QUESTION 1:
Which one of the following activities would span all stages of a software development life cycle
(SDLC) in waterfall-based software development?
a. Coding
b. Testing
c. Project management
d. Design
e. Requirements specification
Correct Answer: c. Project management
Detailed Solution:
In SDLC, project management phase spans across all stages. Without SDLC, the project manager
suffers from 99% complete syndrome.
QUESTION 2:
In waterfall model of software development, unit testing is carried out during which phase of the
waterfall model?
a. Implementation phase
b. Testing phase
c. Maintenance phase
d. Design phase
e. Requirements specification phase
Detailed Solution:
During development/implementation phase, unit testing is usually performed by the developers to
ensure proper development.
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
QUESTION 3:
In waterfall-based development, which one of the following phases accounts for the maximum
effort during development of a typical software?
a. Implementation
b. Testing
c. Designing
d. Specification
e. Feasibility study
Detailed Solution:
During development phase, testing usually accounts for maximum effort, whereas for overall
SDLC, maintenance phase account for maximum effort. Please refer slide 20 of week 2 lecture
material.
QUESTION 4:
Which of the following advantages can be expected to accrue when iterative waterfall model is used
for a project?
a. Easy to understand, easy to use, especially by inexperienced staff
b. Milestones are well understood by the team
c. Provides requirements stability during development
d. Strong management control (planning, staffing, tracking etc) on the project
e. Project progress can be accurately monitored by the project manager, as a result schedule
slippages are rare
f. Continual integration of the developed code occurs throughout the life cycle
g. Continual customer interactions
QUESTION 5:
Which of the following project characteristics would suggest that a waterfall model-based
development would be appropriate?
a. Requirements are well defined and stable
b. Technology is understood
c. Development team have experience with similar projects
d. Delivery date has been aggressively set
e. Substantial reuse of code is targeted
Detailed Solution:
Delivery date and code reuse is not considered in waterfall model. Please refer slide 62 of week 2
lecture material for more information.
QUESTION 6:
Which of the following are not known shortcomings of the iterative waterfall model of software
development?
a. All requirements must be known upfront
b. Can give a false impression of progress
c. Integration is one big bang at the end
d. Little opportunity for customer to pre-view the system.
e. Inadequate documentation produced as part of the process
f. Number of phases in the model is ill defined
QUESTION 7:
Which one of the following may be experienced by a software development team when it adopts a
systematic development process model in preference to a build-and-fix style of development?
a. Increased documentation overhead
b. Increased development cost
c. Increased maintainability
d. Increased development time
e. Increased code size
f. Increased code efficiency
Detailed Solution:
A software development team when it adopts a systematic development process model in preference
to a build-and-fix style of development experience increased documentation overhead and
maintainability.
QUESTION 8:
Prototyping life cycle model is appropriate when a project suffers from which one of the
following risks?
a. Schedule slippage
b. Manpower turnover
c. Incomplete and uncertain requirements
d. Poor quality of outsourced work
e. Technological obsolescence
Detailed Solution:
Prototyping model is best suited when the requirement is unclear. For more information, please
refer slide 80 of week 2 lecture material.
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
QUESTION 9:
Which of the following sections are not important to an effective business case document and can
be omitted?
a. Cost
b. Benefit
c. Risk
d. Configuration management
e. Team structure
Configuration management and team structure are not essential for an effective business case
document. Therefore, these can be omitted. You can refer slide 133 of week 2 lecture material for
additional information.
QUESTION 10:
The operation phase of the waterfall model is a synonym for which one of the following phases?
a. Coding and unit testing phase
b. Integration and system testing phase
c. Maintenance phase
d. Design phase
e. Requirements specification phase