Method-Statement-Form-HDPE-PN16-pipe (Site Utilities)
Method-Statement-Form-HDPE-PN16-pipe (Site Utilities)
of 27
Document No. : Effective Date : Revision
:
Revision History
Re Prep Chec Revie Approv
Date Revision Details
v. ared ked wed ed
Title : Page 2
of 27
Document No. : Effective Date : Revision
:
Categ Contents Pa
ory ge
1 Scope of work
2 Tool & Equipment
3 Work sequence
4 Inspection
5 Test & Commissioning
Appen
dix 1
Appen
dix 2
1. Scope of work
This method statement is prepared to outline the procedure
for installing of HDPE UG pipes of Utility Water System and other
system mentioned below :
- Waste Water System
- Chemical Waste Water System - Fire Fighting Water System
- Service Water System
Title : Page 3
of 27
Document No. : Effective Date : Revision
:
3. Work Sequence
The following procedures are the working method for laying of
HPDE pipes under the proposed construction site Depot Site
Devt. Utilities, there are three main steps which are:
3.1 Excavation
The excavation shall be carried out in two steps. The first
step is to open the ground up at 45 degrees by using a Mini
Backhoe to the depth specified on the drawings with minimum
width specified on the plans. The slope shall be set at 45
degrees angle in order to ensure stability.
The general requirements for standard specification are
as follows:
- The levels for excavation shall be established by the surveyor.
- Any existing structure, cable, or pipe must be identified
before any excavation work can be done.
- The dimension of excavation shall be depended on the
size of the HDPE Pipe.
- Excavated material shall be hauled to be inspected by
qualified person to a dumpsite, however, excavated material
shall be moved to a dump site or if it is required to be store for
further backfill then material must be a stock area.
- There must be a bank man and rigger for each vehicle to
control the vehicle in order to prevent injury to other workers
and damage to the vehicle itself.
- If there is any surface or ground water, it shall be pumped
out from excavated areas to avoid flooding excavated site.
- Safety sign, hard barricade, lighting if working at night
would be required around the working area.
- When the excavation nearly reaches its designated level,
care shall be taken in order to save time and cost if the
excavated level is too deep.
- When excavation reached it design level then the
engineer must be informed.
Title : Page 4
of 27
Document No. : Effective Date : Revision
:
3.5 Backfill
The majority of material for backfill shall be sand which
covered the HDPE pipes up to 1.2 m from the lean level while
the rest of the backfill material would be original material from
the excavation. The excavator shall be used to backfill the rest
of the trench to the new designated ground level then the
compaction process shall carry out to get the optimum level of
compaction to the standard set in the general specification in
order to prepared the ground for concrete lean.
4. Inspection
4.1 Material check
4.2 Alignment check
4.3 Pipe line check
FLUSHING PROCEDURE
Flushing of all lines shall be done after hydrostatic test and
was supervised by commissioning personnel.
Flushing of all lines shall be done in the presence and as per
the approval of the Owner.
The medium for flushing used de-mineral water. Flushing of
pipe lines will be done by start condensate water pump and
use water temporary tank in PURAC.
During flushing care must be taken so that the pressure is
lower than the operating pressures. The pressure for
flushing around 1.90 bar.g
3.5 Flushing will be continued until the inside of the pipe is
fully cleaned. The flushing test result shall confirm by
Owner.
During the flushing, discharged water. Care shall be taken
during flushing so as not to damage / spoil other agencies
work. Precautions shall also be taken to prevent entry of
water in the vicinity of lines being flushed.
The water will be flush into drainage system of Power Plant.
After flushing the temporary installed piping and other spool
piece shall be removed. Piping equipment and instrument
removed for flushing the line shall be re-installed in the
collect position using prescribed gasket.
Title : Page 7
of 27
Document No. : Effective Date : Revision
:
peeling tool
Figure 3.1
Heating Plate
Figure 3.
