PQW5 Final 86
PQW5 Final 86
OF BANGLADESH
These guidance notes have been prepared by the CPTU to assist the Procuring Entities in
the preparation, using this Standard Pre-qualification Document (SPD), for international
procurement of Works and Physical services having estimated cost above Tk 350 million.
The Procuring Entities should also refer to the Public Procurement Act 2006 (Act No 24 of
2006) and the Public Procurement Rules, 2008 and, amendment thereto, issued to
supplement the Act available on CPTU’s website: http://www.cptu.gov.bd/. All concerned are
advised to refer to the aforementioned Act and Rules, in particular Section 33 and Rule 83
respectively, while participating in any Tendering process. The Pre-qualification process is
required to follow Section 41, 42 and 43 of the Act, 2006 and Rule 91, 92 and 93 of the
Rules, 2008.
The Procuring Entities may undertake Pre-qualification for large and complex Procurements
such as, Construction Works, Maintenance Works, Design and build infrastructure, and
Management contracts, subject to the thresholds specified in Schedule II of the Public
Procurement Rules, 2008.
The decision whether to carry out prequalification is a matter of professional judgment based
upon a number of considerations about the contract itself, and about the actual process of
prequalification. Contract considerations include size, complexity, limitations on completion
time, the critical nature of the works, environmental impact, associated risks, etc.
Considerations regarding the process of prequalification should weigh the potential
advantages against the potential disadvantages mentioned in paragraphs below.
The prequalification process may be of benefit to both Tenderers and Procuring Entities
alike, in that:
(a) the process enables prospective Tenderers, who may be insufficiently qualified on
their own, to avoid the expense of Tendering. Conversely it is an incentive for these
potential Tenderers to form a Joint Venture that may give them a better chance of
success;
(b) after being pre-qualified, well-qualified firms will price their Tenders with the
knowledge that they are competing against other qualified Tenderers meeting
realistic minimum competence criteria; the assurance that inadequately qualified
competitors will be excluded from submitting unbalanced low-priced Tenders thus
encourages leading contractors to tender;
(c) pre-qualification enables Procuring Entities to assess the interest from qualified
firms generated by the contract and, in the event that only a limited number of
Applications are received, to make any necessary adjustments in the procurement
process (including, in particular, the Particular Conditions of Contract—sharing of
risk, payment terms, liquidated damages, or completion times, which may be
perceived as onerous by potential Tenderers);
(d) it helps to expose potential conflicts of interest by identifying contractors who may
have a business association with consultants to the project;
2
CPTU-IMED PQW5-OTM (International)
(e) it reduces the amount of work and time involved by Procuring Entities in evaluating
Tenders from unqualified contractors;
(f) it encourages local firms to form Joint Ventures with other local or international
firms, thereby benefiting from their resources and experience;
(g) it enables the Procuring Entities to assess the likelihood of contractors’ eligibility for
‘domestic preference’ where this is applicable; and
(h) it reduces significantly, if not eliminates, problems of rejection associated with low-
priced Tenders submitted by Tenderers of doubtful capability; and.
(i) it gives the Development Partner some indication of Procuring Entities’ ability to
manage an important, early procurement function.
(a) it may increase procurement lead time, although this can be minimized by good
procurement scheduling, e.g., undertaking the prequalification process while
Tender Documents are being prepared;
(b) the Procuring Entities are required to review all prequalification Applications,
whereas post-qualification requires the review of the qualifications of, normally,
only the lowest evaluated Tenderer;
(c) collusion and the possibility of price-rigging is easier among a limited number of
identified Tenderers, particularly if they are of the same nationality;
(d) the element of subjective judgment required by evaluators when applying the
prequalification criteria to a number of Applicants, and the discretionary rights
reserved to the Procuring Entities, provide opportunities for externally influenced
deviations from the expected high standards of ethics and impartiality in pre-
qualifying Applicants.
The Procuring Entities need to carefully consider the advantages and disadvantages of Pre-
qualification before initiating the Pre-qualification process for Procurement of Works and
Physical services and, shall obtain the approval of the Head of the Procuring Entity or an
officer authorized by him or her.
SPD(PQW5) has been designed to: (i) simplify the Procuring Entities’ preparation of a
specific Prequalification Document (PQD) for Procurement of Works; (ii) reduce the
Applicants’ preparation time and effort; and (iii) facilitate and simplify the Procuring Entities’
evaluation of Applications.
SPD (PQW5) is based upon internationally acceptable model formats, which have been
adapted to suit the particular needs of the procurement through a pre-qualification process.
The use of SPD (PQW5) applies when a particular Procuring Entity (Employer) intends to
select a Tenderer (a Contractor) for the international Procurement of Works and physical
services under Open Tendering Method (OTM) while the contract award is being
subsequently determined on the basis of lowest evaluated responsive Tender.
SPD (PQW5) has 4 Sections, of which Section 1: Instruction to Applicants must not be
altered or modified under any circumstances.
The following briefly describes the Sections of SPD (PQW5) and how the Employer should
use these when preparing a particular Pre-qualification Document.
Section 1. Instructions to Applicants (ITA)
This Section provides relevant information to help Applicants prepare their
Applications. Information is also provided on the submission, opening, and
evaluation of Applications and on the award of Contract. The Instruction to
Applicants (ITA) specifies the instructions and procedures that govern the
pre-qualification process. This Section also contains the criteria to be used by
the Employer to determine the qualifications of the Applicants to participate in
the subsequent Tenders and to perform the Contract.
Section 2. Application Data Sheet (ADS)
This Section provides the information that is specific to each object of
procurement and that supplements the information or requirements included
in Section 1: Instructions to Applicants. The Employer shall specify in the
ADS only the information that the ITA instructs to be specified in the ADS. To
facilitate the preparation of the ADS, its Clause Numbers are numbered with
the same numbers of the corresponding ITA Clauses.
Section 3. Application Forms
This Section provides all Application Forms that Applicants must complete
and submit together with their Applications. These Forms are included in
Section 3 of the Pre-qualification Document.
4
CPTU-IMED PQW5-OTM (International)
A Brief Notes on IFP, Sample Formats for Notification and a Pre-qualification Evaluation
Flow Chart attached at the back for information and overall guidance for the Employer only
and shall not be the part of the Pre-Qualification Document.
PRE-QUALIFICATION DOCUMENT
FOR PROCUREMENT OF WORKS (INTERNATIONAL)
[enter here the nature of the works and physical services to be procured]
Table of Contents
6
CPTU-IMED PQW5-OTM (International)
34. Application Evaluation ...................................................................................16
35. Evaluation Process.........................................................................................16
36. Preliminary Examination.................................................................................16
37. Technical Examination and Responsiveness.................................................17
38. Clarification on Application.............................................................................17
39. Restrictions on Disclosure of Information Relating to Pre-qualification Process
......................................................................................................................18
40. Rejection of All Applications...........................................................................18
41. Informing Reasons for Rejection....................................................................18
G. Pre-qualification...........................................................................................
42. Pre-qualification of Applicants........................................................................19
43. Conditional Pre-qualification of Applicants.....................................................19
44. Notification of Pre-qualification.......................................................................19
45. Debriefing of Applicants..................................................................................19
46. Right to Complain...........................................................................................19
47. Invitation for Tenders......................................................................................20
48. Changes in Qualifications of Applicants.........................................................20
49. Post-qualification............................................................................................20
Section 2. Application Data Sheet.................................................................
