017 DLT 5190.4-2004 The Code of Construction Part 4 Chemistry Fo
017 DLT 5190.4-2004 The Code of Construction Part 4 Chemistry Fo
100
P 61
Registration No.: 1349-2004
P DL/T 5190.4-2004
Substitute DLJ 58-1981
This code is written in Chinese and English. The Chinese text shall be taken as the ruling one
in the event of any inconsistency between the Chinese text and the English text.
~
I
-~-------- - -
Contents
Preface 11
I Scope I
2 Normative Cited Documents 2
3 General 3
4 Raw Water Pretreatment 6
5 Boiler Make-up Water Treatment 9
6 Membrane Treatment Facilities IJ
7 Condensation Water Treatment. 13
8 Sample and Dosing System 14
9 Circulated Cooling Water Treatment 15
10 Tank 17
11 Rotary Machine 18
12 Special Pipes and Valves 22
13 Anti-corrosion Construction Technologies 25
14 Startup and Adjustment of Water Treatment System 28
15 Hydrogen-producing Equipment 32
16 Chemical Cleaning of Heating Equipment and System 35
17 Chemical Supervision during Startup and Test Running of Heating Equipments 36
18 Acceptance of Work 40
Appendix A(Normative AppendixtFiltering Material 41
Preface
This code is revised and compiled on the basis of first edition DLJ 58-1981 according to
assignment of Item 74 in electricity [2000] No. 22 document "Notice on Confirming Standard
System of Electricity Industry in 1999 and Modifying Planning Project" issued by State Economic
and Trade Commission.
This code was firstly issued in October 91h of 1981, and this edition is its first revision.
More than 20 years has been passed since the first issue and implement of this code, and
during this period, Chinese electricity industry has been advancing rapidly: generating sets with
large capacity and high parameters have been placed in service one after another, chemical water
treatment for power plant and hydrogen-producing equipments have been significantly changed,
many new equipments and new processes have been adopted, and some traditional equipments
and processed have been improved and renovated. During this period, many achievements and
construction experiences have been obtained by electricity construction workers and researchers,
which provide important scientific foundations for the revision and compilation of this code.
Main revised contents are as follow:
Adding preface;
Adding range and normative cited documents;
Deleting Chapter 4 "Pretreatment of Condensation Water" in original edition;
Adding section "Condensation Water Treatment";
Adding section "Membrane Treatment Equipments";
Adding section "Sample and Dosing System";
Adding section "Heating Equipment and System Chemical Cleaning";
Adding contents of scale inhibition, corrosion mitigation and make-up water
treatment in section "Circulated Cooling Water";
Renovating contents of "Water and Steam Quality Standard for Newly-built Set
Test Run";
Deleting section "Leakage Test of Equipment System" in initial edition, and
merging its contents into "General";
Deleting most contents in Appendix of initial edition, and only holing the part of
filtration materials;
DLJ 58-1981 wi II be substituted by this code after its implement.
This code is advanced by China Electricity Council (CEC).
This code is administrated and explained by Standardization Technical Committee of Power
Plants Chemistry in Electricity Industry.
Chief drafting units: North China Electric Power Research Institute, Henan Electric Power
Construction and Debugging Institute and Henan NO.1 Electric Power Construction Company.
Major Drafter: Lao Qinan, Wei Zhaohui, Sun Zhaoyong, Mo Ni, Van Liubao
II
1 Scope
Clauses in the following documents have become clauses of this code through citation of
this code. For those cited documents with date, their following revised parts or revisions are all
unsuitable for this code. However, studies on the application of the latest editions of these
documents are encouraged by signatory parties to this code. The latest editions of those cited
documents without date are all suitable for this code.
GB 2894 Safety Signs
GB 4962 Technical Safety Regulation for Gaseous Hydrogen Use
GB 8978 Integrated Wastewater Discharge Standard
GB50177 Design Code for Hydrogen and Oxygen Station
GB/T 12145 Quality Criterion of Water and Steam for Generating Unit and Steam Power
Equipment
DL414 Technical Guidelines for Environmental Protection in Thermal Power Plant
OLiT 543 Quality Inspection Standard for Water Treatment Equipments Used in Power
Plant
DLlT665 Acceptance Standard of Water and Steam Integrated Sampling and On-line
Analyzing Unit
DLiT 794 Chemical Cleaning Guide for Steam Power Plant
DLiT 855 Code for Maintenance and Safekeeping of Thermal Power Equipment in
Electric Power Construction
OLiT 5007 Code of Erection and Acceptance of Electric Power Construction (welding
section)
DL 5009.1 Safety Operation in Power Engineering Construction (Thermal Power Plant
Part)
DLiT 50 I I Code of Erection and Acceptance of Electric Power Construction (Section of
steam turbine set)
OLiT 5031 Code of Erection and Acceptance of Electric Power Construction (pi ping section)
DLiT 5047 Code of Erection and Acceptance of Electric Power Construction (Section of
steam boiler set)
SO 233 Guideline for Lay-up of Thermal Power Equipment in Thermal Power Plants
SDJ69 The Code of Erection and Acceptance of Electric Power Construction (Section
of architectural engineering)
Workman Protection (87) No. 36 Electrical Safety Regulation for Explosion Hazard Area of
People's Republic of China (Trial)
Pressure Vessels Safety and Technical Supervision Regulation Issued by China State Bureau
of Quality and Technical Supervision (1999) Boiler No. 154
2
3 General
3
3.3 Cooperation Requirements on Civil Project
3.3.1 Before installation and emplacement of equipments, construction unit shall be jointly with
other parties concerned, such as installation, civil construction and supervision, to check the
following items:
a) Geometrical dimensions, corresponding positions and heights of equipment foundation
shall comply with design requirements;
b) Dimensions and positions of reinforced concrete beam and column, as well as built-in
fitting and reserved holes on equipments foundation shall comply with design requirements;
c) Underlayer shall be set for the foundation of flat bottom water tank, the center of which
shall lean out and be 15mm~20mm higher than the edge.
3.3.2 Reinforced concrete structures related to water treatment shall be checked and accepted
based on regulations of design drawings. Reinforced concrete structures and buildings with
anti-corrosive requirements shall be checked and accepted according to regulations on
anti-corrosive project issued by construction department.
3.3.3 Anti-corrosive coating made in construction site shall be checked by construction unit
layer by later; such bugs as crack, blowups and holes must be eliminated immediately.
Anti-corrosive coating shall be checked and accepted according to regulations on anti-corrosive
project issued by construction department after its construction is finished.