4. Cleaning Before Welding: Clean the surplus plastic after
trimming by using clean cloth, tissue with methyl alcohol to
remove oil and dust at pipe and heating plate and heat up to
210° C
5.3 Slide the pipe ends to connect each other within max
pressure rising-time.
bar
Figure 6.1
bar
Figure 6.2
Figure 6.3
Title : Page 12
of 27
Document No. : Effective Date : Revision
:
Figure 6.4
GENERAL INSTRUCTION OF WELDING WORK
1. Clamping device
2. Heating plate
3. Hydraulic pump
4. Peeling tool
Title : Page 14
of 27
Document No. : Effective Date : Revision
:
WELDING PROCESS
WELDING CYCLE
Title : Page 18
of 27
Document No. : Effective Date : Revision
:
WELDING SPECIFICATION
OD mm 63 75 90 110 160 200 225 250 280 315 355 400 450 500 560 630 710
ND IN 2" 2 1/2" 3" 4" 6" 7" 8" 9" 10" 12" 14" 16" 18" 20" 22" 24" 28"
PN (PE 100) 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
WALL THICKNESS (e) mm 3.8 4.5 5.4 6.6 9.5 11.9 13.4 14.8 16.6 18.7 21.1 23.7 26.7 29.7 33.2 37.4 42.1
PIPE X‐SECTION AREA
sq.mm 707 997 1,435 2,144 4,492 7,032 8,908 10,936 13,736 17,407 22,133 28,018 35,507 43,881 54,946 69,628 88,337
(A1)
WELDING M/C TYPE 110 110 110 315 315 315 315 315 315 315 450 450 450 500 800 800 800
CYLINDER X‐SECTION
sq.mm 653 653 653 855 855 855 855 855 855 855 1351 1351 1351 1351 1890 1890 1890
AREA (A2)
HEATING PLATE TEMP. °C 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10 210±10
HEATING ‐UP PRESSURE. bar 1.9 2.7 4 5 9 15 19 23 29 37 29 37 47 58 52 66 84
HEAT SOAK TIME min. 0.95 1.13 1.35 1.65 2.38 2.98 3.35 3.7 4.15 4.68 5.28 5.93 6.68 7.43 8.3 9.35 10.53
CHANGE OVER TIME sec. 3.63 3.75 3.9 4.1 4.6 5 5.25 5.5 5.8 6.15 6.55 7 7.5 8 8.6 9.3 10.1
MAX. PRESSURE ‐RISING
sec. 4. 9 5.25 5.7 6.3 7.8 9 9. 5 10.5 11.4 12.45 13. 5 15. 0 16. 0 18. 0 19. 0 21.9 24. 0
TIME
WELDING PRESSURE bar 1.9 2.7 4 5 9 15 19 23 29 37 29 37 47 58 52 66 84
COOLING TIME UNDER
min. 6.8 7.5 8.4 9.6 12.5 14.9 16.4 17.8 19.6 21.7 24.1 26.7 29.7 32.7 36.2 40.4 45.1
PRESSURE
WELD SEAM (MIN) mm. 4.9 5.3 5.7 6.3 7.8 9 9.7 10.4 11.3 12.4 13.6 14.9 16.4 17.9 19.6 21.7 24.1
WELD SEAM (MAX) mm. 7.9 8.4 9.1 10 12.1 13.9 15.1 16.1 17.5 19 20.8 22.8 25 27.3 29.9 33.1 36.6
Title : Page 20
of 27
Document No. : Effective Date : Revision
:
INSPECTION REPORT
Package No. _
Report No._ _
Acceptable
Item Description Comments
Yes No N/A
1 Material Inspection
2 Installation Process
_ _ _
( ) ( )
( ) Date : _ Date : _
Date : EGCO Engineering & Service Co., Ltd. REN Korat Energy Co., Ltd.
Italthai Engineering Co., LTD.
Title : Page 23
of 27
Document No. : Effective Date : Revision
:
INSPECTION REPORT
Package No. _
Report No._ _
Acceptable
Item Description Comments
Yes No N/A
1 Material Inspection
2 Installation Process
_ _ _
( ) ( )
( ) Date : _ Date : _
Date : EGCO Engineering & Service Co., Ltd. REN Korat Energy Co., Ltd.
Italthai Engineering Co., LTD.
Title : Page 25
of 27
Document No. : Effective Date : Revision
:
INSPECTION REPORT
Package No. _
Report No._ _
Acceptable
Item Description Comments
Yes No N/A
1 Material Inspection
2 Installation Process
_ _ _
( ) ( )
( ) Date : _ Date : _
Date : EGCO Engineering & Service Co., Ltd. REN Korat Energy Co., Ltd.
Italthai Engineering Co., LTD.
Title : Page 27
of 27
Document No. : Effective Date : Revision
: