DCO.
NO: 0904570-BOM-003
OIL & GAS DEVELOPMENT COMPANY LIMITED
NASHPA 11 PIPELINE CONSTRUCTION PACKAGE PREP. : AHK
REV. :1
BOQ PIPELINE CIVIL WORKS DATE : 18-04-2023
UNIT RATE
SR# ITEM DESCRIPTION UNIT QTY. TOTAL (PKR) REMARKS
(PKR)
1.0 SITE CLEARENCE and ROW
Marking of ROW, cleaning, grading and leveling of site, including
removal of top soil and cut/fill as required including removal of bush
cutting, debris, vegetation, trees, plants, crops, any other undesired
material within specified ROW as per approval of client's Engineer
Incharge.
1.1 For 40ft wide ROW R.M 1800
2.0 EXCAVATION & BACKFILLING FOR PIPELINE TRENCH
Excavation in all kinds of soil, dry or wet, hard or soft, including all
operations, site cleaning, removing of gravel and all debris material up
to required depth to attain the profile of pipeline, maintaining slope,
2.1 R.M 1800
backfilling and leveling the surface to meet the Natural Ground profile.
Backfilling shall be completed as per drawing and approval of the
Engineer in Incharge.
3.0 PIPELINE MARKER
Supply of material, construction and installation of pipeline marker
Nos 8
during backfilling as per instrcution by Engineer Incharge.
4.0 ANCHOR SUPPORT FOR RISER
4.1 EXCAVATION FOR FOUNDATION
Excavation for foundations in all kinds of soil, dry or wet, hard or soft,
including all operation, complete with breaking clods, levelling,
dressing, dewatering, shoring & compacting. Also include backfilling of
excavated earth in plinth and under floors i/c breaking clods, dressing,
watering and consolidating by ramming in layers not exceeding 8" m³ 4
depth to obtain 95% modified AASHTO density for foundations and
suitable compation for flowline including lifting, shifting or disposing of
surplus earth outside the premises or as per approval of Client (Site
Engineer).
4.2 PLAIN CEMENT CONCRETE
Providing and laying Plain cement concrete of specified strength using
approved quality 3/4" max. size graded crushed aggregate & fine
aggregate including approved Steel formwork & its removal, all
operations of vibrating, levelling, compacting and curing etc. complete
as per approval of Client.
m³ 1
PCC 1:4:8 (1 Cement 4 Sand and 8 coarse aggregate)
Note:
1. OPC cement should be used for all works.
2. Mix design for each type of sample will be provided by the
Contractor
4.3 REINFORCED CEMENT CONCRETE
Providing and laying Reinforced cement concrete shall be developed 28
days cylindrical strength of 3000psi specified, using approved quality
3/4" max. size graded crushed aggregate & fine aggregate including
approved form work & its removal, all operations of vibrating, levelling,
compacting and curing etc complete with placing of markers and Road
barriers . Works also includes Lifting and Transportation from store and m³ 3
unloading at work site.
Note:
1. OPC cement should be used for all sub-strucure works.
2. Mix design for each type of sample will be provided by the
Contractor
DCO. NO: 0904570-BOM-003
OIL & GAS DEVELOPMENT COMPANY LIMITED
NASHPA 11 PIPELINE CONSTRUCTION PACKAGE PREP. : AHK
REV. :1
BOQ PIPELINE CIVIL WORKS DATE : 18-04-2023
UNIT RATE
SR# ITEM DESCRIPTION UNIT QTY. TOTAL (PKR) REMARKS
(PKR)
4.4 STEEL REINFORCEMENT
Providing and laying hard grade ribbed deformed(yield strength 60,000
psi) steel reinforcement bars including the cost of straightening, cutting,
bending, binding, wastage and such overlaps that are not shown in
drawings, placing in position on cement concrete 1:2:4 precast spacer Tons 0.2
block or m.s chairs,tying with binding wire (GI wire of 18 guage),
including cost of chairs and wires etc in all kinds of RCC works.