A. General..........................................................................................................
B. Pre-qualification Document.........................................................................
C. Qualification Criteria....................................................................................
D. Application Preparation...............................................................................
E. Application Submission..............................................................................
F. Application Opening and Evaluation..........................................................
G. Pre-qualification...........................................................................................
Section 3. Application Forms........................................................................
Application Submission Letter(Form PQW5-1)
Applicant Information (Form PQW5-2).............................................................................30
JVCA Partner Information (Form PQW5-3)......................................................................33
Specialist Subcontractor Information (Form PQW5-4)...................................................36
Historical Contract Non-Performance (Form PQW5-5)
Personnel Information (Form PQW5-6)............................................................................39
A. General
1. Scope of 1.1 The Employer, as indicated in the Application Data Sheet (ADS)
Application issues this Pre-qualification Document for the international
procurement of Works and associated Services incidental thereto
as specified in the ADS. The name of the subsequent Tender and
the number and identification of its constituent lot(s) are stated in
the ADS.
3. Source of 3.1 The Employer has been allocated ‘public funds’ as indicated in
Funds the ADS and intends to apply a portion of the funds to eligible
payments under the Contract for which this Pre-qualication
Document is issued.
8
CPTU-IMED PQW5-OTM (International)
3.2 For the purpose of this provision, “public funds” means any
funds allocated to the Employer under Government budget, or
loan, grants and credits placed at the disposal of the Employer
through the Government by the Development Partners or
foreign states or organisations.
10
CPTU-IMED PQW5-OTM (International)
5. Eligible 5.1 This Invitation for Pre-qualification is open to all potential
Applicants Applicants from all countries, except for any specified in the
ADS. An Applicant will be eligible if it is a citizen, or is
constituted, registered and operates in conformity with the
provisions of the laws of that country.
5.2 Applicants may be a physical or juridical individual or body of
individuals, or company, association or any combination of them
in the form of a Joint Venture, Consortium or Association (JVCA)
invited to take part in public procurement or seeking to be so
invited or submitting a Applicant in response to an Invitation for
Pre-qualification.
5.4 Applicants shall have the legal capacity to enter into the Contract
under the Applicable Law.
5.5 Applicants and all parties constituting the Applicant shall not have a
Conflict of Interest.
5.6 Applicants in its own name or its other names or also in the case
of its Persons in different names shall not be under a declaration
of ineligibility for corrupt, fraudulent, collusive or coercive
practices as stated under ITA Sub Clause 4.5.
5.9 Applicants shall have fulfilled its obligations to pay taxes and social
security contributions under the provisions of laws and regulations
of the country of its origin.
B. Pre-qualification Document
8. Pre- 8.1 The Sections comprising the Pre-qualification Document are
qualification listed below, and should be read in conjunction with any
: General Addendum issued under ITA Clause 11.
Section 1 Instructions to Applicants(ITA)
Section 2 Application Data Sheet (ADS)
Section 3 Application Forms
Section 4 Scope of Works
8.2 The Employer will not take into consideration any Application if
the Pre-qualification Document was not directly purchased from,
or issued by the Employer, or through its agent(s) as stated in the
ADS.
9.3 The Employer shall respond in writing within five (5) working days
12
CPTU-IMED PQW5-OTM (International)
of receipt of any such request for clarification received under ITA
Sub Clause 9.1.
9.4 The Employer shall forward copies of its response to all those who
have purchased or have been issued with the Pre-qualification
Document, including a description of the enquiry but without
identifying its source.
9.5 Should the Employer deem it necessary to revise the Pre-
qualification Document as a result of a clarification, it will do so
following the procedure under ITA Clause 11 and ITA Sub Clause
31.2.
10. pre- Pre- 10.1 To clarify issues and to answer questions on any matter arising in
qualification the Pre-qualification Document, the Employer may, if stated in the
Meeting ADS, hold a pre-Pre-qualification Meeting at the place, date and time
as specified in the ADS. All Applicants are encouraged and invited to
attend the meeting, if it is held.
10.2 Minutes of the pre-Pre-qualification meeting, including the text of
the questions raised and the responses given, together with any
responses prepared after the meeting, will be transmitted within
seven (7) days of holding the meeting to all those who purchased
or obtained the Pre-qualification Document and, to even those
who did not attend the meeting. Any revision to the Pre-
qualification Document listed in ITA Sub Clause 8.1 that may
become necessary as a result of the pre- Pre-qualification
meeting will be made by the Employer exclusively through the
issue of an Addendum pursuant to ITA Sub Clause 11 and not
through the minutes of the pre- Pre-qualification meeting.
10.3 Non-attendance at the pre- Pre-qualification meeting will not be a
cause for disqualification of an Applicant.
11. Addendum 11.1 At any time prior to the deadline for submission of Applications, the
to Pre- Employer, on its own initiative or in response to an inquiry in writing
qualification from an Applicant, having purchased the Pre-qualification Document,
Document or as a result of a pre- Pre-qualification meeting may revise the Pre-
qualification Document by issuing an Addendum.
11.2 The Addendum issued under ITA Sub Clause 11.1 shall become an
integral part of the Pre-qualification Document and shall have a date
and an issue number and must be circulated by fax, mail or e-mail,
to Applicants who have purchased or been issued with the Pre-
qualification Documents within five (5) working days of issuance of
such Addendum, to enable Applicants to take appropriate action.
11.4 The Employer shall also ensure posting of the relevant Addenda with
the reference number and date on their websites including notice
boards, where the Employer had originally posted the IFPs.
11.5 Applicants who have purchased or been issued with the Pre-
CPTU-IMED PQW5-OTM (International)
qualification Documents and, have not received any Addenda issued
under ITA Sub Clause 11.1 shall inform the Employer of the fact by
fax, mail or e-mail, before two- third of the time allowed for the
submission of Application has elapsed.
C. Qualification Criteria
12. 12.1 Applicants shall be able to abide by the professional and ethical
Qualification standards set out in Section 64 of the Public Procurement Act,
2006 and Rule 127 of the Public Procurement Rules, 2008.
12.2 The Employer requires the Applicants to be qualified by meeting
predefined, precise minimum requirements, which entails setting
pass/fail criteria, which if not met by the Applicants, will result in
consideration of its Application as disqualified.
12.3 In addition to meeting the eligibility criteria, as stated under ITA
Clause 5, the Applicant shall satisfy the other criteria as stated
under ITA Clauses 12 to 19 inclusive.
12.4 Applicants, with regard to professional and technical capacity to
execute Works they are applying for, shall possess:
(i) the professional and technical qualifications;
(ii) managerial capability;
(iii) satisfactory reputation for diligent and non-problematic
performance of contracts; and
(iv) appropriate personnel required to perform the contract; both
in terms of numbers and skills.
12.5 To qualify for a multiple number of lots in a package for which
Applications are invited in the Invitation for Pre-qualification, the
Applicants shall demonstrate having requirements and resources
sufficient to meet the aggregate of the qualifying criteria for
individual lots.
12.6 The requirements of general experience as stated under ITA
Sub Clause 14.1 (a) and specific experience under ITA Sub
Clause 14.1 (b) shall not be separately applicable for each
individual lot.
14
CPTU-IMED PQW5-OTM (International)
13. Litigation 13.1 Non-performance of a contract shall not occur within the last
History years as specified in the ADS, prior to the deadline for
Application submission based on all information on fully settled
disputes or litigation.
For the purpose, a fully settled dispute or litigation is one that has been
resolved in accordance with the Dispute Resolution Mechanism under
the respective contract and where all appeal instances have been
exhausted.
13.2 All pending litigation shall in total not represent more than the
percentage, as specified in the ADS, of the Applicant’s net worth
and shall be treated as resolved against the Applicant.
13.3 For a Joint Venture under ITA Sub Clause 18.1, the precise
minimum requirements of Leading Partner and other partners
shall be as specified in the ADS.
14. Experience 14.1 Applicants shall have the following minimum level of construction
Criteria experience to qualify for participation in the subsequent Tender
and if successful, the performance of the Works under the
Contract:
(a) a minimum number of years of general experience in the
construction of works as Prime Contractor or Subcontractor
or Management Contractor as specified in the ADS; and
(b) a minimum number of years of specific experience as a
Prime Contractor or Subcontractor or Management
Contractor in construction works of a nature, complexity
and methods/construction technology similar to the
proposed Works in at least a number of contracts over the
period, as specified in the ADS; and
(c) satisfactory completion of similar works of a minimum value
under a single or multiple numbers of contracts over a
period, as specified in the ADS.
15. Financial 15.1 Applicants shall have the following minimum level of financial
Criteria capacity to qualify for participation in the subsequent Tender and
if successful, the performance of the Works under the Contract.
(a) the average annual construction turnover as specified in
the ADS during the period specified in the ADS; and
(b) the minimum Tender capacity as specified in the ADS;
(c) availability of minimum liquid assets or working capital or
credit facilities from a Bank, as specified in the ADS.
17. Equipment 17.1 Applicants shall own suitable equipment and other physical
Capacity facilities or have proven access through contractual arrangement
to hire or lease such equipment or facilities for the desired period,
where necessary or have assured access through lease, hire, or
other such method, of the essential equipment, in full working
order, as specified in the ADS.
18. Joint 18.1 Applicants may participate in the pre-qualification process and
Venture, subsequent procurement proceedings by forming a Joint Venture,
Consortium Consortium or Associations (JVCA) or alternately with the intent to
or enter into such an agreement supported by a Letter of Intent.
Association
(JVCA) 18.2 The JV agreement, indicating at least the parts of the Works to be
executed by the respective partners, shall be legally entered into
case-by-case in the Applicant’s Leading Partner’s country of origin,
as specified in the ADS, duly signed by all legally authorised
representatives of the Persons who are parties to such agreement.
18.3 Applicants, as an alternate to ITA Sub Clause 18.2, may intend to
enter into a JV agreement case-by-case in the form of a Letter of
Intent along with the proposed agreement, indicating at least the
parts of the Works to be executed by the respective partners, duly
signed by all partners of the intended JV and authenticated by an
authority of the Applicant’s Leading Partner’s country of origin, as
stated in the ADS, with the declaration that the partners will execute
the Joint Venture agreement in the event the Applicant, in the first
place pre-qualified and then successful in the subsequent Tender.
18.4 Applicants shall submit the Letter of Intent and the proposed JV
agreement along with the Application.
18.5 For a Joint Venture under ITA Sub Clause 18.1, the precise
minimum qualification requirements of Leading Partner and other
partners shall be as specified in the ADS.
18.6 In cases where a JV partner’s, personnel capacity, equipment
capacity and financial capacity individually fulfils the precise
minimum qualifying requirement of that particular component as
specified, capacities of such partner(s) in the JV will be combined
together for summation to determine the total precise minimum
qualifying requirements criterion of that JV as stated under ITA Sub
Clause 18.5.
16
CPTU-IMED PQW5-OTM (International)
18.7 Each partner of the JV shall be jointly and severally liable for the
execution of the Contract, all liabilities and ethical and legal
obligations in accordance with the Contract terms.
18.8 The JV shall nominate a Representative (partner-in-charge) who
shall have the authority to conduct all business for and on behalf of
any and all the partners of the JV during the tendering process and,
in the event the JV is awarded the Contract, during contract
execution including the receipt of payments for and on behalf of the
JV.
18.9 The composition or the constitution of a JV once formed shall not be
allowed to be altered prior to signing of the Contract.
18.10Alteration of partners to the composition or constitution at a date
later than the signing of the Contract during execution shall be
allowed by the Employer only when any of such partners is found to
be incompetent or has serious difficulties which may impact the
overall implementation of the proposed Works, where the incoming
partner shall require to have qualifications higher than that of the
outgoing partner.
18.11Each partner of the JV shall complete the JV Partner Information
(Form PQW5-3) for submission with the Application.
19. 19.1 Applicants may intend to subcontract an activity or part of the Works
Subcontract to a Specialist Subcontractor, in which case such elements and the
or(s) proposed Subcontractor shall be clearly identified and its
qualifications supported by documents.
19.2 A Specialist Subcontractor may participate in more than one
Application, but only in that capacity.
20. Domestic 20.1 If so specified in the ADS, a national Applicant including Joint
Preference Venture comprising only national partners if pre-qualified, shall
qualify for a percentage margin of ‘domestic preference’ in the
subsequent Tender provided the conditions set out in ITA Sub
Clause 20.2 are fully met.
D. Application Preparation
21. Only One 21.1 Applicants shall submit only one (1) Application for each lot, either
Application individually or as a JV. The Applicant who submits or participates in
more than one (1) Application in one (1) lot will cause all the
Applications of that particular Applicant to be considered
disqualified.
22. Cost of 22.1 Applicants shall bear all costs associated with the preparation
Submitting and submission of its Application, and the Employer shall not be
Applications responsible or liable for those costs, regardless of the conduct or
outcome of the Pre-qualification process.
23. Issuance 23.1 The Employer shall make Pre-qualification Documents available
and Sale of immediately to the Applicants, requesting to obtain and willing to
Pre- purchase at the corresponding price by the date the
qualification advertisement has been published in the newspaper.
Document 23.2 Full contact details, with mailing address, telephone and
facsimile numbers and electronic mail address, as applicable,
of those to whom the Pre-qualification Documents have
been issued shall be recorded with a reference number by the
Employer or its agents.
23.3 There shall not be any pre-conditions whatsoever, for sale or
issuance of Pre-qualification Documents and, the sale or
issuance of such Document shall be permitted up to the day
prior to the day of deadline for the submission of Applications.
18
CPTU-IMED PQW5-OTM (International)
23.4 Pre-qualification Document posted in the designated website
may also be used by the Applicants for submission of
Applications, if so permitted by the Employer and specified in the
ADS.
24. Language of 24.1 The Application shall be written in the English language.
Application Correspondences and documents relating to the Application
may be written in English. Supporting documents and printed
literature furnished by the Applicant that are part of the
Application may be in another language, provided they are
accompanied by an accurate translation of the relevant
passages in English, in which case, for purposes of
interpretation of the Application, such translation shall govern.
24.2 Applicants shall bear all costs of translation to the governing
language and all risks of the accuracy of such translation.
