Manyar Smelter Project Manpower Report

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Report Date : August 11, 2023

Report Day : Friday


Project Name : Manyar Smelter Desalination Project

Commodities Installed
Description MH FTE Today Next Day
Unit Qty Name
WIKA Staff 630 63
Actual - WIKA Indirect Worker 1040 104 Concrete Work Concrete Work
WIKA - Subcontractor CM 80 8 - Little Beam Control Building: 2 m3
- Slab (Top) DMF Backwash: 20 m3
WIKA - Batch Plant Worker 170 17
- Wall Manhole-1: 7.5 m3
WIKA - Inspector Scaffolder 20 2
WIKA - Scaffolder 230 23
WIKA - Cleaning Service Worker 30 3 M3 29.5 Concrete Work
WIKA - TCF Worker 0 0
WIKA - Driver 140 14
WIKA - Security 70 7
WIKA - Warehouse Worker & Operator 180 18
WIKA - Survey 120 12
Actual - WIKA Direct Worker 3130 313 Pile Head Treatment Pile Head Treatment
WIKA - Supervisor 150 15 -

WIKA - Foreman 0 0
WIKA - Welder 0 0 M3 - Pile Head Treatment
WIKA - Rigger 80 8

WIKA - Civil Worker 2670 267

Steel Sheet Pile Steel Sheet Pile


-
WIKA - Pipe Fitter 0 0 BAR - Steel Sheet Pile

Structural Steel Erection Structural Steel Erection


- Bolting Piperack & Cable Tray Area-03
- Bolting Piperack & Cable Tray Area-06

WIKA - E&I 0 0 TON - Structural Steel Erection

Concrete Brick Installation Concrete Brick Installation


WIKA - General Labor/Helper 230 23
- Control, Warehouse & Workshop Building
M2 - Concrete Brick Installation
Actual - WIKA Subcontractor Worker 830 83

Roofing & Cladding Installation Roofing & Cladding Installation


- Cladding Installation for Substation Building
- Roofing Installation for Control Building
WIKA - Piling Subcontractor Direct 0 0 M2 - Roofing & Cladding Installation

Drainage Work Drainage Work


- Slab Drainage Area D2-4: 8.5 m3

WIKA - Concrete Subcontractor Direct 0 0

M3 8.5 Drainage Work

WIKA - Architecture Subcontractor Direct 0 0

WIKA - Electrical Subcontractor Direct 0 0

Concrete Coating Work Concrete Coating Work


WIKA - Mechanical Subcontractor Direct 0 0 - Chemical Tanks & Pumps Area-1 Shed: Continue
Surface Preparation M3 - Concrete Coating Work
WIKA - Concrete Coating Subcontractor Direct 130 13 - N-Pit: Surface Preparation for Wall
WIKA - Erection Subcontractor Direct 700 70 - GDMF Backwash: Cleaning Area
Grand Total 5630 563

MANPOWER SUMMARY On Site Personal Business Leave Sick Off TOTAL


Total Direct Worker 396 1 14 0 145 556
Total Indirect Worker 167 0 2 1 3 173
GRAND TOTAL 563 1 16 1 148 729

Equipment Onsite Running Manufacture Capacity Type


Heavy Equipment
- Wheel Loader 1 XCMG 1.8 T XUG0300KJMCB09625
- Excavator 2 Komatsu 0.8 m3 & 0.7 m3 MC08206012 & PC200-8MO
- Boom Lift 4 Genie 227 & 454 kg Z62D-241, S85D-649, S65XCD-1294 dan S60D-1299
- Crawler Crane 1 Zoomlion 60 T 566/3384/PAA/108.5-SBY/XI/2022

- Rough Terrain Crane 3 Kato & Tadano 30 T & 50 T SR - 300 L, GR-500E-3-00101 & 581727

- Truck Mounted Crane 3 Tadano & XCMG 8T & 8.2 T KZ0275, KZ-0329 & 0833K170245
10-110 m3/Jam &
- Concrete Pump 2 IHI IPA 59803 dan FHI-29/4 / F.210
10-120 m3/Jam
- Dump Truck 4 Mitsubishi 8m3
MJEFM8JK1JJE12738, MJEFM8JK1JJE12743 &
- Mixer Truck 3 Hino 7.5 m3
MJEFM8JK1JJE12737
- Water Truck 1 Mitsubishi 5000L MHMFE334E6R037949
Construction Material Today Cumm
Spun Pile Delivery & Stock (EA) - 8.119
Rebar Stock (Ton) - 5.823.061
HSE PERFORMANCE
Leading Indicator Today Cumm Lagging Indicator Today Cumm Weather Record Remarks
PTW Active 33 2.634 Fatality 0 0 06.00 - 08.00 Sunny
Emergency Response (Drill) 0 0 Lost Time Incident 0 0 08.00 - 10.00 Sunny
Management Visit 0 0 Medical Treatment Case 0 0 10.00 - 12.00 Sunny
Safety Talk 1 0 First Aid Case 0 4 12.00 - 14.00 Sunny
SHE Training (WAH, JSA, FRM & STA) 12 0 Near Miss 0 8 14.00 - 16.00 Sunny
SHE Inspection 19 0 Enviromental Violation 0 0 16.00 - 18.00 Sunny
SHE Induction 4 2.387 Property Damage 0 0 18.00 - 20.00 Sunny
Confirmed Covid-19 Case 0 0 20.00 - 22.00 Sunny
TRIR YTD (based on MSHA) 0 0 22.00 - 24.00 Sunny

MISCELLANEOUS
Work on Hold History HSE Personnel 13
Tuesday, September 27, 2022 LC on Grounding Area was held, waiting for Grounding discussion with PTFI (Filtered Operator 29
Water Pumps Shed)

Sunday, October 2, 2022 Rebar ready to install on Filter Water Pumps Shed, awaiting confirmation from BV for IFC Rigger 11
Underground Utility Drawing

Friday, October 14, 2022 WIKA about to commence the Civil Work in Lamella Clarifier Tank area, but the work Scaffolder 29
was halted since BV's Supervisor asked us due to the elevation changes for PHT in the
Lamella Clarifier Tank

Friday, October 28, 2022 Anchor bolt provided by BV for Filtered Water Pumps Shed has not arrived. WIKA needs
to wait the further concrete activity in the area.

Tuesday, November 29, 2022 Pouring priority change to east wing slab for GDMF Tank area that makes west and
middle areas are on hold.

Saturday, December 17, 2022 Arrangement layout for GDMF Tank has not issued, material ready. WIKA needs to wait
for the arrangement layout to be issued.

Sunday, December 25, 2022 BV Personnel informed WIKA with an advance information by mail that there will be
update for TQ #83 regarding safety shower relocating and in slab piping in the Chemical
Tank & Pump Area - 2 Shed.

Wednesday, December 28, 2022 WIKA was about to commence backfill work in the Filtered Water Tank area but was
held by BV QC

Tuesday, January 03, 2023 Earth pit drawing for Substation building has issued but WIKA needs to cut the slab rebar
and added additional rebar.

Tuesday, January 17, 2023 WIKA is about to continue the backfilling activity for B0 concrete in Area 2 RO Building
but BV Engineering held and asked to wait for further info.

Friday, February 24, 2023 Concrete Work on the equipment foundations in Chemical Tanks & Pumps Area 1 & 2
could not be carried out because the anchors supplied by BV had yet to arrive.

Wednesday, June 21, 2023 BV is about to commence excavation for HDPE piping in between Filtered Water Tank
and Lamella Clarifier Tanks. Hence, all resources such as scaffolding access, rebar, etc.
are dismantled. WIKA Civil Work progress in the south side of Filtered Water Tank,
south side of GDMF Tank, Piperack & Cable Tray Area-01, and north side of Lamella
Clarifier Tanks are on hold due to the Piping activity from BV-TPE team.

SIGNATURE
Prepared by Approved by
PT Wijaya Karya (Persero) Tbk Black & Veatch International

Satria Amaral Yosua Silitonga