Ajwang Patricia
Ajwang Patricia
BY
AJWANG PATRICIA
18/U/GMSC/19417/PD
SUPERVISORS
NOVEMBER, 2022
DECLARATION
I, Ajwang Patricia hereby declare that this dissertation is my original piece of work and that it
has never been submitted to any University or Higher Institution of learning for any academic
award.
AJWANG PATRICIA
18/U/GMSC/19417/PD
'
APPROVAL
This is to certifY that this dissertation has been submitted with our approval as academic
supervisors.
,;:f/11~
.... .. .. .................. Date: ............. ......................... .
Second Supervisor
ii
DEDICATION
I dedicate this piece of work to my beautiful daughter who endured my absence to make my
studies a success.
iii
ACKNOWLEDGEMENT
A word of appreciation goes to all people who contributed in distinctive measures to see to it that
this piece of work sees the light of day. Special appreciation goes my supervisors, Dr. Charles
Ndandiko and Dr. Peter W. Obanda for their professional guidance throughout the preparation of
this dissertation.
I am obliged to all my lecturers and friends at Kyambogo University who endeavored to provide
Lastly, I thank God for His grace that enabled me write this dissertation.
iv
TABLE OF CONTENTS
DECLARATION .............................................................................................................................................i
APPROVAL ................................................................................................................................................... ii
DEDICATION .............................................................................................................................................. iii
ACKNOWLEDGEMENT ............................................................................................................................iv
LIST OF FIGURES .......................................................................................................................................ix
LIST OF TABLES .......................................................................................................................................... x
LIST OF ACROYMNS .................................................................................................................................xi
ABSTRACT ................................................................................................................................................. xii
v
CHAPTER TWO .......................................................................................................................................... 17
LITERATURE REVIEW ............................................................................................................................ 17
2.0 Introduction .............................................................................................................................................. 17
2.1 Theoretical Review ................................................................................................................................... 17
2.1.1 Principal Agency Theory (PAT)............................................................................................................ 17
2.2 Conceptual Review .................................................................................................................................. 19
2.2.1 The Concept of PPP............................................................................................................................... 19
2.2.2 Critical Success Factors Influencing the Implementation of PPPs in the Roads Sector ....................... 20
2.2.3 PPP Implementation (Success Criteria for PPP Projects) ..................................................................... 23
2.3 Empirical Review ..................................................................................................................................... 24
2.3.1 Political Factors as a critical success factor for PPP implementation in the roads sector ..................... 24
2.3.2 Economic Factors as a critical success factor for PPP implementation in the roads sector .................. 27
2.3.3 Managerial Factors as a critical success factor for PPP implementation in the roads sector ................ 29
2.4 Summary of Literature review.................................................................................................................. 33
vii
CHAPTER FIVE .......................................................................................................................................... 73
SUMMARY, DISCUSSIONS, CONCLUSIONS AND RECOMMENDATIONS ................................. 73
5.1. Introduction. ............................................................................................................................................ 73
5.2. Summary of the findings. ........................................................................................................................ 73
5.2.1 The influence of political factors on the implementation of PPP road projects .................................... 73
5.2.2 The influence of economic factors on the implementation of PPP road projects.................................. 73
5.3 Discussion of the findings ........................................................................................................................ 74
5.3.1 The influence of political factors on the implementation of PPP road projects .................................... 74
5.3.2 The influence of economic factors on the implementation of PPP road projects.................................. 75
5.3.3 The influence of managerial factors on the implementation of PPP road projects ............................... 75
5.4. Conclusion. .............................................................................................................................................. 76
5.5. Recommendations ................................................................................................................................... 77
5.6 Areas of future research ............................................................................................................................ 78
5.7 Limitations of the study ............................................................................................................................ 78
REFERENCES ............................................................................................................................................... 79
APPENDICES ............................................................................................................................................... 87
Appendix 1: The Krejcie and Morgan Table .................................................................................................. 87
Appendix 2: Research Questionnaire ............................................................................................................. 88
Appendix 3: Interview Guide ......................................................................................................................... 98
viii
LIST OF FIGURES
ix
LIST OF TABLES
Table 8: Showing respondent’s perception on political factors on the successful implementation of PPP
projects in the roads sector ............................................................................................................................. 55
Table 9: Showing the influence of political factors on the successful implementations of PPP projects in the
roads sector ..................................................................................................................................................... 58
Table 10: Showing respondents of economic factors on the successful implementation of PPP projects in
the roads sector ............................................................................................................................................... 60
Table 11: Showing the influence of economic factors on the successful implementation of PPP projects in
the roads sector ............................................................................................................................................... 62
Table 12: Showing respondent’s perception of managerial factors on the successful implementation of PPP
projects in the roads sector ............................................................................................................................. 63
Table 13: Showing the influence of managerial factors on the successful implementation of PPP projects in
the roads sector ............................................................................................................................................... 65
Table 14: Showing success criteria for PPP projects in the roads sector ....................................................... 66
Table 16: showing the Statistical significance of the multiple regression model .......................................... 68
x
LIST OF ACROYMNS
SC Success Criteria
xi
ABSTRACT
The study sought to establish critical success factors influencing the implementation of PPPs in
the roads sector in Uganda. The objectives of the study were to determine CSFs influencing the
implementation of PPP road projects in Uganda, to establish a success criterion for PPP road
projects that provide a mechanism for determining extent of success of a PPP road project and to
examine the extent of influence of PPP CSF to the successful implementation of PPP road
projects in Uganda. A cross-sectional survey design with a quantitative approach was adopted in
this study. A sample size of 140 respondents out of a population of 226 respondents. 140
questionnaires were administered to collect quantitative data. 132 questionnaires were filled and
returned constituting a response rate of 94%. Data was collected from the public and private
sector; specially selected from institutions with PPP exposure in varied capacities. Tests for
normality, validity and reliability of data were carried out. The findings of the study revealed that
there is a moderate positive relationship (0.512**) between political factors and PPP success
criteria and the relationship was statistically significant at 0.01 level of significance P-Value
(0.000) < 0.01. This finding was also reinforced by the interviews conducted in which all
respondents echoed political factors as being crucial to the success of PPP road projects. On the
other hand, the study also revealed that there is a moderate positive (0.620**) relationship
between managerial factors and PPP success criteria. Verbatim interviews also stressed
managerial factors as being critical for PPP implementation with regard to project identification,
skills and competence of PPP practitioners as well as contract management and control. The
findings further revealed that the relationship was statistically significant at 0.01 level of
significance P-Value (0.000) < 0.01. Lastly, there is a moderate positive relationship (0.556**)
between economic factors and PPP implementation and the relationship was statistically
significant at 0.01 level of significance P-Value (0.000) < 0.01. The study recommends that to
ensure the successful implementation of PPPs in the roads sector, the procurement process
should result into selection of a strong private consortium with strong technical strength.
Similarly, strong contract management and control should be undertaken throughout the PPP
project implementation. However, strong contract management and control can only be effective
if the organization staff and transaction adviser are competent in their understanding of PPP
mechanisms.
xii
CHAPTER ONE
INTRODUCTION
1.0 Introduction
The inability of the public sector to independently meet the ever increasing need for
fiscal budgets has prompted governments especially in developing economies to venture into
Public Private Partnership as an alternate method for delivery of the much needed infrastructure
and services (Ndandiko, 2006; Muhammud, Sik, Johar & Sabri, 2016). Infrastructure such as
(Ivanová & Masárová, 2013). Like it is with any infrastructural sector in Uganda’s economy, the
roads sector is faced with an infrastructural deficit estimated at USD 2,212.23m; which is further
Planning Authority, 2012; UNRA, 2019). Since Uganda intends to undertake PPPs, it is crucial
to understand the factors that are critical for the successful implementation of PPPs in the roads
sector and have a criterion against which the PPP project success will be measured. This research
henceforth, set out to investigate critical success factors influencing the implementation of PPPs
and establish a criterion against which PPP project success will be measured in the roads sector;
using Uganda as the case study. Therefore, chapter one focused on the background of the study,
research problem, objectives of the study, significance of the study, its justification, theoretical
and conceptual framework, scope of the study and operational definition of key concepts.
1
1.1 Background of the Study
PPPs can be traced way back in the 14th century where concessions were granted to the private
sector who exclusively operates, maintains and carries out development of infrastructure or
provides service of general economic interest (Jomo, Chowdhury, Sharma & Platz, 2016). For
example; concessions served as legal instruments for road construction during the time of the
Roman Empire (Jomo et al., 2016). In the mid17th century, PPPs were under taken in France
where a company founded by the Perrier brothers was licensed to supply piped water in Paris
In the USA, the late 17th century saw the use of PPPs to implement infrastructure projects such
as the Lancaster Turnpike road; the Erie Canal – opened in 1823 and the Transcontinental
Railroad that was completed in 1869 (Smith, 2009). In Asia, the 1870s saw the construction of
the Princess Docks in India by the Bombay Port Authority, through a public bond issued by the
government, and competitively tendered and built by a private sector contractor (Siemiatycki,
2011).
The modern PPP focus began taking shape in the 1990s in Australia and UK when the latter
launched its Private Finance Initiative (PFI) scheme in bid to attract private finance for
construction of new infrastructure (Hodge & Boardman, 2017). This initiative marked a turning
point from a century of practice where concessions were predominantly used for construction of
infrastructure to a situation where such arrangements were a public policy preference. The late
20th century saw an increase in the use of PPPs; for example, Australia (that is now a leader in
PPP policy), Canada and France (with demonstrated successful PPP results). PPP projects began
to spread around the globe from being only a concern of Western countries to many developing
2
economies in African, Asia, Middle-East, and Latin American economies.
In 2013, a total of US$ 150.3 billion worth of investments in PPPs in developing economies was
reported, with total investments being largely dominated by India and Brazil (World Bank, 2013
as cited in Osei-kyei & Chan, 2018). In 2019, private investment commitments stood at US$96.7
billion in middle and lower income countries, with China largely dominating investments in
infrastructure at 39% (World Bank, 2019). The transport sector with investments in road
infrastructure continued to dominate as the largest PPP sector in 2019, accounting for half of
PPP infrastructure development is on a steady increase in Africa with South Africa dominating
the PPP market with landmark projects like the N4 toll road, Gautrain rail, etc. (Maseko, 2014).
The development of PPPs in Sub-Saharan Africa (SSA) have been relatively slow as compared
to other parts of the developing economies, though it is now gathering pace (Yescombe, 2017).
The World Bank Private Participation in Infrastructure (PPI) Database reported that Uganda has
parties assume operating risks; representing an aggregated investment value of USD 2,036
million. The Government of Uganda (GOU) in 2010 adopted a national PPP Policy Framework;
backed by the PPP Act 2015 with its main objective being encouraging private sector investment
and participation in public infrastructure development where excellent value for money can be
clearly exhibited (Davis et al., 2016; World Bank, 2017). As per the new policy, the provision of
public services and infrastructure will remain with the government department(s) or state
3
determining any expected outcome of the PPP project(s). The government expects that the policy
will result in an even more efficient development of public infrastructure and a simultaneous
growth in economic and foreign direct investments (Public Private Partnership Framework
Policy 2010).
Due to budget constraints, Government of Uganda (GOU) through Uganda National Roads
Authority (UNRA) expressed the desire to use the PPP mechanism to utilize private financing
resources and ensure a sustainable maintenance of the road network (Broek, 2013). In 2013
therefore, IFC was requested to provide recommendations for prioritizing and outlining a
roadmap for PPP implementation in the roads sector, in view of five selected road projects
(50km), Kampala-Bombo Road (35km) and Kampala-Entebbe Express way (51.4km); (Broek,
2013).
The study based on the Principal Agency Theory (PAT), a theory developed by Michael Jensen
of Harvard Business School (HBS) and William Meckling of the University of Rochester (UR)
in the 1970s. The PAT is premised on the relationship between principles and agents who
administer authority for and on behalf of organizations (Fama, 1980). The theory contends that
principals should solve two basic assignments in selecting and managing their agents. First, they
are required to select the best agents (contractors or employees) and create inducements for them
to behave as expected. Secondly, they should monitor the behaviour of their agents to ensure that
they are performing as agreed upon (Baysinger, Kosnik & Turk.1991). However, there are risks
involved when there are conflicting goals of both parties involved or when it is cumbersome and
4
or expensive for the principal to ascertain exactly what the agent is in fact doing. The prevalence
of asymmetric information in such circumstances results into a detrimental selection and a moral
PPPs involves relationships that are in the PAT; whereby the public entity is the principle while
the private party is the agent. These relationships need to be well articulated, lest problems
associated with the PAT arises from the information asymmetry: adverse selection and moral
hazard given the specific nature of risks associated with PPPs; by modelling the relation between
an informed party (the Agent) and an uninformed one (the Principal) (Ong’olo & Spellman &
The study is denoted by two main variables, namely; Critical Success Factors and PPP
Implementation. Critical Success Factors (CSF) being the independent variable, are the
conditions within a PPP project environment that has an influence on the successful
success has a relationship with the other. The successful implementation of a PPP project is thus
dependent on the project level (political and economic) and program level (managerial) within
which it operates. PPP implementation denotes the success criteria against which a PPP project is
measured.
PPP is a long-term contractual arrangement between a private party and a government entity, for
provision of a public facility or service, in which the private party bears substantial risk and
2017). The PPP Framework Policy 2010 defines PPP as a medium to long term contract between
5
the public and private sector to construct/renovate, develop, finance, manage or maintain a public
infrastructure or the provision of public service involving risks and rewards’ sharing, to deliver
desired policy outcomes that are in public interest (Public Private Partnership Framework Policy,
2010). As a result, government attempted to tap into private resources and other benefits of PPP.
