Check List GR
BTS ACCEPTANCE TEST DOCUMENT
Jakarta, ……………………...2014
Hereby stated description and item below refer to the documents attached have been
approved for construction:
Checked
No. Table of Contents Remarks
HTI HS
1 BOQ
NodeB BOQ
2.1 NodeB ATP
Acceptance test
3.1 Installation Checklist
Indoor Installation Checklist
Outdoor Installation Checklist
4.1 Installation Checklist
Feeder System List
Fiber Optic list
4.2 BTS Commissioning Record
Network Parameter Checklist
4.3 Integration Test
Basic Service Checklist
4.4 Handover Test
4.5 24 Hours Stability Test
4.6 Alarm Query Test
4.7 Punch List Summary
5 VSWR Measurement
6 Site Documentation
7 Capture LMT
8 SIR Approve
WMPT 03020JQE WCDMA Main Processing & Transmission Unit (4E1 + 2FE), 1*1 1 1 New
04012542 Internal Cable Set, BTS3900, Single Cabinet Internal Cable Set 0 0 NA
>> B1/1 BTS3900A WCDMA S1/1/1 (Band 1 2100M, CE U:128 D:128, DC -48V)
Auxiliary Kit 02239275 3900 Series BTS Macro, Site Auxiliary Material Kit (G/U/L) 0 0 Existing
Single Cable, Shielding Straight Through Cable, 10m, MP8-IV,
Auxiliary 04046100 0 0 NA
CC4P0.5P430U (S), MP8-IV, LSZH
Signal Cable, Shielded Straight Through Cable, 10m, MP8-II,
Auxiliary 04070012 0 0 NA
CC4P0.5GY(S), MP8-II, FTP
Blank Label, DB0699, Huawei D Blank Cable Label, 40 Groups
Auxiliary 29040316 0 0 NA
40 Pcs, 4 Colum*10 Rows
Auxiliary 29041060 Signal Cable Label 1 1 New
Auxiliary 29041061 Power Cable Label 1 1 New
>> >> BTS3900A WCDMA S1/1/1 (Band 1 2100M, CE U:128 D:128, DC -48V)
Trunkcable,20m,120ohm,4E1,0.4mm,D26M(3ROW),120CC8P0.
Trunk Cable 04120119 0 0 Existing
4P430U(S)
Jumper
04130029 RF Cable,4.0m,7/16DIN50AM,COAX50-8.7/3.55B,DIN50SM-II 0 0 Existing
Cable
Outsourcing Cable,SFP High Speed Transmission
CPRI 2M 04050098 3 3 New
Cable,2.0m,SFP20M,CC2P0.32B,SFP20M,For Indoor
7/8" Aluminium Feeder Kit,Antenna Jumper Included,General
Feeder Kit 02236760 0 0 Existing
Area
Coaxial Cable,Smooth Copper
Feeder 7/8” 25070134 Tube,50ohm,27.8mm,21.5mm,9.3mm,Black, 7/8" Aluminium 0 0 Existing
Cable,With a package exempted from fumigating
Semi Rigid Semi Rigid Cable 6 6 New
Grounding
21120291 Grounding Unit 0 0 Existing
Unit
Base Frame 21150604 HERT Cabinet Base 0 0 Existing
Blue 16mm 25030533 Wire, 450/750V, 227 IEC 02 (RV) 16mm^2, black, 85A 10 10 New
Black 16mm 25030535 Wire, 450/750V, 227 IEC 02 (RV) 16mm^2, blue, 85A 10 10 New
Grounding
25030429 Wire,450/750V,60227 IEC 02(RV)16mm^2,yellow green,85A 10 10 New
Cable
SITE ID : .....