25. Contents of 25.1 The Application prepared by the Applicants shall comprise the
Application following:
(a) Application Submission Letter (Form PQW5-1);
(b) Applicant Information (Form PQW5-2);
(c) documents demonstrating that they are enrolled in the
relevant professional or trade organisations registered in their
country of origin;
(d) written confirmation authorizing the signatory of the
Application to commit the Applicant;
(e) documents confirming the legal capacity stating that there are
no existing orders of any judicial court that prevents either the
Applicant or employees of that Applicant subsequently
entering into or signing a Contract with the Employer;
(f) documents confirming that the Applicant is not insolvent, in
receivership, bankrupt or in the process of bankruptcy,
temporarily barred from undertaking business and shall not
be the subject of legal proceedings for any of the foregoing;
(g) documents confirming that all claims, arbitration or other
litigation cases have been satisfactorily resolved, and if not,
they shall have no serious negative impact on the financial
capacity of the Applicant;
(h) documents confirming that the Applicant has fulfilled its
obligations to pay taxes and social security contributions
under the provisions of laws and regulations of its country
of origin as a proof of fulfilment of taxation obligations;
(i) documents establishing the Applicant’s eligibility to perform
the contract;
(j) documents establishing the origin of all Materials, Equipment
and services to be supplied under the Contract, as stated
under ITA Clause 26;
(k) documents establishing the minimum qualifications of the
Applicant required to be met for due performance of the
Works and physical services under the contract;
(l) any other document as specified in the ADS.
25.2 In addition to the requirements stated under ITA Sub Clause
25.1, Applications submitted by a JV or proposing a Specialised
20
CPTU-IMED PQW5-OTM (International)
28. Documents 28.1 Applicants shall complete and submit the Applicant Information
Establishing (Form PQW5-2) and shall include documentary evidence, as
the applicable to satisfy the following:
Applicant’s (a) details on the financial standing of the Tenderer, such as
Qualification profit and loss statements and corresponding auditor’s report
establishing the liabilities and assets, as stated under ITA
Sub Clause 13.2;
(b) details of general experience in construction works on case-
by-case procurement proceedings performed for each of the
last years along with the sums, dates and recipients, as
stated under ITA Sub Clause 14.1(a) ;
(c)
(d) details of specific experience in construction works of similar
nature and size on case-by-case procurement proceedings
performed for each of the last years along with the sums,
dates and recipients, as stated under ITA Sub Clauses
14.1(b) and (c);
(e) details of average annual construction turnover for a period
as stated under ITA Sub Clause 15.1(a);
(f) details of existing commitments and works to assess the
minimum Tender Capacity as stated under ITA Sub Clause
15.1(b);
(g) details of adequacy of working capital for the subsequent
Tender i.e. access to line(s) of credit and availability of other
financial resources as stated under ITA Sub Clause 15.1(c);
(h) details of numbers of technical and administrative personnel
along with their qualification and experience proposed for
the subsequent Tender as stated under ITA Clause 16;
(i) details of Applicant’s technical facilities, available major
construction equipments, measures for ensuring quality
such as, ISO certification and design, research and
development facilities proposed to carry out the Contract as
stated under ITA Clause 17;
(j) details of Procuring Entities who may be contacted, if
necessary, by the Employer; and
(i) authority to seek references from the Applicant’s bankers or
any other sources.
28.2 Applicants, if applying as an existing or intended JV, shall submit
documentary evidence to establish its qualifications as stated
under ITT Clauses 12,13,14,15,16 &17 and, in particular, in
addition to that as stated under ITT Sub Clause 28.1, it shall
submit an affidavit nominating one of the JV partners as the
REPRESENTATIVE (partner-in-charge) who shall have the
authority to conduct all business for and on behalf of any and all
the partners of the JV during the tendering process and, in the
event the JV is awarded the Contract, during contract execution
including the receipt of payments for and on behalf of the JV.
29. Format and 29.1 The Applicant shall prepare one (1) original of the documents
Signing of comprising the Application as described in ITA Clause 21 and
Application clearly mark it “ORIGINAL.” In addition, the Applicant shall
prepare the number of copies of the Application, as specified in the
ADS and clearly mark each of them “COPY.” In the event of any
discrepancy between the original and the copies, the ORIGINAL
shall prevail.
29.2 The original and each copy of the Application shall be typed or
written in indelible ink and shall be signed by the Person duly
authorized to sign on behalf of the Applicant. This authorization
shall consist of a written authorization and shall be attached to the
Application Submission Letter (Form PQW5-1). The name and
position held by each Person(s) signing the authorization must be
typed or printed below the signature. All pages of the original and
of each copy of the Application, except for un-amended printed
literature, shall be numbered sequentially and signed or initialled
by the person signing the Application.
29.3 In case of JV, the application of the provisions as stated under ITA
Sub Clause 29.2 shall extend up to each partner of that existing or
intended JV.
29.4 Any interlineations, erasures, or overwriting will be valid only if they
are signed or initialled by the Person(s) signing the Application.
29.5 Person(s) signing the Application shall describe his or her name,
address, position along with his or her national Identification
Number, if any.
E. Application Submission
30. Sealing, 30.1 The Applicant shall enclose the original in one (1) envelope and all
Marking and the copies of the Application in another envelope, duly marking the
Submission envelopes as “ORIGINAL” and “COPY.” These sealed envelopes
of Application will then be enclosed and sealed in one (1) single outer envelope.
22
CPTU-IMED PQW5-OTM (International)
30.3 The Applicant is solely and entirely responsible for pre-disclosure
of Application information if the envelope(s) are not properly sealed
and marked.
31. Deadline for 31.1 Applications shall be delivered to the Employer at the address
Submission specified in the ADS and no later than the date and time specified
of Application in the ADS.
32. Late 32.1 Any Application received by the Employer after the deadline for
Application submission of Applications as stated under ITA Sub Clause 31.1
shall be declared LATE, excluded, and returned unopened to the
Applicant.
34. Application 34.1 Applications shall be examined and evaluated only on the basis
Evaluation of the conditions, criteria and requirements defined in the Pre-
qualification Document.
34.3 The Head of the Procuring Entity may form a Technical Sub-
Committee (TSC) of experienced persons to assist the TEC in
the examination and evaluation.
35. Evaluation 35.1 The TEC may consider an Application as qualified in the
Process Evaluation, only if it is submitted in compliance with the
mandatory requirements set out in the Pre-qualification
Document. The evaluation process should begin immediately
after application opening following two broad steps:
(a) Preliminary examination
(b) Technical examination and responsiveness
24
CPTU-IMED PQW5-OTM (International)
(d) verification of the completeness of the Specialist Subcontractor
Information (Form PQW5-4) as furnished in Section 3:
Application Forms;
(e) verification of that the Applicant’s country of origin is not
ineligible;
(f) verification of that the Applicant is enrolled in the relevant
professional or trade organisations registered in its country of
origin;
(g) verification of that the written authorisation confirming the
signatory of the Applicant to commit the Application and the
subsequent Tender has been attached with the Application
Submission Letter (Form PQW5-1) as stated under ITA Sub
Clause 29.2; in order to check the authenticity of the Application
and the Applicant itself;
(h) verification of the eligibility in terms of legal capacity and
fulfilment of taxation obligations by the Applicant;
(i) verification of that all the documents required, as stated under
ITA Clause 28 for an Application, has been provided and
requirements met by an Applicant;
(j) verification of that all the documents required, as stated under
ITA Clause 18 and ITA Clause 27.2 for a Joint Venture
Application, has been provided and requirements met, if it is a
joint venture Application;
(k) verification of that the Applicant is not insolvent, in receivership,
bankrupt, in the process of bankruptcy or temporarily barred;
(l) verification of the status of claims, arbitration and other litigation
cases of the Applicant as stated under ITA Clause 5 and ITT
Clause 13;
37. Technical 37.1 Secondly, the TEC will evaluate the technical aspects of the
Examination Application submitted as stated under ITA Clauses 27 and 28, to
and confirm that all mandatory requirements have been met which
Responsivenes may follow the order below.
s 37.2 The TEC’s determination of an Applicant’s responsiveness is to
be based on the documentary evidence as stated under ITA
Clause 25 without recourse to extrinsic evidence.
37.3 Information contained in an Application submission that was not
requested in the Pre-qualification Document shall not be
considered in evaluation of the Application.
37.4 An Application shall be considered responsive in the evaluation,
only when it is submitted in compliance with the mandatory
requirements set out in the Pre-qualification Document without
material deviation or reservation.
37.5 If, after the examination of the conditions and the mandatory
requirements of the Application, the TEC determines that the
Application is not responsive in accordance with ITA Clause 25,
it shall consider the Application disqualified.
CPTU-IMED PQW5-OTM (International)
37.6 If an Application is considered disqualified by the TEC, it will not
subsequently be made qualified by correction of the material
deviation or reservation.
38. Clarification 38.1 The TEC may ask the Applicants for clarification on their
on Application Applications about specific matters, in order to facilitate the
examination and evaluation of Applications. The request for
clarification by the TEC and the response from the Applicants
shall be in writing, and Application clarifications which may lead
to a change in the substance of the Application or in any of the
key elements of the Application will neither be sought nor be
permitted.
38.2 Any request for clarifications by the TEC shall not be directed
towards making an apparently disqualified Application
qualified and reciprocally the response from the concerned
Applicant shall not be articulated towards any addition,
alteration or modification to its Application.
40. Rejection of 40.1 The Employer may, in the circumstances when evidence of
All Applications professional misconduct affecting seriously the Procurement
process has been established, reject all Applications following
recommendations from the TEC only after the approval of such
recommendations by the Head of the Procuring Entity.
26
CPTU-IMED PQW5-OTM (International)
40.2 The Employer, on justifiable grounds, may annul the
Procurement proceedings with prior approval of the Head of the
Procuring Entity, any time prior to the deadline for submission of
subsequent Tenders following specified procedures.
41. Informing 41.1 Notice of the rejection will be given promptly within seven (7)
Reasons for days of decision taken by the Employer to all Applicants and, the
Rejection Employer will, upon receipt of a written request, communicate to
any Applicant the reason(s) for its rejection but is not required to
justify those reason(s).
G. Pre-qualification
42. Pre- 42.1 All Applicants who’s Applications have met or ‘passed’ the
qualification of minimum specified requirements will, to the exclusion of all
Applicants others, be pre-qualified by the Employer.
44. Notification of 44.1 The Employer, upon completion of the examination and
Pre- evaluation of the Applications with approval of the Head of the
qualification Procuring Entity, shall notify all Applicants in writing, of the
names of those Applicants who have been pre-qualified.
45. Debriefing of 45.1 The Employer shall, upon receipt of a request from an
Applicants unsuccessful Applicant, notify that Applicant in writing of the
grounds for its exclusion, but the Employer is not bound to
provide any further information or explanation of those
grounds.
46.4 In the first instance, the Applicant shall submit his or her
complaint to the Employer who issued the Pre-qualification
Document.
46.5 The place and address for the first stage in the submission of
complaints to the administrative authority is provided in the
ADS.
47. Invitation for 47.1 Promptly after the Notification of Pre-qualification, the
Tenders Employer shall invite subsequent Tenders from only the
Applicants that have been pre-qualified as stated under ITA
Sub Clause 44.1.
48. Changes in 48.1 Any change in the structure or formation, after an Applicant
Qualifications being pre-qualified and invited to tender, shall not be permitted
of Applicants to submit Tender without the written approval of the Head of
Procuring Entity prior to the deadline for submission of
Tenders.
28
CPTU-IMED PQW5-OTM (International)
46.7
ITA Amendments of, and Supplements to, Clauses in the Instructions to Applicants
Clause
IFP IDENTIFICATION NO: ________________________________________
A. General
ITA 1.1 The Employer is [state name of Employer] represented by [state name of representative]
[if there is more than one(1) lot, individual lots are to be identified]
ITA 5.1 Applicants from the following countries are not eligible
B. Pre-qualification Document
ITA 8.2 The following are authorised agents of the Employer for the purpose of issuing the Pre-
qualification Document:
Agent’s Name:
Address:
Telephone No.:
Fax No.:
e-mail address:
[if not applicable, please specify “None”. If there is more than one (1) Agent, then list all Agent’s names and contact
details]
ITA 9.1 For clarification of Pre-qualification Document purposes only, the Employer’s
address is:
Attention:
Address:
30
CPTU-IMED PQW5-OTM (International)
Telephone:
Fax No.:
e-mail address:
C. Qualification Criteria
ITA 13.1 Non-performance of a contract shall not occur within the last [insert number] years.
[a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of
IFP]
ITA 13.2 All pending litigation shall in total not represent more than [ insert number] percent of the
Applicant’s networth.
ITA 13.3 The minimum requirements of Leading Partner and other Partner(s) of a JV shall be as
follows :
ADS Clauses Requirements Requirements for Requirements for other
References by summation Leading Partner Partner(s)
[a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of
IFP]
[Employer is required to specify here the nature, physical size, complexity, methods/construction
technology or other characteristics satisfying the requirements for similarity within the scope of the
proposed Works]
[the minimum number of contracts will depend upon the size and type of construction work, and the Employer should
make its own judgement based upon its experience in the sector and construction industry. For large works, it could
be one (1) contract of similar nature during the last (minimum) three (3) years; years counting backward from the date
of publication of IFP.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, only
when applicable, shall be mentioned separately for each lot in the package]
ITA USD/GBP/EUR/JPY
14.1(c) delete not appropriate
A satisfactory completion of similar works of at least BDT [insert amount] i.e.
32
CPTU-IMED PQW5-OTM (International)
[insert amount] equivalent under [state number] of contract(s) over a period of [state number] years
shall be required.
[the minimum value of the similar works under a single or multiple number of contract(s) is recommended to be
between 60 and 75 percent of the estimated cost , rounded off to nearest BDT thousand, of the proposed work during
the last (minimum) three (3) years; years counting backward from the date of publication of IFP.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, only
when applicable, shall be mentioned separately for each lot in the package]
[ the required average annual construction turn over is recommended to be about twice the estimated
annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract
size the lesser the multiplier should be. The period may be about five (5) years minimum; years counting
backward from the date of publication of IFP.]
Example:
Estimated Contract Value: BDT 24 million
Contract period: 18 months
Estimated Annual Cash Flow: BDT 16 million
Required average annual construction turnover: Tk 32 million, using a multiplier of 2.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be
mentioned separately for each lot in the package]
ITA USD/GBP/EUR/JPY
15.1(b) delete not appropriate
The minimum Tender Capacity shall be: BDT [insert amount] i.e. [insert
amount] equivalent.
[the required Tender Capacity is recommended to be between 70 and 80 percent of the estimated cost ,
rounded off to nearest BDT thousand, of the proposed work]
[the following formulae may be used to assess the Tender Capacity:
Assessed Tender Capacity = (A x N x 1.5 – B)
where;
A = maximum value of works performed in any one year during the last five(5) years; years counting backward from
the date of publication of IFP
N = Completion time of the proposed work in years; its value being taken never as less than one (1)
B = Value of existing commitments and works to be completed during the next N years.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be
mentioned separately for each lot in the package]
ITA The minimum amount of liquid assets or working capital or credit facilities of the Applicant
15.1(c) USD/GBP/EUR/JPY
delete not appropriate
shall be BDT [insert amount] i.e. [insert amount] equivalent.
