Design Guide For Attaining Sustainability in BS Installations
Design Guide For Attaining Sustainability in BS Installations
Sustainability in Building
Services Installations
Objective
Disclaimer
1. Introduction 3
2. Sustainability Strategy 3
Appendix A 73
References 80
This Design Guide should not be regarded as exhaustive. The designers are
recommended to check and incorporate into the building design other appropriate
requirements and the latest technologies for BS sustainability design.
2. Sustainability Strategy
The intention of sustainability design is to eliminate negative environmental impact
through skilful and sensitive design. The designers have influence over the energy use,
greenhouse gases emissions, water use, thermal comfort and other sustainability
outcomes of buildings. Hence, there is increasing pressure to address sustainability issues
and to understand how engineering decisions can deliver a more sustainable built
environment.[1] To address the sustainability issues in a comprehensive and coherent way
and as far as building services installations are concerned, the sustainability strategies for
site aspects, materials aspects, energy use, water use and indoor environmental quality
would be considered separately below.
Site aspects would focus on the site upon which the building is to be built, the land use and
its location with respect to local transport and amenities, planning and design for the site
to take account of both beneficial and negative impacts on neighbours and the
development itself, mitigation of ecological impacts and emissions from the site over the
building’s lifetime, and aspects of site management.
The strategy of site aspects would include:[2]
(e) ground conditions for ground source heat pumps for heating/cooling, and
The initial review can also help to provide information for the strategies of energy use and
water use, e.g. potential energy resources and drainage constraints. To implement the
strategy of site aspects, the designers might have to:[2]
(a) apply adequate mitigation measures for dust and air emissions during the
construction as recommended by the Environmental Protection Department e.g.
using pre-fabricated air duct and storage areas to maintain a cleaner and tidier site
condition.
(b) provide adequate mitigation measures for construction noise for all Noise Sensitive
Receivers.
(d) reduce visual impact to the building neighbourhood through a careful choice of plant
and plant room locations e.g. cooling tower and chimney location.
(e) take into account effect of project to daylight of neighbouring sensitive buildings at
early planning stage, and ensure that the access to daylight of neighbouring sensitive
buildings is maintained to an acceptable level.
(f) demonstrate that the level of the intruding noise at the façade of the potential noise
sensitive receivers is in compliance with the criteria recommended.
(g) demonstrate that obtrusive light from exterior lighting meets the specified
performance for the environment in which the building development is located.
The amount and range of materials used in the construction, operation and maintenance
and fitting-out of buildings represents a significant use of natural resources, in terms of
extracted raw materials, emissions, and embodied energy. There are opportunities to
reduce environmental impacts through improved design, improved materials management,
choice of materials and installation methods, e.g. modular designs allowing off-site
The designers have to develop strategies for sustainable material management and waste
management. A sustainable material management should reduce the embodied lifetime
environmental impacts by selecting on the basis of environmental preference. The
principles for the selection of sustainable materials and equipment are:[1]
(b) selecting materials and equipment with the lowest in-use environmental impacts,
(c) selecting materials and equipment with high recycled content, and
(d) selecting materials and equipment with the lowest embodied environmental impacts.
Hence, the designers should use more rapidly renewable materials, recycled materials
and/or regionally manufactured materials; say locally within 800km from the site. The
designers should also use non-chlorofluorocarbon (CFC)-based refrigerants in HVAC
systems and avoid the use of ozone depleting substances.[2]
A sustainable waste management plan should reduce the production of waste arising from
the construction and operation of buildings to a minimum. Disposal should be considered
a last resort. The principles for managing waste are:[1]
(d) composting biodegradable waste, e.g. food waste composting system, and
(e) recovering energy from waste (and facilitate energy recovery from waste).
Hence, the designers should aim to reduce the amount of construction waste by recycling
waste, reuse more existing plant or equipment, use more off-site prefabricated building
services elements, adopt flexible design of services that can adapt to changes of layout and
use, and provide facilities for the collection, sorting, storage and disposal of waste and
recovered materials.[2]
The main objective of the energy strategy should be to reduce CO2 and other emissions
related to building energy use (e.g. NOx and SOx) as well as the use of finite, non-renewable
resources (fossil fuels) by applying energy efficient design principles and utilizing low or
zero carbon technologies. The considerations of energy strategy include:[2]
The designers are encouraged to adopt more renewable energy systems, e.g. wind turbines,
PV panels and solar hot water systems, and energy efficient appliances and equipment that
will be discussed in Chapter 3. The following might also be considered:[2]
(a) reducing the heat transfer from the outside to the interior through the building
envelope or in other words to minimize the designed OTTV value (OTTV reduction).
(c) assessing the embodied energy in the major elements of the building through a Life
Cycle Assessment (LCA) and ensuring that the major materials with low embodied
energy are used in the project. In this case, the designers might use the integrated
LCEA – LCC software tool as described in the previous section as a reference to assess
the embodied energy.
Hong Kong has long enjoyed a reliable and economic supply of most of its fresh water
needs from the Mainland. However, with increased industrialisation of Guangdong
Province, there is likely to be greater competition for water supply, meaning that water
conservation will become a significant issue for Hong Kong in the future. The designers
should look for means to improve the utilisation and conservation of water resources.
Hence, the aspects of water use should include quality and features that improve
utilization and reduce effluent, i.e.:[2]
(d) recycling black water close to the point of use, if appropriate, and
Besides ensuring that the quality of portable water meets the referenced drinking water
quality standards at all points of use, the designers should install water efficient
devices/appliances and monitoring devices to:[2]
(a) automatic shut-off the devices for the purposes of water conservation,
(b) monitor water leakage within the fresh water distribution system, and
(c) monitor water flow at main supply branches for audit purposes .
The designers should also consider highly efficient irrigation technology and/or the use of
harvested rainwater and/or recycled grey water to reduce water consumption. The
design of rainwater/grey water recycling installations will be discussed in Chapter 3.
Indoor environmental quality (IEQ) includes those aspects of building performance that
impact on the health, comfort or well-being of the occupants, as well as aspects of
performance that improve quality and functionality. Poor indoor environments can
impact on productivity and may impose health risks to users. The design, management,
operation and maintenance of buildings should seek to provide good quality indoor
environments, but with optimum use of energy and other resources.[2]
The objective of IEQ strategy is to provide a healthy and comfortable internal environment
as well as an accessible and inclusive environment. The aspects of IEQ include:[2]
(a) safety,
(b) hygiene,
(e) lighting,
(b) applying good practice in providing for the widest practical range of accessibility needs,
To develop the IEQ strategy, the designers might consider the following:[2]
(b) reducing the potential for transmission of harmful bacteria, viruses and odours
through plumbing and drainage systems;
(e) providing adequate ventilation system especially for all enclosed common areas in a
building and rooms/areas where significant indoor pollution sources are generated;
(i) providing adequate natural lighting and good interior lighting performance; and
(j) providing airborne noise isolation between rooms, spaces and premises, and
maintaining the intruding noise level and mid-frequency reverberation time to meet
the prescribed criteria; etc.