This saw the PPP Policy 2010 and the PPP Act 2015 enacted as well as a dedicated PPP unit
being established (in the MoFPED) to ready the country for PPP infrastructural undertakings
(Public Private Partnership Framework Policy - September 2010). World economies are
consistently faced with chronic infrastructure gaps; and have sought sustainable alternatives in
PPPs to deliver this infrastructure while addressing budgetary constraints (World Bank, 2018).
Important contributions to the development of the CSF concept was brought by John F.
Rockart’s works in 1979 and the Sloan School of Management; who defined CSF as few
indispensable areas of activity for a manager's action in which desirable results are absolutely
necessary to accomplish the established goals (Rockart, 1982). It also facilitates continuous
scrutiny of such crucial factors by management, so that they are explicitly handled. Osei-kyei &
Chan (2018) contend that CSFs signify conditions and circumstances necessary for achieving
project success.
Li et al., (2005) argues that the PPP project procurement stage is very vital to the general success
of PPP projects. Tang, Shen, Skitmore & Cheng (2013) concur with Li et al., (2005) that all
construction projects’ briefing stages are the most important as they determine the projects’
success. However, Osei-kyei & Chan (2018) indicate that PPP projects success is largely
influenced by the PPP project environment – at program level, and at the parent organization – at
project level. This explains why a six-factor grouping of PPP CSFs was adduced as a suitable
6
representation for both the PPP project environment and internal organization. The six categories
Organizational and Managerial conditions. This research study zeroed on the political, economic
and managerial aspects as these are deemed relational to the Ugandan context.
Due to the multi-variate nature of PPPs, evaluating their successful implementation requires
more rigor as the complexity in establishing the success or failure of the project is reliant on
project objectives and criteria as set out/perceived by the varied stakeholders involved in the PPP
project lifecycle such as the project owners, designers, consultants, contractors and end users
According to Osei-kyei & Chan, (2018), success criteria are a set of concepts/parameters against
which success is quantified or evaluated.” It denotes a set of principles on which a project can be
considered as successful (Węgrzyn, 2016). The anticipated results of PPP projects could be
influenced by various factors and their interaction during the PPP project’s lifecycle (Węgrzyn,
2016). These factors could thus be classified according to the project implementation phases
identified as construction, operational and transfer phase (Ahmadabadi & Heravi, 2019).
PPP Success Criteria (SC) has been explored by various authors. From normative literature,
Muhammad & Johar (2017) established that success in PPPs has been denoted by Value for
Money (VFM), adequate financial return to the private investor, costs savings, meeting client’s
requirements and satisfying stakeholder requirements, maintenance of high quality service levels,
From comparative studies on PPP project success criteria conducted in Hongkong and Ghana,
7
Osei-kyei & Chan (2017 b) established that profitability, meeting output specifications, budget
consistency, time adherence and effectual risk management, were the dominant PPP success
criteria.
The road sector in Uganda comprises of both paved and unpaved roads to ease transport. Road
transport is the most dominant mode carrying over 95% of passenger and freight traffic
(MoWorks & Transport, 2017). The country has a total road network of 144,785 km of which
20,856 km of national roads managed by UNRA - consists of paved and unpaved roads, with the
paved roads at 23.8% (4,971 km) while the unpaved road is at 76.2% (15,885 km) (UNRA
UNRA is a body entrenched by Act of Parliament, the UNRA Act, 2006 and became operational
in 2008, as a body mandated to manage the provision and maintenance of the national road
network, rendering advisory services to the government on roads’ policy matters and assisting
the coordination and implementation of roads’ policy (UNRA Corporate Strategic Plan, 2017).
According to Broek (2013), “the road sector in Uganda is in need of rehabilitation and further
expansion as a result of significant road maintenance backlogs and increasing traffic levels.”
This has seen government commit financial resources for road infrastructure development and
maintenance by consecutive budget increases for the last twelve years (MoWT, 2017) channeled
to UNRA.
8
Public Private Partnerships (PPPs) in Uganda’s Roads sector
GOU indicated a desire to undertake PPPs for road infrastructure development; and through
UNRA, engaged the World Bank’s – IFC division in 2013 to undertake studies for five selected
road projects to establish their suitability/potential for PPP application; as well as find out the
adequacy of the legal, regulatory and institutional frameworks for PPPs in Uganda (Broek, 2013;
I F C Advisory, 2013). Their findings indicated that Uganda’s investment climate is not the best
and that the local market is not capable of delivering PPP schemes on its own i.e., there is a need
to attract international investors. Further, neither of the selected road projects are financially
viable and hence a viability gap financing (VGF) would be required or toll rates significantly
higher than international practices taking into account purchase power parity, which may lead to
Significant deficiencies were also noted in the PPP legal, regulatory and institutional
frameworks. It was established that although the PPP Policy 2010 outlines in detail the process,
purpose and need for PPPs in Uganda, it does not provide an indication of key infrastructural
focus sectors (Broek, 2013). Secondly, whereas the PPP Bill appears to be in line with
international best practices, some provisions are inappropriate; like the requirement that
parliament has to approve any future financial commitments or any contingent liability that
arises from a PPP arrangement. This implies that every PPP arrangement has to be approved by
parliament which might be cumbersome and delay the process or lead to unrealistic request for
mechanisms of PPP (Broek, 2013). Similarly, whereas the PPP Act 2015 outlines a clear PPP
institutional design for preparation, implementation and monitoring, the provision for cabinet
9
approval of a PPP project value above a certain threshold is inappropriate and it is not clear how
this requirement fits into the PPP project proceedings (Broek, 2013).
The absence of financial instruments for long-term financing was also identified as an
impediment to PPP implementation in Uganda’s road sector (Broek, 2013; IFC Advisory, 2013).
Uganda is faced with limited access to long-term debt facilities by the available commercial
banks although these banks are backed by large international banks like Barclays, Standard
Chartered and Stanbic bank, that are capable of providing global commercial project finance
(IFC Advisory, 2013). Uganda is also exposed to political and economic risks, in addition to
absence of risk insurance instruments which makes the project financers unwilling to provide
any lending that is exposed to political and market (economic) risk (I F C Advisory, 2013).
Further, it was established that Uganda is faced with limited institutional capacity as highlighted
in the knowledge and skills gap deficiency in PPP mechanisms both at the implementing
National Development Plan 2 (NDP II) 2015 - 2020 and Uganda Vision 2040 recognizes the
roads sector as one of the key sectors fundamental for the development of Uganda’s economy
(National Planning Authority, 2015 & National Planning Authority, 2013). Uganda intends to
comparable levels of the developed countries. The construction of multi-lane paved national
roads, expressways and improvement of road infrastructure; for connecting major cities, exit
ports and economic zones will require whooping capital investments estimated at USD
10
Government hopes to tap into private finance and expertise by use of PPPs to implement these
complex road infrastructure projects. With PPP Policy 2010 and the PPP Act 2015 already in
place; a Road tolling policy, 2017 was enacted in bid to prepare the country for road PPPs
(Public Private Partnership Manual, 1999; Ministry of Works & Transport, 2017). The enactment
of these legal and institutional frameworks for implementation of PPPs provides a basis for the
However, despite having a PPP legal and institutional framework in place, PPPs implementation
in the roads sector have stalled. A case in point is the most feasibly expected PPP road project –
the Kampala-Jinja Expressway (dubbed the PPP ‘pathfinder’ in the roads sector), that stalled
after its procurement and financing proposals were halted due to suspicion and hostility from the
mechanisms (Ref. Daily Monitor Article Sept, 25th 2019 & Feb, 20th 2020).
Notwithstanding, in the energy sector where PPPs have been undertaken, critical audit findings
on PPP projects unearthed improper licensing agreements, none audit cooperation from PPP
partners and failure to meet government objectives like increased efficiencies, reduction of loses,
Following such glaring shortfalls, it is imperative to understand CSF that influence the successful
implementation of road sector PPPs; a study this research intended to fill. Furthermore, since the
introduction of PPP in Uganda, factors contributing to its successful implementation have not
been fully explored. In other words, there had been a paucity of research studies on PPP CSF in
the roads sector within the Ugandan context. Most research studies on CSF covered the general
water projects and others (Bing, Li, Hardcastle, Akintoye, & Edwards, 2005; Zhang, 2005; Li et
11
al., 2007; Osei-kyei & Chan, 2018;) yet PPP success is country and sector specific. This study
therefore sought to contribute to the body-of-knowledge on CFS in regard to road sector PPPs in
The study sought to establish critical success factors influencing the implementation of PPPs in
ii. To establish a Success Criterion for PPP road projects that provides a mechanism for
iii. To examine the extent of influence of PPP CSF to the successful implementation of PPP
To Stakeholders: The study will draw attention to key PPP stakeholder critical areas that
necessitate stakeholders’ attention so as to achieve the success of a PPP road project. This in turn
12
provides key information aimed at improving the success chance of PPP road projects.
PPP Practitioners: The findings can be used as a roadmap for successful implementation of PPPs.
The PPP success factors will inform PPP practitioners on fundamental PPP elements which need
to be controlled and carefully managed, as well as standards to adopt in order to achieve the
envisaged PPP success level. It will also help in the evaluation of the success of the PPP project
To Academic Field: The study sought to contribute to the body-of-knowledge on critical success
$476m loan obtained from China’s EXIM bank for the construction of the Kampala-Entebbe
expressway (KEE) using a PPP financing mechanisms - road tolls, following the enactment of
the Road Tolling policy in 2017 (MOW&T - Road Tolling Policy, 2017; World Bank Group,
13
1.7.2 Content Scope
The studies were limited to PPP Critical Success Factors at the program and project level within
a PPP project environment: specifically, factors influencing the implementation of PPPs in the
Road sector. Thus, the study looked at how political, economic and managerial factors influence
the successful implementation of PPPs in the road infrastructural sector. The study also looked at
government entity, for providing a public asset or service, in which the private party bears
Critical Success factors (SCF): Those few key areas of activity for the manager's action, in
which favourable results are absolutely necessary to achieve the desired goals (Rockart, 1982).
PPP Road Project Implementation: The development or maintenance of a road project under
PPP.
14
1.9 Conceptual framework
ECONOMIC
Available mature financial markets Profitability
Fixed Low interest-rate Financing Long term partnership
Sound Economic policies relationship
Stable Macroeconomic indicators Satisfying the need for
Government financial support/ Subsidies public facility/service
Government Guarantees Adherence to time
Fiscal concession & investment policy Adherence to budget
Project Economic Viability Reduced litigations and
disputes
Reduced public sector
MANAGERIAL
administrative costs
Right Project Identification
Detailed Project Planning Effective technology
Appropriate Risk Allocation transfers and innovation
Sound Financial Package Local economic
Strong Private Consortium with technical development
strength Environmental
Competence of org. staff & T.A performance
Strong Contract management and control
Reduced project
Acceptable Toll/Tariff levels
lifecycle costs
Meeting output
Figure 1.1: Conceptual framework for PPP Implementation specifications
Effective risk
Source: Adopted from Osei-Kyei & Chan 2018; modified by researcher
management
Reduced public and
political protests.
15
The above conceptual framework is indicative of Critical Success Factors (CSF) as the
independent variable being constructs within a PPP project environment that have an influence
condition of success is inter-related with another; i.e., political constructs directly influence
PPP infrastructure project is thus dependent on the project level (political and economic) and
PPP implementation (dependent variable) denotes the success criteria against which a PPP
project is measured i.e., the outcomes of a successful project. The outcomes of a successful PPP
project differ from the traditional bid-build projects due to the uniqueness of PPP projects as the
latter involves complex contractual and stakeholder management, lengthy arrangements, risk
sharing and rewards management (Osei-kyei & Chan, 2018). The success criteria are thus
need for public facility/service, timely project delivery, project budget adherence, minimal
16
CHAPTER TWO
LITERATURE REVIEW
2.0 Introduction
The chapter reviewed the existent body of literature in Critical Success Factors (CSF)
influencing the implementation of PPPs in the roads sector in an effort to identify gaps in
knowledge and practice that need to be filled. It therefore covered the theoretical review,
The theoretical framework of the study was anchored on the Principal Agency theory. This
theory relates to the CSF influencing the implementation of PPPs in road projects. The theory
underpins the concept of PPPs and what needs to be done to ensure its success.
The PAT was evolved in the 1970s by Michael Jensen of HBS and William Meckling of the UR.
The PAT is premised on the disposition of property rights and information in regard to drafting
contracts that define the organization. It is focused on the relationship between principals and
agents who exercise authority for and on behalf of organizations (Fama, 1980). The theory
contends that principals should solve two basic assignments in selecting and managing their
agents. First, they are required to select the best agents (contractors or employees) and create
inducements for them to behave as expected. Secondly, they should monitor the behaviour of
their agents to ensure that they are performing as contractually expected (Baysinger, Kosnik &
17
Turk.1991); by instituting an effective incentivized system for the private party to act in
Realistically, PPPs involve the use of professional and experienced general contractor (private
partner); as well as an external consultant hired on behalf of the public partner – for expert
support in regard to contractual risk and profit allocation (Kehl & Arnold, n.d.). Hence, PPPs can
be considered successful when there is a general “fit” in the partnership. However, there are risks
involved when there are conflicting goals of both parties involved or when it is cumbersome and
or expensive for the principal to ascertain exactly what the agent is doing. The prevalence of
asymmetric information in such circumstances results into a detrimental selection and a moral
hazard drawback (Baysinger et al., 1991). Information asymmetries are existent especially in the
According to Eaton & Akbiyikli (2009), PPP is a procurement approach involving project
execution reinforced with an extensive span of contractual relationships between the public and
private sector to provide an asset and a service over a long-term period of time. PPPs involves
relationships that are in the PAT; whereby the public entity is the principle while the private
party is the agent. These relationships need to be well articulated, lest problems associated with
the PAT arises from the information asymmetry, adverse selection and moral hazard given the
specific nature of risks associated with PPPs; by modelling the relation between an informed
party (the Agent) and an uninformed one (the Principal) (Ong’olo & Spellman & Walker Co.
