Rowena R Solante Vs Commission On Audit Chairperson Ma Gracia Pulido-Tan Et Al
Rowena R Solante Vs Commission On Audit Chairperson Ma Gracia Pulido-Tan Et Al
EN BANC
DECISION
The Case
This is a petition for review filed under Rule 64 assailing the February 15, 2008 Decision' and November 5,
2012 Resolution,2 denominated as Decision Nos. 2008-018 and 2012-190, respectively, of the Commission
on Audit (COA). The assailed issuances affirmed the Notice of Disallowance No. (ND) 2000-002-101(97)
dated November 14, 2001 issued by Rexy M. Ramos, COA State Auditor IV, pursuant to COA Assignment
Order No. 2000-63.3
The Facts
On April 26, 1989, the City of Mandaue and F.F. Cruz and Co., Inc. (F.F. Cruz) entered into a Contract of
Reclamation4 in which F.F. Cruz, in consideration of a defined land sharing formula thus stipulated, agreed to
undertake, at its own expense, the reclamation of 180 hectares, more or less, of foreshore and submerged
lands from the Cabahug Causeway in that city. The timetables, i.e., commencement of the contract and
project completion, are provided in paragraphs 2 and 15 of the Contract which state:
2. COMMENCEMENT. Work on the reclamation shall commence not later than [July 1989], after this
contract shall be ratified by the Sanggunian Panlungsod;
xxxx
15. CONTRACT DURATION. The project is estimated to be completed in six (6) years: (3 years for the
dredge-filling and seawall construction and 3 years for the infrastructures completion). However, if all
the infrastructures within the OWNERS’ share of the project are already completed within the six (6)
year period agreed upon, any extension of time for works to be done within the share of the
DEVELOPERS, shall be at the discretion of the DEVELOPERS, as a growing city, changes in
requirements of the lot buyers are inevitable.
On a best effort basis, the construction of roadways, drainage system and open spaces in the area
designated as share of the City of Mandaue, shall be completed not later than December 31, 1991.
(emphasis supplied)
Subsequently, the parties inked in relation to the above project a Memorandum of Agreement (MOA) dated
October 24, 19895 whereby the City of Mandaue allowed F.F. Cruz to put up structures on a portion of a
parcel of land owned by the city for the use of and to house F.F. Cruz personnel assigned at the project site,
subject to terms particularly provided in paragraphs 3, 4 and 5 of the MOA:
3) That [F.F. Cruz] desires to use a portion of a parcel of land of the [City of Mandaue] described under
paragraph 1 hereof to the extent of 495 square meters x x x to be used by them in the construction of
| Page 1 of 4
their offices to house its personnel to supervise the Mandaue City Reclamation Project x x x.
xxxx
4) That the [City of Mandaue] agrees to the desire of [F.F. Cruz] to use a portion of the parcel of land
described under paragraph 1 by [F.F. Cruz] for the latter to use for the construction of their offices to
house its personnel to supervise the said Mandaue City Reclamation Project with no rental to be paid
by [F.F. Cruz] to the [City of Mandaue].
5) That the [City of Mandaue] and [F.F. Cruz] have agreed that upon the completion of the Mandaue
City Reclamation Project, all improvements introduced by [F.F. Cruz] to the portion of the parcel of land
owned by the [City of Mandaue] as described under paragraph 3 hereof existing upon the completion of
the said Mandaue City Reclamation Project shall ipso facto belong to the [City of Mandaue] in
ownership as compensation for the use of said parcel of land by [F.F. Cruz] without any rental
whatsoever. (emphasis supplied)
Pursuant to the MOA, F.F. Cruz proceeded to construct the contemplated housing units and other facilities
which included a canteen and a septic tank.
Later developments saw the City of Mandaue undertaking the Metro Cebu Development Project II (MCDP II),
part of which required the widening of the Plaridel Extension Mandaue Causeway. However, the structures
and facilities built by F.F. Cruz subject of the MOA stood in the direct path of the road widening project. Thus,
the Department of Public Works and Highways (DPWH) and Samuel B. Darza, MCDP II project director,
entered into an Agreement to Demolish, Remove and Reconstruct Improvement dated July 23, 19976 with
F.F. Cruz whereby the latter would demolish the improvements outside of the boundary of the road widening
project and, in return, receive the total amount of PhP 1,084,836.42 in compensation.
