Ammonia Project IRR Optimization Ideas
Ammonia Project IRR Optimization Ideas
Ideation Workshop
PCPL - Ammonia Project
Action Document
31 January 2019
Priority for
implementation Priority for Impact
timeline - Capex, opex or
Sr. Category Description Remarks
(Immediate / schedule (High /
Short-term / Medium / Low)
Medium-term)
Cost- Design & Use GTG as primary source of power and STG as secondary source ( in case of
1
Spec optimization sudden shut down of primary source)
Sell excess steam generated by Ammonia plant (20 TPH from process & 20
2 Cost- Operations
TPH from HRSG & Boiler) to K1 plant at K1 CFB price
Schedule- Pre- Commence soil investigation based on preliminary plot plan. Could save time
4
construction as even if a bit of minor re-work is required in case of any plot plan change
Cost- Design & Clean and optimized plan for land utilization for OSBL facilities including roads
5
Spec optimization & pathways
Optimize mode of execution for LLI items - costs, time, transparency, effort &
6 Cost- minimize risks- GT-HRSG-Aux Boiler procurment to match overall project
Procurement schedule.
Long term agreement with gas provider at fixed rate to shield from market
7 Cost- Operations price variations. Develop a portfolio of gas sources that assures supply at sub-
$8/mmbtu prices
Cost- Design & Obtain consent for flare radius to reduce 90 m (as per OISD norms) from 60 m
8
Spec optimization as per allowable radiations level
Sell CO2 produced in the plant (which will otherwise be vented) to 3rd parties
and generate additonal revenue. Several Ammonia plants in India (existing
9 Cost- Operations
and past) have sold CO2 produced in their Ammonia plants. Explore alternate
uses of CO2 besides Enhanced Oil Recovery
Cost- Design &
10 Ensure plant capacity exceeds name plate capacity by 10-20%
Spec optimization
Seek a separate offer from EPC for detailed civil engineering design instead of
With the current status of the Project, this is not
waiting for the full EPC contract to be finalised. Enter into an early works
11 expected to provide any advantage. Hence, not
Schedule- Pre- contract to conduct civil design (while EC approval being sought) so that site
recommended.
construction works and civil works can proceed immediately after statutory approvals
Now more clarity on land parcels availability and
To give EPC contract with Toyo based on available plot plan and soil data with topography survey available by Feb end, we
12
Schedule- Pre- rider of revising the same through change proposals should target EPC contract finalization by April
construction Immediate (Now-1High end.
Reduce excess separation distance shown around Diesel storage tank in the
plot plan, by complying with OISD standard which is used extensively in O&G
Cost- Design &
21 industry in India. Separation distance could potentially be brought down to Optimization is possible and is being done.
Spec optimization
4.5 meters per OISD standard. Check if PESO allows a lower limit than the
currently taken distance in the plot plan.
Immediate (Now-1Moderate
Cost- Financing,
26 accounting, Explore low cost funding sources - IFC or other external borrowings PCPL to review this option
taxation Immediate (Now-1High
Cost- Annual maintenance contract and rate contract (RC) for high value This is not relevant to project phase. This may
27
Procurement standardisation can help reduce lead time and on time delivery Medium-term (3-6Low be considered during Plant operation.
Conduct clean sheet costing for equipment or material accounting top 80% of
Yes. Expert advise to be explored. TOYO to be
Cost- OSBL cost. Considering the high value & high priorities, explore deploying
28 asked to provide the break up as much as
Procurement expert negotiator and negotiation techniques for the EPC negotiations
possible to help in negotiation.
(including using the clean sheet costing) Immediate (Now-1High
Current available similar size projects MTOs to
Cost- Benchmark cost estimates for Civil, Erection, Bulk Material for EPC contracts
29 be compared or prorated based on available
Procurement with similar sized projects - to be used during EPC negotiations
Immediate (Now-1Moderate data and used for negotiations.
Instrumentation activities are the last activities to start and also they are the
last activities to be completed. Every plant will be waiting for loop checking
activity to be completed and issue clearance from instrumentation for plant
commissioning. This largely influenced by fronts available for field
This is to be implemented in defining EPC Scope
55 instruments installation, hook-up and loop checking. Field Instruments under
and Execution
package vendors (skid mounted), instruments under EPC scope will have
scope of loop drawings by EPC contractor, which is in turn depends on
DCS/ESD vendor. It is recommended to give priority to the availability of loop
Schedule- drawings, which can be made phase wise – MMS, ITCS, DCS, ESD etc.
Construction Medium-term (3-6Low
Cost-
56 Explore the possiblity of procuring used GTG Not recommended
Procurement
For chemical cleaning, steam blowing, cardboard blasting, Lube oil flushing
Any how it will be outsourced by EPC as well as
Cost- etc it is recommended to outsource the services which will include the
57 SPGP contractor. Steam blowing can not be
Procurement equipment and kits to carry out the activity independently.
outsourced.
Medium-term (3-6Moderate
Cost- Post-pone a few Capex items like CO2 export system until later say 2-3 years Not to be considered as part of current project
58
Procurement after commissioning. Should be in EPC scope Immediate (Now-1Moderate scope
Cost- Design & SOP to be prepared and implemented during
59 N2 consumption to be optimized- part of SoP, can use restriction orifices
Spec optimization Medium-term (3-6Low pre-commissioning and commisioning phase
Though basic and well known, during pre-commissioning and
60 Schedule- commissioning , undertake as many activities as possible concurrently. - To To be incorporated in EPC scope.
Construction add to the SOP- execution manual Medium-term (3-6Low
Cost- Design & This is to be implemented in defining EPC Scope
61 Large areas not requiring back filling to be left as it is, such as flare/greenbelt
Spec optimization Medium-term (3-6Low and Execution
Cost- Design & Toyo to be asked to evaluate the option for cost
62 Use GRE piping for UG services including Fire Fighting
Spec optimization Short-term (1-3 moLow saving.
Obtain permission to deviate on road sizes of plot and stairs in ISBL vs. MIDC
63 Schedule- Very important and to be taken up imeediately.
Construction DC guidelines. Do be dealt immediately along with other matters with MIDC Short-term (1-3 moHigh
Cost- Identify long lead items based on current demand/supply and fast track its
64 To be incorporated in EPC schedule.
Procurement procurement immediately after EPC award by working with the selected EPC Medium-term (3-6Low
We have about 214 nos. of containers supplied with pipe material and they
Cost- are owners property. We can use them for site offices, site camp
65 Yes. To be discussed with Toyo.
Procurement accommodation for critical skilled labour e.g. Skilled welders, concreate
pouring teams etc. Medium-term (3-6Moderate
Completion of base layer of plant road along with site preparation which will
66 Schedule- Yes
Construction ease out the construction equipment movement Medium-term (3-6High
67 Schedule- Early Demolition of existing structure in the available land before EPC Yes
Construction Immediate (Now-1High
Cost- Procurement of required spare parts for the equipment will help in reducing
68 It is already being done
Procurement the inventory cost Medium-term (3-6Low
Cost- Reduction in the delivery time for spares and internal processing time will
69 Operational matter
Procurement help in optimizing the inventory cost Medium-term (3-6Low
Preparation and adherence to the project schedule and close monitoring to
70 Schedule- Yes
Construction identify the gaps Medium-term (3-6High
Steering Committee comprising top officials of PCPL, EPC Contractor, PMC
and OMC to be formed wherein unresolved issues by the Project
71 Management Team are flagged. Steering committee to meet once in a month. Yes
Derive experience and learnings from NPK & Dahej- Can be added to SoP-
Schedule- execution manual
Construction Medium-term (3-6Moderate
Schedule- Editable file of Issue Log Register to be kept at a central location accessible to
72 Yes
Construction all the agencies. Resolution of issues logged to be tracked. Medium-term (3-6Low
Schedule- Open multiple work fronts at construction site by proactive management,
73 Yes. To be incorporated in EPC schedule.
Construction scheduling and prioritization of EPC activities to sqeeze construction schedule Medium-term (3-6High
Schedule- Pre- LD against delay to achieve intermediate milestones rather than against delay Yes. To be discussed and finalised during EPC
74
construction of overall project schedule to keep tabs on the progress Medium-term (3-6Low contract finalisation.
Cost- Design & Separate Metering skid / ultrasonic NG flow meter should not be required.
75 Yes
Spec optimization Only orifice flow meter will be enough for the same Medium-term (3-6Low
Flare stack has been located above superstructure of ISBL plant, in some
Cost- Design & Ammonia plants. This eliminates special land requirement for Flare stack.
76 Not possible.
Spec optimization 'Heat shielding panels' are available nowadays, which can positioned around
Flare tip if need be. Short-term (1-3 moModerate
If HRSG/GT are located closer to Aux.Boiler & STG, then expensive
Cost- Design & interconnecting HP steam piping length can be optimized. HRSG and
77 It is already being done
Spec optimization Boiler/STG are seperated by ~100m in present plot plan. Likewise, HRSG,
Boiler and STG should be close to ISBL plant for same reason. Medium-term (3-6Low
Continuously manned buildings such as Control Room and Laboratory should
Cost- Design &
78 be sited some distance away from Ammonia plants for safety reasons (if they It is already being done
Spec optimization
are not blast-proof). QRA study will reveal recommended separation distance. Medium-term (3-6Low
As soon as land is acquired, use some portion (e.g. North area of site, which is
Cost- Design & not part of plot plan) for laydown/storage of containers & equipment which
79 Yes
Spec optimization can be stored in open, instead of leasing open yard space elsewhere for
equipment storage. Immediate (Now-1Moderate
Cooling water pump should be supplied with a Variable Frequency Drive -
Cost- Design &
80 Summer/winter - payback period is 1 to 2 years - VFD useful for energy Not possible now
Spec optimization
conservation
Cost- Design &
81 Trip system voting logic, Redundancy philosophy, SIL level=3 (TUV 6) Already incorporated
Spec optimization
Bunching the equipment parts, Draw the layout map of equipment in
82 Schedule- Pre- warehouse. Number the equipment parts for easy identification of location Toyo to be asked as part of EW3 scope execution
construction and ease of assembly . Immediate (Now-1Low
Site-preparation for rains if project is starting in the period- 15th June to Sep
- Levelling land- Pre-grading (dependent on EC)
This is to be implemented in defining EPC Scope
83 - Make a shed- assemble the equipment (mainly static)
and Execution
- Making temporary/permanent storm water drains
Schedule- Pre- To check if temporary structures are allowed before EC
construction Short-term (1-3 moModerate
Floating of enquiry for Gratings can be prioritised. Wherever possible, can go This is to be implemented in defining EPC Scope
84 Cost-
Procurement for a standard panel size Medium-term (3-6Low and Execution
Start designing the network for construction power and water, area lighting
on the land acquired till date. Also start application and approval process for TOYO to be asked to evaluate and prpare the
85
Schedule- obtaining the construction power & water. Can be a part of early works. Can schemes upfront
Construction power connection for site be obtained based on sanction for E-31? Immediate (Now-1Moderate
Cost- Construction power and water to be provided by PCPL through the grid
86 To be evaluated and implemented in EPC scope
Procurement instead of asking EPC to get it through tankers Immediate (Now-1Moderate
Can steam driven pumps, compressors & other rotary equipments be used
Cost- Design &
87 instead of motor driven ones- can make use of the steam generated by the Not possible. Almost all equipmnet ordered
Spec optimization
plant for this purpose- provided the equipment is yet to be procured
Fire premium could be reduced by including things like Fire stop painting,
Cost- Design & This is to be implemented in defining EPC Scope
88 coating, barriers etc. if not included in scope already. To check with insurers
Spec optimization and Execution
about factors affecting fire premium Short-term (1-3 moModerate
Cost- Design &
89 Use GRE/HDPE piping for construction water Refer point No : 62.
Spec optimization
Cost- Financing,
To be considered as part of PCPL Business
90 accounting, Strategic investments from domestic / global NG players
strategy
taxation Short-term (1-3 moHigh
Optimizing method of evacuation of ammonia (TCO basis) - capex and
Cost- Design &
91 operational expenses for evacuation, storage of non-captive ammonia All Ammonia will be transferred to K1
Spec optimization
consumption