In respect of energy efficiency, the design should comply with the latest edition of the
following documents and their latest updates issued subsequently from time to time as a
minimum. As the Government is to play an exemplary role in promoting energy efficiency,
designers shall aim to achieve a performance better than the statutory requirements as
much as possible.
The following list of documents should however not be regarded as exhaustive. Designers
are recommended to also follow other documents in relation to energy efficiency issued by
the relevant authorities from time to time, if any.
(c) Waterworks Ordinance, Cap 102 and Waterworks Regulations, Cap 102A
(d) Hong Kong Waterworks Standard Requirements for the Plumbing Installation in
Buildings
(e) Water Supplies Department Circular Letters issued to Licensed Plumbers and
Authorized Persons
(f) Building (Standards of Sanitary Fitments, Plumbing, Drainage Works and Latrines)
Regulations, Cap 123I
(g) Environment, Transport and Works Bureau Technical Circular (Works) No. 16/2005
“Adoption of Energy Efficient Features and Renewable Energy Technologies in
Government Projects and Installations”
(h) Development Bureau Technical Circular No. 5/2009 / Environment Bureau Circular
Memorandum No. 2/2009 “Green Government Buildings”
(i) BSB Circular No. 14 of 2008 “Guidelines on Metering Facilities for Energy and
Greenhouse Gas Emissions Monitoring/Audit Purpose”
(l) BSB Circular No. 25 of 2009 ―Energy Efficient Lighting Design for Offices – Task
Lighting Approach”
(m) BSB Circular No. 15 of 2012 – Design Guides for Energy Efficiency in Building Services
Installations
(o) Various Design Guides, General Specifications and Proforma Specifications issued by
ArchSD
(b) reducing air side distribution losses through imposing limits on air distribution
system fan motor power, ductwork leakage, duct friction loss, enhancing fan
efficiency and identifying conditions warranting separate distribution systems;
(c) reducing water side distribution losses through imposing limits on pipe friction
loss, enhancing pump efficiency and identifying conditions warranting variable
flow;
(e) reducing heat losses in pipework, ductwork and AHU casing through minimum
allowable thickness on insulation thereto; and
(f) reducing the use of energy through efficient controls and monitoring facilities
for energy consumption.
Design with suitable environment comfort for specific operational needs can
enhance energy efficiency. When identifying air-conditioning system zones,
the following should be considered:
i. separate systems serving office areas from those serving special areas,
such as wards, laboratory or process areas;
A thorough analysis of the peak load often leads to design solutions that
further decrease building energy consumption.
The system fan motor power required for a constant air volume (CAV) air
distribution system and a variable air volume (VAV) air distribution system for a
conditioned space should not exceed the corresponding limits in terms of Watt
per litre per second (L/s) of supply system air flow given in the BEC.
Chillers equipped with oil-free type centrifugal compressors can deliver higher
Integrated Part Load Value (IPLV) efficiencies than conventional oil-lubricated
centrifugal, reciprocating, scroll or screw compressors. The designers should
note that the capital cost of oil-free chillers is much higher than that for
conventional chillers and, as a result, sufficient fund should be allowed in the
cost estimation. Chillers with variable frequency drive device also provide
high IPLV with a lower capital investment when comparing to that for oil-free
chillers.
The two most common and efficient types of water distribution systems within
a building are primary-secondary and all-primary pumping systems. For
primary-secondary pumping system, separate pumps serve the primary circuit
(central plant) and the secondary circuit (distribution system to terminal units)
whereas for all-primary pumping systems, the same pumps serve both the
central plant and the distribution system supplying the terminal units. The
primary-secondary systems provide energy-saving opportunities through
variable flow (only pumps the water actually needed to meet the required
loads) and elevates the return-water temperature. Hence, the
primary-secondary pumping systems category is more energy efficient than the
all-primary pumping system and the designers should adopt the
primary-secondary pumping systems as far as practicable.
Water piping should be sized for frictional loss not exceeding the limits in terms
of Pa/m andm/s (water flow velocity) given in the BEC.
A good energy efficiency design will reduce heat losses in pipework, ductwork
and AHU casing through insulation. All chilled water pipes, condensate drain
pipes, low pressure hot water pipes, refrigerant pipes, ductworks and AHU
casings should be insulated with a minimum insulation thickness in accordance
with the BEC.
Please refer to the “Design Guide for Energy Efficiency in Electrical Installation”
issued by Building Services Branch, ArchSD for the requirements on minimum
allowable motor efficiency and high efficiency electric motors.
i. optimizing the equipment start and stop times (e.g. turning fans off
during unoccupied hours)
Free cooling operation mode should be considered for areas requiring 100%
fresh air with 24-hour operation such as isolation wards and laboratory in order
to save energy during winter period. The designers should be aware of the
criteria for the sizing of free cooling air duct and air handling units.
3.1.1.3 For more details, readers are advised to refer to the “Design Guide for Energy
Efficiency in Air-conditioning Installation” issued by Building Services Branch,
ArchSD.[4]
Energy efficiency for electrical installation can be classified into active and passive
ways. Passive energy efficiency is achieved by such measures as reducing heat
generation and using equipment which requires less energy. Active energy
efficiency is achieved by putting in place an infrastructure for measuring, monitoring
and controlling energy use with a view to making lasting changes.
The motor efficiency should meet the minimum allowable values stipulated in
the BEC, which are comparable to Class IE2 of EN 60034-30:2009. This
standard defines the following efficiency classes of low-voltage three-phase
asynchronous motors in the power range from 0.75 kW to 375 kW.
The copper loss, expressed in terms of a certain percentage of the total active
power transmitted along the circuit conductors at rated circuit current, of every
main distribution circuit connecting the distribution transformer and the main
incoming circuit breaker of a LV switchboard should be minimized by means of
either:
ii. Restricting its copper loss to not exceeding the maximum allowable value
stipulated in the BEC.
Sub-main distribution circuits include feeder circuit, sub-main circuit and final
circuit. The copper loss in each type of the sub-main distribution circuits
should not exceed the respective maximum allowable values stipulated in the
BEC and Electrical Design Guide of BSB. However, the designers should
consider cable sizes larger than the said minimum values for of the following
reasons:
iii. standard fuse rating requiring larger cable for safety in overload
conditions; and/or
The presence of harmonics on the power distribution system affects the energy
efficiency of the system. Typical problems include overheating distribution
transformers, overloading neutral conductors, overheating rotating machinery,
unacceptable neutral-to-earth voltage, distorted supply voltage waveform,
communication interference due to electromagnetic interference (EMI),
capacitor banks failure, incorrect tripping of fuses and circuit breakers,
malfunctioning of electronic/computing equipment, and most importance of all,
inefficient distribution of electrical power. Hence, the total harmonic
distortion (THD) of current for any circuit should not exceed the appropriate
figures as per IEEE 519-1992, BEC and supply rules of the power supply
companies.
According to the BEC, the design total power factor for a circuit at or above
400A (based on circuit protective device rating), single or three phase, at
designed circuit current should not be less than 0.85. Power factor correction
using the conventional capacitor bank must be carefully designed to avoid
overcurrent and resonance in the supply networks with high contents of
harmonics. Power factor for non-linear circuit can only be corrected by
appropriate harmonic filters.
In general, the principles for achieving energy efficiency for lift/escalator installations
are:
The selection of speed and rated load of lifts are also the factors to be considered to
optimize the energy efficiency design without sacrifice the performance of lift traffic.
Hydraulic lift is in general not energy efficient due to the reason that the dead
weight of the lift car is the predominating factor on its maximum running
power as there is no counterweight to balance its dead weight. The designers
should always consider using electric traction lift before going to the hydraulic
lift option
The electrical power of the motor drive of the lift, escalator and passenger
conveyor installation should not exceed the corresponding maximum allowable
value given in the BEC.
The total power factor of the motor drive of a lift and escalator at the isolator
connecting to the building’s electrical supply circuit should not be less than
0.85 as stipulated in the BEC when the lift is carrying a rated load at its rated
speed and traveling in an upward direction and when the escalator is operating
under its brake load condition at rate speed, with the steps or pallets moving in
an upward direction.
The maximum allowable total harmonic distortion (THD) should also be limited
to the corresponding maximum allowable value given in the BEC.
The decoration load in a lift should not exceed the corresponding maximum
allowable value given in the BEC.
In accordance with the BEC, under normal operating status, at least one lift of a
lift bank should be in parking mode during the periods when the traffic
demand on vertical transportation system is low. Under parking mode, a lift
should not respond to passenger calls until it returns to the normal operation
mode.
In accordance with the BEC, the ventilation and air-conditioning, if any, of lift
car should be shut off automatically when the lift car is idling for certain
periods until the lift is activated again by passenger call. The automatic
shutoff requirements of ventilation and air-conditioning are different. Please
refer to the BEC for the details. Moreover, the automatic shutoff of
air-conditioning shall not apply to observation lift which travels through non
air-conditioned space or with its lift well located in unconditioned space
(usually the one travelling at the building façade).
3.1.3.3 For more details, please refer to the “Design Guide for Energy Efficiency in Lift and
Escalator Installation” issued by Building Services Branch, ArchSD.[6]
(b) Choose the proper lighting level for the activity to be carried out
(c) Choose energy efficient lighting fittings and/or lamp source with high lumen
efficacy (lumen/watt)
Lighting Power Density (Unit: W/m2) means the electrical power consumed by
lighting installations per unit floor area of an illuminated space.
The maximum allowable lighting power density of general lighting for various
spaces should comply with the relevant requirements stipulated in the BEC.
The minimum number of lighting control points (such as manual lighting switch,
occupancy sensor, daylight sensor and other lighting switching devices etc.) for
an office should comply with the relevant requirements stipulated in the BEC.
The lighting fittings near windows should have control separate from those for
the interior space. For corridor, separate lighting control should be provided
to cater for different activity, such as normal circulation, low circulation and
cleaning/security purpose.
Lighting control points for the general lighting should be separated from the
decorative lighting, so that these two categories of lighting installation may be
switched on/off independently.
Task lighting implies providing the good illuminance only in the actual area
where a task is being performed, while the general illuminance of the area is
kept at a lower level. Energy saving takes place because good task lighting can
be achieved with low wattage lamps. The concept of task lighting if sensibly
implemented, can reduce the number of general lighting fixtures, reduce the
i. Induction lamp
Inductive fluorescent lamps are white light sources with very good color
rendering and color temperature properties. These lamps are energy
efficient and offer extremely long life (over 100,000 hours), good lumen
maintenance characteristics, instant-on capability and dimming is also
possible. They are excellent for lighting large surfaces.
LED lamps are the newest addition to the list of energy efficient light
sources. While LED lamps emit visible light in a very narrow spectral
band, they can produce "white light". LED lamps last for 40,000 to
100,000 service hours depending on its color. The current challenges of
the LED source are low Color Rendering Index (CRI). LED lamps have
made their way into numerous lighting applications including spot lights,
exit signs and various decorative applications.
Fluorescent T5 tubes are now used in many high bay applications in place
of high-intensity discharge (HID) lamps. The long and diffuse nature of
these lamps provides excellent surface lighting, and the smaller lamp
diameters contribute to better optical performance in many luminaires.
Indirect/direct linear fluorescent pendants and wall-mounted uplights are
typical applications of these sources.
Compact fluorescent lamps (CFL) are often used as simple substitutes for
incandescent lamps due to their compatibility with existing luminaires,
their significantly longer life and better energy efficiency. Due to the small
size and the diffuse nature of the CFL lamp, CFL lamp is a good choice for
downlighting and wall lighting.
HID lamps are still one of the best performing and most efficient lamps
Occupancy sensors can reduce a building‘s lighting energy by turning lights off
in unoccupied spaces. Energy savings may not be realized if the sensors are
improperly installed.
The use of daylight sensors in lighting systems can save energy with the parallel
use of dimmers. Daylight sensors are usually mounted to detect the lighting
level near the working area adjacent to the windows of a building. The
effectiveness of daylight dimming relies on daylight sensor placement, the
amount of window area as well as the available ambient light.
3.1.4.3 For more details, please refer to the “Design Guide for Energy Efficiency in Lighting
Installation” issued by Building Services Branch, ArchSD.[7]
Plumbing system consists of pumps, fitments, pipework and calorifier etc. Among
these, pump and calorifier are the most energy consuming equipment. This manual
will outline the major energy efficiency design techniques for plumbing installation.
v. Radiation efficiency
vi. Water temperature in a heating system (which should vary with outside
temperature to reduce heating/cooling costs)
vii. Motor efficiency, pump size and use of variable speed control to match
the system load conditions
Increasing the overall efficiency of the pumping system can achieve significant
energy savings. Overall pump system efficiency depends on the efficiency of
the motor, the pump, and the design of the piping layout.
There are generally two types of systems for hot water heating
In practice, instantaneous type water heaters are used only when there is a
demand for steady, continuous supply of hot water. The storage type water
heaters are commonly used for meeting unsteady and large water demand
because the stored water can be used to meet period of peak demand and
more energy efficiency. The designers should also consider the thickness of
insulation to reduce the heat loss of the pipework, fitting and vessels to reduce
the energy consumption of the boiler.
i. Low-flow showerheads
By using water efficiency labelled plumbing fixtures, the building can obtain
credits (according to annual saving of the devices) for BEAM-Plus certification
scheme.
Thermal insulation for hot water supply system plays an important role in
energy saving in hot water system. Thermal insulation reduces the heat loss
from the hot water pipes and fittings to the surroundings. All hot water pipes
and fittings of the system shall be fixed with thermal insulation. Designers
shall refer to the A/C General Specification for requirements on thickness and
types of thermal insulation applicable to hot water system.
3.1.5.2 For more details, please refer to the “Design Guide for Energy Efficiency in Plumbing
Installation” issued by Building Services Branch, ArchSD.[8]
The provision of renewable energy installation aims to generate clean energy and thus
reduce traditional electricity/gas consumption, which is usually generated from fossil fuel.
It can also serve education and demonstration purposes for environmental awareness.
(a) DEVB Technical Circular No. 5/2009 / ENB Circular Memorandum No. 2/2009 –
“Green Government Buildings”
(b) ETWB Technical Circular (Works) No. 16/2005 - “Adoption of Energy Efficiency
Features and Renewable Energy Technologies in Government Projects and
Installations”
(c) General Specification for Electrical Installation in Government Buildings of the HKSAR
issued by the Architectural Services Department (ArchSD)
(d) General Specification for Air Conditioning, Refrigeration, Ventilation and Central
Monitoring & Control System Installation in Government Buildings of the HKSAR,
issued by ArchSD
(f) Code of Practice for the Electricity (Wiring) Regulations issued by the Electrical and
Mechanical Services Department (EMSD)
(g) Code of Practice on Wind Effects in Hong Kong issued by the Building Authority
(h) Supply Rules of relevant Power Utility Company, (i.e. HEC or CLP)
(i) Technical Guidelines on Grid Connection of Renewable Energy Power Systems issued
by EMSD
(k) General Requirement for Electronic Contracts Specification No. ESG01 issued by
Electronics Division, EMSD
(l) IEC 61215 - Crystalline silicon terrestrial photovoltaic (PV) modules – Design
qualification and type approval
(o) Construction Site Safety Manual issued by the Development Bureau (formerly the
Environment, Transport and Works Bureau)
(u) Hong Kong Water Works Standard Requirement for Plumbing Installation in Buildings
issued by Water Supplies Department
(w) BSB Circular No. 8 of 2012 – Building Services Design Guides for Renewable Energy
Installations
(x) Pamphlet – “Know More about Solar Water Heating Energy” issued by EMSD,
http://www.emsd.gov.hk/emsd/eng/pee/nre.shtml
(y) Pamphlet – “Solar Thermal Collectors for Water Heating” issued by EMSD,
http://www.emsd.gov.hk/emsd/e_download/pee/EMS8313_waterheating(low-res).pdf
Small wind turbine is a distinct category of wind turbine that can be defined as small
machines with a rated power in the range of a few hundred watts to a few tens of
kilowatts. These machines are generally intended either for battery charging to
meet small loads remote from a grid supply or, at the larger end of the range, for
connection directly into a distribution grid. Recently there are some wind turbines
with less than 100 watts output and are regarded as micro wind turbine.
Due to their small size, these machines generally produce power at a higher unit cost
than that from large (several hundred kW and up) machines utilized in wind farms.
(b) Blade
Generally, vertical axis small wind turbines have a higher rated wind speed as
compared with horizontal axis small wind turbines of the same rating. It may
also take up less space as it exploits energy from winds of all directions. Some
people may regard vertical axis small wind turbine more aesthetically pleasing
than horizontal axis small wind turbine.
ii. Cost
iii. Available space
iv. Maintenance
(d) Alternator
Alternator is for converting the mechanical energy exploited from wind into
electrical energy. For small wind turbines, normally the output voltage is DC
which is favourable for both grid-connected or standalone (battery charging)
small wind turbine systems. Brushless permanent magnet type alternator is
common in small wind turbine.
Normally, the higher the elevation, the higher will be the wind speed. So, for
horizontal axis small wind turbine, it is usually supported by a long pole.
Designers shall take into account the wind speed-up effect at the installation
location to determine the pole height. However, vertical axis small wind
turbine system generally does not require a long supporting pole.
(f) Siting
(g) Sizing
When the rating and the type of rotational axis of small wind turbine
installation are determined, designers may estimate the dead weight of the
small wind turbine based on the table below which is drawn up based on a
number of products available in the international market. Designers should
then consult Structural Engineer on the construction of the supporting pole
based on the architectural layout on roof-top of the concerning building.
Rated Power (W) 350 485 1000 1900 2500 6000 1000
Axis H H H H H H V
Weight (kg) 17 25 34 93 190 600 250
No. of Blade or Height of 3 3 3 3 3 3 6.1m
Vertical Axis
Overall Rotor dia. (m) 1.2 1.4 2.0 3.72 3.5 5.5 0.61
Cut-in Wind Speed (m/s) 2.5 – 3.5
Rated Wind Speed (m/s) Around 12
Max Wind Speed (m/s) 45 60 54 63 70 70 45
Bending Thrust Min. Min. Min. Min. 5 kN 10 kN N.A.
Table 3: Characteristics of Different Rating of Wind Turbine
For better utilization of the exploited wind energy and maintaining steady
supply to loads, grid-connection system shall be deployed. For standalone
systems, the system efficiency may be just around 60% of that of
grid-connected system and typically, standalone systems are deployed for
non-critical loads such as for irrigation of slope or green roof.
i. Grid-connection System
Designers shall place a power distribution board close to the small wind
turbine installation for grid-connection. All technical issues and safety
requirements should refer to the “Technical Guidelines on Grid
Connection of Renewable Energy Power Systems (2007 Edition) published
by the EMSD. Designers may consider whether a performance
monitoring and logging system for promotion purpose should be included
in the small wind turbine installation.
3.2.1.3 More details should refer to the “Design Guide for Small Wind Turbine Installation”
issued by Building Services Branch, ArchSD.[9]
Photovoltaic utilize the sun’s protons or light to create electricity. The amount of
power available from a PV device is determined by:
The output of a PV panel depends on the type and structure of solar cell, which is
temperature dependent. Higher cell temperatures lead to lower output, and hence
lower efficiency. The efficiency indicates how much of energy is converted into
useable electrical energy. The four most common cell types are as follows:
There are two main types of PV system configurations, namely stand-alone system
and grid-connected system. Grid connected system should take preference over
standalone system as the latter requires additional plant room space for battery and
the disposal of batteries may cause other environmental problems. In addition,
standalone system usually has higher O&M cost than a grid connected one.
Figure 3: Typical DC Power Stand-alone PV System Figure 4: Typical AC Power Stand-alone System
Sun tracker is a technology for turning the orientation of PV panel such that it
can always face the sun at a very small incident angle so that the energy yield
can be enhanced. Sun trackers can be grouped into classes by the number of
the tracker’s axes. Typically, they can be classified as one-axis tracking and
two-axis tracking. The increase in monthly yield by adding a sun tracker
ranged from 5% to 32% with average increase of 19% on annual basis for PV
system with sun tracker.
i. avoid shading from the building element such as facades, parapets, vent
pipes, flues, landscapes, etc. or adjacent buildings
iii. weather-tightness
v. wind loading
(b) Stage 2: Selecting the type of PV material and sizing of area for PV/BIPV panels
The typical efficiency and required panel area of different types of photovoltaic
cells are as follows:
Typical cell efficiency Required panel area (m2)
to mount 1 kWp PV
Mono-crystalline silicon (m-Si) 15% 7 to 9
Poly-crystalline silicon (p-Si) 10 – 15% 8 to 11
Amorphous silicon (a-Si) 4 – 7% 16 to 20
Copper Indium Diselenide (CIS) 9 – 12% 11 to 13
Table 5: Typical Efficiency and Required Area of Different Types of PV Cells.
i. Roof mounting
In order to capture as much solar energy as possible, the photovoltaic cell must
be oriented towards the sun. If the photovoltaic cells have a fixed position,
their orientation with respect to the south (in northern hemisphere), and tilt
angle, with respect to the horizontal plane, should be optimized.