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction
rate (straight line distribution), accessible or available after taking into account the financial requirements
of existing commitments. The actual period will depend on the speed with which the Employer will pay
the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to
certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:
Contract Value: BDT 24 million
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month
Therefore, the minimum required liquid asset will be BDT 4 million, i.e. 3 months cash flow based on the above
assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be
mentioned separately for each lot in the package]
ITA A Construction Project Manager shall have the following qualifications and experience:
34
CPTU-IMED PQW5-OTM (International)
16.1(a)
ITA The minimum number of Engineers with qualifications and experience shall be as
16.1(b) follows[state requirements] :
In Similar
Total Works
Works
No. Position Experience
Experience
(years)
(years)
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be
necessary for each lot in the package, subject to the nature of the control required over each package]
ITA Other key staff with qualifications and experience shall be as follows [state requirements] :
16.1(c) In Similar
Total Works
Works
No. Position Experience
Experience
(years)
(years)
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be
necessary for each lot in the package, subject to the nature of the control required over each package]
ITA 17.1 The Applicant shall own or have proven access to hire or lease of the major construction
equipments, in full working order as follows :
Minimum Number
No Equipment Type and Characteristics
Required
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be
necessary for each lot in the package, subject to the nature of the control required over each package]
ITA 18.2 In the case the Applicant’s Leading Partner’s country of origin is Bangladesh, the value of
non-judicial stamp for execution of the Joint Venture agreement shall be BDT [insert
amount]
36
CPTU-IMED PQW5-OTM (International)
ITA 18.3 In the case the Applicant’s Leading Partner’s country of origin is Bangladesh, the Letter of
Intent along with the proposed agreement shall be authenticated by a Notary Public.
ITA 18.5 The minimum qualification requirements of Leading Partner and other Partner(s) of a
JV shall be as follows :
ADS Clauses Requirements Requirements for Requirements for other
References by summation Leading Partner Partner(s)
ITA 19.4 The Employer intends to execute the following specific components of the proposed
Works by the Nominated Subcontractor(s) :
[state the components of the proposed works ; if not applicable state ‘none’]
ITA 20.1 Domestic Preference [shall/shall not] be applicable for eligible national Tenderers
[delete as appropriate]
[Domestic Preference shall not be mandatory and again any relaxation will require recommendation of the CCEA]
D. Application Preparation
ITA 23.4 Use of Pre-qualification Document posted in the website [ is/isn’t] permitted for
preparation of Applications.
[delete as appropriate]
ITA The Applicant shall provide with its Application the following additional documents:
25.1(l) [in case of purchase of capital equipment by the Contractor as part of the overall Contract, a Performance Statement
of the capital equipment in Bangladesh may be necessary and may be requested. if no other documents are required
then specify “none”]
In addition to the original of the Application, [state number] copies shall be submitted.
ITA 29.1
[usually only two copies are needed, ask for more only if they are essential]
ITA 31.1 For Application submission purposes only, the Employer’s address is:
Attention:
Address:
The deadline for the submission of Applications is:
Time & Date:
Address:
Time & Date:
G. Pre-qualification
ITA 46.5 The name and address of the office where complaints to the Employer under Rule 57 of
The Public Procurement Rules,2008 are to be submitted is:
Name:
Address:
Fax No.:
e-mail address:
38
CPTU-IMED PQW5-OTM (International)
Section 3. Application Forms
Form Title
Application Forms
809047770.docx 39
Application Submission Letter (Form PQW5-1)
[This letter should be completed and signed by the Authorised Signatory
preferably on the Letter-Head Pad of the Applicant]
This Package is divided into the following Number of Lots [indicate number of Lot(s)]
We, the undersigned, apply to be pre-qualified for the referenced Works and Physical Services
and declare that:
[insert the nationality of the Applicant, including that of all partners in case of a Joint
Venture, and the nationality of each already identified subcontractor, if applicable];
(c) we are submitting this Application as a sole Applicant in accordance with ITA
Sub Clause 27.1;
or
we are submitting this Application as the partners of a JVCA, comprising the
following other partners in accordance with ITA Sub Clause 27.2;
(f) we intend to subcontract an activity or part of the Works, in accordance with ITA
Clause 19, to the following Specialist Subcontractor(s);
40
CPTU-IMED PQW5-OTM (International)
Activity or part of the Name of Specialist
Works Subcontractor with
Address
(g) we, including as applicable any JVCA partner, confirm that we do not have a
record of poor performance, such as abandoning the works, not properly
completing contracts, inordinate delays, or financial failure as stated in ITA
Clause 5, and that we do not have, or have had, any litigation against us, other
than that stated in the Applicant Information (Form PQW5-2);
(h) we, including as applicable any JVCA partner, confirm that we do not have a
record of insolvency, receivership, bankrupt or being wound up, our business
activities were not been suspended, and it was not been the subject of legal
proceedings in accordance with ITA Clause 5;
(i) we, including as applicable any JVCA partner, confirm that we have fulfilled our
obligations to pay taxes and social security contributions applicable under the
relevant national laws and regulations of our country(s) of origin in accordance
with ITA Clause 5;
(j) we, including as applicable any JVCA partner or Specialist Subcontractor for any
part of the contract resulting from this pre-qualification process, have not been
declared ineligible by any International Development Agency or the Government
of Bangladesh on charges of engaging in corrupt, fraudulent, collusive or coercive
practices in accordance with ITA Clause 5; or by an act of compliance with a
decision of the United Nations Security Council.
(k) furthermore, we are aware of ITA Clause 4 concerning such practices and
pledge not to indulge in such practices in competing for or in executing the
Contract;
(l) we are not participating as Applicants in more than one Application in this pre-
qualification process;
(m) we understand that you may cancel the prequalification process at any time and
that you are neither bound to accept any Application that you may receive nor to
invite the pre-qualified Applicants to tender for the contract subject of this
prequalification, without incurring any liability to the Applicants.
[If there is more than one (1) signatory, or in the case of a JVCA, add other boxes
and sign accordingly]
Attachment 1:
[ITA Sub Clause 27.1 and 27.2]
Written confirmation authorising the above signatory(ies) to commit the Applicant and the
subsequent Tenderer
[and, if applicable]
Attachment 2:
[ITA Sub Clause 18.2 & 18.3]
JV Agreement / Letter of Intent to form JV with draft proposed Agreement
809047770.docx 41
Applicant Information (Form PQW5-2)
[This Form should be completed only by the Applicant, preferably on its Letter-Head Pad]
Partnership
Government-owned Enterprise
Others
[please describe, if applicable]
1.5 Applicant’s year of registration
1.6 Applicant’s authorised representative details
Name
National ID number, if any
Address
Telephone / Fax numbers
e-mail address
1.7 Litigation [ITT Cause 13]
Information on non-performance of contract and pending litigation furnished in PQW5-5
1.8 Applicant to attach photocopies of [All documents required under ITT Clauses 5 and 25]
the original documents mentioned
42
CPTU-IMED PQW5-OTM (International)
aside
The following two information are applicable for national Applicants
1.9 Applicant’s Value Added Tax
Registration (VAT) Number
1.10 Applicant’s Tax Identification
Number(TIN)
[The foreign Applicants, in accordance with ITT Clause 5, shall provide evidence by a written
declaration to that effect to demonstrate that it meets the criterion]
2. Qualification Information of the Applicant [ITT Clause 12]
2.1 General Experience in Construction Works of Applicant
Start End Years Contract No and Name of Contract Role of
Month Month Name and Address of Employer Applicant
Year Year [Prime/
Brief description of Works
Sub/
Managem
ent]
809047770.docx 43
2.4 Existing commitments and works
[targeted to be completed by the Intended Completion Date of the proposed works;
ITT Sub Clause 12.3]
Name of Contract Target Value of Existing
Contract No [reference] of [year] Completion Commitments and Works
Date
Name of Employer Amount & USD/GBP/EUR/JPY
Contact Address Currency delete not appropriate
Tel/fax Equivalent
2.5 Financial Resources available to meet the construction cash flow [ITT Sub Clause
12.3]
No Source of Financing Amount Available
In order to confirm the above statements the Applicant shall submit, as applicable, the documents
mentioned in ITT Clause 28.
2.6 Contact Details [ITT Clause 28]
Name, address, and other contact details of Applicant’s Bankers and other Employer(s) that
may provide references, if contacted by this Employer
[Tenderer to complete details of as many personnel as are applicable. Each personnel listed above
should complete the Personnel Information (Form PQW5-6]
2.8 Major Construction Equipments proposed to carry out the Contract [ITT Clause 28]
Condition Owned, leased or to
Item of Equipment (new, good, be purchased
average, poor) (state owner, lessor
or seller)
44
CPTU-IMED PQW5-OTM (International)
JVCA Partner Information (Form PQW5-3)
[This Form should be completed by each JVCA partner].
Partnership
Government-owned Enterprise
Other
(please describe, if applicable)
1.5 JVCA Partner’s year of registration
1.6 JVCA Partner’s authorised representative details
Name
National ID number, if any
Address
Telephone / Fax numbers
e-mail address
1.7 Litigation [ITT Cause 13]
Information on non-performance of contract and pending litigation furnished in Form
PQW5-5
1.8 JVCA Partner to attach copies of
the original documents mentioned
aside [All documents required under ITT Clauses 5 and 25]
809047770.docx 45
The following two information are applicable for national JVCA Partners only
1.9 JVCA Partner’s Value Added Tax
Registration (VAT) Number
1.10 JVCA Partner’s Tax Identification
Number (TIN)
[The foreign JVCA Partners, in accordance with ITT Clause 5, shall provide evidence by a written
declaration to that effect to demonstrate that it meets the criterion]
2. Key Activity(ies) for which it is intended to be joint ventured [ITT Clause 18]
Elements of Activity Brief description of Activity
Employer’s Name
Address
Tel / Fax
e-mail
Brief description with
justifications of the
similarity compared to
[state justification in support of its similarity compared to the
this Employer’s
proposed works]
requirements
3.3 Average annual construction turnover [ITT Sub Clause 12.3]
46
CPTU-IMED PQW5-OTM (International)
[total certified payments received for contracts in progress or completed for each
year of works in progress or completed; using selling exchange rate quoted by the
source being Bangladesh Bank on the date reported, if applicable]
3.5 Financial Resources available to meet the construction cash flow [ITT Sub Clause
12.3]
No Source of financing Amount Available
Amount & USD/GBP/EUR/JPY
Currency delete not appropriate
Equivalent
In order to confirm the above statements the JVCA Partner shall submit, as applicable, the
documents mentioned in ITT Clause 28.
3.6 Contact Details [ITT Clause 28]
Name, address, and contact details of Tenderer’s Bankers and other Employer(s) that may
provide references if contacted by this Employer
809047770.docx 47
Signature
(Name of Authorized Signatory of the JVCA Partner)
Specialist Subcontractor Information (Form PQW5-4)
[This Form should be completed by each Subcontractor, preferably on its Letter-Head Pad]
Partnership
Government-owned Enterprise
Other
(please describe)
1.5 Subcontractor’s year of registration
1.6 Subcontractor’s authorised
representative details
Name
Address
Telephone / Fax numbers
e-mail address
1.7 Subcontractor to attach copies of All documents to the extent relevant to ITT Clause 5
the following original documents and 25 in support of its qualifications
The following two information are applicable for national Subcontractors
1.8 Subcontractor’s Value Added Tax
Registration (VAT) Number
48
CPTU-IMED PQW5-OTM (International)
1.9 Subcontractor’s Tax Identification
Number(TIN)
[The foreign Subcontractors , in accordance with ITT Clause 5, shall provide evidence by a written
declaration to that effect to demonstrate that it meets the criterion]
2. Key Activity(ies) for which it is intended to be Subcontracted [ITT Clause 19]
2.1 Elements of Activity Brief description of Activity
2.2 List of Similar Contracts in which the proposed Subcontractor had been engaged
Name of Contract
and Year of
Execution
Value of Contract
Name of Employer
Contact Person and
Contact details
Type of Work
Performed
___________________________________________________
Signature
(Name of Authorized Signatory of the Proposed Sub-Contractor)
809047770.docx 49
Applicant’s Legal Name: [insert full name]
Date: [dd/mm/yy]
Joint Venture Party Legal Name:[insert full name]
IFP No. and title: [insert IFP number and title]
Page [insert page number] of [insert total number] pages
50
CPTU-IMED PQW5-OTM (International)
Personnel Information (Form PQW5-6)
[This Form should be completed for each person proposed by the Tenderer on Form PW5-2 & PW5-3, where
applicable]
B. Personal Data
Name:
Date of Birth:
National ID Number:
Professional Qualifications:
1.
2.
3.
4.
809047770.docx 51
Contact [manager/personnel officer]:
D. Professional Experience
Summarise professional experience over the last twenty (20) years, in reverse chronological order.
Indicate particular technical and managerial experience relevant to the project.
__________________________
(Name and Signature of the Proposed Personnel)
52
CPTU-IMED PQW5-OTM (International)
Section 4. Scope of Works
Describe the Works in sufficient detail to identify location, nature, and complexity. Estimated
quantities of major components of the Works should be indicated in the Bill of Quantities.
2. Construction Period(s)
State expected construction period and time in days or weeks or months; if alternative time
schedules are permitted, give the range of acceptable construction periods.
Provide general information on the climate, hydrology, topography, geology, access to site,
transportation and communications facilities, medical facilities, project layout, facilities,
services provided by the Employer, and other relevant data.
809047770.docx 53
Notification and advertisement of the Invitation for Prequalification (IFP) shall be conducted in
accordance with Rule 90 of the Public Procurement Rules, 2008 including amendment thereto
unless otherwise specified in the foreign aided project documents. The IFP shall follow the
Sample Format indicated hereafter, and as a Specific Procurement Notice shall be issued in (i)
at least one national English Newspaper or Publication of wide International circulation or (ii)
in UN Development Business online and in dgMarket and if necessary, to Foreign Trade Missions
in Bangladesh of, or Bangladesh Trade Missions abroad in, countries with likely potential
Applicants. The posting of notification in CPTU’s website http://www.cptu.gov.bd shall be
mandatory.
The IFP provides information that enables potential Applicants to decide whether to participate
or not. Apart from the essential items listed in the Standard Prequalification Document, the IFP
shall also indicate any important or specialized prequalification requirements requested to
qualify for the pre-qualification.
Prior to publication of a Specific Procurement Notice (SPN) it is usual that the General
Procurement Notice (GPN) in case of foreign aided project be posted in dgMarket. Further,
pursuant to Rule 16 (11) of the Public Procurement Rules, 2008 including amendment thereto, it
is mandatory that the Total Procurement Plan and updated Annual Procurement Plan under
Development Budgets and, Annual Procurement Plan under Revenue Budgets; all to the extent
above the thresholds as specified in Schedule II of the PPR, 2008, be duly published in CPTU’s
website http://www.cptu.gov.bd and Employer’s own website, if any.
Sample Format
[to be used for publication in the dgMarket]
54
CPTU-IMED PQW5-OTM (International)
[Loan/Credit/Grants No, where applicable]
This Invitation for Prequalification follows the General Procurement Notice that appeared in Development
Business No. [insert number] of [insert date]1 on-line and in dgMarket as well as the Annual Procurement Plan
posted on [insert date] in CPTU’s website for this project .
Interested eligible Applicants may obtain further information from and inspect the Prequalification Document at
the [insert name of Employer] address below [state address at end of document] from [insert office hours].6 A
complete set of the Prequalification Document in English may be purchased by interested Applicants (a) on the
submission of a written application to the address below and upon payment of a non-refundable fee 7 of [insert
amount in BD Taka] or in [insert amount in specified convertible currency]. The method of payment will be [insert
method of payment].8 The document will be issued by [describe delivery procedure] [if permitted insert and
alternatively the PQD can be purchased electronically [describe purchase procedure].
Applications for prequalification should be submitted in sealed envelopes, delivered to the address below 9 by
[insert date], 10 and be clearly marked “Application to Pre-qualify for [insert name of the subsequent Tender with
Application Reference and Lot Number(s)].”
[ name of officer]
[ name of office]
[postal address] and/or [street address]
[ telephone number with country and city code]
[ facsimile or cable number]
[email address]
Notes :
1. Day, month, year; for example 31 January 2002,where applicable.
809047770.docx 55
2. [Insert the following if applicable]. This contract will be jointly financed by [insert name of cofinancing agency].
Employer' s/DP ' s
Sample Format
[to be used for English Newspaper or publication of wide international circulation]
56
CPTU-IMED PQW5-OTM (International)
Invitation for Pre-qualification (IFP)
The Invitation for Pre-qualification (IFP) is a copy of the standard format as appears on the
website and used for published advertisement that provides relevant and essential information to
help Applicants to decide whether or not to participate in the particular Pre-qualification. This is
provided in the Pre-qualification Document for information only. This should not be included in the
PRE-QUALIFICATION DOCUMENT.
809047770.docx 57
17 Pre-qualification Document Last Selling Date < select > V
(must be the date prior to the day of Application
Submission Closing Date)
Date Time
18 Application Submission Closing Date and Time < select > V < select > V
19 Application Opening Date and Time < select > V < select > V
20 Name & Address of the office(s) Address
- Selling Pre-qualification Document < type in name >
- Downloading Pre-qualification Document < type in name >
(This is optional. If permitted by the Procuring Entity;
mention the web address where the electronic version
of PQD will be available. Specify the detail
procedures for payment of the cost of PQD by the
Applicants, if not being provided free of charges)
NO CONDITIONS APPLY FOR SALE , PURCHASE OR DISTRIBUTION OF PQDs
- Receiving Pre-qualification Document < type in name >
- Opening Pre-qualification Document < type in name >
21 Place / Date / Time of Place Date Time
pre-Pre-qualification Meeting (Optional) < select > V < select > < select >
INFORMATION FOR TENDERER
22 Eligibility of Applicant < type in name >
23 Brief Description of Works < type in name >
24 Brief Description of Physical Services < type in name >
25 Price of Pre-qualification Document < type in price >
Lot No Identification of Lot Location Completion Time in Weeks / Months
26 1 < type in name > < type in name > <type in>
EMPLOYER DETAILS
30 Name of Official Inviting Application < type in name >
31 Designation of Official Inviting Application < type in name >
32 Address of Official Inviting Application < type in name >
33 Contact details of Official Inviting Application < Tel. No.> <Fax No.> <e-mail>
34 The Procuring Entity reserves the right to reject all the Applications or annul the Application proceedings
<select> : these fields are “pop-up” fields and the Employer will only have to select the correct name, address or date in order
to complete the form.
<type in name> : these fields are to be completed by typing in the relevant data.
Invitation for Pre-qualification
[for use when there are MULTIPLE lots in a package
This is the website format and as used for published advertisement.
It is included in this document for information only]
GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
1 Ministry/Division < select > V
2 Agency < select > V
3 Procuring Entity Name < type in name >
4 Procuring Entity Code Not used at present
5 Procuring Entity District < select > V
6 Invitation for < select > V < select > V < select > V
7 Invitation Ref No < type in name >
8 Date < select > V
KEY INFORMATION
9 Procurement Method < select > V < select > V
FUNDING INFORMATION
10 Budget and Source of Funds < select > V
11 Development Partners (if applicable) < type in name >
PARTICULAR INFORMATION
12 Project / Programme Code (if applicable) < use MOF code >
13 Project / Programme Name (if applicable) < use MOF name >
14 Proposed Tender Package No. < type in name >
15 Proposed Tender Package Name < type in name >
Date
16 IFP Publication Date < select > V
17 Pre-qualification Document Last Selling Date < select > V
(must be the date prior to the day of Application
Submission Closing Date)
Date Time
18 Application Submission Closing Date and Time < select > V < select > V
58
CPTU-IMED PQW5-OTM (International)
19 Application Opening Date and Time < select > V < select > V
20 Name & Address of the office(s) Address
- Selling Pre-qualification Document < type in name >
- Downloading Pre-qualification Document < type in name >
(This is optional. If permitted by the Procuring
Entity; mention the web address where the
electronic version of PQD will be available.
Specify the detail procedures for payment of the
cost of PQD by the Applicants, if not being
provided free of charges)
NO CONDITIONS APPLY FOR SALE , PURCHASE OR ISSUANCE OF PQDs
- Receiving Pre-qualification Document < type in name >
- Opening Pre-qualification Document < type in name >
Place / Date / Time of Place Date Time
21 pre-Pre-qualification Meeting (Optional) < select > V < select > < select >
INFORMATION FOR TENDERER
22 Eligibility of Applicant < type in name >
23 Brief Description of Works < type in name >
24 Brief Description of Physical Services < type in name >
25 Price of Pre-qualification Document < type in price >
Lot No Identification of Lot Location Completion Time in Weeks / Months
26 1 < type in name > < type in name > <type in>
EMPLOYER DETAILS
30 Name of Official Inviting Application < type in name >
31 Designation of Official Inviting Application < type in name >
32 Address of Official Inviting Application < type in name >
33 Contact details of Official Inviting Application < Tel. No. > < Fax No. > < e-mail >
34 The Procuring Entity reserves the right to reject all the Applications or annul the Application proceedings
<select> : these fields are “pop-up” fields and the Employer will only have to select the correct name, address or date in order to complete the form.<type in name> :
these fields are to be completed by typing in the relevant data.
Note: All italicized text (including footnotes) is for use in preparing this form and shall be deleted from the final product.
809047770.docx 59
Submission of Applications
Are the
Applicant’s deficiencies
Does material? YES
Applicant substantially NO Reject the Application.
comply with Prepare reasons for
preliminary rejection
YES
examination
YES
Qualification Assessment
General Experience
Specific Experience, Similar Works Experience
Average Construction Turnover, Tender
YES Capacity
Liquid Asset, Personal Capacity,
Equipment Capacity, J.V. Requirements; if any
History of Non-Performing Contracts
Pending Litigation
Are the
Applicant’s deficiencies material ?
YES
NO
Does the
Applicant meet all the NO NO
qualification criteria?
YES
Does Conditionally
clarification and/or NO qualify the
Qualify the Applicant
substantiation of Information Applicant
substantially meet the
qualification criteria
60
CPTU-IMED PQW5-OTM (International)