NE1-ITP 400KV Cable Trench Construction
NE1-ITP 400KV Cable Trench Construction
PROJECT
NE1-10-QC-SEC-ITP-ACA(C)-00001
INSTRUCTION
Purpose and Scope: This ITP is issued for the work of 400kv cable trench construction.
Notification: Inspection notification shall be given 48 hours prior to the scheduled inspection of witness or hold point.
C: Construction Subcontractor
S: EPC Contractor SEGC authorized Quality Control Supervisor
O: Owner or Owner’s authorized representative
P: Perform or Submit
A: Approval
H: Holding Point where inspection shall be kept on hold till SEGC/Owner witness. The work shall not proceed without the written agreement or wavier from SEGC or SEGC’s
authorized representative.
W: Witness Point where the inspection notification shall be given to SEGC/Owner and inspection should proceed if SEGC/Owner is not present at the scheduled date.
R: Review of applicable documents or records to ensure compliance with specification.
S: Surveillance Point. Where Subcontractor can proceed the work without notification and SEGC/Owner can check the work and record at any time,
Subcontractor internal inspection record will not be mandatory for quality dossier.
Other Abbreviation:
NA
Inspection
Component & Frequency/ Reference Documents/
No. Characteristics Check Acceptance Criteria Format of Record Agency Remark
Operation Stage Standard/ Specification
C S O
1 Documents
As per Approved As per Approved Drawing/
Check Approvals and Equipment/Material
Material Prior to work Drawing/As per OTS & Civil OTS & Civil Works A/ Submittal to
1.1 Correct Revisions Approval Submittal P R
Approval Commences Works Specifications and Specifications and DEWA H consultant approval
Obtained Form
DEWA requirement requirement
Trial Mix
Civil Technical Specs/Local Civil Technical Specs/Local
Concrete Mix Approval of Design Prior to work Reports/Material A/ Submittal to
1.2 Regulations and DEWA Regulations & DEWA P R
Design Mix/Trial Mix Reports Commences Approval Submittal H consultant approval
requirements requirements
Form
Lab Check the Accreditation Prior to work Accreditation A/
1.3 Local Regulations Local Regulations P R If Applicable
Accreditation Certificates Commences Certificates H
Measuring and Check the Calibration Prior to work Calibration
1.4 Local Regulations Local Regulations P R R
Testing Device Certificates Commences Certificates
2 Materials
Mill Test Certificate/ As per approved Drawing As per approved Drawing Equipment/Material W
Material Submittal to
2.1 Certificates of Each Delivery and Technical and Technical Inspection Request P / R
Incomings consultant approval
Compliance Specifications Specifications Form/Certificates R
W
Materials As per As per BS4449/ASTM As per BS4449/ASTM Submittal to
2.2 Samples to be Tested Test Report P / R
Sampling Specifications C140/applicable standard C140/applicable standard consultant approval
R
3 Excavation Work
Setting out of corner Prior to
3.1 Survey Marking As per Approved Drawing As per Approved Drawing Survey Report P H R
coordinates excavation
Measurement of final
3.2 100% As per Approved Drawing 0,-50mm Survey Report P H R
elevation
After
Measurement of width & Excavation Check
3.3 Excavation As per Approved Drawing As per Approved Drawing P H R
Foundation Pit length List
Completion
Formation
After
Inspection Measurement evenness
3.4 Excavation As per Approved Drawing ±50mm Survey Report P H R
of the surface
Completion
Each 500sqm 3rd party Testing
3.5 Compaction Test As per ASTM D 1556/OTS MDD 95% P H R
2 Points Report
4 Blinding Concrete
Survey Marking Setting out and Prior to work Approved Coordinates
4.1 As per Approved Drawing Survey Report P H R
for Blinding Coordinates Commences Layout Drawing
Once and Blinding Concrete
4.2 Formwork Thickness As per Approved Drawing As per Approved Drawing P H R
prior to Check List
Form Work
pouring Blinding Concrete
4.3 Level / Width, Length As per Approved Drawing As per Approved Drawing P H R
concrete Checklist / Survey
Document Name NE1-10-QC-SEC-ITP-ACA(C)-00001
Rev No. 00
ITP for 400KV cable trench construction
Page 3 of 11
Inspection
Component & Frequency/ Reference Documents/
No. Characteristics Check Acceptance Criteria Format of Record Agency Remark
Operation Stage Standard/ Specification
C S O
Report
Blinding After Pouring
4.4 Check the Elevation As per Approved Drawing +-20mm Survey Report P H R
Concrete Level the Concrete
5 Cast in Situ (Joint bay and Trough-cross road section)
Foundations
Setting Out
5.1 Coordinates and Once As per Approved Drawing As per Approved Drawing Survey Report P H R
Elevation
Diameter of rebar/
Lap Lengths and
Rebar Pre-Pouring
5.2 Spacing/ Anchorage Once As per Approved Drawing As per Approved Drawing P H R
Installation Checklist
Lengths/ Extra
Rebar/ Fixing Detail
Formwork Details/
Formwork Physical
5.3 Once As per Approved Drawing As per Approved Drawing P H R
Pre-Pouring
Form Work Condition/ Supports/
Checklist
Concrete Cover/
Horizontal Alignment
5.4 Once As per Approved Drawing +-10mm P H R
and Vertical plumb
As per Approved Design Concrete Pour Log
5.5 Temperature/ Slump Each Truck P S R
Mix and D.N
Cubes Sampling and Each 100 W 3 for 7 days, 3 for 28
As per Approved Design
5.6 Compressive Cubic Meter 6 40MPA After 28 days Test Report P / R days
Fresh Concrete Mix
Cubes R
Pouring Strength Test
Vibrator Needle Should
Vibration and Pouring During the As per Civil Work Concreting
5.7 be Straight and pouring P S R
Sequence Pouring Specifications Checklist
should be layer by layer
Dismantling of Form As per OTS Civil Works After 12 Hours(Vertical Concreting
5.8 Once P W R
Work Specifications elements) Checklist
Cast in Situ Joint 2 Times a Day
bay and Trough with Hessian
As per OTS Civil Works Concreting
5.9 Curing Cloth and 7 Days P S R
Specifications Checklist
Polythene
Sheet
Document Name NE1-10-QC-SEC-ITP-ACA(C)-00001
Rev No. 00
ITP for 400KV cable trench construction
Page 4 of 11
Inspection
Component & Frequency/ Reference Documents/
No. Characteristics Check Acceptance Criteria Format of Record Agency Remark
Operation Stage Standard/ Specification
C S O
Surface Should be free
of Honey Combs, Pin
Post Pour Visual Surface After Removal As per OTS Civil Works Concreting
5.10 Holes, Blow Holes, P H R
Check of Form Work Specifications Checklist
Segregation and
Cracks
Waterproofing
5.11 Bitumen Coating Once As per Approved Drawing 2 Coats P H R
Checklist
5.12 Layer Thickness Each layer As per Approved Drawing 300mm Backfilling Checklist P W R
Backfilling Each
5.13 Compaction Test 1000sqm 2 As per Approved Drawing MDD95% Test Report P W R
Points
6. Precast trough installation
Setting out and Prior to work Approved Coordinates
6.1 Survey Marking As per Approved Drawing Survey Report P H R
Coordinates Commences Layout Drawing
Installation of Measurement evenness
6.2 Once As per Approved Drawing As per Approved Drawing Check list P H R
Precast Trough of the surface
Note: After execution and completion of this ITP, all the related documents, inspection record and testing reports attached herewith in accordance with this ITP shall be verified by
the below party.
Verified by Sub-Contractor EPC Owner's Representative (s)
Name
CONCRETING CHECKLIST
Subcontractor China State Construction Engineering Corporation (CSCEC)
Structure / Equipment / Location : CT MSR Foundation Plant: CT
Reference MOS:NE1-40-CN-SEC-MOS-OOO(G)-00047 Revision:
Reference Drawing: NE1-40-EM-EAI-DRW-UW (C)-79260 Revision: 2
Reference ITP:Reference ITP No*: NE1-40-QC-SEC-ITP- UW_(C)-00001 ITP Item Number: 5.1, 5.3, 5.4 Revision: 3
RFI Description : Concrete Pouring for MSR Foundation Marked as per attach Drawing
RFI No.:NE1-40-CSC-UW_(C)-RFI-0172 Revision:
Subcontractor
NO. Characteristics Check YES/NO-N/A Date Remarks
Inspector
1 Pouring
1.6 Verify that cubes sampling has been done. P Kafeel 03-07-209
2 Post Pouring
2.2 Verify that dismantelling of form work is done as per ITP. N/A
2.3 Verify that final Elevation and Coordinates as per drawing. N/A
Verify that Tie rod Holes and Concrete Surface Repairing work is
2.6 N/A
done as per approved Procedure
Owner's
Inspected by Sub-Contractor Quality EPC Quality
Representative (s)
Company CSCEC SEGC NE1
Name Kafeel Ahmed
Date 2019/7/3
1.4
1 3
2 4
Remarks:
Name
Signature
Date
CHECKLIST PRE-POURING
Subcontractor China State Construction Engineering Corporation (CSCEC)
1 Pre Pouring
1 3
2 4
Remarks:
Owner's Representative
Inspected by Sub-Contractor Quality EPC Quality
(s)
Company CSCEC SEGC NE1
Name
Signature
Date
BACKFILLING CHECKLIST
1 4
2 5
3 6
Remarks:
Name
Signature
Date
1 Blinding Concrete
1 4
2 5
3 6
Remarks:
Name
Signature
Date
EXCAVATION CHECKLIST
1 4
2 5
3 6
Remarks:
Name
Signature
Date
WATERPROOFING CHECKLIST
1 4
2 5
3 6
Remarks:
Name
Signature
Date