The optimum tilt angle lies within a range of approximately 15 degrees of the
site latitude, where latitude of Hong Kong is 22.32oN. For PV systems in Hong
3.2.2.3 For more details, please refer to the “Design Guide for Photovoltaic (PV) Installation”
issued by Building Services Branch, ArchSD.[10]
Solar hot water system can be designed with different configurations. The basic
application is for preheating water in hot water system. The main components of
the system comprise solar collectors, a storage tank and interconnecting pipe work.
The solar collectors are usually mounted on roof of a building to capture solar
radiation. In Hong Kong, for maximum performance, collectors should ideally be
tilted up from the horizontal at an angle of latitude approximate 22o with an
orientation towards the south. Obstructions that could prevent the collectors from
getting adequate exposure to solar radiation should be avoided as far as practical to
maximize the year-round efficiency.
i. Flat-plate Collector
Direct (also called Open Loop) systems circulate water through the collector
while indirect (also called Close Loop) systems use heat exchanger that
separates the water from the fluid that circulates through the collector (heat
transfer fluid).
Figure 8: Direct System (Open Loop) Figure 9: Indirect System (Close Loop)
Both types of system can be either active or passive. Active system requires
circulation pump to circulate water or a heat transfer fluid. Whereas a passive
system relies on gravity and naturally circulate without the use of an electric
pump.
For active system, the designers may consider to provide an irradiance sensor
in the system for the purpose to enhance the effectiveness during the mild
weather condition. The irradiance sensor can be used to measure the level of
solar radiation to control the circulation pump for adjusting the water flow rate
through the solar panel. Besides, it is recommended to allow metering
provisions such as energy meter and flow meter in the control panel for data
logging and energy audit purpose.
Overheating in a solar hot water system may occur when the system generates
enormous of heat while the demand for hot water is at its low side. This
condition is commonly called “stagnation”.
In assessing the solar resources of the site, designers have to check and make
sure the location of the installation is free from external shading such as trees,
nearby high-rise structures etc.
(b) Estimating site hot water consumption and heating energy requirements
Designers should refer to plumbing and drainage design guides to estimate the
monthly hot water consumption of the site.
The main advantage of flat-plate collector is lower equipment cost than that of
evacuated tube collector. In current market, the cost of flat-plate collector is
about 1/3 to 1/2 that of an evacuated tube collector. However, the evacuated
tube collector is more effective per unit area than flat plate collector and
out-perform flat plate collector for operating in high temperature applications
(e.g. temperature above 50℃).
Direct systems are simpler and cheaper than indirect systems. Direct systems
offer superior heat transfer from the collectors to the storage tank but they
have little overheat protection and their collectors will accumulate scale in hard
water areas. Besides, direct systems are often not considered suitable for
cold climates as damage of collectors may happen through freezing.
Moreover, the designers should be well aware of their design and equipment
selection to ascertain the system should be free from water contamination in
storage tank when any damage occurs at collectors or at water circuits.
Though indirect systems are slightly more expensive, the system very often
equipped with make-up water tank and/or chemical dosing tank. Indirect
system offer options of overheat protection and in cold climates “heat-transfer
fluid”, which typically is non-toxic propylene glycol, can be used to avoid
freeze-damage at collectors. More important, indirect system can eliminate
i. Piping Configuration
The size of the storage tank is proportional to the collector area. Typical size
of storage tank is 75 - 100 litre/m2 of collector net aperture area. The tank
should be well insulated with design target to minimize thermal loss.
Alternatively, there are various softwares available in the market for the
designers to evaluate system size, energy production and life-cycle costs etc.
3.2.2.3 For more details, please refer to the “Design Guide for Solar Hot Water system”
issued by Building Services Branch, ArchSD.[11]
Rainwater recycling is one of the sustainable features in building design. Proper use
of recycled rainwater helps to reduce consumption of fresh water resources as well
as reducing storm water impact. The potential applications of recycled rainwater
for non-potable use may include:
(b) Irrigation
(b) Catchment
Rainwater can be collected from the roof surface of building or other elevated
open spaces. The surface within the property boundary where the rainwater
can be collected without substantial loss of water through the bottom of the
surface before it is directed to the rainwater collection tank is called the
catchment.
i. Selection of Catchment
Catchment and roof for the collection and diversion of rainwater may be
constructed from a variety of materials such as cement or soil tiles,
galvanized iron, polycarbonate or fiberglass sheet. However, the
designers should advise the architect that use of the following paints and
coatings in catchment and roof are not suitable:
There are many researches revealed that the first flush of rainwater in a
rain event washes the roof catchment and hence may contain higher than
average amounts of accumulated dust, bird and animal droppings, leaves
and other debris. Therefore installation of first flush devices designed
to reduce collection of accumulated debris is recommended. As a
general rule of thumb, the minimum capacity of the first flush device
shall be 20 to 25 litres per 100m2 of catchment area.
The objective of the treatment is to ensure the recycled rainwater being used is
acceptable in quality.
The function of mixing tank is to store the treated rainwater and as an interface
between rainwater recycling system and the WSD mains water make-up supply.
The requirement on the capacity of remaining storage depends on specific
project design and application of treated rainwater. The following shall be
considered during the design development:
The distribution pipework and outlet fittings for use of recycled rainwater shall
be designed to prevent the inadvertent use of the collected water as potable
water. All components of the rainwater recycling system should be clearly and
consistently identified. Identification should be through color coding, marking
and warning plate.
3.3.1.3 For more details, please refer to the “Design Guideline for Rainwater Recycling
Installation (Rev. 2)” issued by Building Services Branch, ArchSD.[12]
Grey water is defined as waste water from kitchen, bath, general washing
basins and/or laundry. It does not include waste water from toilet, urinal or
bidet (known as black water). Grey water generally does not contain
significant concentration of excreta. In order to segregate grey water from
other sewage which may be highly contaminated, a dedicated drainage system
has to be provided to collect grey water from the discharge points and convey
the grey water to the treatment facility (usually called the “influence of the
Recycled grey water from the treatment plant (usually called the “effluence of
the treatment plant”) can be used for common urban usages such as toilet
flushing, irrigation, floor/vehicle cleansing, cooling tower make up, and other
similar uses etc. The distribution pipe work conveying the recycled grey water
should be clearly labeled for easy identification.
The basic consideration for applicability of grey water recycling system is the
supply and demand of grey water. The supply of recycled grey water would
mainly depend on whether the site has adequate grey water discharge. The
demand of recycled grey water would depend on the usage, such as for
irrigation, car washing, floor cleansing, making up water for cooling tower and
toilet flushing, etc.
