Sr. No. Activity Start Date End Date
Master Toilet 23/06/2021 02:00 PM 26/06/2021 05:00 PM
1 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
2 Counter Angle fixing 23/06/2021 04:00 PM 23/06/2021 09:00 PM
3 Window coping 23/06/2021 02:00 PM 23/06/2021 05:00 PM
4 Toilet Ventilator fixing 24/06/2021 09:00 AM 24/06/2021 10:00 AM
5 Ledge Wall Coping 23/06/2021 02:00 PM 23/06/2021 05:00 PM
6 Counter Top Fixing 24/06/2021 09:00 AM 24/06/2021 01:00 PM
7 Toliet Door Fixing
8 Wall tile Repair/ Grouting 24/06/2021 01:00 PM 24/06/2021 03:00 PM
9 Switch Plate fixing 25/06/2021 09:00 AM 25/06/2021 12:00 PM
10 Grid tile fixing 25/06/2021 01:00 PM 25/06/2021 03:00 PM
11 Light fixures fixing 25/06/2021 03:00 PM 25/06/2021 05:00 PM
12 CP & Sanitory fixtures fixing 26/06/2021 09:00 AM 26/06/2021 01:00 PM
13 Floor tile Repair/ Grouting 26/06/2021 03:00 PM 26/06/2021 05:00 PM
Master Bedroom 23/06/2021 09:00 AM 26/06/2021 09:00 PM
14 Alumininum Sliding Door & Window fixing With Glass 23/06/2021 09:00 AM 25/06/2021 05:00 PM
15 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
16 Bedroom Door Fixing
17 Ceiling Paint 23/06/2021 09:00 AM 23/06/2021 05:00 PM
18 Wall Paint 1st coat 23/06/2021 02:00 PM 23/06/2021 09:00 PM
19 Switch Plate fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
20 AC Indoor unit Fixing & Commisioning 24/06/2021 09:00 AM 24/06/2021 10:00 PM
21 Electrical Light Fixtures fitting 24/06/2021 09:00 AM 24/06/2021 10:00 PM
22 Ceiling Fan Fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
23 Wall Paint 2nd Coat 25/06/2021 09:00 AM 25/06/2021 01:00 PM
24 Wooden Flooring & Skirting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
25 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Master Bedroom Balcony 23/06/2021 09:00 AM 26/06/2021 09:00 PM
26 External Glazing 23/06/2021 09:00 AM 25/06/2021 05:00 PM
27 Electrical wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
28 Ceiling Painting 23/06/2021 09:00 AM 23/06/2021 05:00 PM
29 Ceiling Light fixures fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
30 Wall painting 25/06/2021 09:00 AM 25/06/2021 01:00 PM
31 Wall Electrical fixtures fixing 25/06/2021 01:00 PM 25/06/2021 09:00 PM
32 Shaft Covering WPC Jali 25/06/2021 01:00 PM 25/06/2021 09:00 PM
33 Floor tile Repair/ Grouting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
34 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Toilet 1,2 23/06/2021 02:00 PM 26/06/2021 05:00 PM
35 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
36 Counter Angle fixing 23/06/2021 04:00 PM 23/06/2021 09:00 PM
37 Window coping 23/06/2021 02:00 PM 23/06/2021 05:00 PM
38 Toilet Ventilator fixing 24/06/2021 09:00 AM 24/06/2021 10:00 AM
39 Ledge Wall Coping 23/06/2021 02:00 PM 23/06/2021 05:00 PM
40 Counter Top Fixing 24/06/2021 09:00 AM 24/06/2021 01:00 PM
41 Toliet Door Fixing
42 Wall tile Repair/ Grouting 24/06/2021 01:00 PM 24/06/2021 03:00 PM
43 Switch Plate fixing 25/06/2021 09:00 AM 25/06/2021 12:00 PM
44 Grid tile fixing 25/06/2021 01:00 PM 25/06/2021 03:00 PM
45 Light fixures fixing 25/06/2021 03:00 PM 25/06/2021 05:00 PM
46 CP & Sanitory fixtures fixing 26/06/2021 09:00 AM 26/06/2021 01:00 PM
47 Floor tile Repair/ Grouting 26/06/2021 03:00 PM 26/06/2021 05:00 PM
Page 1 of 4