Ltd, 2006).
Asymmetric power relationships and dynamic interdependent stakeholder networks found in the
PAT aid in defining government’s role in the organization and maintenance of third party
networks; enabling private partners solve public issues and upholding collectively held
18
objectives in complex policy environments (Casady et al., 2017). Therefore, to avoid
opportunistic behaviour by the private partner, the public partner (principal) has an incentive in
the selection of instruments and contractual clauses which involve risk transfer and the
possibility to fine (punish) or reward the private party for its performance (Firmino, 2018).
agency problems involving various players and in varied forms throughout the project lifecycle
The PPP concept is arched on government’s desire to resolve endemic financial constraints
associated with the delivery of public infrastructure and services by engaging private sector
management skills and expertise to increase the efficiency, effectiveness and quality of service
delivery and facilities (HM Treasury, 2000 as cited in Li, Akintoye, Edwards & Hardcastle,
2007). This notion is supported by Jefferies (2006) who asserts that the adoption of PPPs is
costs. A number of scholars have advanced various definitions of PPP – but with key distinct
features. First, public and private sector arrangement to deliver an infrastructure of mutual
interest and or benefit. Secondly, lengthy contractual periods involving design, construction,
financing, operations & maintenance, thus, bundling up all stages of investment and service
provision; and thirdly, risk sharing and rewards between the private and public sectors (Akintoye
& Beck, 2009; Yescombe & Farquharson, 2018; World Bank, 2018).
Yescombe (2017), defined PPP as a long-term contractual undertaking between the public sector
entity (the ‘public authority’) and the private-sector entity (the ‘project company’), involving
19
significant transfer of risk to the private party. He further explains that under a PPP contract, the
operational and maintenance of the public sector infrastructure. Smith (2009) defined PPP as a
long-term contractual agreement between a public and a private sector entity through which the
expertise, skills and assets of each party are shared in delivering an infrastructural facility or
service for public use. Additionally, project potential risks and rewards are shared in the delivery
Mudi et al., (2015) opined that PPP road infrastructure developments require long-term
investments (between 10 to 30 years) to achieve the project objectives. The tenure of such
projects covers the economic life cycle of the road infrastructural project. According to
(Roehrich et al., 2014 as cited in Sehgal, Dubey & Tiwari, 2015), PPPs aggregate the strengths
of private players in terms of technical and expertise knowledge and skills, managerial acumen
and entrepreneurship, as well as the role of public accountability and local content leverage, to
2.2.2 Critical Success Factors Influencing the Implementation of PPPs in the Roads
Sector
Important contributions to the development of the CSF concept was brought by John F.
Rockart’s works in 1979 and the Sloan School of Management (Jefferies, 2006); who defined
CSF as few indispensable areas of activity for a manager's action in which desirable results are
absolutely necessary to accomplish the ultimately established goals (Rockart, 1982). Such
significant factors are highlighted so that they receive careful and consistent management
attention. According to Hardcastle, Akintoye & Edwards (2005), CSF is defined as those key
20
activity areas in which favourable results are absolutely necessary for a particular manager to
reach his/her goals. Similarly, Rowhinson (1999) agrees that critical success factors are those
key issues inherent in a project which must be upheld for team working to take place in an
Campos et al., (2018) maintains that CSFs (in regard to PPPs) are elements that determine how
well PPPs function. Chua et al. (1999 as cited in Zhang, 2005) maintains that a construction
project’s success is hinged by four features, identified as: project characteristics, contractual
arrangements, project participants, and interactive processes. PPP road projects constitute
construction to a greater extent and hence, falls within the confines of infrastructure
Political Factors
Political factors have been found to have a profound influence on PPP projects as political will
and leadership are key in terms of establishing an overall PPP policy framework (Turley &
Semple 2013). Political factors are an embodiment of political support, stability and good
governance that are enablers of favorable legal, regulatory and institutional frameworks. In their
study on PPP enabling factors in Germany, Kehl & Arnold (n.d.) established that government
political support and commitment accounted for the increased use of PPP for more projects.
Political will coupled with astute public management, are needed in third party settings as private
sector alone cannot be given monopoly over public welfare in lieu of their private interests
Political factors are mirrored by a sound public policy characterized by good governance, to
avoid opposition on the part of citizens and political parties (Firmino, 2018). Carter et al., (2017)
21
revealed that PPPs are a tool for public infrastructure provision requiring rigorous stakeholder
iterative and multi-stakeholder process is essential to determine cost of service provision, users’
ability and WTP, tariff required to achieve Return on Investment (ROI) as well as government
goals (Turley & Semple, 2013). The successful implementation of PPPs necessitates a stable
socio-political environment which is in turn highly dependent on the capability and stability of
Economic Factors
economic conditions, policies and government support. The use of favourable economic policies
oftenly fosters a stable and growing economic environment which allows for private sector
reasonable market certainity which reduces private sector risk (Li et al., 2005b). Stable economic
environments are characterised by the presence of mature financial markets with low interest
rates associated with lower financing benefits. Availability of diversified range of financing that
incentivizes private sector investment in PPP projects as project financing is a key component for
private sector investment in public infrastructure projects (Ghazali, Rashid & Sadullah, 2017; Li
Further, stable economic environments are characterized by the ability to curtail fluctuations in
exchange and interest rates and are able to predict currency exchange risk, thereby fostering
favorable economic systems (Ahmadabadi & Heravi 2019). Economic policies driven towards
revenue guarantee, tax reductions and holidays (Ismail, 2013) as well as government financial
22
subsidies and flexible concession tenure (Yescombe & Farquharson, 2018).
It is imperative to note that private participation in PPPs is largely influenced by the presence of
demand for the products/ services offered by the project; limited competition from other projects;
sufficient profitability of the project to attract investors; long-term cash flow that is attractive to
the lender; and long-term availability of suppliers needed for the normal operation of the project
(Zhang, 2005b).
Managerial Factors
Managerial factors denote conditions which influence the success of a PPP project at a project
level (Osei-kyei & Chan, 2018). These include right project identification, detailed project
planning, appropriate risk allocation, sound financial package, strong private consortium with
technical strength, competence of organization staff and Transaction advisor (T.A), strong
contract management and control and acceptable toll/tariff levels (Ghazali et al., 2017; Li et al.,
Success criteria focuses on the parameters on which a project can be deemed or judged as
successful (Osei-kyei & Chan, 2018). The relative success or failure of any project is usually
measured in terms of cost, time and quality parameters usually linked to meeting these
Farhan, Sheik ; Haris, 2017). According to Osei-Kyei & Chan (2017), “there has been a gradual
shift from the traditional approach of measuring project success in terms of cost, time and quality
towards a mix of objective and subjective measures.” Ahmadabadi & Heravi (2019), reiterate
23
similar opinions that the SC in PPPs is different from that in traditional contracts due to the long-
term nature of these projects, the importance of the operation stage, and the presence of a private
sector consortium in infrastructure projects. The success of a PPP project depends on “reaching
the predetermined objectives set by project stakeholders.” Furthermore, PPP SC is best exploited
during the construction, operation and final transfer stages of a PPP project (Ahmadabadi &
Heravi, 2019).
Osei-kyei & Chan (2018) evaluated fifteen success criteria derived upon the basis of the
satisfaction of the main stakeholders of PPP projects in Ghana (i.e., public, private and users).
These were: profitability, long term partnership relationship, satisfying the need for public
facility/service, adherence to time, adherence to budget, reduced litigations and disputes, reduced
public administration costs, and effective technology transfer and innovation. Others include;
reliable and quality service operation, meeting output specifications, effective risk management
and reduced public and political protests (Osei-kyei & Chan, 2018).
2.3.1 Political Factors as a critical success factor for PPP implementation in the roads
sector
Since PPPs involve lengthy time frames / contractual agreements, the existence of a stable and
favourable political environment establishes the private sectors’ confidence in the PPP project
despite changes in subsequent governments (Firmino, 2018). Dairu & Muhammad (2016) opine
that inherent political instability perpetuates policy discontinuity and may result in project
abandonment, insecurity, weak governance and absence of both transparency and accountability.
Casady et al., (2017) asserts that effective PPP delivery is dependent on institutional maturity (in
24
terms of legal, normative and cultural-cognitive rules and processes) exhibited by robust
standardized judicial practices as well as normative rules and procedures governing public and
private actors’ interaction. Furthermore, the principle of accountability which is a hall mark of
As a political construct, the existence of an enabling PPP legal and regulatory framework/policy
is considered both as a legislative and political factor, empowering the public sector to enable the
private sector undertake investments in a PPP project by creating an enabling PPP environment
(Debela, 2019). According to Ndandiko (2006), “ appropriate legal and regulatory frameworks
streamline PPP set up, implementation and outcome.” Suitable legislation provides a solid
foundation for PPPs against which developers can structure a contractual vehicle that is in
tandem with the country’s laws (Zhang & Kumaraswamy, 2001). Further, the specificity in
enabling laws for a specific PPP road project (as being practiced in Hong Kong for example)
largely eliminates private sector risks and concerns regarding politically derived risks, for
example expropriation, nationalization as well as changes in law. Sharma (2012) in his study on
PPP determinants in developing countries established that regulatory environment are important
considerations.
As Hammami et al., (2006) notes, the sustainability of PPP arrangements are critically dependent
weak institutions foster uncertainties about legal and regulatory instruments. A well-organized
public agency is therefore important in providing essential public management systems (Casady
et al., 2017), as private firms cannot be exclusively relied upon to independently construct and
deliver public structures (Hammami et al., 2006). Campos et al., (2018) opines that a stable
25
regulatory policy contributes to the consecution of rights and guarantees to partnerships which
Ndandiko, 2006).
It is imperative to note that political factors are an enabler for an effective procurement process.
transparency and competitiveness in a procurement process enhances project value for money. Li
et al., (2007) contends that a transparent and competitive procurement process is critical for the
public entity in the procurement a PPP project. Transparency is endeared between the public and
private entity, as well as their advisers; a phenomenon implying that three features are crucial for
transparency: good communication between the public entity and private contractor and their
advisers; the private sector openly consulting with the public sector and its adviser, while
keeping responsibility for all decisions; and the private sector establishing a clear basis for
The public sector should institute a framework that provides an overview of the procurement
process and clarify what appraisal needs to be done and what decisions should be taken at each
stage of the procurement process (Zhang & Kumaraswamy, 2001). Further, competitive
tendering processes should be adhered to till PPP contract award (Zhang, 2005). Tender
evaluation criteria and methods should be transparent enough to ensure fair competition and to
avoid criticism of sponsor selection or political favoritism which are greatly known to hinder
public interest. PPPs are a tool for public infrastructure provision requiring rigorous stakeholder
engagement and management as well performance monitoring (Carter et al., 2017). Prior to PPP
26
service provision, users’ ability and WTP, tariff required to achieve ROI as well as government
goals (Turley & Semple, 2013). Based from the reviewed literature it can be concluded;
2.3.2 Economic Factors as a critical success factor for PPP implementation in the roads
sector
PPPs are intended to eases government budgetary constraints by having the private sector
finance the PPP project through debt and equity financing – this explains why the availability of
flexible, adequate and long-term financial markets is a CSF (Zhang, 2005b). An accessible
financial market is associated with lower financing benefits and diversified range of financing
that incentivizes private sector investment in PPP projects (Ghazali, Rashid & Sadullah, 2017 &
Li et al., 2007).
Li et al., (2005) submits that a stable and growing economic environment brought about by the
confidence. Further, a stable economic environment can also lead to reasonable market certainty
which in turn reduces private sector risk. Ahmadabadi & Heravi (2019) contend that sound
economic policies are characterized by the ability to deal with fluctuations in exchange/interest
rates and are also able to predict currency exchange risk, thereby fostering favourable economic
countries are financed using a significant amount of foreign capital in form of loans and equity;
however, debt and dividend risks devaluation. This explains why sound macroeconomic policies
can substantially reduce commercial project risks and increase the private firms’ profitability
Economic factors also embody the presence of government guarantee / financial support
27
especially as perceived by the private sector (Ismail, 2013). Li et al., (2005) identified
government guarantee as an important success factor in the early PPP stages in the UK
and multi-benefit objectives. Hence, revenue guarantees or firm committed policies from
There are a various ways in which the public sector (government) can support the private sector
in PPP contracts, provided this support is justifiable on grounds of affordability, VFM and does
not create public sector balance sheet problems (Yescombe & Farquharson, 2018). Such support
can be in form of a robust flexible concession time frame, revenue guarantees and subsidies,
partial project construction, capital grants, debt financing, pro-rata debt guarantee, debt
underpinning, credit guarantee finance and equity investment (Yescombe & Farquharson, 2018).
For financially unviable projects that are otherwise economically/politically significant, the
government can provide project-specific support and guarantees to make them financially viable
(Zhang 2005b). Such guarantees may be in form of foreign exchange, high inflation and interest
rates, tax reduction and exemptions, government equity, concession tenure extension in case of
force majeure, property development rights and the use of existing facilities, and a suitable
concerned with project bankability; thus, the project’s ability to generate a sustainably sufficient
cashflow and yield optimal results. The bankability of infrastructure projects attracts private
sector financing and is dependent on the demand for the services or products offered by the
project for a long term period; minimal or no competition from other projects; project
28
profitability to attract investors; sustainable long-term cash flow which is attractive enough to the
lender; and long-term availability of suppliers needed for normal project operations (Zhang,
2.3.3 Managerial Factors as a critical success factor for PPP implementation in the roads
sector
Managerial factors are considered to affect PPPs at project levels as they are concerned with the
project execution and management of all actual intrinsic details of the project during construction
and eventual transfer of ownership (Osei-kyei & Chan, 2018). Qiao et al., (2001) established that
project identification as the most influential CSF in BOT projects in China. A project suitably
identified to be executed through a PPP mechanism implies that it is has both a strong technical
and economic rationale (PPIAF, 2009). Following his analysis on South African PPP CSF,
Maseko (2014) recommended an adequate feasibility analysis on technical capability and funds
availability before any PPP project implementation. A clearly structured and established national
infrastructure plan enables right project selection by public authorities - that is characterized by
demonstrated and accepted need for the project/facility by the public and the project being a
In the selection of suitable projects for delivery using the PPP scheme, the PPIAF (2009)
highlighted factors such as project aims/objectives, practicality and VFM. These factors can be
used to give guidance to public authorities in developing countries when selecting projects for
PPP schemes. Project objectives are hinged on pertinent issues such as economic value of the
facility, risks inherent the facility and environmental impact imposed due to development of the
29
facility. On the other hand, practicality is related to the political, legal and social issues of the
projects as it involves undertaking thorough cost-benefit analyses, clear project briefs and
understanding about client requirements, and output specifications (Ghazali et al.,2017). Cost-
benefit analyses defines correct expenditure parallel to profits gained while a clear project brief
details client requirements and provides clear understanding on the aims and goals of the project
(Ghazali et al., 2017). Output specifications on the other hand detail technical data and project
design details.
According to Li et al., (2007), a strong private consortium is a CSF for PPP/PFI projects’ success
as established in their study on success factors for the UK construction industry. They therefore
suggested that during the PFI projects’ development stage, sponsors ought to strategically pay
attention to the private consortia. Shi et al., (2016) provides attributes of a strong private
consortium as firm’s capabilities of fulfilling the contract, their financial abilities and PPP
project experience. This collaborates with (Zhang, 2005a) who noted that the concessionaire
should also possess strong managerial capabilities, including leading role by a key enterprise or
entrepreneur, workable project organization structure, good relationship with host government,
participants, and a strong project team. Maseko (2014) also emphasized that the selection criteria
for the private partner should prioritize experience and capability to deliver PPP projects.
According to Zhang (2005a), whereas government is better placed to create a favorable political
30
projects. Further, significant risk realignment among multiple project participants is a key PPP
attribute, in which the concessionaire undertakes more commitments and assumes much broader
and deeper risks than a mere contractor. Selection of the right concessionaire is therefore critical
to the success of the project, and can be achieved through a competitive tendering process
(Zhang, 2005a).
Key aspects such as technical and financial strength are key critical success factors in
competitive tendering for a PPP project (Tiong 1996). Technical assessment involves project
design evaluation of and planned facilities in a life cycle scenario including environmental,
safety and health considerations. The financial strength of the private consortia largely affects
their capability to meet investments required for implementing the PPP project (Campos et al.,
2018).
As a managerial factor, competence of organization staff and Transaction Advisor (T.A) is a key
success factor for any PPP project. The impact of experience by key project personnel towards
successful project delivery has been widely acknowledged. Węgrzyn (2016), adopted Pinto and
Slevin’s 1987 success factor list that emphasized the significance of recruitment, selection and
training of competent personnel for PPP projects. Similar studies by Kahwajian et al., (2014)
established that the lack of skilled/experienced private and public consulting organizations in
Syria specializing in technical, legal and financial aspects of PPP projects were among the main
external consulting with sensible fee agreements and reliable business conduct in regard to the
public party (Kehl & Arnold n.d.). A Transaction Advisor is a person or group of persons
31
appropriate skills and expertise to assist and advise the institution in regard with a PPP, including
the preparation and conclusion of a PPP agreement (Public Private Partnership Manual, S.A
1999). The Transaction Advisor is a very important player in the success of a PPP undertaking
and should possess professional skills and experience in areas spanning commercial project
finance, project management, contract (commercial) and administrative law, insurance, PPP
procurement management, as well as all technical disciplines relevant to the particular project
sector.
In PPPs, a key distinct feature is the concept of risk transfer from the public sector to the private
sector in circumstances in which the private party is in best position to manage the risk
(Alinaitwe & Ayesiga, 2013). In PPP contractual arrangements, risk identification and allocation
are key pertinent issues critical for a project success (Zhang, 2005). Explicit contractual
arrangements of importance in PPP projects entail a clear statement of the contract objectives,
obligations and rights of contracting parties, adequacy and clarity of plans; technical
specifications, a formal dispute resolution process; motivation and incentives to the contracting
According to Zhang (2005a), strong representation benefits all parties involved in PPP
transactions. He contends that the inability to resolve legal issues had led to a number of
projects’ failure to reach closures. Strong and effective legal input at the beginning of the project
cycle would have ameliorated partner-agency problems, and in addition, various risks can be
effectively managed by allocating them to parties best able to manage them through appropriate
contractual arrangements, including a concession agreement between the government and the
concessionaire, and shareholder agreement, design and build contract, loan agreement, insurance
agreement, supply agreement and operation agreement among others. From the review, it can be
32
concluded that;
Studies conducted by various PPP researchers such as Li et al., (2005), Kahwajian et al., (2014);
Li et al., (2007); Shi et al., (2016), Zhang (2005a) and others, centered on CSF for PPP project
success in the construction industry; mainly in developed economies. Even Osei-kyei & Chan
(2018), who conducted their studies in Ghana - a developing country, were focused on the
general construction industry. It should be noted that the use of PPPs in road infrastructure have
increased exponentially with the transport sector being the type of infrastructure with the highest
number of projects delivered through PPPs (Siemiatycki, 2011); although studies against them
are scanty (Cui, Liu & Hope, 2018; Ma, Li, Jin & Ke 2019). Normative literature hence forth
suggests that PPPs in the road infrastructure sector have largely escaped academic research in
both theory and practice, save for the few specific studies done by Ahmadabadi & Heravi (2019);
Debela (2019); Shrivastava & Rao, (2011) in Iran, Ethiopia and India respectively. Sector
specific PPP CSF has not been thoroughly undertaken; particularly in regard to the road
construction industry. There is therefore no doubt that CSF influencing PPPs in the roads sector
of a developing country (like Uganda), has not been explored; a phenomenon this research
Despite the significant success of the PFI projects in UK, it has also been criticized on grounds
of abnormally high tendering costs, complexity in negotiation, cost restraints on innovation, and
differing objectives among the project stakeholders (Hardcastle, Edwards, Akintoye & Li, 2002).
Li et al., (2007) also argues that “the opportunity to adopt strategic measures to address project
33
success is best exploited in the early stages of a project.” However, the success of PPP projects
transcends the early project phases. PPPs bundle up various project stages into a single contract
that need to be explicitly managed up to the end of the project lifecycle to ensure successful
project/service delivery. Similarly, there a number of CSF such as the political environment,
country’s investment climate, legal and institutional frameworks, that need to be considered as
they always play out throughout the project lifecycle of the PPP project.
34
CHAPTER THREE
METHODOLOGY
3.1 Introduction
This chapter presented the research methodology that was used during the study. It entails the
research design, study population, sample size determination, sampling design and procedures,
sources of data, data collection methods, data collection instruments, validity and reliability of
research instruments, data collection procedure, data processing and analysis, measurement of
time frame within which the research was undertaken (Saunders, Lewis & Thornhill, 2009). A
cross-sectional survey design with a mixed research approach using both quantitative and
qualitative approach was adopted in this study. With a cross-sectional survey design relating to
the study variables are collected from the selected sample at one specific point in time
(Creswell, 2014). Kumar (2011) affirmed that the cross-sectional design is best suited to studies
point in time by taking a cross-section of the population. A cross-sectional survey was preferred
for this study as it was relatively affordable, easier to conduct, enabled collection of data from
many selected respondents within a limited time frame, and laid the groundwork for decisions
about follow-up studies (Sekarana, 2000). A cross-sectional survey design helps in testing a
theory, hypothesis and/or research questions on a large sample of people, and to generalize the
findings where a large study sample is drawn (Tharenon, Donohue, & Coopers, 2007).
35
The quantitative approach was used to quantify findings on the study variables using the
measures of central tendency, Pearson correlation and multiple regression analysis. Quantitative
analysis techniques, particularly statistics allow for the exploration, presentation, description
and examines relationships and trends with data (Saunders, 2009). Further, quantitative research
was used to confirm the hypothesis from the sample of the population to the entire population. A
correlation approach was employed to establish the relationship amongst the study variables. A
mixed method of data collection techniques was used where both quantitative and qualitative
data were collected using a survey questionnaire and structured interviews conducted to validate
findings.
The study population consisted of 226 respondents who worked at specially selected institutions
with PPP exposure in different capacities and sectors. The respondents were employees at either
strategic or tactical levels, with specific emphasis on those employees or respondents who had
been exposed to PPP projects and mechanisms in the past five years (or more years) or those
who were knowledgeable about PPP projects in Uganda. The study population included; Public
and private sectors, development partners, consultants and academicians on PPPs. This
population category was preferred because of their exposure, knowledge and or experience with
regards to PPPs. The unit of analysis were selected institutions with PPP exposure in different
capacities and sectors and unit of inquiry were selected institutions with PPP exposure in
36
3.4 Sample size determination
The study considered a sample size of 140 respondents based on Krejcie and Morgan (1970)
sampling guidelines as detailed in table 1 below.
sampling were used for this study. Stratified sampling was used for diving respondents into
categories or stratus according to their specific characteristics. In this study, there were three
stratums namely; Public sector, private sector and Development partners exposed to PPPs.
Secondly stratified sampling was used to group managers in public sector institutions who are
directly involved in the sectors where PPP implementation is currently undertaken as well as the
owners or directors of private companies that tender to provide financial support toward delivery
of public services. The use of stratified sampling in this study was preferred as the population
from which the sample was to be drawn did not constitute a homogenous group. Therefore, as
37
recommended by Kothari (2004), there was need to use stratified sampling technique to obtain a
subpopulations or strata so that sample items can be selected from each stratum.
The study used purposive sampling that involves the researcher using own judgment or common
sense regarding the participants from whom the information was collected. Thus the selection of
the respondents was based on the researcher’s experience with the respondents’ possession of
the required information on critical success factors and PPP implementation in the road sector of
Uganda based on Amin (2005) guidance on purposive sampling. Purposive sampling was used
for respondents such as development partners, academicians and consultants actively involved
Primary data was used because it is accurate, reliable and gives up-to-date information about the
journals to reinforce the results from primary data sources. Secondary data from journals were
38
3.7.1. Questionnaire Survey Method
The questionnaire was used to collect quantifiable primary data from the selected respondents by
personally delivering them to the respondents. The questionnaire was issued to all the 140
respondents in their different categories where the respondents recorded their answers within
closely defined alternatives. The choice of the questionnaire was on the basis that it could collect
vast amounts of data in short time with less resources (Hair, Black, Babin & Anderson, 2010).
The questionnaire was also useful in collecting information on perceptions since the variables of
critical success factors and intent to implement PPPs in the road sector of Uganda cannot be
observed or reliably reviewed from secondary data (Amin, 2005). The question method is
associated with the following benefits; absence of bias where it is used to obtain information, it
is an economical method of data collection, respondent is at ease to select or fill their responses,
respondents are likely to cooperate in questions that are confidential in nature, and absence of
respondents through forms of face to face conversations and probing of the respondent’s
responses to gain detailed explanations on the critical success factors that influence PPP
implementation in the road sector of Uganda as suggested by Sekeran (2009). The researcher
interviewed key informants from the field of consultants, academicians and development
partners.
39
3.8 Data Collection Instruments
instrument comprising of written list of questions, the answers to which are recorded by
respondents (Kumar, 2011). The questionnaires were closed-ended as they are much easier to
With a questionnaire, there is less likelihood of researcher bias in summarizing the responses. As
commended by Hurmerinta-Peltomaki & Nummela (1998), the measurement items for all the
study constructs were tested for validity and reliability and then edited through a pilot test
process before the final survey. As part of the pilot study, the instrument was first administered
to 10 purposively selected experienced PPP experts in Uganda. This was done for the purpose of
guiding the study in ascertaining the direction of the responses and the degree of intensity with
These were channeled into observable and measureable elements to enable the development of
an index of the concept. The questionnaire sought the respondent’s perception on PPP CSF and
SC in the roads sector. All the measurement items in the instrument were anchored on a five-
point Likert scale, ranging from 1 – 5 where ‘1’ is perceived as ‘not important’ ‘2’ is perceived
as ‘less important’ ‘3’ is perceived as ‘some importance’ 4 is perceived as ‘important’ and ‘5’is
perceived as ‘very important. The instrument was pretested for reliability and the Cronbach alpha
values of 0.7 or above for all the study variables were acceptable as this indicated that the
The use of a questionnaire as an instrument of data collection was preferred in this study because
it was cost effective, free from interviewer bias, and respondents had adequate time to give well
40
thought out responses. Besides, it was convenient for reaching out respondents who were not
easily approachable (Tharenon et al., 2007; Kothari, 2004). Since they are highly structured,
questionnaires are suitable for generating quantitative data from a large sample for the purpose of
factors and PPP implementation in the road sector (See Appendix III).
The measurement items were subjected to both validity and reliability tests.
3.9.1 Validity
Validity is the ability of the research instrument to measure what it is intended to measure
(Kumar, 2011). The validity of the instrument was determined using content validity, criterion-
related validity, and construct validity (Kothari, 2004). This is consistent with Sekaran (2000)
who reiterated that a data collection instrument should be valid and able to yield similar results at
all time.
Content validity was performed to establish the degree to which the measures accurately
represent what they are supposed to measure (Hair et al., 2010). An exploratory factor analysis
was then run and the study ensured that the items correlated and that they loaded well with each
other. Factor analysis was done for questions of all variables so as to test their factor loadings. In
the analysis, Varimax Rotation was run to achieve a more meaningful factor structure. The factor
analysis technique facilitated the itemization of success factors into major categories. In carrying
41
out factor analysis, certain questions that were not explained by more than one factor (or
discriminant items) were dropped from the scales and not included in subsequent analysis.
Content validity is the extent to which a measuring instrument provides adequate coverage of the
study variables under study. Content validity was determined with the help of the two research
supervisors who were regarded as subject experts. Content validity was also guaranteed by
giving the instruments to 4 respondents who were experts and practitioners in the field of PPPs.
The researcher pre-tested the instrument among a section of the intended respondents (4 experts
and practitioners) and inappropriate questions that were detected were subsequently revised or
removed. The Content Validity Index (CVI) was used to test for the validity of the instrument to
ensure that the scale items were meaningful to the sample and that the issues that were captured
were measurable. The instrument was valid since the coefficients for all the study variables
exceeded the minimum acceptance value of 0.70 as recommended by Nunnally (1978). The
3.9.2 Reliability
Reliability relates to the degree at which the research instrument gives consistent results a
number of times when it is administered more than once at different time intervals (Sekaran,
2009). The researcher tested the internal consistency reliability of the research instrument in
order to ascertain whether it consistently measured the study variables on the scales used
(Nunnally, 1978). The Cronbach alpha coefficients (measures of internal consistency) of study
variables (Field, 2009) were computed using SPSS version 25. The instrument was reliable since
all the coefficients for the study variables were above 0.7 (Nunnally & Bernstein, 1994).
42
During the study, the internal consistency reliability of the research instrument was tested in
order to ascertain whether it consistently measures the study variables on the scales used.
Findings in table 2 revealed a Cronbach alpha coefficients of political factor variables as 0.729
which is greater than 0.7. It can therefore be concluded that the collected data for these variables
is reliable. For the economic factors, the Cronbach alpha coefficients (0.712) were found to be
greater than 0.7 and also the Cronbach alpha coefficients (0.805) were found to be greater than
0.7. Overall, the Cronbach alpha coefficients for all the variables were found to be 0.874 greater
than 0.7 implying that there was good consistency and reliability of the data used in this study.
In order to determine the critical success factors of PPP projects in the roads sector, an
exploratory factor analysis (EFA) was conducted. An exploratory factor analysis was preferred
This analysis included conducting a Kaiser-Meyer-Olkin (KMO) test for reliability assurance.
The researcher tested whether the collected data was suitable to conduct factor analysis.
Findings in table 3 below revealed that the resulting value of 0.760 significantly exceeded the
recommended threshold of 0.5, thus indicating the justification for implementation of this
43
method. The realized value for Bartlett’s test also showed that all conditions were met (χ 2
=1058.912; df = 276; Sig. = 0.000), which means that a certain degree of correlation that exists
between the variables will enable their grouping and forming of the factors.
The analysis in table 4 shows the rotated factor matrix with factor loadings. The factor loadings
indicate the relative importance of each statement in forming a particular factor. In other words,
it is the correlation coefficient between each statement with the factor itself. For a higher
correlation coefficient implies that the given statement better fits the factor. This analysis was
The first factor contained a total of four statements (Sound Financial package, Strong Private
Consortium with Strong technical strength, Competence of Organization staff and Transaction
Advisor (T.A) and Strong Contract Management and Control). The highest loading factor 0.705
had the statement strong contract management and control. This was closely followed by 0.607
with the statement that competence of organization staff and transaction advisor (T.A). other
factor loadings were 0.556 and 0.546 with statement that strong private consortium with strong
A total of three statements loaded on factor 2. These included (multi-benefit objectives, stable
macro-economic indicators and fiscal concession and investment policy). The highest loading
44
factor 0.679 had the statement fiscal concession and investment policy. This was followed by
multi-benefit objectives and stable macro-economic indicators with factor loadings of 0.611 and
0.513 respectively
The third factor contained only one factor with a 0.557 factor loading. This loading factor had
45
3.10 Data Collection Procedure
The researcher obtained an introductory letter from the Kyambogo University which introduced
the researcher to the respondents and the purpose of carrying out the study. The introductory
letter was used to seek for permission from relevant authorities to carry out the study in their
study, questionnaires were uploaded on a data collection software and sent to the respondents via
a link on the internet which allowed for data response and online submission for preceding data
analysis. Primary data obtained from the field using questionnaires were sorted, edited,
summarized, coded and analyzed in order to draw conclusions and recommendations about the
study variables.
The data collected from the field were sorted, and coded. Data were then tabulated and input in
the Statistical Package for Social Scientists (SPSS) version 25. Thereafter, data were checked
for entry errors, missing values, presence of outliers and normality prior to the multivariate
analysis. Negatively worded scale items were reverse-coded. Simple frequency runs were done
so as to screen the data to identify and replace missing values using series of means value
Quantitative data analysis techniques including descriptive statistics and inferential statistics
were then used for analyzing the research findings. Descriptive statistics like the measures of
central tendency were run so as to establish the demographic characteristics of the respondents.
46
The Pearson’ correlation coefficient was used to establish the relationship between independent
variables and the dependent variable. Inferential statistics (like multiple regression analysis)
were conducted to determine variance in the dependent variable, which is explained by the
independent variables. Reliability and factor analysis were performed in order to test the
research data. An Exploratory Factor Analysis (EFA) was conducted to detect the factor
dimensions of success of PPP projects. EFA was preferred in this study because it allowed
common items to hang on a common factor and it also made it possible for the researcher to
reduce items to fewer constructs which were then used for further analysis.
Qualitative Analysis
Key themes were developed from the key issues raised by the key informants and later analyzed
to draw conclusions and recommendations. These were used to back up the quantitative analysis
and findings.
The variables in this study were measured based on previous scholarly works. This is in line with
Okafor & Osuagwu (2006) who recommend adapting item scales from previous studies due to
their wide item scale reliability and validity. Critical success factors which were the independent
variable, were conceptualized as political, economic and managerial factors (Ahmadabadi &
Heravi, 2019). For all the constructs in the study, the item scales were anchored on a five-point
Likert scale, ranging from ‘‘5’’ = Strongly agree to ‘‘1’’ = strongly disagree. On the other hand,
PPP implementation being the dependent variable were conceptualized as profitability, long term
partnership relationship, satisfying the need for public facility/service, adherence to time,
adherence to budget, reduced litigations and disputes, reduced public sector administrative costs,
47
effective technology transfers and innovation (Casady et al., 2017). Responses were anchored on
Ethical principles that were upheld in this study include; confidentiality, seeking consent,
The researcher protected the identity and information provided by respondents so as to avoid
regarded as confidential.
The researcher avoided plagiarism by acknowledging scholarly works done by other researchers
48
CHAPTER FOUR
PRESENTATION, ANALYSIS AND INTERPRETATION OF RESULTS
4.0 Introduction
This chapter presents and interprets findings from the data collected by use of a questionnaire
(Appendix II). The chapter was presented in relation to the study objectives, literature,
This section consists of information that describes basic demographic characteristics of the
respondents that include; gender, age category, position in entity, highest education level
During the study, a total of 132 respondents responded to the questionnaire. Figure 4.1 below
revealed that of the 132 respondents, majority 79.5% (n=105) were males and only 20.5% (n=27)
of the respondents were females. This implies that most employees in the companies/ sectors
49
4.1.2. Age categories of respondents.
The study also revealed that majority 71.2% (n=94) of the respondents were between 25-45 years
of age. Only 28.8% (n=38) of the respondents were above 45 years. This implies that companies/
25-35 38 28.8
36-45 56 42.4
46-50 15 11.4
51+ 23 17.4
During the study, respondents were asked their highest level of education. Figure 4.2 below
revealed that majority 54.5% (n=72) of the respondents had attained master’s degree followed by
34.1% (n=45) of the respondents who had attained Bachelor’s degree. About 10.6% (n=14) of
respondents reported that they had attained diploma as their highest level of education. Only 1
50
Figure 4. 2: Showing respondent’s highest level of education
During the study, respondents were asked their positions held in their institutions or entities.
From table 6, it was revealed that majority 27.3% (n=36) of the respondents held managerial
positions. This was closely followed by 25.8% (n=34) of the respondents who reported that they
were officers. About 20.4% (n=27) of the respondents reported that they held senior officer
positions in their entities. Other positions held by the respondents in their respective entities
included head of departments and directors as reported by 19.7% and 6.8% respectively as
51
Table 6: Showing respondent’s positions held in their entities/ companies
Managerial positions Frequency Percent
Director 9 6.8
Manager 36 27.3
Officer 34 25.8
During the study, the researcher wanted to know under which sector the respondents’
entity/company exposed to PPPs projects in the roads sector in Uganda belonged. From figure
4.3 below, it was established that majority 65.1% (n=86) of the respondents reported that they
belong to public sector. This was followed by 20.5% (n=27) of the respondents reported that
they were from the private sector. Other respondents of the study were from the academia, civil
society organizations, development partners and consultants with exposure to PPPs projects.
52
Figure 4. 3: Showing sector under which the respondents belong
During the study, it was established that majority 58.3% (n=77) of the sampled respondents had
less than 5 years of exposure to PPP projects. About 26.5% (n=35) of the respondents reported
that they had completed 6-10 years of exposure to PPP projects and only 15.1% (n=20) of the
respondents reported that they had completed more than 10 years of exposure to PPP projects.
This implies that majority of the respondents did not have much experience in PPP projects in
the roads sector although they had encountered PPPs in other spheres. This is attributed to the
fact that PPPs are a relatively new phenomenon in Uganda and particularly in the roads sector.
53
4.2. Critical Success Factors
This section presents and discusses the findings on influence of critical success factors on the
successful implementation of the PPP project. The section focuses on the influence of political,
Political factors are an embodiment of political support, stability and good governance that are
enablers of favorable legal, regulatory and institutional frameworks. During this study, the
researcher sought the respondent’s perception of political factors (political support, political
stability, good governance, favorable legal & regulatory framework, effective PPP procurement
process, well organized & committed public agency, stakeholder acceptance/support and multi-
benefit objectives) on the successful implementation of PPP projects in the roads sector in
Uganda. The instrument used was anchored on a five-point Likert scale, ranging from 1 – 5
where ‘1’ was perceived as ‘not important’ ‘2’ was perceived as ‘less important’ ‘3’ was
perceived as ‘some importance’ 4 was perceived as ‘important’ and ‘5’ was perceived as ‘very
important as shown in table 8 below. A mean result below 4.2 suggests low Political factors’
influence on PPP implementation while a mean result of >4.2 suggests a high political factor’s
54
Table 8: Showing respondent’s perception on political factors on the successful
implementation of PPP projects in the roads sector
Freq. 64 38 25 5
Political support 4.22
Percent 48.5 28.8 18.9 3.8
Freq. 73 42 13 4
Political Stability 4.39
Percent 55.3 31.8 9.8 3.0
Stakeholder Freq. 55 55 17 5
4.21
acceptance/support Percent 41.7 41.7 12.9 3.8
Freq. 29 73 25 5
3.95
55
Political support: During the study, respondents were asked their perception of political support
on the successful implementation of PPP projects in the roads sector in Uganda. Table 8 revealed
that majority 48.5% (n=64) of the respondents reported that political support is a very important
factor in determining the successful implementation of PPP projects in the roads sector. In this
case political support meant an increment in inclinations towards PPPs and effective address of
barriers faced in the roads sectors by leaders in the executive and legislature (Parliament). Only
3.8% (n=5) of the respondents reported that political support is not an important factor in
Political Stability: Political stability is defined as “…the likelihood that the government will be
violence and terrorism” (Kaufmann et al., 2010; p.4). A stable political environment largely
affects factors such as regulatory and macro-economic environments. Political instability may
result in PPP project termination, poor governance, insecurity and lack of transparency and
accountability on the part of government. During the study, respondents were asked the extent to
which political stability influences the successful implementation of PPP projects in the roads
sector. From table 4.4 above, it was revealed that majority 55.3% (n=73) of the respondents
reported that political stability is a very important factor that influences successful
implementation of PPP projects in the roads sector. This was followed by 31.8% (n=42) of the
respondents who reported that political stability is an important factor in determining the success
of the implementation of PPP projects in the roads sector. Only 3.0% (n=4) of the respondents
reported that political stability is less important in determining the success of a PPP project in the
roads sector.
56
Good Governance: The study revealed that 47.0% of the respondents reported that good
project in the roads sectors. This was followed by 43.2% of the respondents who ranked good
governance an important factor in the success of a PPP project in the roads sector. About 9.9% of
the respondents reported that good governance is not important in the successful implementation
Favorable Legal & Regulatory Framework: The study further revealed that majority 81.0% of
the respondents reported that favorable legal & regulatory framework is an important factor in
determining the success of a PPP project in the roads sector. Only 19.0% of the respondents
reported that favorable legal & regulatory framework is not an important factor in the success of
In conclusion, political stability was the most rated political factors with an influence on the
successful implementation of PPP projects in the roads sector with a mean value of 4.39. This
was closely followed by good Governance with mean value of 4.35, Political support with a
mean value of 4.22 and Stakeholder acceptance/support with a mean value of 4.21. Political
factors reported to have a less influence on the successful implementation of PPP projects in the
roads sector were well organized & committed public agency with a mean value of 3.98,
effective PPP procurement process with a mean of 4.20, Favorable legal and Regulatory
framework with a mean of 4.18 and multi-benefit objectives with a mean value of 3.95. Items
with mean scores above or equal to 4.2 implies that the respondents accorded much importance
to the factors and agreed that they have an influence in PPP implementation while items that
were below 4.2 implies that the respondents did not accord them much importance.
57
4.2.2. Influence of Political factors on the successful implementation of PPPs.
To establish the influence of political factors on the successful implementation of PPPs projects
in the roads sector, a Pearson’ correlation coefficient was conducted. From table 9 below, it was
established that there is a moderate positive (0.512) relationship between political factors and
PPP Success Criteria. The results further revealed that this relationship was statistically
significant at 0.01 level of significance since the p-value (0.000) < 0.01. Thus, political factors
have an influence on the on the successful implementation of PPPs projects in the roads sector
implying that if the political factors are favorable, then PPP implementation would progressively
be achieved.
Successful Implementation
Political factors
of a PPP road project
Pearson Correlation .512** .512**
Political factors Sig. (2-tailed) .000 .000
N 132 132
Successful Pearson Correlation 1
implementation of a PPP Sig. (2-tailed)
road project N 132 132
**. Correlation is significant at the 0.01 level (2-tailed).
Source: Primary data
In this study economic factors for the successful implementation of PPP projects in the roads
sector included available mature financial markets, fixed low interest-rate financing, sound
58
government guarantees, project economic viability and fiscal concession and investment policy.
During the study, the researcher sought the respondent’s perception of economic factors on the
successful implementation of PPP projects in the roads sector in Uganda. The researcher applied
descriptive statistical analysis to the sample and frequencies, percentages and arithmetic mean
for each economic factor were calculated as shown in table 9 below. A mean result below 3.93
suggests low economic factors’ influence on PPP implementation while a mean result of >3.93
suggests a high economic factor’s influence on PPP implementation on a particular item of the
variable.
Regarding the available mature financial markets, majority of the respondents 40.9% (n=54)
reported that it is a very important factor in determining the successful implementation of the
PPP projects in the road projects. This was followed by 32.6% (n=43) of the respondents who
reported that availability of a mature financial markets is an important factor in the successful
implementation of the PPP projects in the road projects. Only 3.0% (n=4) reported that
availability of a mature financial markets has less importance on the successful implementation
For fixed low interest-rate financing, about 35.6% (n=47) of the respondents reported that it is a
very important factor in the successful implementation of the PPP road projects. This was closely
followed by 31.1% (n=41) of the respondents who reported that it is an important factor in the
successful implementation of the PPP projects in the roads. Only 3.8% of the respondents
reported that fixed low interest-rate financing has less importance in the successful
59
Table 10: Showing respondents of economic factors on the successful implementation of
In conclusion, availability of mature financial markets was the most rated economic factor with
an influence on the successful implementation of PPP projects in the roads sector with a mean
value of 4.11. This was closely followed by sound economic policies with mean value of 4.07,
government financial support/subsidies with a mean value of 4.06 and project economic viability
60
with a mean value of 4.05. Economic factors reported to have a less influence on the successful
implementation of PPP projects in the roads sector were stable macro-economic indicators with a
mean value of 3.66, government guarantees and fiscal concession and investment policy with
mean values of 3.71 and 3.83 respectively. Fixed low interest rate financing had a mean of 3.98
implying that items whose mean was above the average mean of 3.93 were accorded much
importance as economic factors influencing PPP implementation while those items whose mean
was below 3.93, the respondents did not accord them much importance as economic factors
For the researcher to establish the influence of economic factors on the successful
implementation of PPPs projects in the roads sector, the researcher conducted a bivariate analysis
where a Pearson’ correlation coefficient was conducted. The results of the Pearson’ correlation
coefficients are shown in table 11 below. The study findings in table 4.7, revealed that there is a
strong positive (0.556) relationship between economic factors and PPP Success Criteria. The
results further revealed that this relationship was statistically significant at 0.01 level of
significance since the p-value (0.000) < 0.01. Thus, economic factors have an influence on the on
61
Table 11: Showing the influence of economic factors on the successful implementation of
PPP projects in the roads sector
Economic Successful implementation
factors of a PPP road project
Economic factors Pearson Correlation 1 .556**
Sig. (2-tailed) .000
N 132 132
Successful Pearson Correlation .556** 1
implementations of a Sig. (2-tailed) .000
PPP road project N 132 132
**. Correlation is significant at the 0.01 level (2-tailed).
Source: Primary data
In this study, managerial factors that influence the successful implementation of PPP projects in
the roads sector in Uganda are an embodiment of right project identification, detailed project
planning, appropriate risk allocation, sound financial package, strong private consortium with
strong technical strength, competence of organization staff and transaction advisor (T.A), strong
contract management and control and acceptable toll/tariff levels. The instrument was used to
understand the respondents’ perception on the influence of managerial factors on the successful
implementation of PPP projects in the roads sector was anchored on a five-point Likert scale,
ranging from 1 – 5 where ‘1’ was perceived as ‘not important’ ‘2’ was perceived as ‘less
important’ ‘3’ was perceived as ‘some importance’ 4 was perceived as ‘important’ and ‘5’ was
perceived as ‘very important as shown in table 12 below. The researcher applied descriptive
statistical analysis to the sample and frequencies, percentages and arithmetic mean for each
managerial factor were calculated as shown in table 4.8 below. A mean result below 4.22
suggests low managerial factors’ influence on PPP implementation while a mean result of >4.22
suggests a high managerial factor’s influence on PPP implementation on a particular item of the
variable.
62
Table 12: Showing respondent’s perception of managerial factors on the successful
implementation of PPP projects in the roads sector
From the study findings in table 12 above, majority 56.8% (n=75) of the respondents reported
that right project identification as a very important managerial factor in influencing the
successful implementation of PPP projects in the roads sector in Uganda. This was closely
followed by detailed project planning reported by 47.0% (n=62) of the respondents, strong
private consortium with strong technical strength 43.2% (n=57). Further analysis revealed that
important managerial factors to influence the successful implementation of PPP projects in the
63
roads sector included acceptable toll/tariff levels 47.7% (n=63) followed by competence of
organization staff and transaction advisor (T.A) 46.2% (n=61) and strong contract management
and control 45.5% (n=60). On the other hand, acceptable toll/tariff levels, at 8.3% were reported
to be the least important managerial factor in determining the successful implementation of PPP
In conclusion, right project identification was the most rated managerial factor in determining the
successful implementation of PPP projects in the roads sector with a mean value of 4.48. This
was closely followed by detailed project planning with mean value of 4.35, strong private
consortium with strong technical strength with a mean value of 4.27 and strong contract
management and control with a mean value of 4.26. Managerial factors reported to have a less
influence on the successful implementation of PPP projects in the roads sector were acceptable
toll/tariff with a mean value of 3.98 and sound financial package with mean values of 4.09.
Appropriate risk allocation had a mean of 4.20 implying that items whose mean was above the
average mean of 4.22 were according much importance compared to those below 4.22 as
projects in the roads sector, the researcher conducted a bivariate analysis where a Pearson’
correlation coefficient. The results of the Pearson’ correlation coefficients are shown in table 13
below. The study findings in table 13, revealed that there is a strong positive (0.620) relationship
between managerial factors and PPP implementation. The findings further revealed that this
relationship was statistically significant at 0.01 level of significance since the p-value (0.000) <
64
0.01. Thus, managerial factors have an influence on the on the successful implementation of
Table 13: Showing the influence of managerial factors on the successful implementation of
Successful Implementations of
Managerial factors a PPP road project
Managerial factors Pearson Correlation 1 .620**
parameters on which a project can be deemed/judged as successful. In this study, Public Private
Partnership (PPP) Success Criteria in the roads sector in Uganda were profitability, long term
partnership relationship, satisfying the need for public facility, adherence to time, adherence to
budget, reduced litigation and disputes, reduced public administration costs and effective
technology. A mean result below 4.01 suggests low success criteria for PPP projects in the road
sector while a mean result of >4.22 suggests a high success criterion for PPP projects in the road
65
Table 14: Showing success criteria for PPP projects in the roads sector
From table 14 above, satisfying the need for public facility (4.11) and adherence to budget (4.11)
were ranked highly by the study respondents as the success criteria for PPP projects in the roads
sector. This was closely followed by reduced litigation and disputes and effective technology.
The least ranked success criteria for PPP projects in the roads sector in Uganda was profitability
(3.89). Long term partnership relationship had a mean of 3.99, Adherence to time had a mean of
4.01, reduced litigation and dispute had a mean of 4.02, reduced public administration costs had
a mean of 3.95 and effective technology had a mean of 4.02 implying items above 4.01 were
66
accorded much importance than items below 4.01 in measuring success criteria for PPP project
During the study the researcher employed the multiple regression analysis to determine the
strength of the relationship between successful implementation of a PPP road project and
managerial factors, economic factors and political factors. The multiple regression was also used
From table 15 below, it was revealed that the R² = of the model was 0.443 which implies that
44.3% of the variance in successful implementation of a PPP road project can be explained by
67
Further analysis in table 16 below, revealed that the F-statistic of the model was statistically
significant at 0.05 level of significance since the p-value (0.000) < 0.05 thus we can assume that
the model explains a statistically significant amount of the variance in the factors determining the
successful implementation of a PPP road project. It can be concluded that managerial factors,
economic factors and political factors can be used to reliably predict the successful
Table 16: showing the Statistical significance of the multiple regression model
ANOVAa
b. Predictors: (Constant), Total score Managerial factors, Total score Economic factors,
Success factors = 4.687 + 0.082 Political factors + 0.282 Economic factors + 0.415 Managerial
factors. ………………………………………………………Equation 2
68
From equation 2 above and table 17 below, it was revealed that when the score on political
factors, managerial factors and economic factors is zero, the score on success factors on the
implementation of a PPP project in the roads sector in Uganda is 44.3%; keeping other factors
and compatibility between partners. These three factors contribute 44.3% variations in PPP
implementation.
Further analysis from the standardized coefficient results revealed that the score of managerial
factors was the strongest predictor of PPP implementation in the road sector the strongest effect
with (β = 0. 415) which is significant at 5% level of significance since the p-value 0.000 <0.05
leaving other factors constant. Therefore, the study concluded that managerial factors have an
influence on the successful implementation of PPP projects in the roads sector. This implies that
availability of managerial factors like appropriate risk allocation, detailed project planning,
strong contract management and control, competence of the organizational staff and transaction
The study further revealed that economic factors were the second most predictors of PPP
implementation in the road sector and was statistically significant at 5% level of significance
since the p-value (0.000) ˂0.05 with a (β = 0.282) implying that availability of a favorable
economic environment in form of fixed low interest financing, project economic viability and
The study also revealed that a political factor were the least predictors of PPP implementation in
the road sector p-value (0.003) <0.05 and a (β = 0.082) implying that implying that a presence of
favorable factors like political support, political stability, good governance, stakeholder support,
69
favorable legal and regulatory framework among others results into success of PPP
Coefficientsa
Unstandardized Standardized 95.0% Confidence
Coefficients Coefficients Interval for B
t Sig.
Lower Upper
Model B Std. Error Beta Bound Bound
1 (Constant) 4.687 2.735 1.714 .089 -.725 10.099
Total score Political factors .087 .097 .082 .898 .003 -.105 .279
Total score Economic
.330 .099 .282 3.337 .001 .134 .526
factors
Total score Managerial
.418 .087 .415 4.784 .000 .245 .590
factors
a. Dependent Variable: Total score Successful Implementation of a PPP road project
Views on the influence of political, economic and managerial factors for PPP implementation
were sought. Four people were interviewed to reinforce the study findings. These included a
Senior Engineer with Kampala Jinja Express way PPP Project, a director from UNRA, a director
from MoFPED’s PPP unit and a Senior Manager in the PPP unit.
4.3.1 Political Factors as a CSF in the implementation of PPPs in the roads sector
All the interviewees strongly agreed that political factors were important for PPP
implementation.
Interviewee 1 pointed out that political factors are very important for the successful
70
.…political support is very important, but PPPs do not need any interference and meddling as
PPP processes are very lengthy and you are dealing with funders coming to invest their money in
a project. No one would invest their money in a high-risk place (politically unstable) and when
they are not sure of the transparency of the process…. Political factors play a key role and if you
don’t have your factors in order, the chances are that you won’t have a PPP and even if you do,
the chances are that you won’t attract the right players.
….. politics play a very critical in the Public Private undertakings in terms of passing relevant
…… you cannot underestimate the impact of political factors in the successful implementation a
PPP project as any contracting authority would tell you that without political buy-in, a project
The mentioned interviewees’ perspectives suggest that political factors are important for PPP
implementation: as established by the questionnaire data. This is consistent with Ramli &
Mohamed (2019) who contend that government political influence was a highly rated factor for
4.3.2 Economic Factors as a CSF in the implementation of PPPs in the roads sector
Interviewee 1 … Economic policies reduce the risk profile of the project …. available financial
markets enable private players obtain financing that can be repaid using the local currency,
71
Interviewee 2 asserted that; …… economic factors are very key for PPP project success. Factors
such as interest rates and financial markets, favorable economic environment - all translate to the
total cost of the project and have a bearing on tolling rate determination.
4.3.3 Managerial Factors as a CSF in the implementation of PPPs in the roads sector
Interviewee 2 …. Managerial factors are very critical for PPP project success because project execution
is handled by the implementing agency on behalf of government ……... you must have a highly skilled
and robust staff portfolio to handle PPP road projects; a team that is able to interrogate, review and make
substantial remedy or comments in view of PPP project reports – even those from the T.A - not simply
relying on the T.A 100%, …. a team that is able to interpret whatever the T.A submits.
Interviewee 4 reiterated that …. Managerial factors are key as you won’t be able to structure a PPP
Managerial factors are very key for PPP project implementation especially skills set and
72
CHAPTER FIVE
5.1. Introduction.
This chapter presents the summary of the findings, conclusions drawn and recommendations of
the study.
5.2.1 The influence of political factors on the implementation of PPP road projects
The study revealed that when political factors, managerial factors and economic factors are
Specifically, the findings revealed that there was a strong positive relationship between political
factors and PPP implementation in the road projects and this relationship was statistically
significant. Thus, political factors have an influence on the on the successful implementation of
PPPs projects in the roads sector. The study also revealed that political factors were the least
predictors of PPP implementation in the road sectors and also significant implying that political
factors like support from policy makes is highly important if these kinds of financing
5.2.2 The influence of economic factors on the implementation of PPP road projects
The study also revealed that there is a strong positive relationship between economic factors and
PPP Success Criteria. The results further revealed that this relationship was statistically
significant. Thus, economic factors have an influence on the successful implementation of PPPs
73
projects in the roads sector. The study further adduced that a presence of favorable economic
factors would increase in the successful implementation of a PPPs project in the roads sector
keeping other factors constant. This is statistically significant thus it can be concluded that
economic factors have an influence on the successful implementation of a PPPs project in the
roads sector. This was the second most predictor of PPP implementation in the road sector of
Uganda.
5.2.3 The influence of managerial factors on the implementation of PPP road projects
It was also reported that there is a strong positive relationship between managerial factors and
PPP Success Criteria. The findings further revealed that this relationship was statistically
significant. Thus, managerial factors have an influence on the on the successful implementation
of PPPs projects in the roads sector. Further analysis from the standardized coefficient results
revealed that the score of managerial factors has the strongest effect PPP implementation
implying that presence of managerial factors would result into increase on the successful
implementation of a PPPs project in the roads sector which is significant. Therefore, the study
concluded that managerial factors have an influence on the successful implementation of a PPPs
5.3.1 The influence of political factors on the implementation of PPP road projects
From the findings, political factors have an influence on the successful implementation of PPP
road projects. These study findings and observations are supported by previous studies which
attributed political instability as a determinant towards project implementation success (Dairu &
Muhammad (2016) . Additionally, Casady et al., (2017) asserts that effective PPP delivery is
dependent on institutional maturity. Political factors are mirrored by a sound public policy
74
characterized by good governance, to avoid opposition on the part of citizens and political parties
(Firmino, 2018). Furthermore, Carter et al., (2017) revealed that PPPs are a tool for public
performance monitoring. From the study findings and related literature, the study affirms that
political factors have an influence on the successful implementation of PPPs in road projects
implying that the government of Uganda and policy makers should put this in consideration
5.3.2 The influence of economic factors on the implementation of PPP road projects
Economic factors were also found to have an influence on the successful implementation of PPP
road projects. These study findings were in line with Li et al., (2005) who submits that a stable
and growing economic environment brought about by the adoption of appropriate economic
policies is an enabler of private sector participation with confidence. Ahmadabadi & Heravi
(2019) contend that sound economic policies are characterized by the ability to deal with
fluctuations in exchange/interest rates and are also able to predict currency exchange risk,
thereby fostering favorable economic systems. Economic factors also embody the presence of
government guarantee / financial support especially as perceived by the private sector (Ismail,
2013). Therefore, economic factors as well has influence the successful implementation of PPP
projects in roads. This implies that private sector investment is desirable to have implementation
a success.
5.3.3 The influence of managerial factors on the implementation of PPP road projects
Lastly, managerial factors pose an influence on the implementation of PPP road projects. this is
supported by previous studies for example, Osei-kyei & Chan, 2018 who noted that a clearly
75
structured and established national infrastructure plan enables right project selection by public
authorities - that is characterized by demonstrated and accepted need for the project/facility by
the public and the project being a near-monopoly in providing the public facility. Similar studies
by Kahwajian et al., (2014) established that the lack of skilled/experienced private and public
consulting organizations in Syria specializing in technical, legal and financial aspects of PPP
projects were among the main problems being encountered in PPP projects in Syria. Maseko
(2014) also emphasized that the selection criteria for the private partner should prioritize
experience and capability to deliver PPP projects. based on the study findings and the reviewed
literature, it’s evident enough to affirm that proper management in all aspects has an influence on
whether the implementation of these PPP projects in the road sector succeed or fail.
5.4. Conclusion.
This study set three hypotheses which included 1) Political factors have no influence on the
implementation of PPPs.
From the findings the researcher can conclude that political factors, economic factors and
Private Partnership projects in the roads sector in Uganda. This implies that favorable political
factors are key in terms of establishing an overall PPP policy framework which influences the
successful implementation of PPPs and the adoption of appropriate economic policies could lead
to a stable and growing economic environment which allows private sector participation with
confidence. In conclusion therefore, more emphasis should be put on the three factors that were
under study because it was found out that all have an influence in the success of PPP
76
implementation hence favorable conditions should be put in place if implementation is to
succeed.
5.5. Recommendations
There should be deliberate political will to enable institutions work without undue interference
and meddling in the implementation of PPP road projects as such projects are characterized by
lengthy time frames, costly investments and multilevel stakeholders’ involvements. Functional
institutions will facilitate right project identification, transparent procurement processes that
enables selection of a strong private consortium as well as selection of a Transaction Advisor for
the PPP road project; as all these factors contribute to the success of PPP road projects.
The study also recommends that to ensure the successful implementation of PPPs in the roads
sector, the procurement process should result into selection of a strong private consortium with
strong technical strength. The procurement process should therefore be transparently void of
undue influence. Similarly, strong contract management and control should be undertaken
throughout the PPP project implementation. However, strong contract management and control
can only be effective if the organization staff and transaction adviser are impeccably competent
in their understanding of PPP mechanisms. The study additionally should be able to inform the
policy makers and stakeholders that detailed planning is key to the success of PPP projects. The
PPP frameworks put in place should be key informants in project identification, planning and
execution, to be an enabler of a successful PPP road project implementation as PPPs are country
77
5.6 Areas of future research
The study revealed that the R² = of the model was 0.443 which implies that 44.3% of the
factors, economic factors and political factors. 56.7% of the variation is caused by other factors
which were not studied. Therefore, the study recommends that other studies be conducted to
establish the other factors that influence PPP implementation in the road sector.
Some respondents had reservations towards answer the questionnaire as they thought that the
researcher could obtain and release confidential information about PPP projects to the public.
This challenge was addressed by the researcher through assuring the respondents that the
information that they would give would be treated as confidential and that they would remain
The measurement scales that were used in the current study were adapted from previous
research studies. Subsequently, the limitations that were entrenched in them likewise affected
this study. However, the researcher utilized secondary data source for more explanation on the
study variables.
Respondent were slow at filling in the questionnaire due to their busy work schedule, which
somehow delayed the data collection exercise. The researcher attempted to resolve this
challenge by sending humble reminder messages to respondents to fill the questionnaire within
78
REFERENCES
Ahmadabadi, A. A., & Heravi, G. (2019). The effect of critical success factors on project success
in Public Private Partnership projects: A case study of highway projects in Iran. Transport
Policy, 73(July 2017), 152–161. https://doi.org/10.1016/j.tranpol.2018.07.004
Akintoye, A., & Beck, M. (2009). Policy , Finance & Management for Public Private
Partnerships (Akintola Akintoye and Matthias Beck (ed.)).
Alinaitwe, Henry ; Ayesiga, R. (2013). Success Factors for the Implementation of Public –
Private Partnerships in the Construction Industry in Uganda. Journal of Construction in
Developing Countries, 18(2), 1–14.
Baysinger, B. D., Kosnik, R. D., & Turk, T. A. (1991). Effects of Board and Ownership
Structure on Corporate R&D Strategy. Academy of Management Journal, 34(1), 205–214.
https://doi.org/10.2307/256308
Bing, Li, Hardcastle, C., Akintoye, A., & Edwards, P. (2005). Critical success factors for PPP /
PFI projects in the UK construction industry CRITICAL SUCCESS FACTORS FOR PPP /
PFI PROJECTS IN THE UK CONSTRUCTION INDUSTRY : A FACTOR ANALYSIS
APPROACH. Construction Management and Economics, February.
https://doi.org/10.1080/01446190500041537
Campos, M. L., Morini, C., Herminio, G., & Marcondes, S. (2018). A performance model for
Public Private Partnerships : the authorized economic operator as an example. Revista de
Administração, 53(2), 268–279. https://doi.org/10.1016/j.rausp.2017.07.002
Carter, B., Casady, B., Eriksson, K., Levitt, R. E., & Scott, W. R. (2017). A ‘ New Governance ’
Approach to Public Private Partnerships : Lessons for the Public Sector. 1–40.
79
Cui, C., Liu, Y., Hope, A., & Wang, J. (2018). Review of studies on the public private
partnerships (PPP) for infrastructure projects. International Journal of Project
Management, 36(5), 773–794. https://doi.org/10.1016/j.ijproman.2018.03.004
Dahiru, A., & Muhammad, R. (2016). Critical Success Factors of Public Private Partnership
Projects in Nigeria. ATBU Journal of Environmental Technology, 1–12.
Davis, F., Long, C., & Wabwire, M. (2016). Age of choice Uganda in the new landscape. April.
Debela, G. Y. (2019). Critical success factors (CSFs) of public private partnership (PPP) road
projects in Ethiopia. International Journal of Construction Management, 0(0), 1–12.
https://doi.org/10.1080/15623599.2019.1634667
E.R Yescombe ; Edward Farquharson. (2018). Public Sector Support for PPP Contracts. In
Public Private Partnerships for Infrastructure (pp. 251–259). https://doi.org/10.1016/B978-
0-08-100766-2.00018-8
Eaton, D., & Akbiyikli, R. (2009). Innovation in PPP. Policy, Finance & Management for Public
Private Partnerships, 301–326. https://doi.org/10.1002/9781444301427.ch16
F. E Mohamed Ghazali, S. A. R. and A. . M. S. (2017). The Critical Success Factors for Public
Private Partnership Highway Construction Project in Malaysia. Journal of Engineering and
Technology, 8(1), 69–84.
Fama, E. F. (1980). Fama - Agency Problem and the theory of the firm.pdf. The Journal of
Political Economy, 88(2), 228–307.
Hammami, M., Ruhashyankiko, J., & Yehoue, E. B. (2006). Determinants of Public Private
80
Partnerships in Infrastructure (WP/06/99).
Hodge, G., & Boardman, A. (2017). Public Private Partnerships : The Way They Were and What
They Can Become. 76(3), 273–282. https://doi.org/10.1111/1467-8500.12260
I F C Advisory. (2013). Uganda Roads PPP Project Pre-Mandate assessment Report Public and
Private Perceptions to funding Uganda ’ s Roads (Issue August).
Ismail, S. (2013). Critical success factors of public private partnership (PPP) implementation in
Malaysia. Asia-Pacific Journal of Business Administration, 5(1), 6–19.
https://doi.org/10.1108/17574321311304503
Ivanová, E., & Masárová, J. (2013). Importance of Road Infrastructure in the Economic
Development and Competitiveness. Economics and Management, 18(2).
https://doi.org/10.5755/j01.em.18.2.4253
Jefferies, M. (2006). Critical success factors of public private sector partnerships A case study of
the Sydney SuperDome. Engineering, Construction and Architectural Management, 13(5),
451–462. https://doi.org/10.1108/09699980610690738
Jomo, K., Chowdhury, A., Sharma, K., & Platz, D. (2016). Public Private Partnerships and the
2030 Agenda for Sustainable Development: Fit for purpose? DESA Working Paper, 43(11),
998–1005. http://www.un.org/en/development/%0Ahttps://www.oecd-
ilibrary.org/content/paper/f42bd4bb-
en%0Ahttps://sustainabledevelopment.un.org/index.php?page=view&type=400&nr=2288&
menu=1515%0Ahttp://www.un.org/esa/desa/papers/2016/wp148_2016.pdf
Kahwajian, A., Baba, S., Amudi, O., & Wanos, M. (2014). Identification of Critical Success
Factors ( CSFs ) for Public Private Partnership ( PPP ) Construction Projects in Syria.
Jordan Journal of Civil Engineering, 8(4), 393–405.
81
Kong, H. (2001). P Artnered P Rojects. Manager, 127(October), 351–358.