Due to the high capital cost of grey water recycling system, the application
would need to be carefully scrutinized. The handling capacity of the smallest
size equipment for recycling grey water in the current market is 30m3/day. In
order to fully utilize the plant, it is suggested that the discharge volume to be
generated from the project should be 30m3/day or above.
The capacity of the treatment plant, usually in terms of dry weather grey water
discharge flow rate(hereafter also named flow rate), is determined according to
the population of the premises. For most of the single building Government
venues, the design flow rate should be in the range between 30 m3/day to 100
m3/day. This represents an office building of population size from 1,800 to
6,000.
There is currently no established standard for grey water quality in Hong Kong.
Having reviewed the standards set out by US EPA, WHO, and China on recycled
grey water quality, the following quality standard can be used as reference for
the design of treatment facility:
The physical sizes of the major water tanks for reference are as follows:
A store room is required for storage of chemicals used in the treatment process.
However, due to the small amount of chemical consumption, the storage
quantity could be small enough to be exempted from the requirements of DG
stores.
For the equipment rating, while most of the pumps for sewage transfer can be
sized using the design dry weather sewage flow rate of the plant, the sizing of
the major air blowers and membrane units are shown in the following table:
The following design practices should be considered during the design of the
grey water treatment facility:
iv. Power meters should be provided to record the total power consumption
of the treatment plant for monitoring.
3.3.2.3 For more details, please refer to the “Design Guideline for Grey Water Recycling
Installation” issued by Building Services Branch, ArchSD.[13]
Since indoor environmental conditions have a significant impact on the quality of life,
buildings should provide safe, healthy, convenient and efficient indoor spaces.
Buildings applicable are:
(a) Air-conditioned buildings
(b) Naturally ventilated buildings
(c) Mechanical ventilated buildings
(a) Security
Certain features of building and building services design are likely to have
contributed to health problems. Proper provisions for inspection, cleaning and
maintenance allows for comprehensive management of hygiene in buildings.
IAQ is the human perceived response to nasal irritants in the air. According to
ASHRAE’s definition, “Acceptable Indoor Air Quality” is “air in which there are
no known contaminants at harmful concentrations as determined by cognizant
authorities and with which a substantial majority (80% or more) of the people
exposed do not express dissatisfaction”.
(d) Ventilation
Indoor noise above certain levels can cause discomfort, irritation and
interference with workplace activities. In addition, poor acoustics in certain
premises will interfere with speech intelligibility. Background noise inside
buildings comes from a number of sources, including noise break-in from the
surrounding environment and noise produced inside the building.
Background noise should be limited to levels suitable for the use of the
premises. Good planning and design are especially important to mitigate
external noise. Possible measures should be explored to minimize the
external noise. The design of building envelope is also important in further
reducing the propagation of noise into the premises. The selection and
installation of building services systems and equipment also influence the
background noise levels and may also induce unwanted vibration. The sound
insulation properties of floors and internal walls are crucial in controlling noise
propagation inside a building.
3.4.2.1 Security
3.4.2.2 Hygiene
i. To provide tight-fitting lids and appropriately sized drain valves for water
storage tanks.
ii. To minimize the number and length of spurs in the plumbing systems.
iii. To provide circulating pumps to overcome the problems of stratification
and stagnation of water, especially in centralized hot water system.
iv. To maintain a minimum of 25mm water seal traps for all sanitary fitments,
including floor drains (if provided), before they are connected to a
common drainage stack in accordance with BD’s PNAP ADV-24. Self
priming type drainage traps or drainage pipe connections which ensure
trap priming (e.g. connection of wash basin discharge to the u-trap of
floor drains) shall be considered. Care shall also be taken to prevent
back-flowing at the floor drain.
v. To adopt two-pipe system or even an independent stack for floor drains.
ii. Flushing Out – After the construction works and finishing are completed;
all cleaning is finalized; and all fixed furniture are installed, the building
should be flushed out prior to occupancy by purging the room air and
cleaning the building as well as removing all residuals left in the MVAC
system.
Fresh Air Intake Location – Location of fresh air intake shall not be
located below ground level and shall be far away from sources of
contaminants, including the exhaust outlet from the building or
adjacent buildings, traffic, car-park, unloading bays, refuse chutes,
kitchens, toilets, cooling towers, industrial exhaust, or where source
of combustion (including smoking) is present as the concentration
of carbon monoxide and nitrogen dioxide usually is high at these
locations. Fresh air intake shall be protected from rain
entrainment, and covered by a screen to prevent the entry of birds,
rodents, and extraneous articles.
i. Building Uses and Layout – Good planning of building uses and internal
layout may help to prevent many unnecessary indoor air quality problems.
For example, areas where pollutants are actively emitted shall be sited
away from areas susceptible to pollution or provided with partitioning so
Air Filters – As the HCHO and VOC from building and furnishing
materials will be re-circulated into the room through the MVAC
system, adequate air filters shall be provided for MVAC design.
3.4.2.4 Ventilation
ii. To determine the zone air distribution effectiveness (Ez) of each zone, the
primary outdoor air fraction (Zp) of each zone; and the system ventilation
efficiency (Ev) using the relevant tables and Appendix in ASHRAE 62.1.
vi. Increased ventilation rates will have a negative impact on energy use,
particularly in a hot humid climate such as Hong Kong. Consideration
should be given to use heat recovery techniques to lessen the impact or
utilize CO2 sensors in conjunction with BMS to effect Demand Control
Ventilation.
In case any areas undergoing fitting out or renovation, the ventilation system
design can be adapted to exhaust the air from those areas without recirculation
or entrainment to occupied areas; and the exhaust is discharged such that it
does not re-enter the premises or enter adjacent premises under typical wind
conditions.
i. Room air temperature can be sustained at the design value within ±1.5°C
when the air-conditioning unit is operating at steady state under normal
occupied periods.
i. To achieve at least 80% of floor area in all normally occupied spaces being
adequately lit with an average daylight factor (DF) of 2% or more, with
suitable daylight glare control.
iii. Designers may make use of daylighting design software such as Radiance
in the calculation of average DF.
iv. Designers shall also determine whether sky glare will be a problem, and
make adjustment to the design to control glare and, where necessary,
provide fixed or moveable glare control such as louvre, shade and
draperies.
ii. To locate the noisy plant away from noise sensitive areas and to design air
distribution system to avoid unintended noise creation and/or
transmission in reference to BSB Circular No. 20 of 2004 “Noise Control
Design Guide for Air Distribution System”
iv. To carry out and document the site measurement during commissioning
to demonstrate that acoustic quality in a sample of each type of room in
which speech intelligibility is important, as measured and/or calculated,
meets appropriate performance criteria.
i. To define the performance criteria appropriate to the type and use of the
premises/rooms (e.g. office, classroom and quarter) in the building in
accordance with General Specification, CIBSE Guide and Client’s
requirements
ii. To design the air distribution system and air duct layout in order to avoid
unintended breakout noise and cross talk (i.e. airborne noise between
rooms/spaces) at the design stage in accordance with:-
BSB Circular No. 20 of 2004 “Noise Control Design Guide for Air
Distribution System”.
Chapter 47 – Sound and Vibration Control, ASHRAE Handbook –
HVAC Application
i. To determine the external noise generating sources (e.g. traffic noise etc.)
and the internal noise generating sources (e.g. fan noise etc.) for
considering the noise mitigation measures (e.g. double glazed window,
acoustic silencer etc.).
ii. To control the LAeq (equivalent continuous A-weighted sound pressure
level) for the most susceptible spaces/rooms/premises (e.g. offices,
classrooms, quarters, indoor game halls & indoor swimming pools etc.) in
accordance with Clause 8.3.2 of the “Building Services Design Guide for
Indoor Environmental Quality” issued by Building Services Branch,
ArchSD.
iii. Sound insulation and noise reduction for buildings – Refer to Table 5 and
Table 6 of BS8233.
i. To evaluate and identify the major vibration sources (e.g. chiller plant,
pump, lift motor etc.).
ii. To locate noise sensitive area away from the major vibration sources.
iii. To calculate and select the appropriate vibration isolator for achieving the
acceptable vibration isolating efficiency at different locations. Project
Officer may refer to:-
General Specification
BSB Circular No. 22 of 1995 “Selection Guidelines for
Plant/Machine Vibration Isolators and Tips on Vibration Control
Measures for Building Services Installation”
Table 48 in the chapter for “Sound and Vibration Control’ of the
ASHRAE Application Handbook.
iv. To carry out and document the site measurement during commissioning
to demonstrate that the required vibration isolation efficiency is achieved.
The test on vibration isolation may refer to ISO 2631-2 – Evaluation of
human exposure to whole-body vibration – Part 2 : Continuous and
shock-induced vibration in buildings (1 to 80Hz).
3.4.3 For more details, please refer to the “Building Services Design Guide for Indoor
Environmental Quality” issued by Building Services Branch, ArchSD.[14]
Design and quality of construction determines the broad range of possible sustainability
outcomes for a building, but the actual outcomes depend ultimately on how a building is
used, i.e. how it is managed by its owners, how its facilities are operated, and how
occupants, visitors etc. interact with those facilities. Mechanisms and opportunities for
services engineers to influence operational sustainability typically include:[1]
4.1.1 Commissioning
(a) chillers;
(b) cooling towers;
(c) controls for central plant and for HVAC, including, if present, the energy
management system or building automation system (BAS);
(d) unitary and split-air conditioners;
(e) fans;
(f) pumps;
(g) heat exchangers;
(h) boilers;
(i) domestic hot water and hot water heaters;
(j) ducts and associated dampers;
(k) piping and associated valves; and
(l) waste heat recovery, thermal storage, etc
CIBSE, BSRIA and ASHRAE publications as well as the Testing & Commissioning
Procedures for various Building Services Installations issued by Building Services
Branch, ArchSD, provide guidance on commissioning requirements and procedures,
such as management, design for commissioning, access, testing, measurements and
tolerances, installed transducers, specification for portable measuring equipment,
etc.
4.1.2 Re-commissioning
The need for re-commissioning of services arises where significant changes are made
to systems or to the physical configuration of a building, either of which can affect
the systems’ efficiency or effectiveness. An example of a physical change to a
building that might require re-commissioning of building services is a move from
open plan to cellular office space, or vice versa. Services should also be periodically
re-commissioned to ensure that they are operating as intended and to reset what
may have been intended as short term changes to set points and system settings.[1]
Typically, it is performed to ensure that original and modified building systems
perform interactively to meet the owner’s current operational needs and to suit the
operational changes.
Furthermore, owing to the technical complexity and the client’s concern on the
functional requirements and energy consumption of the building services (BS)
systems in the recently completed buildings, it is essential to oversee the
performance of these systems and to ensure that they not only function satisfactorily
and meet with the client’s operational requirements, but also perform with optimum
energy efficiency during the initial post occupation period.
iii. To conduct operational training and review feedback from operators and
facility management to formulate manning requirements,
i. To collect energy data of each type of installed BS systems and carry out
energy usage analysis,
iii. To capture and monitor actual energy consumption data for the building
and each group of users and give advice to client for equipment selection
and housekeeping practice,
ii. To monitor the testing and commissioning of the installation and capture
the operational parameters and performance data for verification with
the intended performance,
Depending on the project nature, there may also be a need to conduct a Post
Occupancy Evaluation (POE) exercise for the completed project. Guidance notes for
conducting POE are as set out in BSB Circular No. 25 of 2006 – Guidance Notes on
conducting Post Occupancy Evaluation (POE) Exercise.
Where buildings are not properly maintained they deteriorate more quickly, in extreme
cases requiring major refurbishment or demolition. In such cases the process of
Facilities to carry out basic maintenance and equipment for monitoring resources
consumption can help improve operating efficiency and environmental performance of a
building.[2] Facilities engineering and operational management may involve:[1]
(b) specifying and procuring a variety of maintenance contracts for building services
systems.
(a) list of all elements of the building services systems subject to regular inspection,
cleaning, servicing and maintenance;
An Operation and Maintenance Manual should be provided and environmental issues shall
be included in the manual. The manual covering building maintenance shall provide
(f) operation and maintenance of plant and equipment installed on the building; and
(g) details showing type and location of utility services on and adjacent to the site, etc.
Proactive management will seek to improve the performance of systems and equipment,
i.e., improved energy efficiency, and promote energy conservation, i.e., minimize wastage
of energy. Staff awareness of the importance of energy costs and efficiency is important
if efficiency is to be improved through management procedures. Financial support for an
action plan for implementing energy-saving measures is essential, either by a budget
allocation or by allocation of all or part of saving in fuel bills. It is also vital that an
appropriate senior person in the organization be responsible for energy management.
End-users of premises in a building should also be made aware that reducing energy use
within their premises not only will reduce their own energy bills, it will also lead to reduced
energy cost for providing air-conditioning for their premises.[3]
(c) Building Log Books – Energy performance can be recorded and compared with the
designer’s estimates of what the building should consume. Regular main and
subsidiary meter readings can be recorded on the meter reading pro-forma set up by
the log book author. Overall performance and end-use performance can then be
observed over time and compared to good practice benchmarks and design
estimates.
The best way to ensure that sustainability measures are implemented in such fast track
minor projects is to integrate good practice requirements into standard specifications and
working practices. Changes may need to be flagged and reinforced with additional
guidance and training to help them become ‘embedded’, particularly if they replace long
standing practices, or have implications in terms of additional project effort and/or cost.[1]
According to the DEVB Technical Circular no. 5/2009 / EB Circular Memo No. 2/2009 –
Green Government Buildings, all new government buildings with construction floor area of
more than 10,000m2 should aim to obtain the second highest grade or above under an
internationally or locally recognized building assessment system such as Hong Kong
Building Environmental Assessment Method (BEAM) or the Leadership in Energy and
Environmental Design Green Building Rating System (LEED) . This section will briefly
introduce the BEAM assessment which is a system developed locally.
The previous green building assessment system under BEAM is BEAM Plus Version
1.1 issued in 2010 which provides comprehensive assessment details and
methodology for both New Buildings (BEAM Plus (NB)) and Existing Buildings (BEAM
Plus (EB)). In response to stakeholder engagement, BEAM Plus Version 1.2 was
developed and issued in 2012 which brings together a holistic component of passive
design for residential development as an alternative method of assessment. BEAM
Plus version 1.2 also contains minor amendments from the original guidelines in
order to add clarity to the assessment.
Having reviewed local and international assessment schemes and other relevant
information, a weighting over each environmental performance category has been
assigned to reflect its importance and global trends as follows:[2,3]
Overall SA EU IEQ IA
Platinum 75% 70% 70% 70% 3 credits (Excellent)
Gold 65% 60% 60% 60% 2 credits (Very Good)
Silver 55% 50% 50% 50% 1 credit (Good)
Bronze 40% 40% 40% 40% - (Above Average)
Table 13: Determination of Overall Grade of BEAM Plus
For more details, please refer to “BEAM Plus for New Buildings Version 1.2”[2] and
“BEAM Plus for Existing Buildings Version 1.2”[3] issued by Hong Kong: Hong Kong
Green Building Council (HKGBC) and Beam Society.
Material Aspects
22 1 13 - Material & Resources (MR)
(MA)
Indoor
Indoor Environmental Quality
Environmental 32 3 15 -
(IEQ)
Quality (IEQ)
Innovations &
Additions (IA) - 5+1 5 - Innovation in Design (ID)
Maximum Credits /
127 5+1* 69 -
Maximum Bonus
Note: * The maximum bonus credits in BEAM PLUS (NB) are 5 nos. + 1 no.(for BEAM Pro.)
Table A1: Summary of Credits for BEAM Plus (NB) and LEED-NC
(b) Pre-requisites for New Buildings in BEAM Plus (NB) and LEED-NC
No CFC-based refrigerants in
HVAC&R systems
Implementation of a Construction -
Waste Management Plan
EU /EA Comply the latest edition of Building Minimum Energy Performance (ASHRAE 90.1 – 2004)
Energy Codes (BEC 2007)
IEQ / IEQ Comply with the minimum Comply with the minimum IAQ Performance of ASHRAE
requirements of ASHRAE 62.1-2007 62.1 – 2004 (Ventilation for Acceptable Indoor Air
(Ventilation for Acceptable Indoor Quality)
Air Quality)
IA / ID - -
Table A2: Pre-requisites for New Buildings in BEAM Plus (NB) and LEED-NC
SA/ SS SA8: Microclimate Around Building – 1 credit for No Comparable credit in LEED - NC
no pedestrian areas subject to excessive wind
velocities caused by amplification due to site
layout/ building design
No Comparable credit in BEAM Plus (NB) SS Credit 4.2 – 1 credit for providing bicycle
racks / storage and shower and changing
facilities
No Comparable credit in BEAM Plus (NB) SS Credit 4.3 – 1 credit for providing preferred
parking for low-emitting and fuel efficient
vehicles
MA/ MR MA2: Modular Standard Design – 1 credit for No Comparable credit in LEED - NC
demonstrating the application of modular and
standard design
EU/ EA EU1: Reduction of CO2 Emissions – For EA Credit 1: Optimize Energy Performance - 1
commercial buildings, 1 to 15 credits for a to 10 credits for new buildings to achieve
reduction of CO2 emission or annual building energy cost savings percentage by
consumption by 3%, 5%, 7%, 9%, 11%, 14%, 10.5%, 14%, 17.5%, 21%, 24.5%, 28%, 31.5%,
17%, 20%, 23%, 26%, 29%, 33%, 37%, 41% & 35%, 38.5% & 42%. (From 26.06.2008, 14% (2
45% credits) of energy saving is NECESSARY to any
LEED credit level)
EU/ EA EU5: Lighting system in Car Parks - 1 credit for No Comparable credit in LEED - NC
using lamps and ballasts that will consume less
electricity than the zero-credit requirements by
20% or more; 2 credits for 25% or more.
EU9: Energy Efficient Appliances – 1 credit for EA Credit 6: Green Power – 1 credit for
60% of total rated power of appliances are providing at least 35% of the building’s
certified energy efficient products electricity from renewable sources by
engaging in at least a two-year renewable
energy contract.
WU/ WE WU2: Monitoring and Control – 1 credit for No Comparable credit in LEED – NC
installation of devices to monitor water leakage
within the fresh water distribution system.
IEQ/ IEQ IEQ1: Security – 1 credit for scoring at least No Comparable credit in LEED – NC
75%of the applicable security measures and
facilities for the building.
IEQ/ IEQ IEQ19: Noise Isolation – 1 credit for No Comparable credit in LEED – NC
demonstrating airborne noise isolation between
rooms, spaces and premises meets the
prescribed criteria.
Major baselines ASHRAE 90.1-2004 (for EA-c1 – Optimize BEC 2007 or ASHRAE 90.1-2007 (for EU1 -
Energy Performance) Reduction of CO2 Emissions)
[2] BEAM Plus for New Buildings Version 1.2 Building Environmental Assessment Method
(Hong Kong: Hong Kong Green Building Council (HKGBC) and Beam Society) (2012)
[3] BEAM Plus for Existing Buildings Version 1.2 Building Environmental Assessment Method
(Hong Kong: Hong Kong Green Building Council (HKGBC) and Beam Society) (2012)
[4] Design Guide for Energy Efficiency in Air-conditioning Installation (Hong Kong: Building
Services Branch, Architectural Services Department) (2012)
[5] Design Guide for Energy Efficiency in Electrical Installation (Hong Kong: Building Services
Branch, Architectural Services Department) (2012)
[6] Design Guide for Energy Efficiency in Lift and Escalator Installation (Hong Kong: Building
Services Branch, Architectural Services Department) (2012)
[7] Design Guide for Energy Efficiency in Lighting Installation (Hong Kong: Building Services
Branch, Architectural Services Department) (2012)
[8] Design Guide for Energy Efficiency in Plumbing Installation (Hong Kong: Building Services
Branch, Architectural Services Department) (2012)
[9] Design Guide for Small Wind Turbine Installation (Hong Kong: Building Services Branch,
Architectural Services Department) (2012)
[10] Design Guide for Photovoltaic (PV) Installation (Hong Kong: Building Services Branch,
Architectural Services Department) (2012)
[11] Design Guide for Solar Hot Water System (Hong Kong: Building Services Branch,
Architectural Services Department) (2012)
[12] Design Guideline for Rainwater Recycling Installation (Rev. 2) (Hong Kong: Building Services
Branch, Architectural Services Department) (2010)
[13] Design Guideline for Grey Water Recycling Installation (Hong Kong: Building Services
Branch, Architectural Services Department) (2008)
[14] Building Services Design Guide for Indoor Environmental Quality (Hong Kong: Building
Services Branch, Architectural Services Department) (2012)