Complete in all respect to the approval of Client (Site Engineer).
4.5 BITUMEN COATING
Providing & Laying 1200 micron thick 10/20 grade of bitumen after one
coat of primer outside foundations, columns and plinth beams upto
finished ground level including cost of all material,labour,equipmen etc m² 5
complete as per drawing and specification and as directed by the Client
(Site Engineer).
4.6 STRUCTURAL STEEL
Supply of all material including bolts, plates structural members; works
inculde fabrication, painting, erection, surface preparation of steel
structure (A-36) etc. Complete in all respect as per drawing, instruction Kg 80
and specification of the Consultant and approval of Client ( Site
Engineer).
4.7 STEEL EMBEDDED PARTS
Providing, fabricating and fixing of steel embedded parts in concrete
such as stainless steel dowel plates, Angles etc. Complete as per Kg 90
drawings, specifications and approval of Client (Site Engineer).
4.8 NON SHRINKAGE CEMENTITIOUS GROUT
Supply & laying of non shrinkage cementitious grout and filling in
Pockets, having minimum required compressive strength in accordance
with the Company specification, Including preparation of pockets by
m² 0.3
means of soft wood or Thermophore sheet in foundations as per
drawings, instruction and specification of the Consultant and approval
of Client ( Site Engineer).
5.0 ROAD CROSSING
5.1 REINFORCED CEMENT CONCRETE
Providing and laying Reinforced cement concrete shall be developed 28
days cylindrical strength of 3000psi specified, using approved quality
3/4" max. size graded crushed aggregate & fine aggregate including
approved form work & its removal, all operations of vibrating, levelling,
compacting and curing etc complete with placing of markers and Road
barriers . Works also includes Lifting and Transportation from store and m³ 4
unloading at work site.
Note:
1. OPC cement should be used for all sub-strucure works.
2. Mix design for each type of sample will be provided by the
Contractor
DCO. NO: 0904570-BOM-003
OIL & GAS DEVELOPMENT COMPANY LIMITED
NASHPA 11 PIPELINE CONSTRUCTION PACKAGE PREP. : AHK
REV. :1
BOQ PIPELINE CIVIL WORKS DATE : 18-04-2023
UNIT RATE
SR# ITEM DESCRIPTION UNIT QTY. TOTAL (PKR) REMARKS
(PKR)
5.2 STEEL REINFORCEMENT
Providing and laying hard grade ribbed deformed(yield strength 60,000
psi) steel reinforcement bars including the cost of straightening, cutting,
bending, binding, wastage and such overlaps that are not shown in
drawings, placing in position on cement concrete 1:2:4 precast spacer Kg 350
block or m.s chairs,tying with binding wire (GI wire of 18 guage),
including cost of chairs and wires etc in all kinds of RCC works.
Complete in all respect to the approval of Client (Site Engineer).
TOTAL (PKR)
NOTES:
1 Where road/track/area along the ROW is available construction of 20' wide ROW will be required, otherwise 40' wide ROW required
2 For backfilling material, soft / graded soil required wherever necessary, otherwise excavated material utilized as per approval of engineer incharge
3 The Quantities taken in this BOQ are estimated only for bidding purpose. Contractor is responsible to estimate the quantities as per site requirements, drawings & tender documents
4 Contractor is responsible to add any missing / required item as per scope of works, drawings, specifications & tender documents.
5 MPCL reserves the right to increase / decrease the quantum of work. However payment will be made on actual work done.
6 Contractor to comply with Relevant codes & standards, specifications and drawings.
7 All area must be cleared and reinstated after completion of work
8 Mobilization / De-Mobilization, Equipment, Machinery, Tools, Manpower, Camping, utilities, etc required for completion of work.
9 Estalishment of camp at nearest suitable location for execution of work at site
10 Approval of client should be taken by the contractor before undertaking any kind of construction and installation work at site.