ID Task Task Name Duration Start Finish Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
0 PROPOSED 2-STOREY W/ ROOF 187 days Fri 23 Jun '23 Fri 02 Feb '24
DECK RESIDENTIAL BUILDING
1 PHASE 1 (Structural) 187 days Fri 23 Jun '23 Fri 02 Feb '24
2 SITE WORKS 32 days Fri 23 Jun '23 Sat 29 Jul '23
3 Construction of Barracks 7 days Fri 23 Jun '23 Fri 30 Jun '23
4 Construction and Warehouse 4 days Sat 01 Jul '23 Wed 05 Jul '23
5 Layout and Staking 3 days Thu 06 Jul '23 Sat 08 Jul '23
6 Application of Rust Converter 5 days Thu 06 Jul '23 Tue 11 Jul '23
for Reinforcement Bars
7 Application of Epoxy Primer for 4 days Wed 12 Jul '23 Sat 15 Jul '23
all Steel Materials
8 Preparation of Perforated HDPE 4 days Thu 06 Jul '23 Mon 10 Jul '23
Pipes i.e. Drilling Holes
9 Fabrication of Metal Circular 21 days Thu 06 Jul '23 Sat 29 Jul '23
Formworks for Columns
10 FOUNDATION 25 days Thu 06 Jul '23 Thu 03 Aug '23
11 Excavation 4 days Mon 10 Jul '23 Thu 13 Jul '23
12 Trimming 6 days Fri 14 Jul '23 Thu 20 Jul '23
13 Pumping Water out of Pit holes 6 days Fri 14 Jul '23 Thu 20 Jul '23
14 Compaction 4 days Fri 14 Jul '23 Tue 18 Jul '23
15 Fabrication & Assembly of 8 days Thu 06 Jul '23 Fri 14 Jul '23
Rebars and Formworks of
Footing
16 Laying of Perforated HDPE 2 days Wed 19 Jul '23 Thu 20 Jul '23
Pipes around the Foundations
17 Installation of Polyethylene 1 day Fri 21 Jul '23 Fri 21 Jul '23
Sheet around the Column
Foundation
18 Concrete Pouring 4 days Sat 22 Jul '23 Wed 26 Jul '23
19 Concrete Curing (7 days, 14 7 days Thu 27 Jul '23 Thu 03 Aug '23
days, 28 days)
20 COLUMN (FTG TO GFL) 25 days Thu 06 Jul '23 Thu 03 Aug '23
21 Assembly of Circular Column 6 days Thu 06 Jul '23 Wed 12 Jul '23
Rebars (20 Sets)
Task Project Summary Manual Task Start-only Deadline
Project: PROPOSED 2-STOREY W Split Inactive Task Duration-only Finish-only Progress
Date: Thu 22 Jun '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1
ID Task Task Name Duration Start Finish Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
22 Fabrication and Installation of 12 days Thu 13 Jul '23 Wed 26 Jul '23
Lateral Ties
23 Installation of Metal Formworks 5 days Thu 27 Jul '23 Tue 01 Aug '23
24 Installation of Dowels for 2 days Thu 27 Jul '23 Fri 28 Jul '23
Footing Tie Beams
25 Concrete Pouring 3 days Sat 29 Jul '23 Tue 01 Aug '23
26 Removal of Formworks 2 days Wed 02 Aug '23 Thu 03 Aug '23
27 FOOTING TIE BEAM 12 days Fri 04 Aug '23 Thu 17 Aug '23
28 Splicing from Dowels for Main 5 days Fri 04 Aug '23 Wed 09 Aug '23
Bars
29 Fabrication and Installation of 6 days Fri 04 Aug '23 Thu 10 Aug '23
Stirrups
30 Fabrication and Installation of 4 days Thu 10 Aug '23 Mon 14 Aug '23
Formworks
31 Concrete Pouring of Tie Beams 1 day Tue 15 Aug '23 Tue 15 Aug '23
32 Soil Back fill 2 days Wed 16 Aug '23 Thu 17 Aug '23
33 COLUMN (GFL TO UGL) 14 days Thu 10 Aug '23 Fri 25 Aug '23
34 Splicing and Rebar Assembly 7 days Fri 18 Aug '23 Fri 25 Aug '23
