RISK ASSESSMENT
Name Of Activity: Pole Erection Date: 22/04/2024
Hazard
evolving Possible Risk / Hierarchy
Hazard / Residual
Sl Normal / Outcome Probability Severity Impact Existing Control Measures Control of
Activity Environment Risk / Action By
No Abnormal / Rating Rating Level Risk E/ S/
Aspect Impact
Emergency EC/ AC/
Situation PPE
1 Pole
Erection
11manpower shall be
deployed for pole
erection(8.5mts).
Manual pole shifting
Mechanism Must be used.
Pole shall not be dragged by
tractor.
If pole shifting is being done
by tractor &
Trolley, pole & workmen
shall not be transported in
the same vehicle. Site
Shifting of Slip & Fall of Abnormal Leg/Arm Pole shall be properly tied Engineer &
1.1 pole at Pole 3 3 M AC L
Injury/ Hit with the trolley to prevent HSE
location Pole damage by pole any slip of pole from tractor Officer
while transportation.
Red Flag shall be tied with
the project part of pole
during transportation.
Pole shall not be dashed
from trolley to ground.
Channel or sufficient man
power shall be used for
unloading the pole from
trolley.
1.2 Lifting of Site
Pole A MS pipe/Bamboo ladder of AC Engineer &
2 mts & 4Mtr height should HSE
be provided for initial Officer
3 4 M supporting of pole erection.
Ensure that bamboo ladder
tense with slings at top & AC L
bottom corner to ensure the
stability of runners & ladder.
Tie the pole by PP rope at
the height of 6 mtr from the
bottom. Pole shall be
supported by 25mm dia (25
Meter length) PP Rope from
4 corners (Guy rope
S
arrangement).
.Avoid children to come near
the work place
Check the condition of PP
Abnormal Serious rope.
Slip & Fall Injury on MS channel (ISMC-150 of 2
either mtr length) shall be placed in
human, the pole pit (opposite to the
animals or pole base).
equipment. Nobody shall stand on the
pole end as dead weight.
Site
All the area shall be Engineer &
Abnormal Serious barricaded with safety cone HSE
Injury & safety caution tape before Officer
start of pole erection where
residential area available or EC
road crossing.
Breaking of Ensure that no one shall
3 4 M
pole come in the vicinity of pole
(to avoid accident in case of
L
breaking of guy rope). AC
Must avoid children/animals
near the workplace.
Must ensure the full time
supervision during work.
PP ropes shall be removed
from the pole top by using EC Site
Removing Slip & Fall L
Abnormal Serious the FRP Ladder/ Pole Engineer &
the rope (during 3 3 M
1.3 Injury climbing paddle. HSE
from Pole Climbing)
Direct climbing must be Officer
prohibited.
1.4 Pole Fall of Pole 3 5 H Only authorized operator Site
Erection by (Valid DL) shall be allow Engineer &
Hiyab operate the crane. AC HSE
Ensure prohibition of mobile L
phone use by the hiyab
Single & operator & Signal man.
Abnormal Multiple Before staring work, hiyab
Fatality Inspection must be Officer
important. EC
Check all the lifting tools &
tackles.
Hiyab fitness certificate shall AC
be available and hiyab hook Site
having hook latch, over load, L Engineer &
Failure of Abnormal Single & 3 5 H over hoist limit switch & HSE
hiyab Multiple boom limit switch are EC Officer
Fatality provided & checked for its
function.
Ensure the Tag line to Site
Single & control the load & instruct L Engineer &
Hit by the
Abnormal Multiple 3 5 H the workmen to keep away EC HSE
pole
Fatality from front tire Officer
.
The Site
movement of Where residential area or Engineer &
Trespassers / crowed available. There HSE
Vehicle may must be caution required Officer
Abnormal Serious Barricaded the area or EC L
Cause
injury 2 4 M inform the people about the
danger. (In
very few work work associated hazard.
location this
problem may
arise).
_____________________
PM Safety Officer
E=Elimination
S=Substitution
EC=Engineering controls
AC=Administrative controls
PPE=Personal Protective Equipment