02 Design Basis Report Highway (Naidupeta Turpukanupur) 05-08-2023
02 Design Basis Report Highway (Naidupeta Turpukanupur) 05-08-2023
Independent Engineer
M/s URS SCOTT WILSON PVT. LTD. in joint venture with LION
ENGINEERING CONSULTANTS
Independent Design
Employer Concessionaire
Engineer Consultant
TT URS SCOTT
WILSON PVT.
LTD.
IN JOINT VENTURE
WITH
APCO SRI
LION APCO INFRATECH
NATIONAL HIGHWAYS VENKATESHWARA
` ENGINEERING PVT. LTD.
AUTHORITY OF INDIA EXPRESSWAY PVT.
CONSULTANTS
LTD.
PVT. LTD.
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Issue Status
Issue Status Date
Revision - R0 Ist Submission Aug 05, 2023
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
TABLE OF CONTENTS
1. PROJECT: ........................................................................................................................................................... 1
1.1 PROJECT BACKGROUND: ............................................................................................................................. 1
1.2 PROJECT DESCRIPTION: ............................................................................................................................... 1
1.3 SCOPE OF WORK .......................................................................................................................................... 3
1.4 SALIENT FEATURES OF THE PROJECT .......................................................................................................... 3
1.5 DEVIATION FROM THE MANUAL ................................................................................................................. 4
1.6 OBJECTIVES OF DESIGN BASIS REPORT........................................................................................................ 5
2. HIGHWAY DESIGN STANDARDS ................................................................................................................. 6
2.1 GENERAL ..................................................................................................................................................... 6
2.2 DESIGN ELEMENTS ...................................................................................................................................... 6
2.2.1 Terrain Classification ............................................................................................................................. 6
2.2.2 Design Speed ........................................................................................................................................... 6
2.2.3 Design Traffic and Capacity ................................................................................................................... 7
2.2.4 Proposed Right-of-Way (ROW) ............................................................................................................... 7
2.2.5 Width of Carriageway ............................................................................................................................. 8
2.2.6 Width of Median ...................................................................................................................................... 8
2.2.7 Shoulders ................................................................................................................................................. 8
2.2.8 Cross fall ................................................................................................................................................. 8
2.2.9 Speed Changing lanes ............................................................................................................................. 8
2.3 GEOMETRIC DESIGN STANDARDS FOR MAIN CARRIAGEWAY ..................................................................... 8
2.3.1 Horizontal Alignment .............................................................................................................................. 8
2.3.2 Radius of Horizontal Curves ................................................................................................................... 9
2.3.3 Transition (Spiral ) Curve ....................................................................................................................... 9
2.3.4 Super Elevation ....................................................................................................................................... 9
2.3.5 Sight Distance ......................................................................................................................................... 9
2.3.6 Safe Sight Distance ................................................................................................................................. 9
2.3.7 Intermediate Sight Distance .................................................................................................................. 10
2.3.8 Vertical Alignment ................................................................................................................................ 10
2.3.9 Gradients ............................................................................................................................................... 10
2.3.10 Vertical Curve ....................................................................................................................................... 10
2.4 DESIGN STANDARDS FOR SERVICE ROADS AND CONNECTING ROADS ...................................................... 11
2.4.1 Design Speed ......................................................................................................................................... 11
2.4.2 Horizontal Curve Design ...................................................................................................................... 11
2.4.3 Transition Curve Design ....................................................................................................................... 11
2.4.4 Camber and Super-elevation ................................................................................................................. 11
2.4.5 Entry and Exit of Service Road ............................................................................................................. 11
2.5 SUMMARY OF CROSS-SECTIONAL ELEMENTS AND DESIGN STANDARDS .................................................. 11
2.6 INTERSECTIONS ......................................................................................................................................... 13
2.6.1 At-Grade Intersection............................................................................................................................ 13
2.6.2 Emergency Median Opening ................................................................................................................. 14
2.6.3 Service Road/Slip Road/ Connecting Roads.......................................................................................... 14
2.7 TYPICAL CROSS-SECTION .......................................................................................................................... 15
2.8 EMBANKMENT AND CUT SECTION ............................................................................................................ 15
2.8.1 High Embankment ................................................................................................................................. 15
2.8.2 Slope Protection Measures.................................................................................................................... 16
2.9 DRAINAGE ................................................................................................................................................. 16
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
1. PROJECT:
Table 1.2
Project Road Chainage Length as per Design Remarks
Name From To
Naidupeta- 57+046 91+927 34.881 Km Greenfield
Trupukanupur Alignment
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 1 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 2 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
• Construction of Project Highway on the site set forth in Schedule-A and as per the scope
specified in Schedule-B together with the provision of Project Facilities as specified in
Schedule-C, and in conformity with the specifications and standards set forth in
Schedule-D;
• Operation and maintenance of the Project Highway in accordance with the provision of
the Agreement; and
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 3 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Table 1.3
S. Feature Unit Existing Proposed (As per
NO. (As per Schedule B)
Schedule
A)
1 Length Km 34.881
2 Median Width without kerb m - 4.00
Shyness
3 Service Road (LHS+RHS) Km - 25.540
(Width = 7.00/ 7.50m)
4 Slip Road ( LHS+RHS) Km - Nil
(Width = Nil)
5 Major Bridge Nos. - 1
6 Minor Bridges Nos. 1 13
7 Box Culverts (at- MCW) Nos. - 34
8 Pipe Culverts (at-cross road) Nos. - 41
9 Grade separated structures (Flyover Nos. - 18
+ VUP + LVUP+ Trumpet
Interchange)
10 Toll Plaza Nos. - 1
11 Bus Bays (Both LHS & RHS) Nos. - Nil
12 Truck – lay – byes Nos. - 2
13 Minor At-Grade intersection Nos. - 27
14 Proposed ROW m 60m 60m and extra width at
Toll Plaza, Interchanges,
Truck Terminal, Service
roads and Truck Lay
byes.
Table 1.4
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 4 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
• To propose the design standards to be followed during horizontal and vertical alignment
design along with all interlinked aspects for the project road.
• To serve as a platform for discussing the merits and de-merits of the design proposals for
the roads and structures.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 5 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Table : 2.1
Design Chainage Type of Terrain
S No Length in (km)
From (Km) To (Km)
1 57+046 91+927 34.881 Plain
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 6 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
design, the actual operating speed of the road, the maximum speed limit permissible by
law, and the traffic volume of the road.
For National Highways, the preferable design speed shall be desirable(ruling) design
speeds as per IRC: SP:87-2019 i.e. 100 Kmph and minimum design speed is 80 kmph for
the plain/rolling terrain. The design speed is given in Table 2.2.
Table 2.2
Design Chainage Design Speed
S No Length in (km)
From (Km) To (Km)
Main Carriageway
1 57+246 91+927 34.681 100 kmph
2 Trumpet 57+246 As per interchange 40 kmph
interchange at design
57+046
Service / Slip/ connecting road
3 Total (BHS) 25.540 40 kmph
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 7 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
2.2.7 Shoulders
In open country, paved shoulders of 1.5m width shall be provided and balance 2.0m
width of earthen shoulder shall be covered with 200mm thick layer of granular material
on outer each side of the Carriage way. At location of high embankment, the width of
paved shoulder has been proposed as 2.0m as per applicable TCS. The compositions and
specification of the paved shoulder and median edge strip shall be as that of the main
carriageway.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 8 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 9 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
2.3.9 Gradients
The ruling and limiting gradients as per IRC: SP:87-2019 are given in Table 2.6.
Table 2.6: Gradient as per Terrain
Nature of Terrain Ruling Limiting Gradient
Gradient
Plain and Rolling 2.5% 3.3%
A minimum gradient of 0.3% shall be provided to the extent possible along the project
highway.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 10 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
parabolic and are assigned stationing based on a horizontal axis. Vertical curves shall be
provided at all grade changes exceeding 0.5%.
Vertical curves will be designed to provide for visibility as per the sight distance
described above in Table no- 2.4 & 2.5. All the summit curves shall be designed for
intermediate site distance as per Table-2.5 and all valley curves shall be designed for
Head light distance which is equal to Safe stopping Distance as given in Table-2.4. As
per IRC: 73-1980 and IRC: SP: 23 design standards, the minimum lengths of vertical
curves are 60m for design speeds of 100Kmph.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 11 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Table 2.7
sS.No. Design Specification Proposed Design Standards
Plain Terrain
1 Design Speed-Main Highway 100Kmph except at Trumpet
2 Design Speed-Service Road & 40Kmph
Connecting Road
3 Carriage Width for Six Lane 2 x 10.5m
4 Shyness 2 x 0.5m
5 Median Width • Flush Type Median-4.0m excluding Shyness
6 Paved Shoulder • In Rural section-1.5m
• At RE Wall Approaches to underpass-2.0m
7 Un-paved Shoulder • In Rural/Urban-2.0m
• At RE wall Approaches to Connecting road
and service Road- Nil
8 Proposed width of Service road 7.0m /7.5m
9 Earthen Shoulder for Service As per applicable TCS.
Raod
10 Proposed Connecting Road width Same as existing roads but minimum 3.75m
11 Earthen Shoulder for Connecting 1m Earther Shoulder on both side of the
Road connecting Road
12 Separator Cum Drain As per TCS
13 Separator Without Drain As per TCS
14 Footpath cum Drain As per TCS
15 Footpath without Drain As per TCS
16 Utility Corridor 2.0m
17 Longitudinal Gradient
Ruling 2.5%
Limiting 3.3%
18 Camber on Flexible Pavement
Main Carriageway and service 2.5%
road
Paved Shoulder 2.5%
Un-paved Shoulder 3.0%
19 Camber on Rigid Pavement
Toll Plaza 2.0%
20 Minimum Radius of curvature in 400m
New Construction
21 Minimum Vertical Curve Length 60m for 100Kmph
22 Vertical Clearance
a Vehicular underpass 5.5m
b Light vehicular Underpass 4.0m
23 Lateral Clearance
a Vehicular Underpass 20.0m
b Light Vehicular Underpass 12.0m
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 12 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
2.6 Intersections
The cross roads underneath the Flyovers, Interchange, Underpass shall be treated as At-
Grade intersection as provisioned under para 4.1 of Annexure-I to Schedule B. These
junctions of the crossroads shall be developed as at-grade intersection as per
requirements stipulated in the manual subject to availably of the ROW. Also the
connecting roads to service roads shall be developed as junction within available land.
List of such junction is as given in Sch B.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 13 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 14 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
• Any variations in the lengths specified in the TCS schedule as per Sch. B, shall not
constitute a Change of Scope, save and except any variations in the length arising out of a
Change of Scope expressly undertaken in accordance with the provisions of Article 16.
• Chainage may be adjusted according to location of structures as per drawings.
• The requirement of kerb in the median for surface drainage at super elevated portions and
approaches to structures shall be finalized in consultation with Independent
Engineer/NHAI. TCS for super-elevated location shall follow dimension of elements as
per applicable TCS, with additional provision of median drain.
• Carriageway width tapering shall be provided as per manual.
considerations. Side slopes and earthen shoulders shall be protected against erosion by
providing a suitable vegetation cover, kerb channel, chute, energy dissipation basin,
stone/cement concrete pitching etc.
2.9 Drainage
Road side drainage system shall be provided as per TCS drawing given with Schedule-B
and median drainage system shall be provided as per Schedule-D in conformity with
IRC: SP:87-2019 and IRC: SP:42-2014. As far as possible, longitudinal slope shall not
be less than 0.2% for the lined drain and 0.1% for unlined drains. Permissible non-
erodible flow velocity for corresponding earth surface as mentioned in Table 7.1 of IRC:
SP:42-2014 shall be kept in view. The side slope of unlined drains shall be as flat as
possible and shall not be steeper than 2H:1V.
Drainage system of cross roads shall be maintained. RCC pipe of size as mentioned in
Schedule-B shall be provided wherever required across the cross road to maintain
longitudinal drainage along the project highway. RCC Drain cum footpaths shall
conform to the cross- sectional features and other details specified as per section 3.0 in
Schedule-B. However, modification required, if any, shall be shown in drawings
submitted to Independent engineer for review.
Tentative length of Trapezoidal Unlined Drain – 21.507km LHS + 13.702km RHS=
35.209km
Tentative length of Rectangular lined drain – 11.185km LHS +14.355km RHS =
25.540km
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 16 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Flexible pavement of Main Carriageway shall be designed for design traffic of 100MSA
or actual design traffic as per manual whichever is higher and flexible pavement for
connecting/ cross/ service/ slip road shall be designed for design traffic of 10MSA or
actual design traffic as per manual whichever is higher.
Note:
The Pavement crust composition shall be designed in accordance with latest guidelines
of IRC 37-2018 and IRC: SP:98. The Type of pavement crust may be decided in
consultation with Independent Engineer.
The Concessionaire shall use waste plastic in the bituminous layers of Service Roads in
accordance with latest guidelines of IRC-SP-98.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 17 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
3. PROJECT FACILITIES
3.1 General
The Concessionaire shall construct the project Facilities described in Annex-I to
Schedule C of Concession Agreement, to form part of Project Highway.
Toll Plaza location and Minimum Lane Requirement in the Opening Year at slip road.
Table 3.2
Direction (Entry to No. of Toll lanes
Highway, Exit from (ETC+ Extra wide
S.no Chainage Location
Highway) ETC)
(km)
Note:
• The Toll Plaza shall be designed and constructed as per IRC: SP 84-2019 considering the
modification as per NHAI Circular NHAI/Policy Guidelines/Management of Toll
Plaza/2021 Policy Circular No. 17.5.82 dated 24th May, 2021.
As per aforementioned circular the layout as provided in Annexure-II of Schedule C
shall be followed.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 18 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
• Entry approach to each toll Booth shall be having Weigh in Motion equipment. It is
clarified that WIM shall not be proposed for Exit ramp Toll plaza. In addition to WIM,
Static weigh Bridge (SWBs) shall be provided on each direction as per manual.
• Based on the minimum toll lane requirement as given above, toll booths, toll Booth
complex, weighbridges, electrical systems, toll Booth and all other facilities
required/mentioned in manual shall be provided as per Schedule D with approval from IE
and NHAI.
• RE wall/Retaining wall shall be provided at toll Booth locations to restrict the
embankment slope within the right of way, if required.
• The Concessionaire shall design and provide toll lane subject to minimum specified
above. The capacity of Toll lanes shall be as per NHAI Circular dated 24th May 2021.
• All Toll Lanes in both direction of traffic shall be ETC/ FASTag lanes.
• A separate toilet facility for road users shall be provided near toll plaza location along
with parking facility. One toilet block on each direction shall be provided as per drawing
at Annex-II of Schedule-C. These toilet facilities shall follow CPWD specifications for
sanitary ware items and fittings such as EWC, wash basin, Washbasin-Under counter,
Urinal flat back, PVC Cistern, IWC Orissa Pan, Flush Value CP, Wash Basin pillar cock-
CP, Bib Cock CP, Health Faucet, W/c Bib cock, Wash Basin angle cock.
• Point of Sale (POS)with card swapping machines shall be provided.
• Adequate surface and sub-surface drainage system at toll plaza area will be provided.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 19 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 21 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 22 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
sTable 3.4
1 79+120 LHS 2.00 Only development of land shall be done. (Complete area shall
be filled and compacted with borrow area soil up to minimum
1.5 m height above existing Ground level). The connecting
road from Main Carriageway to Way side amenity should be
constructed as per Manual.
Table 3.5
Sr.No. Design Chainage Side Remarks
2 76+200 RHS
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 23 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
3.4.15.1 Median:
Median plantation including maintenance shall be as per provision of IRC SP-21 and
Manual requirements.
3.4.15.2 Avenue:
In addition to compulsory afforestation specified in Schedule B, tree plantation and
landscaping shall be done as per IRC: SP:21 and Section 11 of the Manual on the project
highway.
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 24 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 25 of 26
DESIGN BASIS REPORT FOR PROPOSED HIGHWAY
Six laning of Naidupeta Junction - Turpukanupur Section from Km.57.046 to km 91.927 in the
state of Andhra Pradesh on HAM, Under Bharatmala Pariyojana Phase-I
Page 26 of 26