BOQ
Project: Stone Masonry in Cement Mortar One Storey Building
Location: Jajarkot, Nepal Date: April, 2024
S.N. ITEMS Quantity unit Rate Amount REMARKS
A CIVIL WORKS
Site Clearance (Clearing & grubbing of site for
1 construction as per drawings,specifications and
instruction of site engineer) 465.20 sq.ft. 2.03 944.66
2 Excavation earthwok 625.71 c.ft 19.40 12137.63
Earth filling with the required quality backfill soil in
foundations,floors etc. including ramming/compaction
3 in 15 cm layer by layer and watering all complete as
per drawings,specifications and instruction of site
engineer. 632.02 c.ft 13.45 8502.09
Providing & laying gravel soling in foundation
including voids filling with stone dust all complete as Stone provided by
4 per drawings,specifications and instruction of site beneficiary
engineer. 165.39 c.ft 40.36 6674.81
Concreting of foundations, vertical faces, walls (PCC
5 1:3:6) including supply of materials and haulage
distance upto 30 m 79.42 c.ft 149.08 11839.63
Random rubble stone masonry works in cement sand Stone provided by
6
mortar 1:4 in foundation & retaining wall in line beneficiary
638.31 c.ft 156.22 99714.52
Concreting works (PCC 1:1.5:3) of superstructures,
7 deck slabs, beams including supply of materials and
haulage distance upto 30 m 246.79 c.ft 211.13 52104.72
Cutting, bending, placing in position as shown in the
drawing & binding by GI wire of reinforcement steel
8 bars for RCC works including haulage distance up to
30 m 0.51 M.T. 65000.00 32833.46
Rubble masonry works for construction of arch or
conical surface including supply of block stones, Stone provided by
9 preparing cement mortar (1:4) and constructing walls beneficiary
(Haulage distance up to 30 m) 767.64 c.ft 91.59 70307.20
Making forms for structural beam (Depth 0.3-0.8 m)
10 including selection of materials, fixing, oiling,
dismantling, removal & haulage up to 30 m 248.62 s.ft 63.83 15868.90
Providing and fixing wooden post, rafter, joist, purlin &
Wood provided by
12 beam etc. as per the drawings and specification, all
complete beneficiary
1.00 Nos. 42000.00 42000.00
Make sal wood frame & fixing (door size 900*2100, Wood provided by
13 frame size 100*75)
7.47 c.ft 1269.16 9475.86 beneficiary
Making and fitting 4 mm glazed shutter in 38*75 mm sal Wood provided by
14 wood frame (Shutter size 0.91*1.37)
40.50 sq.ft 913.62 37001.79 beneficiary
12.5 mm thick cement sand (1:4) plastering works
15 (Except in ceiling)
832.36 sq.ft 36.82 30646.80
16 Painting Work 832.36 sq.ft 17.10 14231.39
CGI sheet roofing works with supply of materials
17 complete
495.49 sq.ft 147.25 72959.38
Making ridge of GI plain sheets and fittings with supply
18 of materials complete
23.83 rft 174.25 4152.97
19 Door Panel 2.00 No 4000.00 8000.00
B Water Supply & Sanitation Works 1.00 L.S. 10% of A 52939.58
Total amount (Civil Part) excluding VAT[A] NRs. 529395.80
Total Amount [A+B] NRs. 582335.38