Accordingly, petitioner Rowena B. Rances (now Rowena Rances- Solante), Human Resource Management
Officer III, prepared and, with the approval of Samuel B. Darza (Darza), then issued Disbursement Voucher
(DV) No. 102-07-88-97 dated July 24, 19977 for PhP 1,084,836.42 in favor of F.F. Cruz. In the voucher,
Solante certified that the expense covered by it was “necessary, lawful and incurred under my direct
supervision.”
Thereafter, Darza addressed a letter-complaint to the Office of the Ombudsman, Visayas, inviting attention to
several irregularities regarding the implementation of MCDP II. The letter was referred to the COA which then
issued Assignment Order No. 2000-063 for a team to audit the accounts of MCDP II. Following an audit, the
audit team issued Special Audit Office (SAO) Report No. 2000-28, par. 5 of which states:
F.F. Cruz and Company, Inc. was paid P1,084,836.42 for the cost of the property affected by the
widening of Plaridel Extension, Mandaue Causeway. However, under Section 5 of its MOA with
Mandaue City, the former was no longer the lawful owner of the properties at the time the payment was
made.8
Based on the above findings, the SAO audit team, through Rexy Ramos, issued the adverted ND
2000-002-101-(97)9 disallowing the payment of PhP 1,084,836.42 to F.F. Cruz and naming that company,
Darza and Solante liable for the transaction. Therefrom, Solante sought reconsideration, while F.F. Cruz
appealed, but the motion for reconsideration and the appeal were jointly denied in Legal and Adjudication
Office (LAO) Local Decision No. 2004-040 dated March 5, 2004, which F.F. Cruz in time appealed to COA
Central.
In the meantime, the adverted letter-complaint of Darza was upgraded as an Ombudsman case, docketed as
OMB-V-C-03-0173-C, against Solante, et al., albeit the Ombudsman, by Resolution of June 29, 2006,10
would subsequently dismiss the same for lack of merit.
| Page 2 of 4
In its February 15, 2008 Decision,11 the COA, as indicated at the outset, affirmed ND 2000-002-101-97 on
the strength of the following premises:
From the above provision of the MOA, it is clear that the improvements introduced by F.F. Cruz x x x
would be owned by the City upon completion of the project which under the Contract of reclamation
should have been in 1995. However, the project was not completed in 1995 and even in 1997 when
MDCP paid for these improvements. The fact that the reclamation project had not yet been
completed or turned over to the City of Mandaue by F.F. Cruz in 1997 or two years after it
should have been completed, does not negate the right over such improvements by the City x x
x. Clearly, the intention of the stipulation is for F.F. Cruz x x x to compensate the government
for the use of the land on which the office, pavement, canteen, extension shed, house and
septic tank were erected. Thus, to make the government pay for the cost of the demolished
improvements will defeat the intention of parties as regards compensation due from the
contractor for its use of [the] subject land. Under Article 1315 of the Civil Code, from the moment a
contract is perfected, the parties are bound to the fulfillment to what has been expressly stipulated and
all the consequences which according to their nature, may be in keeping with good faith, usage and law.
Thus, even if the contractual stipulations may turn out to be financially disadvantageous to any party,
such will not relieve any or both parties from their contractual obligations.12 (emphasis supplied)
From such decision, Solante filed a Motion for Reconsideration dated June 28, 2010 purportedly with Audit
Team Leader, Leila Socorro P. Domantay. This motion was denied by the COA in a Resolution dated
November 5, 201213 wherein the commission held:
x x x The arguments of Ms. Solante that as long as the Project has not yet been turned over, the
ownership of the said improvements would not be acquired yet by the City would put the entire contract
at the mercy of F.F. Cruz & Co., Inc., thus, negating the mutuality of contracts principle expressed in
Article 1308 of the New Civil Code, which states:
Art. 1308. The contracts must bind both contracting parties; its validity or compliance cannot be
left to the will of one of them.