T01-0101
□Pass □Fail □NA
Power-on Check of the BBU
T01-0102
□Pass □Fail □NA
Power-on Check of the RRU
T01-0103
Power-on Check of Boards- □Pass □Fail □NA
BTS3900A
T01-0104
Power-on Check of Boards- □Pass □Fail □NA
BTS3900
T01-0105
Power-on Check of Heat □Pass □Fail □NA
T01-01 Exchanger
T01
Hardware Status T01-0106
Hardware
Check □Pass □Fail □NA
Status Check of Boards
T01-0107
Status Check of E1/T1 Ports □Pass □Fail □NA
of IuB Interface
T01-0108
Status Check of Optical □Pass □Fail □NA
Modules of CPRI Interface
T01-0109
Status Check of Local □Pass □Fail □NA
Ethernet Port
T01-0110
Status Check of Ethernet □Pass □Fail □NA
Ports of IuB interface
T02-01 T02-0102
User Permission Locking Local Maintenance □Pass □Fail □NA
Management Terminal
T02-0103
□Pass □Fail □NA
Configuration Privilege
T02-0201
Querying NodeB Software □Pass □Fail □NA
Version
T02-0202
Querying Active NodeB □Pass □Fail □NA
Versions
T02-0203
□Pass □Fail □NA
Querying Board Version
T02-0204
Downloading NodeB □Pass □Fail □NA
Software Package
T02-0206
Synchronizing Software □Pass □Fail □NA
Version
T02-0207
□Pass □Fail □NA
Activating NodeB Software
T02-0208
Activating BootRom □Pass □Fail □NA
Package
T02-0209
Upgrading the NodeB □Pass □Fail □NA
Through the M2000
T02-03 T02-0301
License File Distributing a License File □Pass □Fail □NA
Management to the NodeB
T02-0401
T02-04 □Pass □Fail □NA
System Restart
Equipment
Management T02-0402
□Pass □Fail □NA
Querying NodeB Type
T02-0404
Board Blocking and □Pass □Fail □NA
Unblocking
T02-0405
□Pass □Fail □NA
NodeB Time Management
T02-0406
NodeB Time Zone □Pass □Fail □NA
Management
T02-0407
□Pass □Fail □NA
NodeB SNTP Management
T02-0408
RFU TX Switch □Pass □Fail □NA
Management
T02-0409
□Pass □Fail □NA
Hot Plugin on CPRI Port
T02-0410
Maintenance of the Power □Pass □Fail □NA
Supply System
T02-0411
Maintenance of the RRU □Pass □Fail □NA
Power System
T02-0412
Maintenance of the NodeB □Pass □Fail □NA
Clock
T02-0413
Querying NodeB Abnormal □Pass □Fail □NA
Status
T02-0501
□Pass □Fail □NA
E1/T1 Link Management
T02-05
T02-0502
IuB Interface □Pass □Fail □NA
IMA Group Management
Management
T02-0503
□Pass □Fail □NA
Ethernet Link Management
T02-0505
Standard Protocol Tracing □Pass □Fail □NA
at IuB Interface
T02-0206
□Pass □Fail □NA
Sector Management
T02-0507
□Pass □Fail □NA
Local Cell Management
T02-0508
□Pass □Fail □NA
Local Cell Operations
T02-0509
CE Consumption of R99 □Pass □Fail □NA
AMR12.2K Service
T02-0510
CE Consumption of R99 □Pass □Fail □NA
VP Service
T02-0511
CE Consumption of R99 □Pass □Fail □NA
PS384K Service
T02-0512
CE Consumption of □Pass □Fail □NA
HSDPA Service
T02-0601
Local Maintenance through □Pass □Fail □NA
Local Ethernet Port
T02-06
T02-0602
Maintenance Channel □Pass □Fail □NA
Remote Maintenance
Management
through Omch Channel
T02-0603
□Pass □Fail □NA
BootP Funcion
T02-0701
Uploading Data □Pass □Fail □NA
T02-07 configuration File
File management T02-0702
Dowloading Data □Pass □Fail □NA
Configuration File
PT. Huawei Services PT. Huawei Tech Investment
T02-0801
Checking NodeB Data □Pass □Fail □NA
Consistency
T02-0802
RTWP Measurement □Pass □Fail □NA
Monitoring
T02-0803
CPU/DSP Usage □Pass □Fail □NA
Monitoring
T02-08 T02-0804
Configuration RFU Temperature □Pass □Fail □NA
Management Monitoring
T02-0805
Cell Service Resource □Pass □Fail □NA
Query
T02-0806
RFU Output Power □Pass □Fail □NA
Monitoring
T02-0807
Board Service Resource □Pass □Fail □NA
Query
T02-09 T02-0901
□Pass □Fail □NA
Alarm Management Alarm Query
T02-1001
□Pass □Fail □NA
NE Startup
T02-1002
□Pass □Fail □NA
NE Shutdown
T02-1003
NodeB Software Download □Pass □Fail □NA
Start / Finish
T02-10 T02-1004
□Pass □Fail □NA
Typical Alarms Board Startup
T02-1005
□Pass □Fail □NA
Board Fault Alarm
T02-1006
□Pass □Fail □NA
E1/T1 Loss of Signal
T02-1007
E1/T1 Remote Alarm □Pass □Fail □NA
Indication
3.1 Installation Checklist
Remarks
Site Documentation
Remarks
Equipment Specific Checks
Procedure Pass Fail N/A Remark Audit
Remarks
Final Checks
Procedure Pass Fail N/A Remark Audit
Remarks
Remarks
Feeders
Procedure Pass Fail N/A Remark
Remarks
Connectors
Procedure Pass Fail N/A Remark
Remarks
Weather sealing
Procedure Pass Fail N/A Remark
Antenna Steelwork
Remarks
Remarks
Remarks
Remarks
Remarks
Feeder Grounding
Procedure Pass Fail N/A Remark
Concluding Checks
Procedure Pass Fail N/A Remark
T02-1008
IMA/UNI Link Loss of Cell □Pass □Fail □NA
Delineation
T02-1009
□Pass □Fail □NA
CCP Fault
T02-1010
Tx Branch Switch off □Pass □Fail □NA
Manually
T02-1011
□Pass □Fail □NA
RFU VSWR Abnormal
T02-1012
NodeB Clock Source □Pass □Fail □NA
Abnormal
T02-1013
□Pass □Fail □NA
FE Interface Fault Alarm
T02-1014
□Pass □Fail □NA
External Alarm
T04-01
T04 T04-0101
AISG ALD □Pass □Fail □NA
Antenna System TMA Maintenance
Management
Conclusion: Totally 64 items included for acceptance test, in which ____passed, ____ failed, and ____ were
not applicable.
Signature:__________________ Signature:__________________
Date:______________________ Date:______________________
RRU Feeder
No. RRU Panel N port VSWR Distance To Fault (DTF) Audit
Board Length(m)
RFU _TXM
1 RFU 0
RFU _TXD
RFU _TXM
2 RFU 2
RFU _TXD
RFU _TXM
3 RFU 4
RFU _TXD
Notes:
1. VSWR value shall be referring to the specification manual from the supplier.
2. Setting at site master for cable 7/8" (VF and cable loss shall refer to the specification manual from the supplier).
3. Setting at site master for cable 1-5/8" (VF and cable loss shall refer to the specification manual from the
supplier).
4. VSWR ≤ 1.3
5. DTF test will be carried out according to the test procedure and test result included in the test documentation.
CI
Antenna
Sector 2 direction(Azimuth)
Antenna Tilt (M+E)
(Degree)
CI
Antenna
Sector 3 direction(Azimuth)
Antenna Tilt (M+E)
(Degree)
CELL2
CELL3
CELL(2G)A
CELL1
CELL3
CELL(2G)B
CELL1
CELL2
CELL3 CELL(2G)C
CELL(2G)A CELL 1
CELL(2G)B CELL 2
CELL(2G)C CELL 3
Notes:
1. In the Target cell column, the parameter ARFCN &S-code is for 3G cell, the parameter BCCH &BSIC is for
2G cell.
2. Verify with the TOC if inter site neighbor relationship has been defined before test.
3. GSM 2G cell mush add corresponding 3G neighbor cell.
OK
--
This is to be confirmed that the BTS 3G has been running at least 24 hours without any
related self fault.
Remarks
Notes: The 24 hours is to be done in TOC/NOC, which will be passed if NODEB is normal operation and no alarm.
OK
--
Remarks
Notes: if the site is no active alarms then write “OK, no active alarm”, otherwise record the alarm information in detail
Note:
Please record in detailed for testing items that unable to complete.
Rectified By
No. Items Description Remark
HTI HS
Site ID : …..
Site Name : …..
Site Type : …..
BTS Type : …..
Site Description: …..
Proj Def : …..
CERTIFICATE
of
Preliminary Acceptance
It is agreed that, from to , the acceptance test
for site has been successfully held by both the PT. Huawei
Services and Huawei Tech Investment engineer.
It also had been proved by both parties that Huawei’s NodeB
equipments can fully satisfy the need of PT . XL AXIATA under the contract
and can be rightly put into full service.
Date Date
5 VSWR Measurement
V SW R
3G_NGINGAS_SIDOA RJO SECTOR 1 A
1.4
V S W R
Limit : 1.3
1.3
1.2
1.1
M1
1.0
1975 2000 2025 2050 2075 2100 2125 2150
Frequency (1970.0 - 2170.0 MHz)
M1: 1.009 @ .000 Meter M2: 1.016 @ 3.401 Meter M3: 1.04 @ 32.616 Meter M4: 1.09 @ 34.797 Meter
1.30
1.25
1.20
V S W R
1.15
1.10
Limit : 1.05
1.05
M1 M2 M3 M4
1.00
0 5 10 15 20 25 30 35 40 45
Distance (0.0 - 45.0 Meter)
1.4
V S W R
Limit : 1.3
1.3
1.2
1.1
M1
1.0
1975 2000 2025 2050 2075 2100 2125 2150
Frequency (1970.0 - 2170.0 MHz)
1.25
1.20
V S W R
1.15
1.10
Limit : 1.05
1.05
M1 M2 M3 M4
1.00
0 5 10 15 20 25 30 35 40 45
Distance (0.0 - 45.0 Meter)
1.4
V S W R
Limit : 1.3
1.3
1.2
1.1
M1
1.0
1975 2000 2025 2050 2075 2100 2125 2150
Frequency (1970.0 - 2170.0 MHz)
1.25
1.20
V S W R
1.15
1.10
Limit : 1.05
1.05
M1 M2 M3 M4
1.00
0 5 10 15 20 25 30 35 40 45
Distance (0.0 - 45.0 Meter)
1.4
V S W R
Limit : 1.3
1.3
1.2
1.1
M1
1.0
1975 2000 2025 2050 2075 2100 2125 2150
Frequency (1970.0 - 2170.0 MHz)
1.25
1.20
V S W R
1.15
1.10
Limit : 1.05
1.05
M1 M2 M3 M4
1.00
0 5 10 15 20 25 30 35 40 45
Distance (0.0 - 45.0 Meter)
1.4
V S W R
Limit : 1.3
1.3
1.2
1.1
M1
1.0
1975 2000 2025 2050 2075 2100 2125 2150
Frequency (1970.0 - 2170.0 MHz)
1.25
1.20
V S W R
1.15
1.10
Limit : 1.05
1.05
M1 M2 M3 M4
1.00
0 5 10 15 20 25 30 35 40 45
Distance (0.0 - 45.0 Meter)
1.4
V S W R
Limit : 1.3
1.3
1.2
1.1
M1
1.0
1975 2000 2025 2050 2075 2100 2125 2150
Frequency (1970.0 - 2170.0 MHz)
1.25
1.20
V S W R
1.15
1.10
Limit : 1.05
1.05
M1 M2 M3 M4
1.00
0 5 10 15 20 25 30 35 40 45
Distance (0.0 - 45.0 Meter)
2. Main Cabinet
3. Display VSWR
4. List Alarm
5. Display Locell
12. Traffic