3.3.4 Water filling test shall be carried out for reinforced concrete containers.
3.3.5 Before adjustment and trial running of water treatment equipments, the following work
shall be finished by civil construction:
a) Constructions of indoor and outdoor anti-corrosive floor and channels for water treatment
room as well as neutralization tank shall be finished and passed acceptance. Channels for drainage
and deslagging shall be unblocked with all-ready cover boards, the surface of which shall be flush
with floor;
b) Indoor painting and coating for water treatment room, as well as constructions of floor,
platform, ladder, doors and windows shall be finished according to design requirements;
c) Constructions for facilities in laboratory, such as water supply, drainage, heating,
ventilation, air-conditioning, illumination, electric source and test-bed shall be finished according
to design requirements;
d) Constructions for structures of acid and alkali storage as well as anti-corrosive and
ventilation facilities shall be finished and passed acceptance.
3.3.6 Before adjustment and trial running of hydrogen-producing equipments, the following
work shall be finished by civil construction:
a) Constructions for wan, lightning rod and earth mat shall be finished according to design
requirements and passed acceptance.
b) Constructions for facilities in hydrogen-producing station, such as water supply, drainage,
heating, ventilation, illumination and electric source shall be finished according to design
requirements and passed acceptance.
4
be carried Ollt according to relevant regulations in DUT 503 I.
3.4.2 Pressure for hydraulic test of rubber-line, fiberglass reinforced plastic, plastic and other
nonmetal pipes are equal to their rated work pressure. For equipments and pipes with different
rated pressure installed in the same system, hydraulic pressure test for system shall be carried out
under the lowest rated pressure among equipments and pipes.
3.4.3 Desalting water shall be adopted for hydraulic pressure test of stain Jess steel pipe.
3.4.4 Element working pressure hydraulic test shall be carried out for ion exchanger and ion
regenerator in water treatment system to ensure tightness of valves connected to the ion exchanger
or generator after system installation is finished.
3.4.5 Hydraulic pressure test shall be carried out according to relevant regulations of Boiler No.
154 Documents issued by China State Bureau of Quality and Technical Supervision (1999) for
pressure equipments and containers. For those equipments and containers with certification to
prove them passing hydraulic pressure test before leaving factory, this test can be exempted.
Hydraulic pressure test for tightness on connected pipelines shall also be carried out for these
certificated equipments and containers.
3.4.6 Inleakage shall be ensured for open containers by water filling test and welding line by oil
penetration test.
3.4.7 Water filling test shall be carried out for equipment and pontoon in container to ensure
their inleakage.
3.4.8 Test for containers and equipments of cement structure shall be carried out according to
relevant regulations in SDJ69.
3.4.9 Water filling test, water penetration test, oil penetration test or hydraulic pressure test for
each equipment, container and system shall be carried out before painting and heat preservation.
Tests for equipments and containers with coating layer shall be carried out before construction of
anti-corrosive coating.
5
4 Raw Water Pretreatment
6
c) Internal horizontal and vertical steady flow plates shall be welded firmly, pore size and
distance between pores shall comply with drawing regulations, and pore edge shall be smooth and
free of burr.
d) The cone of influent nozzle shall be processed strictly in accordance with design
requirements, inner surface of which shall be bright and clean. Nozzle and sleeve shall be installed
levelly. The two nozzles shall be paralleled to each other, and tangent to the cone of clarifier.
e) Link bearing of inner and outer tubes shall be welded firmly. Manhole of inner tube and
cone shall be watertight.
f) Upper and nether edges of sludge feeding hole in the same layer of inner lube shall be
positioned in the same level, and pore edge shall be smooth and free of bun'.
g) Water shall be filled into inner tube and then outer tube in water filling test for clarifier.
not exceed 0.5% of collecting channel diameter, and ovality of collecting channel and hydraucone
in throat of reaction chamber shall not exceed 1%. Velticality and levelness of reaction chamber
7
be constructed according to design drawings, the deviation of which shall not exceed ± IOmm.
4.4.2 Breakwater below the cover of filter tank shall be kept horizontally, the deviation of which
shall not exceed ±2mm.
4.4.3 Quarter bend shall not be adopted for the installation of siphon auxiliary pipe. Pipe nozzle
shall not be extended into elbow pipe during welding. Orifice of gas suction pipe on the top of
siphon elbow pipe shall be inserted into siphon pipe for approximately 10mm-20mm.
4.4.4 Chute pipe of 15° used for pressure rinsing shall be constructed accord ing to design
drawings, with angle permissible variation of ±2°. Orifice of chute pipe shall be close to gas
suction pipe as much as possible; meanwhile, these two pipes shall be both installed in the same
side of siphon auxiliary pipe.
4.4.5 Siphon pipe and its jiquidometer, siphon auxiliary pipe, gas suction pipe, and siphon
breakage pipe shall all be watel1ight.
4.5 Filter
4.5.1 Mechanical filter shall comply with the following requirements:
a) Filter shall be installed verticaJly with shell with vertical errors of shell no higher than
0.25% of its height. After shell spotting, stabilizer, sizing blocks and foundation embedded parts
shall be welded firmly before back grouting.
b) Central lines of branch pipe and main pipe shall be mutually perpendicular for distribution
system, drainage system and air distribution system of fi Iter. The horizontal deviation of branch
pipe shall not exceed ±2mm.
c) Central line of release cap seat shall be perpendicular to branch pipe level. The height of
release cap seat shall be consistent with allowable deviations of ±3mm.
d) For filter with distribution system of branch-and-main-pipe type, distribution holes shall
be smooth and free of burr. Mesh used as branch pipe sleeve shall comply with design
requirements and be fastened firmly.
e) For filter with air scrubbing device, upper level of bottom blanket shall be flush with the
top of air-blowing hole or water cap.
t) For filter with anti-corrosive layer set in its shell, the quality of anti-corrosive layer shall
be inspected before materials filling.
g) For filter used in reverse osmosis system, if activated carbon or other brittle filter
materials is fi lied into fi Iter, its bottom blanket shall comply with requirements of Appendix A in this
code.
4.5.2 Fibrous filter shall comply with the following requirements:
a) All blowing pipes shall lead directly to blowing channel independently.
b) The installation of Roots blower shall be carried out according to relevant regulations in
DUT 5047.
c) Inverse U-type elbow and exhaust damper shall be set for blast pipe of Roots blower. The
apex of communicating pipe between inverse U-type elbow and fibrous fi Iter shall be higher than
the apex of fibrous filter.
8
5 Boiler Make-up Water Treatment
9
be checked and calibrated according to the following clauses:
a) Assembling allowable deviations of catching devices and drainage (such as inlet damper,
quaquversal grid plate, pile-type water cap, etc.) are as follow: its deviation with central line of
tunnel body shall be lower than 5mm, and horizontal deviation shall not exceed ±4mm.
b) For catching devices and drainage of branch-and-main-pipe type, central line of branch
pipes shall be perpendicular to central line of main pipe. Their levelness and verticality shall be
lower than 4mm/m and 3mm/m, respectively. Distance deviations between two adjacent branch
pipes and any two branch pipes shall not exceed ±2mm and ±4mm, respectively.
c) Regeneration devices and medium drainage shall be installed horizontally. Eyelet
directions of regeneration pipe and medium drainage pipe shall be in accordance with
manufacturing drawings. Nozzle of actinoid regeneration pipe shall upright, and no blocking
phenomenon appears by water test.
5.2.2 Inert resin, plastic bailor resin of the same type can be adopted for resin compaction layer
of up-flow regeneration ion exchanger, the thickness of which shall comply with design
regulations. Charged thickness of those without design regulations shall be 200mm~250mm.
Upper limit shall be taken for ion exchanger with diameter bigger than 2500mm.
5.2.3 For ion exchanger with air scrubbing device, bottom blanket level shall be flush with the
top of air-blowing hole or water cap.
5.2.4 Large shim shall be adopted for ion exchanger with bolt-fastening fittings to prevent the
damage of anti-corrosive layer.
5.2.5 Water quality for charged resin: clarified tiltering water used for cation bed, effluent of
cation bed used for anion bed, and desalting water used for mixed ion.
5.2.6 Trademark, physical chemical propelties and the proportion between anion and cation
exchanger resin of the resin charged in mixed bed shall comply with design requirements.
10
6 Membrane Treatment Facilities
II
manufactory before installed into system.
6.2.2 Pressure vessel shell shall be stored indoor and positioned horizontally, and meddle
hang-up is forbidden. Impact damage shall be prevented during construction.
6.2.3 Soundness of parts, such as fresh water pipe, membrane sheet, baffle and brine seal ring,
shall be inspected before the assembly of membrane module. Pressure vessel shell shall be
installed in prescribed order of manufactory after vessel soundness and installation direction of
brine seal ring are confirmed. Assembly environment shall satisfy requirements of manufactory,
and no leakage shall be found after installed module filled with water.
6.2.4 For multicell reverse osmosis equipments, allowable deviations of geometrical dimensions
for membrane module frame on foundation and membrane module on frame shall be ±5mm and
±3mm, respectively.
6.2.5 Polytetrafiuoroethylene shim shall be applied for fiange between high-pressure pump and
membrane module.
6.2.6 Internal wall of pipe between security filter and membrane module shall be kept clean, and
chemical cleaning can be adopted if necessary.
6.2.7 Temperature and pressure protective devices for water supply system shall be sensitive and
reliable.
6.2.8 Chemical feeder and on-line chemical meters in reverse osmosis system shall be installed
and inspected before trial running, which shall be able to put into operation at any moment.
6.2.9 Infiuent water quality shall comply with regulations of manufactory for reverse osmosis
equipments.
12
7 Condensation Water Treatment
13
8 Sample and Dosing System
8.1 The installation of water and steam analysis and sampling device shall comply with the
following requirements:
a) Installation position of sampling device, valve, materials of connecting pipe and
drainage system shall comply with design requirements.
b) Secondary valve installation shall be firm and easy to operate and maintain; pressure,
temperature and flow of measured medium entering into water and steam analysis and sampling
device shall comply with manufactory regulations.
e) Allowable deviation range for hole diameter at sampling point and sample pipe diameter
shall be in the range of +0.5mm~+ 1.0mm, and hole edge shall be smooth and free of burr. Weld
junction shall comply with regulations in OUT 5007. Insert depth of sample pipe shall be 1/2 of
pipe diameter with sample connection back to medium flow direction.
d) Sampling pipe line, cooling system, depressurized system and sampling valve shall all
be watertight and able to put into operation normally.
e) Sampling and analysis device shall be checked and accepted according to DUT 665.
8.2 The location of sampling point shall comply with design requirements. Sample point for
low-pressure water supply before dosing, if not prescribed, shall be located at the position about
Im below outlet of deaerator. [nlet pipe of dosing point shall be 0.5m lower than the sample point.
8.3 Specs and materials of sample pipe shall comply with design requirements, the inside of
which shall be clean and straightway. Proper minimum distance shall be chosen for pipe and cable
laying with arrangement like smooth vertical and horizontal strokes. Mechanical damage shall be
avoided for pipe processing. Pipe arrangement shall be kept away from place with severe shake,
moisture or corrosive medium. Rigid bracket shall be set in the front of door firstly. Radian of pipe
and cable laying in row shall be consistent, the outer surface of which shall be no crack, sagging
and overroasting phenomenon after bent. There shall be obvious deviation of pipe in the same
diameter. Weld junction shall comply with regulations in DUT 5007. Unblockage and tightness
test shall be carried out after pipe construction.
8.4 The installation of dosing system shall comply with the following requirements:
a) Manufacturing quality of box and channel shall comply with requirements of Clause 10.1
in this code.
b) Materials of dosing pipe shall comply with design requirements, the inside of which shall
be clean and straightway. Outer surface of the pipe shall be no crack, sagging and overroasting
phenomenon after bent. There shall be obvious deviation of pipe in the same diameter. Weld
junction shall comply with regulations in OUT 5007. Tightness hydraulic pressure test shall be
carried out after construction is finished. Test method and notice shall be executed according to
regulations in OUT 503 1.
e) Installation and maintenance of feeding pump shall comply with requirements of Clause
11.2.3.
d) Liquidometer of box or channel shall be installed vertically in the position easy to observe,
with clear indication and solid protection cover.
14
9 Circulated Cooling Water Treatment
15
9.1.3.4 Aerator and automatic alarm leakage detecting device shall be settled in the chlorine
dioxide feeding room. Anti-corrosion measures shall be taken for floor according to design
requirements.
9.1.3.5 A great variety of drug blowing pipe shall be jointed respectively. They mustn't be
arranged in the same pipe.
9.1.4 Corresponding anti-corrosion measures shall be taken for other feeding equipments and
pipes of chlorization chemicals.