Li, B., Akintoye, A., Corresponding, P. J. E., Hardcastle, C., Li, B., Akintoye, A.,
Corresponding, P. J. E., Hardcastle, C., Li, B., Akintoye, A., Edwards, P. J., & Hardcastle,
C. (2007). Critical success factors for PPP / PFI projects in the UK construction industry
Critical success factors for PPP / PFI projects in the UK construction industry. Construction
Management and Economics, 6193, 1–14. https://doi.org/10.1080/01446190500041537
Ma, L., Li, J., Jin, R., & Ke, Y. (2019). A Holistic Review of Public Private Partnership
Literature Published between 2008 and 2018. Advances in Civil Engineering, 2019, 1–18.
https://doi.org/doi.org/10.1155/2019/7094653
Maseko, M. (2014). Analysis of critical success factors for Public Private partnerships in
infrastructure development in South Africa. The Southern African Institute of Mining and
Metallurgy, 129–142.
Matti Siemiatycki. (2011). The Theory and Practice of Infrastructure Public Private
Partnerships Revisited: The Case of the Transportation Sector. 1–38.
Mudi, A., Lowe, J., & Manase, D. (2015). Public Private Financed Road Infrastructure
Development in North-Central Region of Nigeria. 5(4), 58–67.
https://doi.org/10.5539/jms.v5n4p58
Muhammad, Z., & Johar, F. (2017). A Conceptual Framework for Evaluating the Success of
Public Private Partnership ( PPP ) Projects. Journal of Built Environment, Technology and
Engineering, 2(January 2018), 1–10. https://doi.org/10.1166/asl.2017.10038
Nallathiga, Ramakrishna ; Farhan, Sheik ; Haris, S. (2017). Factors Affecting the Success /
Failure of Road Infrastructure Projects Under PPP in India. Journal of Construction
Engineering and Project Management, 12(January), 1–12.
https://doi.org/10.6106/JCEPM.2017.12.00.001
82
National Planning Authority. (2012). Accelerating Implementation of Infrastructure Projects.
National Planning Authority (NPA). (2015). Second National Development Plan (Issue June
2015).
Ong’olo, D. O., & Spellman & Walker Co. Ltd. (2006). Public private partnerships (PPP)
practice and regulatory policy in Kenya. 1–40.
Osei-Kyei, R., & Chan, A. P. C. (2017). Developing a project success index for Public Private
partnership projects in developing countries. Journal of Infrastructure Systems, 23(4), 1–12.
https://doi.org/10.1061/(ASCE)IS.1943-555X.0000388
Ramli, S., & Mohamed, Z. A. (2019). Understanding of CSFs in the application of Public Private
Partnership ( PPP ) Toll expressway in Malaysia. International Journal of Innovative
Technology and Exploring Engineering, 9(1), 2082–2087.
https://doi.org/10.35940/ijitee.A4230.119119
Robert Osei-kyei & Albert P. C. Chan. (2017). Comparative Analysis of the Success. Project
Management Journal, September, 80–93.
Robert Osei-kyei & Albert P. C. Chan. (2018). Model for predicting the Success of Public
Private Partnership Infrastructure Projects in Developing Countries : A Case of Ghana.
Architectural Engineering and Design Management, 0(0), 1–20.
https://doi.org/10.1080/17452007.2018.1545632
Rockart, J. F. (1982). The Changing Role of the Information Systems Executive: A Critical
Success Factor Perspective. 1–44.
83
Sehgal, R., Dubey, A. M., & Tiwari, N. (2015). A CONCEPTUAL FRAMEWORK ON
CRITICAL SUCCESS FACTOR FOR IMPLEMENTATION OF PUBLIC PRIVATE
PARTNERSHIP ( PPP ) BASED ON LITERATURE REVIEW. International Journal of
Science, Technology & Management, 04(01), 692–704.
Shi, S., Chong, H., Liu, L., & Ye, X. (2016). Examining the Interrelationship among Critical
Success Factors of Public Private Partnership Infrastructure Projects.
https://doi.org/10.3390/su8121313
Shrivastava, V. K., & Rao, K. R. (2011). Public Private Partnerships (PPP) in Road Projects :
Critical Success Factors in the Indian Context. Proceedings of the 30th Southern African
Transport Conference (SATC 2011), July, 16–25.
Tang, L., Shen, Q., Skitmore, M., & Cheng, E. W. L. (2013). Ranked critical factors in PPP
briefings. Journal of Management in Engineering, 29(2), 164–171.
https://doi.org/10.1061/(ASCE)ME.1943-5479.0000131
Turley, L., & Semple, A. (2013). Financing Sustainable Public Private Partnerships. The
International Institute for Sustainable Development, February, 1–11.
https://www.iisd.org/sites/default/files/publications/ppp_financing.pdf
Ulli Arnold; Vanessa Kehl. (n.d.). PUBLIC PRIVATE PARTNERSHIP (PPP) ON THE MOVE
OR GOING SOUTH? EMPIRICAL INDICATIONS FOR SUCCESSFUL PPP DECISIONS
FROM GERMAN MUNICI- PALIES. 1–34.
UNRA. (2017). UNRA CORPORATE STRATEGIC PLAN FY 2017 18 - 2022 23.pdf (pp. 1–88).
Uganda National Roads Authority.
Węgrzyn, J. (2016). The Perception of Critical Success Factors for PPP Projects in Different
84
Stakeholder Groups. Entrepreneurial Business and Economics Review, 4(2), 81–92.
https://doi.org/http://dx.doi.org/10.15678/EBER.2016.040207
World Bank. (2017). Uganda Economic Update - Infrastructure Finance Deficit: Can Public
Private Partnerships Fill the Gap? May, 1–1.
http://documents.worldbank.org/curated/en/101271500881802370/pdf/117719-WP-
PUBLIC-21-7-2017-19-56-56-UEUfinalprintedversion.pdf
World Bank Group. (2017). PUBLIC PRIVATE PARTNERSHIPS Reference Guide. In PPP
Knowledge Lab library (Issue 3). https://doi.org/10.1002/tie.5060290205
World Bank Group. (2019). Improving Transparency and Accountability in Public Private
Partnerships: Disclosure Diagnostic Report - Uganda.
Yescombe, E. . (2017). Public Private Partnerships in Sub-Saharan Africa: Case Studies for
Policymakers. www.mkukinanyota.com. www.uongozi.or.tz
Zayyanu, Muhammad, Kim Kwang, Sik, Foziah, Johar, Soheil, S. (2016). AN OVERVIEW OF
CRITICAL SUCCESS FACTORS OF PUBLIC PRIVATE PARTNERSHIP IN THE
DELIVERY OF URBAN INFRASTRUCTURE AND SERVICES. Journal of the
Malaysian Institute of Planners, Iv, 147–162.
Zhang, X. (2005a). Critical Success Factors for Public Private Partnerships in Infrastructure
Development. Journal of Construction Engineering and Management, 131(1), 1–12.
https://doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3)
Zhang, X. (2005b). Paving the Way for Public Private Partnerships in Infrastructure
Development. Journal of Construction Engineering and Management, 131(February), 168–
85
175. https://doi.org/10.1061/(ASCE)0733-9364(2005)131
http://www.commonwealthgovernance.org/countries/africa/uganda/public private-partnerships/
86
APPENDICES
87
Appendix 2: Research Questionnaire
QUESTIONNAIRE
Dear Sir/Madam,
My name is Patricia Ajwang, a student of Kyambogo University pursuing a Master of Science in Procurement and Supply Chain
Management. As a requirement for the award of this degree, I am conducting a research study on Critical Success Factors
influencing the Implementation of Public Private Partnerships (PPP) in the Roads Sector in Uganda.
As an esteemed respondent, all information you provide will be treated with utmost confidentiality and used strictly for purposes of
this academic research. At no times shall the information you provide be used against you.
The survey is aimed at identifying critical success factors influencing the implementation of Public Private Partnerships (PPPs) in
Gender:
Male Female
88
Age Group
Level in Management
Sector
Public Sector Private Sector Development Partners Consultants Academicians
yll
89
Number of years of Exposure to PPP projects
0-5 years 6-10 years 11-15 years 16 + years
SECTION 2
SECTION 2:
Please evaluate the extent to which each of the listed Critical Success factors affects or promotes the successful implementation of
PPP road projects in Uganda. Basing on a scale of 1 to 5 where ‘1’ is perceived as ‘not important’ ‘2’ is perceived as ‘less important’
‘3’ is perceived as ‘some importance’ 4 is perceived as ‘important’ and ‘5’is perceived as ‘very important.
POLITICAL FACTORS
1 Political Support Policy should increase inclinations towards PPPs and
1 2 3 4 5 effectively address barriers faced.
2 Political Stability A stable political environment largely affects factors such
as regulatory and macro-economic environments. Political
1 2 3 4 5 instability may result in PPP project termination, poor
governance, insecurity and lack of transparency and
accountability of the government.
3 Good Governance Good governance is important for developing sound
90
1 2 3 4 5 economic policy and effectiveness of public institutions to
empower them administer projects.
4 Favourable Legal & Regulatory Allows a PPP project to be developed without undue legal
Framework restrictions on private sector involvement. Regulatory
1 2 3 4 5 policy contributes to the consecution of rights and
guarantees to partnerships.
5 Effective PPP Procurement An effective procurement process is anchored on the
Process principles of competition and transparency which
1 2 3 4 5
enhances project value for money and fosters stakeholder
confidence in the project.
6 Well Organized & Committed A well-organized and committed public agency to
Public agency 1 2 3 4 5 negotiate on behalf of the public body is essential for a
PPP project.
7 Stakeholder acceptance/support Critical stakeholder management system to identify and
manage issues and concerns that may impact the project.
1 2 3 4 5 Public acceptance of the concept of private provision in
terms of localized employed, economic and social
development.
8 Multi-benefit objectives PPP partners must understand and respect each other’s
91
ECONOMIC FACTORS
9 Available Mature Financial Presence of flexible and long-term project financers with
Markets appropriate risk insurance instruments.
1 2 3 4 5
10 Fixed Low interest-rate Financing Acts as a mitigant against interest-rate risk that affects
1 2 3 4 5 project value for money and financial viability of the
project.
11 Sound Economic Policies Government adoption of economic policies to maintain a
stable and growing economic environment which fosters
1 2 3 4 5
private sector confidence e.g., fiscal policy.
12 Stable macro-economic indicators Presence and extent of geo-political risks where the
market exhibits reasonable certainty and market risk is
1 2 3 4 5 correspondingly low, does a great deal to reduce risks for
private investors. Macro-economic indicators such as
purchase power parity/income levels, GDP and level of
investments in the economy (local & foreign).
13 Government Financial Government support through provision of partial capital
Support/Subsidies 1 2 3 4 5 financing, grants and tax exemptions.
14 Government Guarantees Government guarantees tend to lower the risk taken by the
concessionaire, support the cash flows of the
1 2 3 4 5
92
concessionaire, and raise the level of confidence of
investors and lenders.
15 Project Economic Viability Emphasizes the bankability of PPP projects. Bankability
(Split econ & fin, abilities) 1 2 3 4 5 connotes the project’s ability to generate a sustainably
sufficient cash flow and yield optimal results.
16 Fiscal Concession and Investment Use of budgetary process in line with government fiscal
policy 1 2 3 4 5 policy to minimize fiscal risk and ensure project
affordability in consideration of government expenditure
and revenue levels.
MANAGERIAL FACTORS
17 Right Project Identification A good PPP projects means a project is suitable and has a
strong technical and economic rationale. It should be in
1 2 3 4 5
line with the country’s national development plan and/
sector specific plan.
18 Detailed project Planning Aims to highlight all project intrinsic stages and
associated costs, risks and measurable output from the
1 2 3 4 5
inception stage to transfer of the good/service to the public
sector.
19 Appropriate Risk Allocation Technical, construction, operational, financial, foreign
(corner stone of PPPs) exchange risks, force majeure. Risk allocation entails
1 2 3 4 5 identification & allocation of risks to the party best suited/
positioned to handle, through a competitive concession
93
agreement.
20 Sound Financial package Cost of delivering the PPP project should be
94
2.2 Are there any other critical success factors you consider to be important that are not included in this questionnaire? (Please tick as
…………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………
95
SECTION 3
PPP Success Criteria denote the extent of success of an implemented PPP project. To what extent do the following signify the
successful implementation of a PPP road project? Basing on a scale of 1 to 5 where ‘1’ is perceived as ‘not important’ ‘2’ is perceived
as ‘less important’ ‘3’ is perceived as ‘some importance’ 4 is perceived as ‘important’ and ‘5’is perceived as ‘very important.
96
3.1 Are there any other PPP road project Success Criteria that you would like to draw to this research’s attention? (Please Tick as
appropriate)
…………………………………………………………………………………………………………………………………………..
SECTION 4
4.1 To what extent do PPP CSFs influence the implementation of PPP road projects in Uganda? (Please Tick as appropriate)
97
Appendix 3: Interview Guide
INTERVIEW GUIDE FOR PPP SPECIFIC RESPONDENTS
Self-introduction
My name is Patricia Ajwang, a student of Master of Science in Procurement & Supply Chain
Management at Kyambogo University. I am conducting a study on Critical Success Factors
influencing the Implementation of PPPs in the Roads sector – A case of Uganda; as the partial
requirement for the Master’s degree award.
You have been selected as a respondent to provide me with your views on this study based on
your experience on the subject matter. Your views will be kept and treated confidentially and at
no moment will it be used against you.
project.
4. What can government do to encourage private sector involvement in PPP road projects?
5. Comment on the influence of Managerial Factors as a PPP critical success factor in the
roads sector.
6. PPP Success Criteria denote the extent of success of an implemented PPP project. How
are you able to tell that a PPP road project has been implemented successfully?
98