Activity ID Activity Name Original Duration Remaining Schedule Start Finish Total
Duration %
Complete Float
ANNEX CONSTRUCTION 325 325 0% 02-Nov-24
30-Jan-260
ANNEX.1 INITIAL CONSTRUCTION PHASE 302 302 0% 02-Nov-24
30-Dec-250
ANNEX.1.1 Site Preparation 5 5 0% 02-Nov-24
08-Nov-240
A1520 Moving in 5 5 0% 02-Nov-24
08-Nov-24
A1530 Site Clearing andd Grubbing 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.2 Earthworks 5 5 0% 02-Nov-24
08-Nov-240
A1540 Excavation for Foundation & Wall Footing 5 5 0% 02-Nov-24
08-Nov-24
A1570 Backfilling and Compaction 5 5 0% 02-Nov-24
08-Nov-24
A1810 Excavation for Septic Tank & Catch Basins 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.3 Reinforcement Steelworks 5 5 0% 02-Nov-24
08-Nov-240
A1580 Steelworks for Footing 5 5 0% 02-Nov-24
08-Nov-24
A1590 Steelworks for Wall Footing 5 5 0% 02-Nov-24
08-Nov-24
A1600 Steelworks for Column 5 5 0% 02-Nov-24
08-Nov-24
A1610 Steelworks for Grade Beam 5 5 0% 02-Nov-24
08-Nov-24
A1611 Steelworks for Intermediate Beam 5 5 0% 02-Nov-24
08-Nov-24
A1620 Steelworks for Ground Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1630 Steelworks for 2nd Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1640 Steelworks for 3rd Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1650 Steelworks for 4th Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1660 Steelworks for Roof Beam 5 5 0% 02-Nov-24
08-Nov-24
A1820 Steelworks for Septic Tank & Catch Basins 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.4 Formworks 5 5 0% 02-Nov-24
08-Nov-240
A1670 Formworks for Footings 5 5 0% 02-Nov-24
08-Nov-24
A1680 Formworks for Wall Footings 5 5 0% 02-Nov-24
08-Nov-24
A1690 Formworks for Columns 5 5 0% 02-Nov-24
08-Nov-24
A1700 Formworks for Beams 5 5 0% 02-Nov-24
08-Nov-24
A1710 Scaffoldings 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.5 Concrete Works 5 5 0% 02-Nov-24
08-Nov-240
A1720 Concrete Works for Footing 5 5 0% 02-Nov-24
08-Nov-24
A1730 Concrete Works for Column 5 5 0% 02-Nov-24
08-Nov-24
A1740 Concrete Works for Lean Concrete 5 5 0% 02-Nov-24
08-Nov-24
A1750 Concrete Works for Grade Beam 5 5 0% 02-Nov-24
08-Nov-24
A1751 Concrete Works for Intermediate Beam 5 5 0% 02-Nov-24
08-Nov-24
A1760 Concrete Works for Ground Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1770 Concrete Works for 2nd Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1780 Concrete Works for 3rd Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1790 Concrete Works for 4th Floor Slab 5 5 0% 02-Nov-24
08-Nov-24
A1800 Concrete Works for Roof Beam 5 5 0% 02-Nov-24
08-Nov-24
A1840 Concrete Works for Septic Vault 5 5 0% 02-Nov-24
08-Nov-24
A1850 Concrete Works for Catch Basins 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.6 Masonry Works 5 5 0% 02-Nov-24
08-Nov-240
A1830 Masonry Works for Exterior Walls 5 5 0% 02-Nov-24
08-Nov-24
A1860 Masonry Works for Interior Walls 5 5 0% 02-Nov-24
08-Nov-24
A1870 Masonry Works for Septic Vault 5 5 0% 02-Nov-24
08-Nov-24
A1880 Masonry Works for Catch Basins 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.7 Roofing Works 5 5 0% 02-Nov-24
08-Nov-240
A1920 Roof Framing Works 5 5 0% 02-Nov-24
08-Nov-24
A1930 Roof Framing Works 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.8 Elevator Shaft and Stairs Construction 197 197 0% 02-Nov-24
05-Aug-250
A1120 Pit Excavation & Foundation 10 10 0% 25-Jun-25*
08-Jul-25
A1130 Shaft Construction 10 10 0% 25-Jun-25*
08-Jul-25
A1140 Steelworks for Stairs 20 20 0% 09-Jul-25*05-Aug-25
A1890 Concrete Works for Stairs 5 5 0% 02-Nov-24
08-Nov-24
A1900 Masonry Works for Stairs 5 5 0% 02-Nov-24
08-Nov-24
A1910 Masonry Works for Elevator Walls 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.9 Installation of MEPF Systems 232 232 0% 02-Nov-24
23-Sep-250
A1150 HVAC Ducting 15 15 0% 06-Aug-25*
26-Aug-25
A1160 Electrical Wiring & Conduits 20 20 0% 27-Aug-25*
23-Sep-25
A1170 Plumbing Pipes & Fixtures 15 15 0% 27-Aug-25*
16-Sep-25
A1180 Fire Safety Systems 10 10 0% 27-Aug-25*
09-Sep-25
A1200 Rainwater Harvesting System 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.1.10 Interior Finishing 287 287 0% 02-Nov-24
09-Dec-250
A1189 Doors and Windows Installation 10 10 0% 12-Nov-25*
25-Nov-25
A1190 Railings and Handrails Installation 5 5 0% 02-Nov-24
08-Nov-24
Activity ID Activity Name Original Duration Remaining Schedule Start Finish Total
Duration %
Complete Float
A1191 Tile Works 15 15 0% 24-Sep-25*
14-Oct-25
A1192 Painting Works 20 20 0% 15-Oct-25*
11-Nov-25
A1220 Fixtures & Fittings 20 20 0% 12-Nov-25*
09-Dec-25
ANNEX.1.11 Commissioning 302 302 0% 02-Nov-24
30-Dec-250
A1230 System Testing 10 10 0% 10-Dec-25*
23-Dec-25
A1240 Elevator Testing 5 5 0% 10-Dec-25*
16-Dec-25
A1250 Final Inspections 5 5 0% 24-Dec-25*
30-Dec-25
A1550 Moving out 5 5 0% 02-Nov-24
08-Nov-24
A1560 Handover 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.2 OPERATIONAL PHASE 325 325 0% 04-Nov-24
30-Jan-260
ANNEX.2.1 Utilities 5 5 0% 05-Jan-2609-Jan-260
A1260 Utility Management 5 5 0% 05-Jan-26*
09-Jan-26
ANNEX.2.2 Cleaning and Custodial Services 10 10 0% 19-Jan-2630-Jan-260
A1270 Daily Cleaning 5 5 0% 19-Jan-26*
23-Jan-26
A1280 Waste Collection & Disposal 5 5 0% 26-Jan-26*
30-Jan-26
ANNEX.2.3 Elevator Operation 1 1 0% 04-Nov-24
04-Nov-240
A1290 Elevator Operation 1 1 0% 04-Nov-24
04-Nov-24
ANNEX.3 MAINTENANCE PHASE 5 5 0% 02-Nov-24
08-Nov-240
ANNEX.3.1 Routine Inspections 3 3 0% 04-Nov-24
06-Nov-240
A1300 Monthly Visual Inspections 1 1 0% 04-Nov-24
04-Nov-24
A1310 Quarterly System Testing 3 3 0% 04-Nov-24
06-Nov-24
ANNEX.3.2 HVAC System Maintenance 5 5 0% 02-Nov-24
08-Nov-240
A1320 Filter Replacement 5 5 0% 02-Nov-24
08-Nov-24
A1330 Duct Cleaning 5 5 0% 02-Nov-24
08-Nov-24
A1340 Cooling/Heating Maintenance 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.3.3 Elevator Maintenance 5 5 0% 02-Nov-24
08-Nov-240
A1350 Monthly Safety Checks 5 5 0% 02-Nov-24
08-Nov-24
A1360 Annual Inspection 5 5 0% 02-Nov-24
08-Nov-24
A1370 Component Lubrication 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.3.4 Plumbing and Electrical Maintenance 5 5 0% 02-Nov-24
08-Nov-240
A1380 Pipe Inspections 5 5 0% 02-Nov-24
08-Nov-24
A1390 Electrical Panel Maintenance 5 5 0% 02-Nov-24
08-Nov-24
A1400 Lighting Replacement 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.4 REPAIR & REPLACEMENT PHASE 15 15 0% 02-Nov-24
22-Nov-240
ANNEX.4.1 Major Repairs 15 15 0% 04-Nov-24
22-Nov-240
A1410 Roof Repair/Replacements 15 15 0% 04-Nov-24
22-Nov-24
A1420 Facade Repairs 15 15 0% 04-Nov-24
22-Nov-24
ANNEX.4.2 System Replacements 15 15 0% 02-Nov-24
22-Nov-240
A1430 Elevator System Replacement 15 15 0% 04-Nov-24
22-Nov-24
A1440 HVAC System Replacement 10 10 0% 04-Nov-24
15-Nov-24
A1450 Electrical & Plumbing Upgrade 5 5 0% 02-Nov-24
08-Nov-24
ANNEX.4.3 Interior Refurbishments 10 10 0% 04-Nov-24
15-Nov-240
A1460 Flooring Replacement 10 10 0% 04-Nov-24
15-Nov-24
A1470 Interior Painting 10 10 0% 04-Nov-24
15-Nov-24
ANNEX.5 END-OF-LIFE (DISPOSAL) PHASE 15 15 0% 02-Nov-24
22-Nov-240
ANNEX.5.1 Demolition & Site Clearing 15 15 0% 02-Nov-24
22-Nov-240
A1480 Pre-Demolition Inspection 5 5 0% 02-Nov-24
08-Nov-24
A1490 Structural Demolition 15 15 0% 04-Nov-24
22-Nov-24
ANNEX.5.2 Salvage or Recycling 7 7 0% 04-Nov-24
12-Nov-240
A1500 Material Sorting & Salvage 7 7 0% 04-Nov-24
12-Nov-24
ANNEX.5.3 Site Restoration 5 5 0% 02-Nov-24
08-Nov-240
A1510 Site Cleanup & Restoration 5 5 0% 02-Nov-24
08-Nov-24