35 Fabrication and Installation of 5 days Thu 10 Aug '23 Tue 15 Aug '23
Lateral Ties
36 Installation of Metal Formworks 5 days Wed 16 Aug '23 Mon 21 Aug '23
37 Concrete Pouring 3 days Tue 22 Aug '23 Thu 24 Aug '23
38 Removal of Formworks 1 day Fri 25 Aug '23 Fri 25 Aug '23
39 UGL BEAM and SLAB 36 days Tue 08 Aug '23 Mon 18 Sep '23
40 Fabrication and Installation of 6 days Tue 08 Aug '23 Mon 14 Aug '23
Beam Rebars and Stirrups
41 Erection of Under-support of 6 days Tue 08 Aug '23 Mon 14 Aug '23
Beam and Bracings
42 Installation of Slab's 5 days Tue 15 Aug '23 Sat 19 Aug '23
Under-support and Bracings
43 Slab Rebar Assembly 4 days Mon 21 Aug '23 Thu 24 Aug '23
44 Electrical and Plumbing 2 days Fri 25 Aug '23 Sat 26 Aug '23
Stab-outs
45 Preparation and Assembly of 2 days Fri 25 Aug '23 Sat 26 Aug '23
Dowels for Stairs and Wall
Reinforcement
46 Site Inspection 1 day Mon 28 Aug '23 Mon 28 Aug '23
Task Project Summary Manual Task Start-only Deadline
Project: PROPOSED 2-STOREY W Split Inactive Task Duration-only Finish-only Progress
Date: Thu 22 Jun '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 2
ID Task Task Name Duration Start Finish Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
47 Concrete Pouring 2 days Tue 29 Aug '23 Wed 30 Aug '23
48 Concrete Curing (14 days) 14 days Thu 31 Aug '23 Fri 15 Sep '23
49 Removal of Under-Supports and 3 days Fri 15 Sep '23 Mon 18 Sep '23
Bracings
50 STAIRS (GFL TO UGL) 15 days Sat 16 Sep '23 Tue 03 Oct '23
51 Lay-outing of stairs 3 days Sat 16 Sep '23 Tue 19 Sep '23
52 Fabrication and Installation of 6 days Wed 20 Sep '23 Tue 26 Sep '23
Stair Forms
53 Rebar assembly of Stairs 4 days Wed 27 Sep '23 Sat 30 Sep '23
54 Concrete Pouring 2 days Mon 02 Oct '23 Tue 03 Oct '23
55 COLUMN (UGL TO 2FL) 28 days Mon 11 Sep '23 Thu 12 Oct '23
56 Splicing and Rebar Assembly 8 days Mon 11 Sep '23 Tue 19 Sep '23
57 Fabrication and Installation of 8 days Wed 20 Sep '23 Thu 28 Sep '23
Lateral Ties
58 Fabrication and Installation of 8 days Fri 29 Sep '23 Sat 07 Oct '23
Rectangular Column Forms
59 Concrete Pouring 3 days Mon 09 Oct '23 Wed 11 Oct '23
60 Removal of Formworks 1 day Thu 12 Oct '23 Thu 12 Oct '23
61 SEPTIC TANK & CISTERN TANK 28 days Tue 19 Sep '23 Fri 20 Oct '23
62 Manual Excavation of Septic 12 days Tue 19 Sep '23 Mon 02 Oct '23
and Cistern Tank
63 Trimming 3 days Tue 03 Oct '23 Thu 05 Oct '23
64 Compacting and Gravel Bedding 1 day Fri 06 Oct '23 Fri 06 Oct '23
65 Rebar Assembly 3 days Sat 07 Oct '23 Tue 10 Oct '23
66 CHB Laying 2 days Wed 11 Oct '23 Thu 12 Oct '23
67 Plastering 5 days Fri 13 Oct '23 Wed 18 Oct '23
68 Water Proofing 2 days Thu 19 Oct '23 Fri 20 Oct '23
69 2FL BEAM AND SLAB 30.25 days Thu 12 Oct '23 Thu 16 Nov '23
70 Fabrication and Installation of 6 days Thu 12 Oct '23 Wed 18 Oct '23
Beam Rebars and Stirrups
71 Erection of Under-support of 6 days Thu 12 Oct '23 Thu 19 Oct '23
Beam and Bracings
72 Installation of Slab's 4 days Fri 20 Oct '23 Tue 24 Oct '23
Under-support and Bracings
73 Slab Rebar Assembly 4 days Fri 20 Oct '23 Tue 24 Oct '23
74 Electrical and Plumbing 2 days Mon 23 Oct '23 Thu 26 Oct '23
Stab-outs
Task Project Summary Manual Task Start-only Deadline
Project: PROPOSED 2-STOREY W Split Inactive Task Duration-only Finish-only Progress
Date: Thu 22 Jun '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 3
ID Task Task Name Duration Start Finish Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
75 Preparation and Assembly of 2 days Mon 23 Oct '23 Thu 26 Oct '23
Dowels for Stairs and Wall
Reinforcement
76 Site Inspection 1 day Thu 26 Oct '23 Fri 27 Oct '23
77 Concrete Pouring 1 day Thu 26 Oct '23 Fri 27 Oct '23
78 Concrete Curing (14 days) 14 days Fri 27 Oct '23 Mon 13 Nov '23
79 Removal of Under-Supports and 3 days Mon 13 Nov '23 Thu 16 Nov '23
Bracings
80 STAIRS (UGL TO 2FL) 12 days Wed 01 Nov '23 Tue 14 Nov '23
81 Lay-outing of stairs 3 days Wed 01 Nov '23 Fri 03 Nov '23
82 Fabrication and Installation of 3 days Sat 04 Nov '23 Tue 07 Nov '23
Stair Forms
83 Rebar assembly of Stairs 5 days Wed 08 Nov '23 Mon 13 Nov '23
84 Concrete Pouring 1 day Tue 14 Nov '23 Tue 14 Nov '23
85 WALL (UGL) 25 days Sat 16 Sep '23 Sat 14 Oct '23
86 Lay-outing 1 day Sat 16 Sep '23 Sat 16 Sep '23
87 CHB Laying 14 days Mon 18 Sep '23 Tue 03 Oct '23
88 Preparation and Stabbing- out 6 days Wed 04 Oct '23 Tue 10 Oct '23
of Electrical pipes and Plumbing
Pipes
89 Reinforcing of Lintel Beams 5 days Wed 04 Oct '23 Mon 09 Oct '23
90 Plastering 10 days Wed 04 Oct '23 Sat 14 Oct '23
91 COLUMN (2FL TO RDL) 10 days Wed 01 Nov '23 Sat 11 Nov '23
92 Splicing and Rebar Assembly 3 days Wed 01 Nov '23 Fri 03 Nov '23
93 Fabrication and Installation of 3 days Wed 01 Nov '23 Fri 03 Nov '23
Lateral Ties
94 Installation of Rectangular 4 days Sat 04 Nov '23 Wed 08 Nov '23
Column Forms
95 Concrete Pouring 2 days Thu 09 Nov '23 Fri 10 Nov '23
96 Removal of Formworks 1 day Sat 11 Nov '23 Sat 11 Nov '23
97 RDL BEAM AND SLAB 39 days Mon 13 Nov '23 Sat 30 Dec '23
98 Fabrication and Installation of 6 days Mon 13 Nov '23 Sat 18 Nov '23
Beam Rebars and Stirrups
99 Erection of Under-support of 6 days Mon 20 Nov '23 Sat 25 Nov '23
Beam and Bracings
100 Installation of Slab's 4 days Mon 27 Nov '23 Thu 30 Nov '23
Under-support and Bracings
Task Project Summary Manual Task Start-only Deadline
Project: PROPOSED 2-STOREY W Split Inactive Task Duration-only Finish-only Progress
Date: Thu 22 Jun '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 4
ID Task Task Name Duration Start Finish Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
101 Slab Rebar Assembly 4 days Fri 01 Dec '23 Tue 05 Dec '23
102 Electrical and Plumbing 2 days Wed 06 Dec '23 Thu 07 Dec '23
Stab-outs
103 Preparation and Assembly of 2 days Wed 06 Dec '23 Thu 07 Dec '23
Dowels for Stairs and Wall
Reinforcement
104 Site Inspection 1 day Fri 08 Dec '23 Fri 08 Dec '23
105 Concrete Pouring 1 day Sat 09 Dec '23 Sat 09 Dec '23
106 Concrete Curing (14 days) 14 days Mon 11 Dec '23 Fri 29 Dec '23
107 Removal of Under-Supports and 3 days Thu 28 Dec '23 Sat 30 Dec '23
Bracings
108 COLUMN (RDL TO RL) 9 days Sat 30 Dec '23 Fri 12 Jan '24
109 Splicing and Rebar Assembly 4 days Sat 30 Dec '23 Sat 06 Jan '24
110 Fabrication and Installation of 4 days Sat 30 Dec '23 Sat 06 Jan '24
Lateral Ties
111 Fabrication and Installation of 3 days Mon 08 Jan '24 Wed 10 Jan '24
Square Column Forms
112 Concrete Pouring 1 day Thu 11 Jan '24 Thu 11 Jan '24
113 Removal of Formworks 1 day Fri 12 Jan '24 Fri 12 Jan '24
114 ROOF BEAM 15 days Sat 13 Jan '24 Tue 30 Jan '24
115 Fabrication and Installation of 3 days Sat 13 Jan '24 Tue 16 Jan '24
Beam Rebars and Stirrups
116 Erection of Under-support of 4 days Wed 17 Jan '24 Sat 20 Jan '24
Beam, Sidings, and Bracings
117 Concrete Pouring 1 day Mon 22 Jan '24 Mon 22 Jan '24
118 Concrete Curing and Removal 7 days Tue 23 Jan '24 Tue 30 Jan '24
of Forms
119 WALL (2FL) 23 days Sat 30 Dec '23 Mon 29 Jan '24
120 Lay-outing 1 day Sat 30 Dec '23 Sat 30 Dec '23
121 CHB Laying 8 days Thu 04 Jan '24 Fri 12 Jan '24
122 Preparation and Stabbing- out 4 days Sat 13 Jan '24 Wed 17 Jan '24
of Electrical pipes and Plumbing
Pipes
123 Reinforcing of Lintel Beams 3 days Sat 13 Jan '24 Tue 16 Jan '24
124 Plastering 11 days Wed 17 Jan '24 Mon 29 Jan '24
125 STAIRS (2FL TO RDL) 8 days Thu 04 Jan '24 Fri 12 Jan '24
126 Lay-outing of stairs 2 days Thu 04 Jan '24 Fri 05 Jan '24
Task Project Summary Manual Task Start-only Deadline
Project: PROPOSED 2-STOREY W Split Inactive Task Duration-only Finish-only Progress
Date: Thu 22 Jun '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 5
ID Task Task Name Duration Start Finish Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
127 Fabrication and Installation of 3 days Sat 06 Jan '24 Tue 09 Jan '24
Stair Forms
128 Rebar assembly of Stairs 2 days Wed 10 Jan '24 Thu 11 Jan '24
129 Concrete Pouring 1 day Fri 12 Jan '24 Fri 12 Jan '24
130 WALL (STAIR WALL) 12 days Sat 30 Dec '23 Tue 16 Jan '24
131 Lay-outing 1 day Sat 30 Dec '23 Sat 30 Dec '23
132 CHB Laying 4 days Thu 04 Jan '24 Mon 08 Jan '24
133 Preparation and Stabbing- out 2 days Tue 09 Jan '24 Wed 10 Jan '24
of Electrical pipes
134 Reinforcing of Lintel Beams 1 day Thu 11 Jan '24 Thu 11 Jan '24
135 Plastering 4 days Fri 12 Jan '24 Tue 16 Jan '24
136 ROOFING WORKS 3 days Tue 30 Jan '24 Fri 02 Feb '24
137 Layout of Stair's Roof 0 days Tue 30 Jan '24 Tue 30 Jan '24 30/01
138 Casting of Purlins 3 days Wed 31 Jan '24 Fri 02 Feb '24
139 Fabrication and Installation of 3 days Wed 31 Jan '24 Fri 02 Feb '24
Fascia Board
140 Roof and Gutter Installation 2 days Wed 31 Jan '24 Thu 01 Feb '24
Task Project Summary Manual Task Start-only Deadline
Project: PROPOSED 2-STOREY W Split Inactive Task Duration-only Finish-only Progress
Date: Thu 22 Jun '23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 6