SMP - Oil Filled Power Transformer
SMP - Oil Filled Power Transformer
Revision History
Revision Approvals
Date Reason of revision
no Prepared by Checked by Approved by
Mr. Jagannath Mr. Ved Prakash
0 New Document Mr. U. Prasad
Mr. Sandeep Thakur
1. Change in Frequency of Transformer Inspection as
recommended by ETD
29-10- 2. Testing to be done as & when required as Mr. Jagannath Mr. Ved Prakash
1 Mr. U. Prasad
2013 recommended by ETD. Mr. Sandeep Thakur
3. Changes due to revision in oil testing standards.
IS:1866
Revision Approvals
Date Reason of revision
no Prepared by Checked by Approved by
A. Introduction: Three phase transformers are meant to transfer power from one voltage level to other voltage level. It
can be classified into following categories.
i. Power transformer: That supplies bulk power to wide area or lot of load centers
ii. Distribution transformer: That supplies power to small area or load centers
iii. Converter transformer: This transformer is meant for power supply to rectifier loads or VFD loads
B. Operating Parameter/Working Condition/Basic condition:
Ambient Temperature: 30 - 40 Degree C
C. Scope: The document covers the standard Inspection & maintenance Guideline & procedure for Oil filled power
transformer above ≥ 5 MVA
D. Safety:
a) Safety Interlock: Within Fencing
b) Protection Interlock: Emergency Push button trip
E. Failure mode / Reason of Failure:
Failure modes Referral points in the SMP
Sl. No
Deviation of Winding resistance >5% G. b) 19.1
1.
Low Oil Level G. a) 9, 10
2.
Evolving of gas in Oil H.
3.
Low IR Value G. b) 19.2
4.
F. Guidelines from OEM: Refer OEM Operational manual
G. Inspection Guidelines:
a) Running Inspection (Daily/Weekly/Monthly)
b) Periodic Inspection
a) Running Inspection:
Sl.
Check Point Details Frequency How to Check Criteria Action (if out of criteria)
No.
1 Transformer Loading: D/W Ammeter on Should not be >100% Take action to reduce load on the
• HV Amps SWGR/RCP transformer
• LV Amps
2 Winding Temperature D/W Temp. meter on • Should not be >85 oC • If Winding Temp. >85oC, analyze
• At field Marshalling Box • Variation between & take action
• At RTCC panel near RTCC and field should • If variation found >5oC check the
(If provided) Transformer & not be > 5oC. repeater at RTCC panel
on RTCC
Sl.
Check Point Details Frequency How to Check Criteria Action (if out of criteria)
No.
3 Oil Temperature D/W Temp. meter on • Should not be >80 oC • If Oil. Temp. >80 oC take action to
• At field Marshalling Box • Variation between reduce load
• At RTCC panel near RTCC and field not • If variation found >5oC check the
(If provided) Transformer. & be> 5oC. repeater at RTCC panel
on RTCC
4 Oil leakages from D/W Visual No Leakage. In case of leakage assess the
flanges and welded severity and take corrective action
joints
5 OLTC counter reading M Counter in OLTC Readings at RTCC and Plan for inspection of connection
At field Marshalling Box OLTC MB should match from RTCC and OLTC MB during stop
and RTCC. and check inspection
6 HV/MV cable box M The temp. should be • Variation > 5oC from previous
By infrared
body temperature via consistent with previous record shall be investigated
thermal imaging
spot temperature record plus variation of
camera
measurement ambient temp.
7 Condition of clamps & M • Should not be >90 oC • If temperature found >90oC,
By infrared
connectors in power check the connection, clean or
thermal imaging
circuit. change the clamp at the earliest
camera
8 Condition of Silica Gel M Colour of Silica Colour shall be Blue • If colour found completely pink
breather Gel get the crystals dried or changed
• Check oil level in the pot below
the breather
9 Oil-level in the M Visual / The oil level shall be full • Take action if oil level is below the
bushing (for oil filled Binocular or above the marked marked level or not visible
bushings only) level • Clean gauge glass or replace
during shutdown if it is opaque
10 Main Tank Oil Level M Visual / Level should be Take action if oil level is below the
(Gauge Glass & MOG) Binocular between 35oC mark and marked level & fill with new oil
half mark on the MOG
11 OLTC Tank Oil Level M Visual / Level shall be above the Take action if oil level is below the
Binocular half mark of the gauge half mark level of gauge glass & fill
glass with new oil
12. Noise D/W dB meter Should be <75dB Inform sectional head and plan for
inspection
b) Periodical inspection/maintenance
Sl. Check Point Details Frequency How to Check Criteria Action (if out of
No. criteria)
1 Oil leakage from Y Visual No oil leakage • Proper tightening
Transformer of the inspection
covers to be
ensured
• Check condition
of gaskets
2 Cleaning of Bushing / Y Visual Shall be clean To be cleaned by
supporting insulators clean cotton cloth
(Jute should not be
used)
3 Tightness of Bushing Y By torque spanner Shall be tight Should be
clamps tightened with
proper torque
spanner
Sl. Check Point Details Frequency How to Check Criteria Action (if out of
No. criteria)
4 Condition of cable box Y Visual Shall be clean & no If moisture
moisture condensation or condensation or
contamination contamination is
found, it shall be
cleaned with petrol
or ether
5 Operation of Buchholz, Y Operation of alarm / trip Shall operate as desired Replace the relay if
Oil Surge relay (OLTC) contact by draining oil found defective
Sl. Check Point Details Frequency How to Check Criteria Action (if out of
No. criteria)
vibration or abnormal • Direction of rotation • The dust
sound shall be as marked on deposition on
• Check direction of the fan the fan blades
rotation with a piece shall be cleaned
of cloth with plain cloth
• Set right the
direction by
interchanging
any two-phase
connection
16 Neutral Grounding Y • Measure NGR • Resistance value of NGR • If Resistance
Resistor health resistance by Multi- shall be within ±10% of value more than
meter nameplate value ± 10%
• IR Value to Ground • IR value shall be more investigate for
after opening ground than rated system shorting/
connection voltage +1 MΩ loosening of
• Physical inspection for • Shall be clean some section &
cleanliness • All joint connection shall set right
• Connection tightness be tight • IR value is less,
by suitable spanner check for any
insulator
damage. Clean
or replace the
insulator to
improve the IR
17 Monsoon protection of Y (Before Visual Rain protection shall be in Take corrective
DM Box and Marshalling Monsoon) good condition action if required
Kiosk
18 Monsoon protection of Y (Before Visual Rain protection shall be in Take corrective
Buchholz and Oil-Surge Monsoon) good condition action if required
relay.
19.1 Winding Resistance 4Y • To be done as per • The variation in • In case
measurement standard procedures resistance between resistance value
of Elect. Testing dept. consecutive tap shall be exceed the limit
consistent further
• The variation in winding investigation to
resistance between be made
phases shall be ≤ 5%
19.2 Insulation Resistance & PI 4Y • To be done as per • > 30M Ω for up to 33 KV
• If IR values
Measurement standard procedures of • > 80M Ω for 132 KV
found less, then
Elect. Testing dept. • >142M Ω for 220 KV
refer to PI
• >255M Ω for 400 KV
HV-E+LV (5000 V) readings.
• > 100 M Ω (Core IR)
• For new
LV-E+HV (5000 V) • New Transformers: Transformers, If
IR of Core (1000 V) o PI of HV > 2 PI value found
o PI of LV > 2.2 less, consult the
• Old Transformers > manufacturer
10Years: • For old
o PI of HV >1.3 Transformers, If
o PI of LV > 1.3 PI is less than
that mentioned,
consensus
decision to be
taken
Sl. Check Point Details Frequency How to Check Criteria Action (if out of
No. criteria)
19.3 Core insulation 4Y • To be done as per
• The IR value shall be
measurement by 1000V standard procedures
megger >100
of Elect. Testing dept.
20 Calibration of WTI & OTI 3Y • To be done as per * *
at site standard procedures
of Elect. Testing dept.
21 Wash the OLTC diverter 3Y • To be done as per * *
assembly with oil. standard procedures
of Elect. Testing dept.
22 OLTC Tap changing 3Y • Check operation In case of deviation
operation after • The number of rotations it shall be set right
manually by counting
shall be same for each
overhauling the number of as per OEM
operation for guideline
rotations.
forward/reverse
• Check for consistency
of operation at each • They should be perfectly
tap position. matching. No
• Check whether the tap discrepancy is allowed.
no. at the top of
transformer is • Shall be consistent.
matching with the tap • Shall be around 2 – 3 .
position indicator at
DM Box & RTCC panel.
• Check the value of the
resistance.
23 Oil sample testing of Y • To be done as per IS N.A
transformer standard.
23.1 BDV of transformer or Y • As per IS 1866 If test Values
Up to system voltage of
OLTC oil crosses the limit,
• <=72KV: >30KV consensus decision
to be taken for oil
• >72 to <=170KV: >40KV filtration or
• >170 to <=420KV: >50kV replacement.
• <=72KV: >50PPM • If found more, then filter the oil through high
3 Moisture content • 72 to 170KV: >40PPM vacuum filter
• 170 to 420KV: >20 PPM
Tan at 900C • <=72KV: Max 1 • If tan value is high, replace the oil
6 • 72 to 170KV: Max 1 • Carry out periodic measurement
• 170 to 420KV: Max. 0.2
Periodic filtering of oil through • If all the test of oil is OK then filtering shall
8 Every 10 years
high vacuum filter. be done after every 10 years of service
I. Core coil assembly inspection of transformer for electrical and mechanical connection integrity.
Core coil assembly inspection of transformer for electrical and mechanical connection integrity shall be done for the
transformer having age>=30 years and rating more than equal to 10MVA on one time basis.
Priority shall be decided based on Electrical test, DGA, OST of oil, application and criticality.
Note:
If after oil replacement the winding IR value and PI value does not improve to the desired level, winding dehydration will be
required.
• Inspection frequency for Oil filled power Transformers of Voltage rating (Ul ≥ 132 KV) will be Daily.
• Inspection frequency for Oil filled power Transformers of Voltage rating (Ul< 132 KV) will be weekly.
• The following test to be done only during Transformer commissioning or if a transformer trips on any
transformer fault.
▪ Magnetic Balance Test.
▪ Ratio Test
▪ Tan Delta testing of transformer winding.
D : Daily, W : Weekly, M : Monthly, Q : Quarterly, HY : Half Yearly, Y : Yearly
Shares Services Technology Group 7
Oil Filled Transformer DOCUMENT NO. REV
(≥5MVA) SSTG/SMP/ELEC/0001 3
Date:31.12.2022 Page 8 of 8