On February 15, 2013, Solante received a Notice of Finality of Decision (NFD)14 stating that the COA
Decision dated February 15, 2008 and Resolution dated November 5, 2012 have become final and executory,
a copy of the Resolution having been served on the parties on November 9, 2012 by registered mail. Notably,
Solante never received a copy of the COA Resolution. She came to get one only on May 8, 2013 after
inquiring from the Cebu Central Post Office, which, in a Certification of Delivery dated May 8, 2013,15 stated
that the registered mail containing said copy was in fact not delivered.
The Issue
The resolution of the present controversy rests on the determination of a sole issue: who between the City of
Mandaue and F.F. Cruz owned during the period material the properties that were demolished.
The petition is meritorious. The COA and its audit team obviously misread the relevant stipulations of the
MOA in relation to the provisions on project completion and termination of contract of the Mandaue-F.F. Cruz
reclamation contract.
Essentially, the COA is alleging that the Contract of Reclamation establishes an obligation on the part of F.F.
Cruz to finish the project within the allotted period of six (6) years from contract execution in August 1989.
Prescinding from this premise, the COA would conclude that after the six (6)-year period, F.F. Cruz is
| Page 3 of 4
automatically deemed to be in delay, the contract considered as completed, and the ownership of the
structures built in accordance with the MOA transferred to the City of Mandaue.
On this point, the Civil Code provision on obligations with a period is relevant. Article 1193 thereof provides:
Article 1193. Obligations for whose fulfillment a day certain has been fixed, shall be demandable only
when that day comes.
Obligations with a resolutory period take effect at once, but terminate upon arrival of the day certain.
A day certain is understood to be that which must necessarily come, although it may not be known
when.
If the uncertainty consists in whether the day will come or not, the obligation is conditional, and it shall
be regulated by the rules of the preceding Section. (emphasis supplied)
A plain reading of the Contract of Reclamation reveals that the six (6)-year period provided for project
completion, or, with like effect, termination of the contract was a mere estimate and cannot be considered a
period or a “day certain” in the context of the aforequoted Art. 1193. To be clear, par. 15 of the Contract of
Reclamation states: “[T]he project is estimated to be completed in six (6) years.” As such, the lapse of six (6)
years from the perfection of the contract did not, by itself, make the obligation to finish the reclamation project
demandable, such as to put the obligor in a state of actionable delay for its inability to finish. Thus, F.F. Cruz
cannot be deemed to be in delay. Parenthetically, the Ombudsman, in a Resolution of June 29, 2006 in
OMB-V-C-03-0173-C, espoused a similar view in dismissing the complaint against Solante, thus:
A careful reading of the pertinent section of the Contract of Reclamation between F.F. Cruz and
Mandaue City, however, would confirm respondents Rances-Solante[’s] and Sungahid’s view that
herein respondent Cruz was still the owner of the subject properties at the time these were demolished.
Indeed, the Contract specifies that the six (6)-year period was no more than an estimate of the project
completion. It was not a fixed period agreed upon. Being so, the mere lapse of six (6) years from
the execution of the Contract, did not by itself deem the reclamation project completed, much
less bring about the fulfillment of the condition stipulated in the MOA (on the shift of ownership
over the demolished properties). Herein respondent Cruz, and/or his company, at least on this
particular regard, can be said to be still the owner of the structures along Plaridel Extension x x
x, when these were demolished to give way to road widening. It was nothing but equitable that
they get compensated for the damages caused by the demolition.16 (emphasis supplied)
Put a bit differently, the lapse of six (6) years from the perfection of the subject reclamation contract, without
more, could not have automatically vested Mandaue City, under the MOA, with ownership of the structures.
Moreover, even if we consider the allotted six (6) years within which F.F. Cruz was supposed to complete the
reclamation project, the lapse thereof does not automatically mean that F.F. Cruz was in delay. As may be
noted, the City of Mandaue never made a demand for the fulfillment of its obligation under the Contract of
Reclamation. Article 1169 of the Civil Code on the interaction of demand and delay and the exceptions to the
requirement of demand relevantly states: