
6 B 26 A 46 A 66 D 86 B 106 D
7 D 27 D 47 A 67 A 87 A 107 B
8 A 28 D 48 C 68 A 88 B 108 D
9 A 29 D 49 D 69 C 89 D 109 B
10 C 30 C 50 A 70 D 90 C 110 A
11 B 31 D 51 D 71 D 91 C 111 B
12 B 32 D 52 D 72 A 92 C 112 D
13 A 33 B 53 A 73 A 93 A 113 C
14 D 34 A 54 B 74 B 94 A 114 A
15 C 35 A 55 D 75 C 95 A 115 A
16 D 36 A 56 C 76 A 96 B 116 A
17 A 37 D 57 B 77 B 97 A 117 C
18 B 38 C 58 D 78 B 98 B 118 D
19 D 39 A 59 D 79 D 99 B 119 B
20 B 40 D 60 A 80 A 100 D
2: Which one of the following illustrates why effective Project Management is beneficial to an
organization
Ans: It utilizes resources as and when required under direction of a PM.
6: Information on the project type, size, number of staffs, and technology level would be included in
which section of the audit report:
Ans: Classification of project
7: The section of the final project report that new project teams are likely to find most useful is the:
Ans: Lessons learned
9: Top-down estimates are most likely to occur during the ______ phase:
Ans: Concept
11: Detailing all identified risks, including descriptions, category, and probability of occurring, impact,
responses, contingency plans, owners and current status is called:
Ans: Risk Register
14: Which one of the following is not one of the steps in facilitating group decision making:
Ans: analyzing the situation
15: All of the following are part of the agile project management model EXCEPT:
Ans: Design up front
16: A good project management system provides for defining the interface between the project team
and the organization in all the following areas except:
Ans: Development of project team members
18: Many projects will fail because of circumstances beyond the control of the project team is called:
Failed Project
19: Project costs are typically viewed from all of the following except:
Ans: Sunk
20: When a project has completed the handover and closure phase:
Ans: The capability is now in place for the benefits to be realized
23: An uncertain event or condition that, if it occurs, has a positive or negative effect on project
objectives is termed a:
Ans: Risk
24: Which each of these Agile principles: Test assumptions early and build working prototypes to solicit
customer feedback and refine product requirements:
Ans: Experimentation and adaptation
26: Which of the following is NOT one of the tips for alleviating communication problems of virtual
teams:
Ans: Include face to face time if at all possible
27: A person who acts on behalf of customers to represent their interests is called a:
Ans: Product Owners
28: A portfolio can be defined as a:
Ans: a group of projects and programmes carried out within an organization
29: Which of the following would be considered the MOST effective project reward:
Ans: all expenses paid trip for members and their family
31: Mega Computers, Inc. has assigned a project manager for each of the five new-product teams. The
managers as well as the project team members work on the projects on a full-time basis. The structure
being used is ________ organization:
Ans: Project
32: The project structure that is ranked as least effective is _______ organization:
Ans: functional
33: Which of the following methods will measure the scheduling efficiency of the work accomplished to
date:
Ans: EV/PV
34: Which structure shows the reporting relationships & communications channels for a project:
Ans: Work Breakdown Structures (WBS)
35: The easiest and most commonly used technique for analyzing risks is _____ analysis:
Ans: Scenario
36: Which of the following is NOT one of the steps in the risk management process
Ans: Analyzing the situations
38: Which of the following is not one of the basic rules to follow when developing project networks:
Ans: Conditional statements are allowed but looping statements are not allowed
41: What is a visual representation of a project's planned activity against a calendar called:
Ans: A Gantt chart.
44: In organizations where projects are managed within a ____________, the team member's area
manager, not the project manager, is responsible for assessing performance:
Ans: Functional organization
46: Change management systems are designed to accomplish all of the following except:
Ans: All of these
47: In terms of commonly traded organizational currencies, being involved in a task that has a large
significance or having a chance to do something important and do it well are examples of ______ related
currencies:
Ans: Inspiration
49: A new holistic approach in new commercial product development efforts is known as:
Ans: Scrum
50: The approach that begins with a top-down estimate for the project and then refines estimates as the
project is implemented is known as ______ method:
Ans: Phase estimating
51: An Earned Value System used to monitor project progress includes comparison of:
Ans: Both actual cost versus budget & scheduled progress versus plan
54: Once a change has been requested what is the next step in the change control process
Ans: Evaluate the change
56: Which of these is NOT part of the "technical dimension" of project management:
Ans: Problem solving
58: The percent complete index that looks at percent complete in terms of budgeted amounts is
calculated by which of the following:
Ans: EV/BAC
59: Project mission and objectives, procedures and systems used, and organization resources used
typically appear in the ______________ section of the final project report:
Ans: Analysis
61: The content of the final report typically includes the following topics:
Ans: All of these
62: Which one of the following best describes project success criteria:
Ans: Measures by which the success of the project is judged
63: A review undertaken to decide whether a project should proceed into its next phase is known as a:
Ans: Gate review
66: Which of the following is provided by a project network but not by the work breakdown structure:
Ans: All of these
67. the content of the final report typically includes the following topics:
Ans: all of these
69 which of the following is not one of the most significant sources of conflict during the project
definition phase?
Ans: Costs
70 Project closures can fall into all of the following categories except:
Ans: All of these are categories for project closure
72 Which of the following will calculate the estimated cost to complete the project?
Ans: (BAC-EV)/(EV/AC)
73Which one of the following is true for the project management plan (pmp)?
Ans: The project management plan is developed by the project manager and team and owned by the
sponsor
78 The amount of time an activity can be delayed and yet not delay the project is termed
Ans: total slack
79Which of the following questions does the organization's mission statement answer?
Ans: What do we want to become?
80All of the following are included in the risk identification process except
Ans: Competitors
82 Which one of the following is a valid project key performance indicator (kpi)?
Ans: Milestone achievement
83 All projects should be aligned with their organization's strategic plan, which includes the
organization's vision, goals and objectives. Which of these is the definition of a vision statement
Ans: Conveys a large sense of organizational purpose, and is both inspiring and guiding
86 The president of a software company remarks in a speech that new technologically advanced
software will be available in one year. This is an example of reducing project duration caused by:
Ans: Imposed project deadlines
88 Which of the following is not one of the more common problems associated with scheduling multi
project resources?
Ans: All of these
99 Project mission and objectives, procedures and systems used, and organization resources used
typically appear in the section of the final project report.
Ans: Analysis
101 Learning curves are more likely to apply in situations A where most of the costs are
Ans: Labor
102 A list of questions that address traditional areas of uncertainty on a project is termed a risk
Ans: profile
104 Under which heading of the wrap-up closure checklist should the question "have project accounts
been finalized and all billing closed?" be answered
Ans: Vendors/contractors
105. Which of the following stages are likely to find status reports, many changes and the creation of
forecast?
Ans: Execution
106. Janet’s is forecasting how much money her departments needs to support a new project. She
estimates that two people and 25000 in expenses will cover her need…..?
Ans: Padding estimate
107. Bottom-up approach for estimating times and costs that uses cost from past projects that were
similar to the current project is known as?
Ans: Template Method
111. MegaComputers, Inc. has assigned a project manager for each of the five new-product teams.
The managers as well as the project team members work on the projects on a full-time basis. The
structure being used is ________ organization.
Ans: Project
112. Elizabeth is considering how to structure a project team that will not directly disrupt ongoing
operations. The project needs to be done quickly and a high level of motivation will be needed in
order to do that. For this situation, the ______ organization would be the best choice.
Ans: Project
113. A project management system provides a framework for launching and implementing project
activities within a ______ organization.
Ans: Parent
114. In which of the following is the balance of authority strongly in favor of the functional
managers?
Ans: Weak matrix
116. The project structure that is ranked as least effective is _______ organization
Ans: Functional
117. From the list below, which is not a primary characteristic of organization culture?
Ans: History
118. Who is responsible for determining how tasks will be done in a matrix project management
structure?
Ans: The functional manager
119. The Macintosh development team at Apple is a good example of what kind of project
structure?
Ans: Project
120. The Organizational Culture Diagnosis Worksheet classifies cultural characteristics into all of
the following except:
Ans: Ethics
121. Which of the following is not one of the typical forms of a project management office?
Ans: Command center
122. Which of the following cultural characteristics relates to the degree to which management
focuses on outcomes rather than on techniques and processes used to achieve those results?
Ans: Means versus end orientation
123. The most common circumstance for project closure is simply a ________ project.
Ans: Completed
125. __________ of lessons learned are designed to improve performance on current and future
projects.
Ans: Retrospectives
126. When the project may be completed early with some parts of the project eliminated this is
considered to be ___________ closure.
Ans: Premature
127. This type of closure occurs when the project may never seem to end. This is considered to be
___________ closure.
Ans: Perpetual
128. When a project may start with a high priority but see its rank erode or crash during its project life
cycle as conditions change this is an example of:
Ans: Changed Priority
129. If a project has more than one activity that can begin when the project is to start a common start
node should be used to indicate a clear project beginning on the network. Without a common start
node, each path is a
Ans: Dangler Path
130. Which of the following can be used without coordinating with managers of succeeding activities?
Ans: Free slack
132. Bill is building a project network that involves testing a prototype. He must design the
prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1
is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype
fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1.
This is an example of
Ans: Looping
133. On a project network, the activity times are derived from the
Ans: Work packages
134. Which of the following is provided by both the project network and the work breakdown structure?
Ans: Activity duration
135. If, for some reason, the project must be expedited to meet an earlier date, which of the
following actions would the project manager take first?
Ans: Check to see which activities are on the critical path
136. Concurrent engineering, which has dramatically reduced the development time for new products,
relies on what kind of lag?
Ans: Start to start lags
137. Activities which can take place at the same time are termed
Ans: Parallel activity
138. Which of the following will correctly calculate the total slack in an activity?
Ans: Either LS – ES or LF – EF
3. of lessons learned are designed to improve performance on current and future projects.
A. Retrospectives
4. The content of the final report typically includes the following topics:
5. When the project may be completed early with some parts of the project eliminated this is
considered to be closure.
Premature
6. This type of closure occurs when the project may never seem to end. This is considered to be
closure.
A. Perpetual
7. Many projects will fail because of circumstances beyond the control of the project team is
called:
A. Failed Project
8. When a project may start with a high priority but see its rank erode or crash during its
project life cycle as conditions change this is an example of:
a. Changed Priority
10. Which is not part of the team portion of the Wrap-up closure checklist?
All are included.
11. Under which heading of the Wrap-up closure checklist should the question "Has an in-
depth project review and evaluation interview with the customer been conducted?" be
answered.
a. Customer/Users
12. Under which heading of the Wrap-up closure checklist should the question "Have project
accounts been finalized and all billing closed?" be answered.
Vendors/contractors
13. Releasing the project team typically occurs during the closure phase.
a. Gradually
14. In the Snapshot from Practice, New Balls Goes Flat in NBA, is an example of a project
gone wrong when the is/are not consulted.
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
End-users
15. Closing out is often messy and filled with untied ends.
a. Contracts
16. Information on the project type, size, number of staff, and technology level would be
included in which section of the audit report?
a. Classification of project
17. Project mission and objectives, procedures and systems used, and organization resources
used typically appear in the section of the final project report.
a. Analysis
18. Items technical in nature and focus on solutions to problems that surfaced would typically
appear in the section of the final project report.
a. Recommendations
19. The section of the final project report that new project teams are likely to find most useful is
the:
a. Lessons learned
20. Corrective actions that should take place (such as shifting to more resilient building
material) would typically appear in the section of the final project report.
a. Recommendations
21. In the Snapshot from Practice, the results of analyzing the Katrina hurricane resulted in a
new evaluation plan from:
a. The Red Cross
22. The most common circumstance for project closure is:
a. Project completion after modification of costs, schedule, or quality
23. Project closures can fall into all of the following categories except:
a. All of these are categories for project closure
24. In the Research Highlight, Chaos: Software Projects, the criterion which was deemed the
most important for project success was
a. Proper planning
25. begins with a review of the strategic intent of the project, selection criteria,
project charter, project objectives, project scope, and acceptance criteria.
a. Process Review
26. The typical mechanism for evaluation of teams is normally:
a. A survey completed by the team members
27. More and more companies are discarding the traditional superior-subordinate performance
feedback process and replacing it with:
a. The 360-degree feedback
28. The project closure process includes all of the following except:
a. Conduct an audit
29. In organizations where projects are managed within a , the team member's
area manager, not the project manager, is responsible for assessing performance.
a. Functional organization
31. is the most common circumstance for project closure is simply a completed
project. Normal
32. The project may be completed early with some parts of the project eliminated is known as
. premature
33. are usually easy to identify and easy for a review group to close down. Failed
project
34. Projects in process may need to be altered or canceled. Thus, a project may start with a high
priority but see its rank erode or crash during its project life cycle as conditions change. This
is called .
changed priority
35. A schedule for reducing project staff been developed and accepted is a question that is
asked in the completion of the .
wrap-up closure checklist
36. The summary simply highlights the key findings and facts relating to the project
implementation is called the .
executive summary
37. Some organizations have project closure checklists of over wrap-up tasks!
100
38. The section of the final project report includes succinct, factual review
statements of the project such as, project mission and objectives, procedures and
systemsused, and organizational resources used.
Analysis
39. Perhaps are the most valuable contribution of the closure process.
lessons learned
40. The section of the final project report are often technical in nature and focus on
solutions to problems that surfaced.
Recommendations
41. A completed is a good example of the need to work out the details in
advance.
software program
42. A project closure is considered if it never seems to end due to constant "add-
ons" in attempt to improve the project outcome.
Perpetual
43. The purpose of is to assess how well the project team, team members, and
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
44. The feedback approach gathers anonymous feedback solicited from others is
compared with the individual's self-evaluations, the individual may form a more realistic
picture of her strengths and weaknesses.
360-degree
45. In some , project managers conduct the performance reviews, while area
managers are responsible for pay reviews.
matrix organizations
46. Project managers should be giving team members feedback throughout the
project so that individual team members can have a pretty good idea how well they have
performed and how the manager feels before the formal meeting.
constantly
47. The of projects by characteristics allows prospective readers, teams, and
project managers to be selective in the search and use of report content.
Classification
48. The most common reason given for not creating lessons learned is .
lack of time
49. A is a methodology that analyzes a past project event to determine what worked and
what didn't, develops lessons learned, and creates an action plan that ensures lessons learned
are used to improve management of future projects.
retrospective
50. are binary; either you have reached requirements completion or you have not.
Milestones
51. The Standish Group International's market research on software projects, called Chaos
showed that percent of all software projects are cancelled before completion.
31
52. A is a guide who leads the project team through an analysis of project
activities that went well, what needs improvement, and development of a follow-up
actionplan with goals and accountability.
project facilitator
53. represent an analysis carried out during and shortly after the project life
cycle; they attempt to capture positive and negative project learning.
Lessons learned
54. An upbeat, festive celebration brings closure to the enjoyable experiences everyone has
had and the need to say good-bye is considered to be a .
Celebration
55. In a Perpetual project the most common circumstance for project closure is simply a
completed project.
FALSE
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
56. In a Premature projects, the project may be completed early with some parts of the project
eliminated.
TRUE
57. Retrospectives of lessons learned are designed to improve performance on current and
future projects.
TRUE
58. When a project may start with a high priority but see its rank erode or crash during its
project life cycle as conditions change this is an example of change changed priority.
TRUE
59. Part of the content of the final report typically includes profit made on the project.
FALSE
60. The project manager's challenge is to keep the project team focused on the remaining
project activities and delivery to the customer until the project is complete.
TRUE
61. Implementing closedown includes getting delivery acceptance from the customer.
TRUE
62. Project Summary is the summary that simply highlights the key findings and facts relating to
the project implementation.
FALSE
63. Analysis examines in detail the underlying causes of problems, issues, and successes.
TRUE
64. The ideal scenario is to have the team member's next assignment ready when project
completion is announced.
TRUE
65. The maximum items on a checklist for closing a project are 50.
FALSE
66. Lessons learned from the Katrina disaster are not limited to the military. Almost every
agency and support group, such as individuals, communities, churches, and other groups, has
developed lessons learned from their project response experience.
TRUE
68. Performance evaluations of project team members are typically well done because the
evaluations are conducted by the team member's home department.
FALSE
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
69. The most common circumstance for project closure is simply a completed project such as
building a new facility or creating a customized information system.
TRUE
70. A project closure where the project is completed early with some parts of the project
eliminated would be classified as project failure.
FALSE
71. The key requirement in selection of the facilitator is one who is the end-user.
FALSE
74. A 360-degree performance evaluation includes feedback from peers, project managers,
subordinates, and even customers.
TRUE
75. Project managers should, when possible, draw comparisons to other team members when
conducting individual team member reviews.
FALSE
76. Retrospective methodology is one positive step toward ensuring lessons learned are
developed and implemented.
TRUE
77. What are the six major activities implementing project closedown?
1. Getting delivery acceptance from the customer, 2. Shutting down resources and releasing to
new uses, 3. Reassigning project team members, 4. Closing accounts and seeing all bills are paid,
5. Delivering the project to the customer, 6. Creating a final report.
80. How does the project managers meet the challenge to keep the project team focused on the
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
remaining project activities and delivery to the customer until the project is complete?
Communicating a closure and review plan and schedule early allows the project team to (1)
accept the psychological fact the project will end and (2) prepare to move on. The ideal
scenario is to have the team member's next assignment ready when project completion is
announced. Project managers need to be careful to maintain their enthusiasm for completing the
project and hold people accountable to deadlines, which are prone to slip during the waning
stages of the project.
81. Identify the five common parts to the final project report.
82. Identify and briefly describe the five most common classifications for the way that projects end.
1. normal; project ended as planned, 2. premature; project ended early with some parts
eliminated, 3. perpetual; project extend due to increases in scope, 4. failed; project could not be
completed, and 5. changed priority; shifts in organization priorities due to changes in market or
technology.
84. How does Norman Kerth define retrospective in his text Project Retrospectives?
A retrospective is a methodology that analyzes a past project event to determine what workedand
what didn't, develops lessons learned, and creates an action plan that ensures lessons learned are
used to improve management of future projects.
85. What guidelines should a project manager follow in conducting performance reviews?
1. Have the individual prepare a self-evaluation, 2. compare with standards not other people,
3. focus on specific behaviors rather than the individual, 4. be consistent and fair with all team
members, and 5. treat the review as a point in an ongoing process.
87. In the Research Highlight "Measures of Team Performance," what was the major findingof
the research survey?
1. too few teams (52%) received a collective evaluation of their performance and 2. of the
22% who said they did receive an evaluation, it lasted only approximately 20 minutes.
Lessons learned represent an analysis carried out during and shortly after the project life cycle;
they attempt to capture positive and negative project learning. That is, "what worked and what
didn't?" Lessons learned (postmortems, post-project review, or whatever name you choose to
use) have long been part of project management.
91. MegaComputers, Inc. has assigned a project manager for each of the five new-product teams.
The managers as well as the project team members work on the projects on a full-time basis.
Thestructure being used is organization.
Project
92. Elizabeth is considering how to structure a project team that will not directly disrupt ongoing
operations. The project needs to be done quickly and a high level of motivation will be
needed inorder to do that. For this situation, the organization would be the best choice.
Project
93. A project management system provides a framework for launching and implementing
project activities within a organization.
Parent
94. In which of the following is the balance of authority strongly in favor of the
functionalmanagers?
• Weak matrix
95. Matrix management violates the management principle of
• Unity of command
96.From the list below, which is not a primary characteristic of organization culture?
• History
97. Who is responsible for determining how tasks will be done in a matrix project
management structure?
A) The functional manager
98. The Macintosh development team at Apple is a good example of what kind of
project structure?
• Project
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
99.The Organizational Culture Diagnosis Worksheet classifies cultural characteristics into all of
the following except:
Ethics
100. Which of the following is not one of the typical forms of a project management office?
• Command center
101. Which of the following cultural characteristics relates to the degree to which
management focuses on outcomes rather than on techniques and processes used to achieve
those results?
Means versus end orientation
102. If a project has more than one activity that can begin when the project is to start a
common start node should be used to indicate a clear project beginning on the network.
Without a common start node, each path is a
• Dangler Path
103. Which of the following can be used without coordinating with managers of
succeeding activities?
• Free slack
104. Which of the following represents an activity on an AON project network?
• A node
105. Bill is building a project network that involves testing a prototype. He must design
the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity
3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for
activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore,
activity 3 is a predecessor for activity 1. This is an example of
• Looping
106. On a project network, the activity times are derived from the
• Work packages
107. Which of the following is provided by both the project network and the work
breakdown structure?
• Activity duration
108. If, for some reason, the project must be expedited to meet an earlier date,
which of thefollowing actions would the project manager take first?
• Check to see which activities are on the critical path
109. Concurrent engineering, which has dramatically reduced the development time for
new products, relies on what kind of lag?
• Start to start lags
110. Activities which can take place at the same time are termed
• Parallel activity
111. Which of the following will correctly calculate the total slack in an activity?
A. Either LS – ES or LF – EF
116. A list of questions that address traditional areas of uncertainty on a project is termed a risk.
Profile
117. Learning curves are more likely to apply in situations where most of
118. Detailing all identified risks, including descriptions, category, and probability of occurring,
impact, responses, contingency plans, owners and current status is called
Risk register
119. ____ begins with a review of the strategic intent of the project,
selection criteria, project charter, project objectives, project scope,
and acceptance criteria Process review
120.which of the following is the most common method for shortening project time?
Assigning additional staff and equipment
121.which of the following is not one of the steps in the risk management
process?
Risk identification
122. which one of the following best describes users
Those intended to receive benefits or operate outputs.
and status
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
124.The amount of time an activity can be delayed and yet not delay the project is termed
Total slack
125.14: The optimum duration for a project is at the point where
Total project costs are the lowest
126. which of the following represents an activity on an aon project network Anode
constraints except
Information
organizational a Personality
129.Under which heading of the Wrap-up closure checklist should the question "Have project
accounts been finalized and all billing closed?" be answered
b— Vendors/contractors
Vendors/contractors
130.which one of the following statements best defines procurement
The process by which products and services required for the project are acquired
stakeholder
Often the kind that can cause the project to be shut down
134. Mega Computers, Inc. has assigned a project manager for each of the five new-product
teams. The managers as well as the project team members work on the projects on a full-time
d—Project
compared to:
WBS/OBS
136. Information on the project type, size, number of staffs, and technology level would be
included in which section of the audit report?
c—Classification of project
137. the assessment of the external and internal environments is called analysis
a—Swot
analysis
comparing
140. Many projects will fail because of circumstances beyond the control of the project team
is called
d--Failed Project
141. Once a change has been repeated what is the next step in the change control process?
resource
d—Utilization
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
145. The president of a software company remarks in a speech that new technologically
advanced software will be available in one year. This is an example of reducing project
duration caused by.
146. Project mission and objectives, procedures and systems used, and organization
resources used typically appear in the section of the final project report.
—Analysis
147. Which of the following illustrates why effective project management is beneficial to an
organization
the a—Analysis
d—Lessons learned
149. In terms of commonly traded organizational currencies, vision, excellence, and ethical
correctness are part of _ related currencies
Inspiration
150. What is a visual representation of a project's planned activities against a calendar called
Executing
153. Adverse weather, design flaws, and equipment breakdown can create negative slack. This is
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
c--Unforeseen project
delays
except
159. which one of the following is a valid project key performance indicator (kpi) a—Staff
appraisals c—Milestone achievement
except
163. Project closure can fall into all of the following categories except
164. A new holistic approach in new commercial product development effect is known as
a—Scrum
dividing the
166. All projects should be aligned with their organizations strategic plan, which includes
the organizations vision goals and objectives. Which of these is the definition of a vision
statement?
d—Is smart specific, measurable, achievable, results based and time specific
process:
d-- the reporting structure and lines of communication for all individuals in the
projects.
following except
d--All of these
171. Janet is forecasting how much money her department needs to support a new project. She
estimates that two people and $25,000 in expenses will cover her needs. Because management
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that
reduction. Which of the following factors is illustrated in this situation?
a--Padding
estimates
comparison of
d—All of these
174. The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
a--Slowly rise
175. When developing a new software package, the software must be designed, the code
must be written, and the code must be tested. This is an example of a constraint
Technical
Written documents
177. The Risk Management Plan, which is the outcome of the process Plan Risk Management
includes all except
Tracking
178. The process of identifying quality requirements and/or standards for the project and its
deliverables and documenting how the project will demonstrate compliance with quality
requirements and/or standards is called:
179. What is the term used for processes that are required to ensure timely and appropriate
planning, collection, creation, distribution, storage, retrieval, management , control monitoring,
and the ultimate disposition of project information?
180. Approximately what percentage of the project manager''s time is spent in some form of
communication, such as: conferences, meetings, writing memos, reading and preparing reports,
and talking with project team members, upper management, and all other stalk holders?
75-90%
182. which one of the following is true about for the project management plan
the Project management plan is developed by the project manager and team owned by the project
manager
183. During project executing, a team member comes to the project manager because he is not
sure of what work he needs to accomplish on the project. Which of the following documents
contain detailed descriptions of work packages? Work breakdown structure (WBS) dictionary
highest.
188. The process of monitoring the status of the project to update the project costs and
managing changes to the cost baseline is called
Control Costs
189. The project manager is considering contracting some of the work of the project to a service
bureau. The service bureau has been used in the past by this project manager. The manager has
several choices of contracts that can be used to subcontract this work. Which of the following is
not a type of contract that the project manager might choose?
Make or buy
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
190. Which of the following has the greatest effect on product's reliability and maintenance
characteristic?
a and b (quality, product design)
191. The measure along the level of uncertainty or the level of impact at which a stakeholder may
have a specific interest. Below that, the organization will accept the risk, and above this measure
the organization will not accept the risk. It is known as
Risk Threshold
192. The project you are managing has nine stakeholders. How many channel of
communications are there between these stakeholders?
36
Start-to-Finish
195. A planning phase for an engineering component generated 80 engineering drawings. The
QA teamrandomly selected 8 drawings for inspection. This exercise can BEST be described as
example of:
Statistical Sampling
196. Which of the following does NOT generate changes to the Project
197. The contingency budget will: Reduce the probability of cost overruns.
198. Omar, a project manager in a construction company is preparing for a meeting with the
stakeholders to update them about the status of the project after the monitoring and controlling of
the project work. For the information, Omar will access automated tools such as performance
indicators, databases, financials, or resourcing tools through:
200. When checking the calendar of a team member to schedule a meeting, you see she has
scheduled a meeting with a key stakeholder that you were not informed of. The best approach
would be to:
activity attribute:
202. The sum of all budgets established for the work to be performed is
203. The inputs used in the process of Perform Qualitative Risk Analysis includes
204. The process of developing an approximation of the monetary resources needed to complete
project activities is known as Estimate Costs
205. The processes involving planning, estimating, budgeting, financing, funding, managing, and
controlling costs so that the project can be completed within the approved budget fall under
206. The process under Process Risk Management that prioritizes risks for further analysis or
action by assessing and combining their probability of occurrence and impact is called
207. The tools and techniques used in the process of Determine Budget
208. The name for the tool used in Perform Quality Assurance to represent decomposition
hierarchies such as the WBS (work breakdown structure), RBS (risk breakdown structure), and
OBS (organizational breakdown structure) is:Tree Diagrams
219. Which one of the following is not an input used in the process of Estimate
221. When is the risk and uncertainty in a project's life cycle at the
highest ? Start
222. A project team has completed, and the customer has accepted, the completed project scope.
However, the lessons learned required by the project management office have not been
completed. What is the status of the project?
The project is incomplete until all the activities required for closing a project are
completed.
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
225. A new project that was initiated, involved new technology and had never been done before.
What type of contract would the owner want to issue to reduce or eliminate as much risk as
possible? fixed price
226. The results of the Plan Communications Management Process should be reviewed regularly
throughout the project and revised as needed to ensure continued applicability. The statement is
TRUE
227. The process control charts are used: to determine whether a process is or not
229. A Project Manager is preparing a Project Schedule network diagram. During the diagram
development, she removes a dependency between two tasks that was defined in an earlier stage.
After the network diagram is completed, she updates activity attributes for the two tasks. This is
an example of:Lack of change control
230. You just found out that a major subcontractor for your project consistently provides
deliverables late. The subcontractor approaches you and asks you to continue accepting late
deliverables in exchange for a decrease in project costs. This offer is an example of: compromise
232. Project managers have to assess the risks that may affect a project.
b) False
234. The process each manager follows during the life of a project is known as
high
236. Which of the following is/are main parameters that you should use when computing
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
b) project
238. Which of the following is incorrect activity for the configuration management of a
software system?
a) Internship management
240. An independent relationship must exist between the attribute that can be measured
and the external quality attribute.
b) False
c. Team
3. The project you are managing has nine stakeholders. How many channel of
communications are there between these stakeholders?
d. 36
b. email
5. A Project with a total funding of $100,000 finished with a BAC value of $95,000. What
term can BEST describe the difference of $5,000?
7. Which of the following is the most important element of Project Management Plan that
is useful in HR Planning process:
8. Which of the following types of Organizational Charts can be BEST used to track
project costs :
9. Which of the following is not true for a Responsibility Assignment Matrix (RAM):
A. Process Analysis
B. Statistical Sampling
13. Andrew has joined as the Project Manager of a project. One of the project documents
available to Andrew lists down all the risks in a hierarchical fashion. What is this
document called?
14. During which stage of Risk planning are risks prioritized based on probability and
impact?
16. Which of the following does NOT generate changes to the Project documents:
A. Define Activities
A. Define Activities
18. A schedule activity may begin 10 days before the predecessor activity finishes. This is
an example of:
A. Finish-to-Start
19. Sam Consultancy is planning to buy ten desktops for $1500 each from a leading
computer store. Which type of contract will get signed in this case?
A. Purchase Order
20. Alice is a Project Manager. She is coordinating a bidder conference to allow vendors
to get clarification on the work that needs to be performed. Which phase of Project
Management is in progress.
A. Conduct Procurements
21. The process of Control Procurements falls under which process group
c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and
meet stakeholder expectations.
7. Which one of the following statements best defines the purpose of a Product
Breakdown Structure (PBS)?
a. To define the hierarchy of deliverables that are required to be produced on the project.
9. Which one of the following is a valid project Key Performance Indicator (KPI)?
c. Milestone achievement.
a. The business case is owned by the sponsor and is created during the concept phase of the project life
cycle.
14. A project is typically defined in terms of scope, time, cost and which other
parameter?
b. Quality.
16. What is defined as “the ability to influence and align others towards a common
purpose”?
d. Leadership.
19. The main outcome of risk identification, in a risk management process, is to:
b. identify and describe all risks that might occur on the project.
b. Influencing resources.
21. Which one of the following does project change control primarily seek to ensure?
22. Which one of the following is captured in the Work Breakdown Structure (WBS)?
a. An approximation of project time and cost targets, refined throughout the project life cycle.
25. The justification for the investment to be made in a project is documented in the:
c. business case.
26. Which one of the following is a responsibility of the project steering group/board?
.27. One of the reasons a project life cycle is split into phases is to:
30. The document that identifies what information needs to be shared, to whom, why,
when and how is called the:
32. The process that evaluates overall project performance to provide confidence is
called:
a. quality assurance.
33. Which one of the following statements about the project risk register is false?
d. The process by which products and services required for the project are acquired.
35. Once a change has been requested what is the next step in the change control
process?
d. the reporting structure and lines of communication for all individuals in the projects.
38. Which one of the following best describes project success criteria?
c. document the outcomes of the planning process and provide the reference document for managing
the project.
c. Project sponsor.
43. When a project has completed the handover and closure phase:
44. Which one of the following illustrates why effective project management is beneficial
to an organization?
47. A review undertaken to decide whether a project should proceed into its next phase is
known as a:
a. gate review.
Downloaded by Vishal Malik ([email protected])
lOMoARcPSD|27174083
48. Which one of the following statements best describes the use of an issue log?
49. The main aim of a project risk management process should be to:
a. A Gantt chart.
55. Which one of the following is true for the Project Management Plan (PMP)?
d. The Project Management Plan is developed by the project manager and team and owned by the
project manager.
60. Which structure shows the reporting relationships and communications channels
for a project?
1-A ____ is a set of activities which are networked in an order and aimed towards
achieving the goals of a project.
(A) Project
2-Resources refers to
(B) Project
6-Following are the phases of Project Management Life Cycle. Arrange them in correct
order
(A) 3-2-1-4
(C) Quality
10-Resorce requirement in project becomes constant while the project is in its _____
progress stage.
(D) 80 to 95%
11-The probability of completing the project can be estimated based upon the ____ .
12-In the initial stage of the project the probability of completing the project is ___ .
(C) Low
14-Tool used for comparison of the proposed project to complete projects of a similar
nature whose costs are known.
(D) Analogy
15-Each component of the software product is separately estimated and the results
aggregated to produce an estimate for the overall job.
(C) Bottom-up