Godrej Nest - Sample Flat
Sr. No. Activity Start Date End Date
Bedroom 1,2 23/06/2021 09:00 AM 26/06/2021 09:00 PM
48 Alumininum Sliding Door & Window fixing With Glass 23/06/2021 09:00 AM 25/06/2021 05:00 PM
49 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
50 Bedroom Door Fixing
51 Ceiling Paint 23/06/2021 09:00 AM 23/06/2021 05:00 PM
52 Wall Paint 1st coat 23/06/2021 02:00 PM 23/06/2021 09:00 PM
53 Switch Plate fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
54 AC Indoor unit Fixing & Commisioning 24/06/2021 09:00 AM 24/06/2021 10:00 PM
55 Electrical Light Fixtures fitting 24/06/2021 09:00 AM 24/06/2021 10:00 PM
56 Ceiling Fan Fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
57 Wall Paint 2nd Coat 25/06/2021 09:00 AM 25/06/2021 01:00 PM
58 Wooden Flooring & Skirting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
59 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Bedroom 1,2 Balcony 23/06/2021 09:00 AM 26/06/2021 09:00 PM
60 External Glazing 23/06/2021 09:00 AM 25/06/2021 05:00 PM
61 Electrical wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
62 Ceiling Painting 23/06/2021 09:00 AM 23/06/2021 05:00 PM
63 Ceiling Light fixures fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
64 Wall painting 25/06/2021 09:00 AM 25/06/2021 01:00 PM
65 Wall Electrical fixtures fixing 25/06/2021 01:00 PM 25/06/2021 09:00 PM
66 Floor tile Repair/ Grouting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
67 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Living Room 23/06/2021 09:00 AM 26/06/2021 09:00 PM
68 Alumininum Sliding Door & Window fixing With Glass 23/06/2021 09:00 AM 25/06/2021 05:00 PM
69 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
70 Bedroom Door Fixing
71 Ceiling Paint 23/06/2021 09:00 AM 23/06/2021 05:00 PM
72 Wall Paint 1st coat 23/06/2021 02:00 PM 23/06/2021 09:00 PM
73 Switch Plate fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
74 AC Indoor unit Fixing & Commisioning 24/06/2021 09:00 AM 24/06/2021 10:00 PM
75 Electrical Light Fixtures fitting 24/06/2021 09:00 AM 24/06/2021 10:00 PM
76 Ceiling Fan Fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
77 Floor Tile Repair 24/06/2021 05:00 PM 24/06/2021 10:00 PM
78 Wall Paint 2nd Coat 25/06/2021 09:00 AM 25/06/2021 01:00 PM
79 Floor Tile Grouting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
80 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Living Room Balcony 23/06/2021 09:00 AM 26/06/2021 09:00 PM
81 External Glazing 23/06/2021 09:00 AM 25/06/2021 05:00 PM
82 Electrical wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
83 Ceiling Painting 23/06/2021 09:00 AM 23/06/2021 05:00 PM
84 Ceiling Light fixures fixing 24/06/2021 09:00 AM 24/06/2021 05:00 PM
85 Wall painting 25/06/2021 09:00 AM 25/06/2021 01:00 PM
86 Wall Electrical fixtures fixing 25/06/2021 01:00 PM 25/06/2021 09:00 PM
87 Floor tile Repair/ Grouting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
88 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Kitchen 23/06/2021 09:00 AM 26/06/2021 09:00 PM
89 Alumininum Door & Window fixing With Glass 23/06/2021 09:00 AM 25/06/2021 05:00 PM
90 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
91 Ceiling Paint 23/06/2021 09:00 AM 23/06/2021 05:00 PM
92 Wall Painting 1st coat 23/06/2021 02:00 PM 23/06/2021 09:00 PM
93 Wall Tile Grouting 24/06/2021 01:00 PM 24/06/2021 03:00 PM
94 Electrical Light Fixtures fitting 25/06/2021 09:00 AM 25/06/2021 12:00 PM
95 Wall Painting 2nd Coat 25/06/2021 12:00 PM 25/06/2021 01:00 PM
96 Floor tile Repair/ Grouting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
97 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Page 2 of 4
Godrej Nest - Sample Flat
Sr. No. Activity Start Date End Date
DH Toilet 23/06/2021 02:00 PM 26/06/2021 05:00 PM
98 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
99 Window coping 23/06/2021 02:00 PM 23/06/2021 05:00 PM
100 Toilet Ventilator fixing 24/06/2021 09:00 AM 24/06/2021 10:00 AM
101 Ledge Wall Coping 23/06/2021 02:00 PM 23/06/2021 05:00 PM
102 Toliet Door Fixing
103 Wall tile Repair/ Grouting 24/06/2021 01:00 PM 24/06/2021 03:00 PM
104 Switch Plate fixing 25/06/2021 09:00 AM 25/06/2021 12:00 PM
105 Grid tile fixing 25/06/2021 01:00 PM 25/06/2021 03:00 PM
106 Light fixures fixing 25/06/2021 03:00 PM 25/06/2021 05:00 PM
107 CP & Sanitory fixtures fixing 26/06/2021 09:00 AM 26/06/2021 01:00 PM
108 Floor tile Repair/ Grouting 26/06/2021 03:00 PM 26/06/2021 05:00 PM
DH Room 23/06/2021 09:00 AM 26/06/2021 09:00 PM
109 Alumininum Door & Window fixing With Glass 23/06/2021 09:00 AM 25/06/2021 05:00 PM
110 Electrical Wiring 24/06/2021 09:00 AM 24/06/2021 07:00 PM
111 Bedroom Door Fixing
112 Ceiling Paint 23/06/2021 09:00 AM 23/06/2021 05:00 PM
113 Wall Paint 1st coat 23/06/2021 02:00 PM 23/06/2021 09:00 PM
114 Switch Plate fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
115 Electrical Light Fixtures fitting 24/06/2021 09:00 AM 24/06/2021 10:00 PM
116 Ceiling Fan Fixing 24/06/2021 09:00 AM 24/06/2021 10:00 PM
117 Floor Tile Repair 24/06/2021 09:00 AM 24/06/2021 05:00 PM
118 Wall Paint 2nd Coat 25/06/2021 09:00 AM 25/06/2021 01:00 PM
119 Floor Tile Grouting 26/06/2021 02:00 PM 26/06/2021 08:00 PM
120 Final Touchup & Cleaning 26/06/2021 03:00 PM 26/06/2021 09:00 PM
Page 3 of 4
Godrej Nest - Marketing Office
Sr. No. Activity Start Date End Date
Handicap Toilet 23/06/2021 01:00 PM 29/06/2021 05:00 PM
1 Waterproofing Works 23/06/2021 01:00 PM 24/06/2021 01:00 PM
2 Toliet Door Frame Fixing 25/06/2021 03:00 PM 25/06/2021 09:00 PM
3 Wall tile 26/06/2021 01:00 PM 26/06/2021 09:00 PM
4 Floor Tiling 27/06/2021 09:00 AM 27/06/2021 01:00 PM
5 Electrical Wiring 27/06/2021 03:00 PM 27/06/2021 07:00 PM
6 Counter Angle fixing 26/06/2021 04:00 PM 26/06/2021 09:00 PM
7 Window coping 26/06/2021 02:00 PM 26/06/2021 05:00 PM
8 Toilet Ventilator fixing 27/06/2021 09:00 AM 27/06/2021 10:00 AM
9 Ledge Wall Coping 26/06/2021 02:00 PM 26/06/2021 05:00 PM
10 Counter Top Fixing 27/06/2021 09:00 AM 27/06/2021 01:00 PM
11 Toliet Door Shutter Fixing 27/06/2021 01:00 PM 27/06/2021 03:00 PM
12 Wall tile Repair/ Grouting 27/06/2021 01:00 PM 27/06/2021 03:00 PM
13 Switch Plate fixing 28/06/2021 09:00 AM 28/06/2021 12:00 PM
14 Grid tile fixing 28/06/2021 01:00 PM 28/06/2021 03:00 PM
15 Light fixures fixing 28/06/2021 03:00 PM 28/06/2021 05:00 PM
16 CP & Sanitory fixtures fixing 29/06/2021 09:00 AM 29/06/2021 01:00 PM
17 Floor tile Repair/ Grouting 29/06/2021 03:00 PM 29/06/2021 05:00 PM