16
10 Tank
10.1 Manufacturing quality of tank shall comply with the following requirements:
a) Tank shall be strictly processed and manufactured following design with level tank wall
(bottom);
b) Such reinforcement as ribbed bar shall be welded firmly;
c) For tank with anti-corrosive layer, the layer shall be intact and pass inspection;
d) Its accessories shall be all ready, and the quality of which shall comply with relevant
operation standards;
e) It shall be eligible in water filling test (concrete product shall be tested according to code
SDJ 69, and metal members shall be of no leakage in 24 hours after water filling).
10.2 Anti-corrosion layer for internal wall shall be constructed after electric welding of all pipes
and accessories (meter supports, water gage, fastening iron, etc.) is finished and accepted.
10.3 For flat bottom tank mounted on foundation, the contact between tank bottom and
foundation shall be even and tight. Antirust painting shall be brushed on outer surface of tank
bottom before tank emplacement. Bedding shall be laid on foundation according to design
requirements. Water filling test shall be carried out after water tank emplacement, and relevant
pipes shall be connected after the stability of foundation settlement.
10.4 Arc of horizontal tank or abutment shall be identical and evenly contact with tank wall, and
there shall be no obvious gap between them.
10.5 Enough flow area shall be left for breathing pipe of water tank, and the end of overflow
pipe shall not be extended under water surface of drain.
10.6 Floating roof tanks shall comply with the following requirements:
a) Floating roof can only be mounted after internal anti-corrosion layer construction is
finished. 24-hour leakage test shall be carried out for floating roof.
b) Tightness of rubber bladder shall be inspected before installation for soft floating roof
tank. The connection between upper port of floating roof and mounting ring shall be watertight,
and these two parts shall be kept in the same level with deviation not exceeding ±O.2% of water
tank diameter.
c) Ovality of tunnel body and floating roof shall be ±O.J% for hard floating roof tank, and
concentricity between guide tube of floating roof and water tank shall not exceed ± IOmm.
Verticality between tunnel body and guide tube shall be lower than 0 15% of tank height. Top
circle bearing seal of floating roof shall be watertight and able to freely up-and-dovvn fluctuate in
the tank.
10.7 Mesh of proper materials shall be set in outlet and blowing outlet for tank sealed with
plastic covered ball
10.8 Water gage shall be installed vertically in the position easy to observe with clear indication,
and solid protection cover shall be mounted. Glass tube water meter mustn't be adopted for
outdoor water tank in extremely cold areas.
17
11 Rotary Machine
18
surface shall be applied as measurement benchmark for centering of pump body.
b) Safety valve in fluids conveyance system shall be checked by disassembly, and operating
pressure shall be adjusted according to design regulations. Operating pressure, if not prescribed,
shall be adjusted to 1.25 times of working pressure.
c) For reciprocating pump with working medium directly contacting with piston (plunger),
quick detachable sieve shall be mounted at entry according to design drawings. Sieve of 50 Mesh
-100 Mesh can be mounted, if no design requirement refers to sieve. Effective area of sieve shall
be no less than three times of sectional area of entry pump. Materials resistant to working medium
corrosion shall be adopted.
d) The following clearance value shall be measured and recorded during installation:
1) Drunkenness clearance between worm wheel and worm in gear box.
2) Clearance between plunger and lining of plunger.
e) Installation requirements for cylinder body of diaphragm pump are as follow:
1) All bolts in front and back cylinder ends shall be screwed down evenly. Diaphragm shall
not be deformed owing to extrusion after installation.
2) Capping for filling materials shall not be over-tight or loose.
3) Anti-corrosion materials shall be wrapped around connections of all screw threads of
feeding valve and drainage valve for seal during installation.
4) Hydraulic fluid shall be injected according to regulations of equipment technical
document, and there shall be no vapor in hydraulic cavity.
f) Test running of reciprocating pump:
1) It shall be carried out in the following order: no-load running shall be no less than 15
minutes; after functioning, the pump shall be operated under pressure in the order of 1/4, 1/2,3/4
of working pressure for at least 0.5 hours, and continuous operation shall be no less than 4 hours.
Record flow changes under each pressure.
2) After test running, reciprocating pump shall comply with the following requirements:
suction valve and drainage valve shall be available for use; safety valve, oil make-up valve and
exhaust valve of diaphragm pump shall be functioning, sensitive and reliable.
3) Diaphragm with crack shall be exchanged during test running, and diaphragm made of
butadiene-acrylonitrile rubber shall be adopted for concentrated acid medium.
4) Parts of safety valve, oil make-up valve and exhaust valve shall be manufactured by
anti-corrosion materials.
11.2.4 Self-priming pump shall comply with the following requirements:
a) Quick detachable sieve shall be mounted at entry according to design drawings. Sieve
without design requirement shall be selected and installed according to relevant regulations of
Clause 11.2.3.
b) Pump installation shall be carried out according to relevant regulations of Clause 11.2.1
and Clause 11.2.2.
c) There shall be some water sources near to self-priming pump, which is convenient for
water fi 11 ing of pump startup.
d) Pressure gauge shall be checked before startup. The function of inlet valve and outlet
valve shall also be inspected.
e) fnlet and outlet valve shall be opened before startup, and J min-2min is required for pump
startup when pump body is filled with water. Then gradually increase pressure indicated by
19
pressure gauge, and check operation conditions of pump.
20
11.4 Agitator
ll.4.1 After the installation of agitator impeller, there shall not be obvious bend and deformation
for guide bar and impeller, respectively. ldle running of agitator shall be flexible and free. Intense
vibration is forbidden during loaded running.
11.4.2 Quality of hose for lime slurry agitator shall comply with design requirements. Suction
pipe port shall be 250mm~300mm higher than conical bottom of agitator when floating drum
located at the lowest level.
11.4.3 Floating drum shall be watertight in 24-hour water filling test. Floating drum shall have
enough weight to guarantee emersed part accounting for 50% of drum body after dipped in water.
21
12 Special Pipes and Valves
22
a) During pipe construction:
1) Pipe shall be welded by qualified welder to guarantee welding quality.
2) Flange connection shall be watertight, and protective cover or baffle shall be adopted for
valve and flange of pipe for concentrated acid or alkali adjacent to sidewalk.
3) Materials of flange shim shall be selected according to design regulations; rubber
asbestos plate and acid-resistant (alkali-resistant) rubber pad can be employed for dilute sulfuric
acid pipe and hydrochloric acid (alkali liquor) pipe, respectively.
b) Exhaust pipe of hydrochloric acid tank shall be extended to outdoor through acid mist
absorber. Outlets of discharging pipe and overflow pipe shall be sealed by water sealed packing,
and connected to underground drain with anti-corrosion treatment.
c) Repaired pipe fittings lined with rubber or plastic is forbidden for concentrated
hydrochloric acid system.
d) Long tabulation shall be adopted for concentrated sulfuric acid pipe to decrease
connections.
e) Brass or aluminum material mustn't be used for fittings or valve in alkali liquor pipe.
Paint is also forbidden for internal wall of alkali liquor container and pipe.
12.2.3 Installation of plastic pipe shall comply with the following regulations:
a) It shall be carried out according to material characters, technical regulations and welding
regulations.
b) Quality of plastic pipe shall comply with the following requirements:
1) Pipe wall shall be free of exfoliation, crack and obvious sags and crests.
2) Ovality of plastic pipe with internal diameter below 150mm shall not exceed 5%.
3) Thickness error of plastic pipe with wall thickness below 30mm shall not exceed - 15%.
c) Rubber lagging box or bayonet joint shall be adopted following design for permanent
connections of pipe. Aboral welding shall be employed for gravity flow pipe.
d) Quality requirements of plastic welding rod and quality inspection of welding line after
welding shall be executed according to relevant regulations in Section 13.3.
e) Expansion joint shall be mounted for each 30 meters in straight pipe section. Expansion
joint shall be straight and free of distortion, the surface of which shall be free of such faults as
crack, bubble and deterioration. Ovality of elbow part shall be below 6%.
l) When the method of bayonet joint with binder is employed for connection of ABS
engineering plastic pipe, the pipe shall be immediately insel1ed without holdup and torsion after
processed, chamfered, snagged and coated with binder according to process requirements, and
then it can be used after completely solidification with at least 24-hour standing.
12.2.4 Installation of glass reinforced plastic pipe shall comply with the following regulations:
a) Appearance inspection shall be carried out for each fitting before installation, and any
fault, such as exfoliation, uneven thickness or bubble, is forbidden.
b) Binder shall be prepared according to manufactory requirement or design requirement.
Lab-scale test shall be made according to local climate conditions and material characters before
binding, and construction can only be carried our when test results comply with relevant quality
requirements. Overdue or depleted chemicals mustn't be used.
c) Binder on connections shall be even and smooth with height flush with pipe wall after
binding. Binding shall be close-grained, and its surface shall be free of air hole and rugosity.
d) Sampling pipe or meter pipe shall not be directly connected with pipe; sampling (or meter)
23
pipe flange or seat shall be mounted at flange connections if sampling (or meter) pipe must be
connected.
12.2.5 Installation of lining pipe (pipe lined with rubber or plastic, etc.) shall comply with the
following regulations:
a) All tabulations and pipe fittings shall be inspected before assembly:
1) Appearance quality and metal binding conditions shall be judged by visual inspection or
tightly knocking by wood mallet with weight below O.25kg.
2) Its tightness shall be completely inspected by creepage monitor, and creepage must be
avoided. Voltage for creepage test shall be larger than ISkV with probe movement speed of
3m/min-6m/min. Long-term stay of probe in rubber layer shall be avoided, and it shall be broken
immediately when disusing to prevent sparking through rubber layer.
3) Flange interface shall be smooth with tight joint and no radial channel. Rough flanging
of large-diameter pipe flange shall be polished.
b) Solvent in which rubber can soluble shall not be applied for the treatment of stained pipe
and pipe fittings lined with rubber.
c) Electric welding or drilling is forbidden on installed pipe lined with rubber.
d) Equipments and pipe fittings lined with hard rubber shall be stored in environment with
temperature above 5'C and kept away from long-term exposure under the sun.
24
13 Anti-corrosion Construction Technologies
25
mixed optionally. Overdue materials mustn't be used.
13.2.3 Ambient temperature for construction and drying time of each layer shall be determined
according to different requirements of various paints and weather conditions.
13.2.4 During coating, water shall not be carried by painting tools, equipment surface and paints.
The layer shall be kept away from acid or alkali, dust and insolation, and smoking or lighting fires
shall be strictly forbidden. 1n addition,
13.2.5 The number and color of coatings shall be fixed according to design requirements.
Thickness of coating: primer shall be generally larger than SOlJ,m; final coating shall below 20lJ,m.
13.2.6 Thermal treatment shall be carried out according to design (or manufactory) regulations
after one coat of thermosetting resins paint to make it completely solidify.
13.2.7 Construction of glass fiber plastic.
a) For anti-corrosion layer manufactured by glass fiber plastic, such as anti-corrosion layer
for neutralization tank, ditch and floor contact with acid or alkali, its raw materials shall comply
with the following requirements:
1) Epoxy resin, furan resin, bisphenol A unsaturated polyesters resins and various curing
agents, diluting agents and filling materials shall comply with quality requirements in chemical
industry.
2) Shelf life of phenol-formaldehyde resin shall not exceed 3 months (calculated from
production date of product), and it mustn't be used when viscosity increases.
3) Acid fastness and grain size of filling materials shall be larger than 98% and less than
0.125mm, respectively.
4) Roving fillet cloth free of alkali, wax and twist, with thickness of 0.2mm~0.4mm
(0.3mm is proper in general), shall be adopted for glass cloth. Glass cloth shall be kept cool, dry,
clean and away from moisture and contamination.
b) Containers and tools for material preparation shall be anti-corrosion, clean, dry and free of
oil stain. Sizing material shall be prepared in prescribed order, which shall not be used if
gelatinization phenomenon appears during usage.
c) Manual pasting method, divided into continuous mode and intermittent mode, shall be
generally adopted for on-site lining of glass reinforced plastic. It shall be constructed according to
requirements of design indication. Those without design requirements shall be constructed
according to requirements in chemical industry.
d) Lining quality of glass reinforced plastic shall comply with the following requirements:
1) Lining layer and body surface shall be adhered tight, free of delimination, bubble, white
point, unsafe solidification and exposure of glass fiber. It can be checked by slightly knocking
with hand hammer with weight below 0.25kg, compact echo demonstrating firm coherence, and
bad binding in other conditions. Those lining layer with large-area air bubble or delimination shall
be completely removed and coated with cloth again after surface treatment. Repairing number in
the same position shall not exceed twice.
2) Glass reinforced plastic lining shall be smooth, sleek and with even color, and rubber
content mustn't be below 50% (w/w).
3) It shall pass creepage test under test voltage higher than 15kY.
4) The number of air bubble with diameter lower than 5mm shall not exceed 3 per square
meter.
5) It shall be dry, compact and smooth by solidification inspection. Complete solidification
26
can be inspected by the method below: wiping glass reinforced fiber surface with cotton dipped
with acetone, those without cotton sticking to them and cotton color not changing will be
qualified.
13.3.3 Welding rod shall be soft, straight, of the same size, and free of impurity and aging rod.
Welding rod of different diameters shall be used for weldment of different thicknesses:
a) Welding rod with diameter of 2mm shall be chosen for weldment with thickness of
2mm~Smm.
b) Welding rod with diameter of 3mm shall be chosen for weldment with thickness of
Smm~ISmm.
c) Welding rod with diameter of 3mm-4mm shall be chosen for weldment with thickness of
~16mm.
13.3.4 Welding rod and the position of welding line shall be wiped by dichloroethane or alcohol
before welding to removal oil and grease as well as dirties on surface.
13.3.5 After welding, plastic product shall be free of crack, discolouration, charring,
delamination, bubble, and salient knurl. The surface of Welding line shall clean, and welding mark
shall be arranged evenly, closely and consistently with width.
27
14 Startup and Adjustment of Water Treatment System
completed.
14.1.2 Electric, hot working, on-line chemical meter, programmed control and automatic control
equipment related with water treatment system shall be fixed and debugged. It shall be showed
14.1.3 Before startup of water treatment system, approved adjustment technica I measures for
14.1.4 Lighting and communication facilities indoors shall meet requirements of test running.
14.1.6 When water treatment system is started under environmental temperature below 5·C,
14.1.7 All pipelines and equipments shall be color code all ready according to design regulations,
14.1.8 Before startup of water treatment system, all equipments and systems shall be checked
equipment shall be tagged; regulations about operating maintenance and weaving register report
forms have been pressed completely; analytical and assay instruments and appearances shall be all
ready.
28
design regulations.
14.2.2 Adjustment of automatic valveless gravity filter
a) When watering into automatic valveless gravity filter, temporary water pipe shall be used
to reverse watering in order to soaked filter cake from bottom to top.
b) Rinsing strength, rinsing time, siphon formation time and filter operation period shall be
adjusted and measured via the adjustment of automatic valveless gravity filter. Effluent water
quality and equipment output pressure shall be up to design regulations.
14.2.3 Adjustment of mechanical filter:
a) Backflushing strength, backflushing time and operation period, misfunctioning pressure
difference between inlet and outlet, effluent water quality, and equipment output pressure of
mechanical equipment shall be adjusted and measured.
b) Backflushing strength, effluent water quality and equipment output pressure shall be up to
design requirements after adjustment test.
14.2.4 Adjustment of fine sand, activated carbon and security filter:
a) Turbidity of backflushing water for fine sand filter and activated carbon filter shall
comply with design requirements. And backflushing strength shall be controlled to prevent
carrying of filtering materials.
b) Product water of reverse osmosis shall be adopted for security filter, and backflushing
strength shall be controlled according to manufactory indication.
c) Misfunctioning pressure difference of fine sand, activated carbon and security filter shall
be controlled according to design regulations or manufactory indications. Those without concrete
regulations can refer to the following data: maximum pressure differences for fine sand, activated
carbon and security filter are 0.\ MPa, 0.042MPa and 0.176MPa, respectively. Controlling data can
al so be fixed by test running.
d) During stoppage, fine sand filter and activated carbon filter shall be operated for I h~2h
everyday and backflushed once a weak.
14.2.5 Adjustment of fibrous filter
a) Preliminary water filling startup of fibrous filter shall be carried out according to
regulations of manufactory documents.
b) Pressure difference between inlet and outlet shall be maintained at about 0.05MPa during
filter rinsing.
c) After operation adjustment, operation period shall be fixed, and effluent water quality as
well as equipment output pressure shall be up to design requirements.
14.2.6 Startup and adjustment of electrodialysis equipment.
a) Startup and adjustment of electrodialysis equipment can be carried out on the promise that
operation of raw water pretreatment equipment is stable and effluent water quality complies with
requirements.
b) Earthing of membrane stack, pipe frame, metal pipe and electrical cabinet shall be
checked and accepted. Voltage and frequency of electric source shall be fixed, and connections
between cable and polar plate bolt shall be inspected.
c) Inlet pipe and membrane stack shall be completely rinsed before startup of electrodialysis
equipment, and than direct current voltage can be applied. Electric source must be firstly shut
during stoppage, and then water can be stopped after membrane stack rinsing.
d) Influent and effluent water quality of electrodialysis equipment shall be periodically 01'
29
continuously measured.
e) Time intervals for electrode switching shall be determined according to water quality and
process operation cond itions.
t) Acid cleaning shall be used when desalting ratio decreases 5%, and disassembly cleaning
shall be employed if acid cleaning malfunctioning. Water quality and chemical impurity quality
for membrane stack rinsing shall be on the promise of not inducing ion exchanging membrane
pollution.
g) Membrane stack shall be kept wet during stoppage of electrodialysis equipment to prevent
dryness and deformation.
h) Items of adjustment test:
1) Detection of membrane stacks voltage.
2) Voltage value and effluent water quality corresponding to limited current.
3) Voltage value and effluent water quality corresponding to limited current under different
water quality conditions.
4) Desalting ratio.
S) Recovery ratio.
14.2.7 Startup and adjustment of reverse osmosis equipment.
a) All water equipments, tanks and pipes in system shall be rinsed by clean water; chemical
feeding and cleaning system shall be debugged and accepted.
b) Operation of high-pressure pump and membrane module can only be carried out on the
promise that operation of prepositive pretreatment equipment is stable and effluent water quality
complies with regulated indexes of reverse osmosis equipment manufactory.
c) When newly-mounted equipment is started, shell of pressure vessel, pipe and cleaning
system shall be cleaning up by clean water firstly, then membrane module can be installed, and
then low-pressure rinsing is adopted to make air out. High-pressure pump can only be stalted after
air is totally displaced and pipe system is free of leakage. When equipment is stopped, product
waler of reverse osmosis equipment shall be used to rinse membrane module for I Omin~20min
after the stoppage of high-pressure pump.
d) Protective measures shall be taken to prevent abrupt increasing of system internal pressure
damaging membrane module during high-pressure pump staltup and system switching. Inlet water
pressure of membrane module shall be adjusted to permissible range of design.
e) Membrane module shall be dipped in qualified water with temperature of 5·C~30·C
during short-term stoppage of reverse osmosis membrane, and it shall be operated for I h~2h
everyday and rinsed once a weak. For long-term stoppage, membrane module shall be rinsed, and
then membrane elements shall be fetched out of the shell of pressure vessel and placed into
double-layer plastic bag with protection liquor. Then fasten the plastic bags and place them in cool
room. Protection liquor concentration and conditions of membrane element shall be periodically
inspected.
t) Performance test with 48-hour continuous operation under different operation modes
(series or parallel connections) shall be carried out according to given pressure, flow rate and
temperature. Product water quality and quantity shall comply with design values. Desalting ratio
and recovery ratio shall also be calculated.
30
14.3 Adjustment of Desalting Equipment
14.3.1 Tank and pipe in regeneration system shall be flushed and qualified in tightness test.
14.3.2 Clean water suction test or flow adjustment test shall be carried out for injector or
metering pump in regeneration system, and regeneration liquor can't be fed into metering box
before qualified test.
14.3.3 Acid or alkali pretreatment of ion exchange basin before operation shall depend on
quality and manufactory of the basin.
14.3.4 Regeneration dosage shall be 1.5~2 times of designed regeneration dosage for the first
regeneration of ion exchange basin.
14.3.5 Automatic control system of desalting system shall be debugged before charging of ion
exchange basin into ion exchanger by thermal professionals accompanied with chemical
professionals.
14.3.6 After adjustment of desalting equipment, effluent water quality and output pressure of
each pressure shall be up to design requirements.
31
15 Hydrogen-producing Equipment
(specific gravity 1.20-1.25). Potassium hydroxide or sodium hydroxide shall be chemical pure or
analytical pure. 2g potassium dichromate (analytical pure) shall be added per liter of electrolyte.
15.1.10 Insulations between electrobath and earth as well as between terminal polar plate and
tension screw shall be measured by tramegger of 500Y, and insulation resistance shall be higher
than 1MD.
15.1.11 Short circuit between adjacent modules of electrobath is forbidden.
15.1.12 Carbon tetrachloride Iiqllor shall be filled in insolating container.
32
test shall be carried out for pontoon, and two nuts shall be mounted to fasten connections between
guide and pontoon. Distance between pontoon and needle valve shall be properly adjusted to
maintain water level of pressure adjuster adjacent to central line of nilometer.
15.2.5 Installation requirements of electrobath.
a) Inspection before assembly.
1) Nickel layer on anode side shall be contact and free of oil stain on its surface.
2) Nickel layer in insulating case and sealing waterline shall be contact. Gas-guide hole and
electrolyte flow hole shall be straightway, and asbestos cloth shall be tightened and qualified in
transmission test.
3) Two-electrode plate and main electrode plate shall be smooth, and those with roughness
can only be leveled up by wood hammer.
4) Asbestos rubber gasket or polytetrafluoroethylene gasket shall be smooth and free of
fold. These gaskets shall not be cut by joint method.
b) Thermal screwing requirements for electrobath.
1) Installation of temporary vapor source and pipe shall guarantee that electrobath can be
evenly heated and prescribed temperature can be reached.
2) Thermal screwing temperature for electrobath using asbestos rubber plate or
polytetrafluoroethylene plate as gasket shall be IJO"C and 95"C, respectively.
3) Thermal screwing time shall be J6h~48h. Spring leaf stress shall be in the prescribed
range of manufactory after thermal screwing. Lengths of four tension screws between two
terminal polar plates shall be equal, with permissible error of ± Imm.
4) Cold screwing shall be carried out when natural cooled below 50·C after thermal
screwing, and hydraulic pressure test shall be carried out by desalting water or condensation water
under 1.5 times of working pressure after cooling to room temperature. Electrobath shall be free of
leakage.
15.2.6 Pressure adjuster, separator, cooler and hydrogen tank shall be cleaned up until free of
such impurities as rust, welding slag and paint before installation. Nondestructive evaluation test
shall be carried out for welding crater of equipment before leaving factory according to
regulations of Boiler No. 154 Documents issued by China State Bureau of Quality and Technical
Supervision (1999).
15.2.7 Requirements for pipe installation.
a) Pipe, valve and pipe fittings shall be free of cracks, scale and residual slag. The surface
contact with gas shall be cleaned up.
b) Except for connections with equipment and valve flanged or threaded, other connections
shall all be welded. Argon-arc welding shall be adopted for primer of carbon steel pipe and
stainless steel pipe.
c) Both ends of long metal pipe or members shall be earthed, and flanged connections shall
be bridged by metal lead.
d) Smooth 1Cr 18Ni9Ti stainless steel pipe shall be chosen for hydrogen pipe with gradient
higher than 0.3%. Discharging gate shall be mounted in the lowest position of the pipe.
e) Anti-freezing measures shall be taken for hydrogen pipe in cold region.
l) Tightness test under 1.25 times of working pressure, or gas tightness test under 1.05 times
of working pressure shall be carried out by desalting water or nitrogen after installation. Qualified
installation in gastightness test shall meet the following requirements: test pressure will not
decrease for 10 minutes after gas make-up stopped, or average leakage rate is below 0.1 % per
hour after gas make-up stopped for 24 hours.
g) Cold screwing shall be carried out to make distance between the two terminal polar plates
comply with manufactory requirements after emplacement of medium-pressure electrobath.
34
16 Chemical Cleaning of Heating Equipment and System
Chemical cleaning of heating equipment and system shall comply with regulations in DLiT
794.
35
17 Chemical Supervision during Startup and Test Running of
Heating Equipments
36
system is relatively stable.
17.2 Quality Standard of 'Vater and Vapor for Newly-built Machine Set during
Test Running
17.2.1 No quality standard for feed water, boiler water and steam is provided during boiler
ignition, main steam tube purging and relief door setting at present. Heating system shall be rinsed
until effluent is clear before boiler ignition.
17.2.2 Silicon dioxide content in superheated steam shall not exceed IOOf.lg/L during
rotation-impulsing for steam turbine.
17.2.3 During united startup of machine set, feed water quality shall be executed according to
Table I for the set with 1/2 rated load or above.
Table 1 Quality Standard for Feed Water
~)
Utility drum boiler Once-through boiler
Remarks
Item ::: 137 137-183 183-225 >22.5
Hydrazine
10-50 10-50 10-50 20-50
~lg/L
Silicon dioxide
<60 <50 <30 <20
flg/L
Conductivity (25'C, after
hydrogen ion exchange) <04 <0.4 <0.3 <0.3
fl S/cm
17.2.4 Quality of boiler water shall be executed following Table 2 according to working pressure
of utility drum boiler during united startup of machine set.
Table 2 Quality standard for water in utility drum boiler
Drum pressure Salinity Sil icon dioxide Iron Phosphate
Treatment method pH
MPa mg/L mg/L Ilg/ L mglL
137-156 Phosphate treatment S50 :::;:150 _100 2-8 9-10
157-18.3 Phosphate treatment S20 so 25 - 300 05-3 9·-10
>18.3 Volatilization treatment gO SO.20 S300 90-9.5
17.2.5 During united startup of machine set, condensation water recovery shall be on the
promise of not influencing feed water quality for those sets without condensation water treatment
equipments. It shall be generally executed following Table 3.
Table 3 Quality standard for recovery condensation water and drainage water
Iron Dissolved oxygen Silicon dioxide Hardness
Appearance
flg/L flg/L flg /L flmol/L
o suspended substances S80 S30 :::;:80 :::;:10
37
17.2.6 Quality of internal cooling water of electric generator shall be executed according to
Table 4 during united stal1up of machine set.
Table 4 Quality standard for internal cooling water of electric generator
Conductivity (2S"C) Hardness Copper
pH (2S"C)
fl S/cm flmol/L flglL
~2.0 gO _40 ~6.8
17.2.7 Vapor and water quality shall be executed according to relevant regulations In GB/T
12145 after 72-hour or 168-hour test running of united operation of machine set.
38
approved chemical cleaning measures.
c) Qualified steam turbine oil shall be coated for oil equipment and system unable to be
timely installed after cleaning or sweeping, and then they shall be temporarily sealed.
d) Steam turbine oil, fire-resistant oil, insulating oil and mechanical oil shall all comply with
relevant national quality standards.
e) Oil equipment and system shall be inspected before oil injection to make sure that they
meet oil injection conditions, and oil trademark and quality both comply with application
requirements. Equipment and system shall be washed by qualified oil firstly and then oil can be
injected.
f) Sizing test of oil shall be carried out before test running of machine set with load after oil
circulation rinsing, and granularity shall comply with requirements.
17.4.2 Acceptance, application and storage of oil.
a) Oil of different trademarks shall be stored in different storage tank. Oil mixing, if
necessary in special cases, can only be carried out after oil mixing test.
b) Oil shall be stored in by its sort, and kept away from heat source, inflammables, sunshine,
and rain to prevent oil from deterioration.
c) Oil tank and barrel shall be obviously labeled to give clear indication of oil category,
source, quantity and inspection certificates, and sealed tightly for storage. Oil without label or
unqualified mustn't be used. Mixing of oil barrel is forbidden.
39
18 Acceptance of WOI'k
18.1 The following materials, duplicates and fittings shall be handed over from supervision,
construction and troubleshooting unit.
a) Instructions and drawings of design modification.
b) Equipment installation record and acceptance certificate for subsection test running.
c) Adjusting test report of water treatment system and hydrogen-producing equipment.
d) Quality determination results of chemical cleaning for boiler body and heating system
before boiler.
e) Chemical supervision and adjusting test report during startup and test running of machine
set.
f) Supervision reports.
g) Extraworks acceptance cel1ificate and indications of equipments
h) Standby, fittings and special tools equipped with equipment by manufactory.
18.2 Water treatment equipment and hydrogen procuring equipment can be accepted and handed
over to production unit as unit project after installation and test running.
40
Appendix A(Normative Appendix)
Filtering Material
A.l Filtering material shall comply with design requirements. In the case without design
regulations, it shall be selected according to chemical stability and mechanical strength. General
requirements are as follow:
A.I.l Quartz sand can be adopted for water after agglomerate treatment.
A.I.2 Marble or anthracite coal can be adopted for water after lime treatment.
A.I.3 Dolomite or anthracite coal can be adopted for water after silicon removal by magnesia
mixture.
A.I.4 Anthracite coal can be adopted as filtering materials for phosphate or salt filter.
A.I.5 Quartz sand can be adopted as bedding in the bottom of ion exchanger and activated
carbon fi Iter.
A.2 Chemical stability test in acid, alkali and neutral solutions shall be carried out for quartz
sand and anthracite coal. Chemical stability test in alkali and neutral solutions shall be carried out
for marble and dolomite. After 24-hour dipping, filtering materials shall respectively comply with
the following requirements:
A.2.1 Increment of total solids shall not exceed 20mg/L.
A.2.2 Increment of silicon dioxide shall not exceed 2mg/L.
Note: Test method: Respectively add 500mL the following three kinds of solution into three conical beakers
(700mL-1 OOOmL): HCI of 400mglL (prepared by HCI with specific gravity a I' 1.19); NaOH of 400mg/L; NaCI of
500mg/L Then add 109 tiltering materials (with grain size in the range of 0.5mm-1 mm) to each beaker under
20'C. and shake the beaker for each 4 hours Take out filtrate after 24-hour dipping, and analyze total solids.
silicon dioxide and oxygen consumption.
A.3 Quartz sand in bedding of ion exchanger and activated carbon filter shall comply with the
following requirements: A.3.1
A.3.1 Purity: Silicon dioxide ~99%
41
Table A.I Granularity of Filtering Materials
-
Serial Grain size Nonuniformity coefficient
Category
number mm KRIJ
Quartz sand dm",=0.5 d","x=I.O
Monolayer filtering Marble d"",,=0.5 dnlnx=I.O
I 20
materials Dolomite d"",,=0.5 d",,,,.= 1.0
Anthracite coal dnlll,=0.5 d",nx= 1.5
Doublelayer filtering Anthracite coal dni l/l=0.8 dmnx= 1.8
2 2-3
materials Quartz sand d"III1=0.5 d",nx= 1.2
A.S Granularity uniformity test shall be carried out for filtering materials before charged into
filter, and test result shall comply with the following standard:
below 2;
A.S.2 Nonuniform ity coefficient of fi Itering materials in bidirectional flow type fi Iter (d J80
diD
shall be 2~3;
Note: d so and diD are sieve pores that 80% and 10% tiltering materials can pass through. respectively.
A.6 Granularity of supporting layer shall comply with regulations in Appendix Table A.2 if
supporting layer structure is adopted for fi Iter (tank).
Table A.2
Layer Granularity Layer Granularity
(from above to below) mm (from above to below) mm
I 2-4 3 8-16
2 4-8 4 16-32
42