036 JSA Sand Blasting & Painting Rev.2
036 JSA Sand Blasting & Painting Rev.2
JSA Title
Personal Protective Equipment Minimum PPE’s “Safety Helmet, Safety Shoes, Safety Glass (dark &
CC-1 PROJECT Required clear glasses), Long sleeves shirt” & Ready to use / wear working gloves,
Face shield, ear plug.
1. Pre-Commencement Activities (Preparation of 1.1. Human Injury due to lack of communication 1.1.1. Barricade the working area (Physical Barricade)
Work, work site, equipment & tools) and necessary information 1.1.2. Toolbox meeting
1.1.3. Preparation of the area/ vicinity (Approval from
Clients)
1.1.4. Placement of required warning signs (Safety
Signs)
1.1.5. MSDS Requirements (site availabilities)
1.1.6. Approved support and stand for big pipes and
structures
1.2. Personal injury due to lack of experience and 1.2.1. Only experience personnel are allowed to do the
training. task (Unauthorized person is not allowed)
1.2.2. A particular training if requires (Nozzle man
qualification)
General Instruction:
“If there is any doubt, please ask!”
1.3. Equipment may have a harmful effect on 1.3.1. All equipment shall be inspected prior to entrance to
environment. site by the AL-BINALI HSE Dept. (Unapproved
equipment must be removed from site)
1.3.2. Report all environmental spill to the AL-BINALI-HSE
1.3.3. MSDS requirements
1.4. Personal injury due to not being aware of the 1.4.1. Everyday pre-start meeting shall be conducted
activities. regarding the daily activities
1.4.2. JSA’s and MSDS Shall be posted at site for safety
awareness and references
1.4.3. Only authorized person is allowed in the area
1.5. Personal injuries due to usage of unfit 1.5.1. Daily routine checks on equipments and tools by the
equipment. supervisors.
1.5.2. A particular training if requires (Nozzle man
qualification)
General Instruction:
“Defective tools is not allowed to use”
“Self Fabricated Tools are not allowed”
1.6. Damage equipment due to Poor supervision 1.6.1. Close supervision of all work activities at all times by
the supervisor in charge
1.6.2. Inspection / checklist and to be pass to AL-BINALI
HSE Dept. for documentation
1.7. Permit to Work 1.7.1. The required Permits to Work shall be obtained and
kept at work area at all times along with the JSA
and MSDS
1.8. Dust Control 1.8.1. Provision of dust masks for workers and
ensure their use as per MSDS
1.8.2. Provide dust mitigation by spreading water – if
possible (be aware of lying cables)
2. Mobilize materials, tools, and equipment to 2.1. Back injury (manual handling) 2.1.1. Manual handling shall be covered in daily pre-start
worksite meeting and be implemented on site
2.1.2. Buddy-buddy system may apply
2.1.3. Use of mechanical lifting if possible
2.2. Traffic and pedestrians 2.2.1. Audible reversing alarms shall be installed on
equipment / vehicles
2.2.2. Pedestrian safety precautions shall be discussed in
pre-start meeting.
2.2.3. All traffic rules and signs should be followed (on site
speed limit .
2.2.4. Only approved routes shall be used for access to
and egress from the site and fabrication
2.2.5. The drivers shall be made aware of the approved
routes
2.2.6. Trained standby-men with high-visibility vests shall
accompany the work activities near traffic/roads
2.3. Overturning of vehicle / Crash injuries 2.3.1. All drivers shall have valid Saudi Arabia driving
licenses
2.3.2. The areas where heavy equipment are working shall
be clearly marked on site
2.3.3. Safe access shall be maintained at site for vehicles
and equipment
2.3.4. Use of seatbelts shall be mandatory
2.4. Slips / Trips / Falls 2.4.1. Housekeeping shall be discussed in daily pre-start
meeting and be implemented on site on a daily
basis
2.4.2. Provide safe access / emergency walkways (free
from any materials)
3. (Unloading of Pipes, Structural and materials 3.1. Material Falls; Environmental hazard cause by 3.1.1. Use Approved lifting equipment with daily checklist
[for sand blasting and painting]) use of Lifting equipment (operator’s inspection)
equipment (Crane, Boom truck, Fork lift) 3.1.2. Only Riggers are allowed to give signals for the
crane
3.1.3. Only crane rigger will give signal for the crane
3.1.4. Approved support and stand for big pipes and
structures
3.1.5. Use softener (protection pad) to protect the sling to
damage from sharp edge materials
3.1.6. Use slings and shackles of the correct SWL for
unloading. Lifting gear to have the current
quarterly colour code displayed
3.1.7. Crane operation to be barricaded, restricted access
to unauthorized personnel
3.1.8. Two (2) tag lines are required for long pipe lifting
3.1.9. Provide lifting signboards
3.1.10. Provide approved Temporary Piping supports
3.1.11. Provide stopper to prevent the pipe to roll-over
3.1.12. Report all environmental spills
General Instruction:
- Only approved equipment to be used (crane, ,etc)
- No standing under a suspended load
4. Use of Generators for hand tools and 4.2. Electrocution 4.1.1. Use all necessary requirements including PPE for
Luminescent the task
4.1.2. Use only approved extension cables with quarterly
colour coding
1. Use of Pneumatic Tools for Sand Blasting 1.1. Health Hazard / Injury 1.1.1. Availability of MSDS and Applied approved
(only at the approved area) Inspections by third party vendor.
1.1.2. Wear appropriate PPE as per MSDS Requirements
1.1.3. Only trained or qualified person (trained) is allowed
for handling and do the paint work as per MSDS
1.1.4. Restriction of the area by Barricade (Containment)
1.1.5. Available Emergency First Aid Box require for
the area including eye wash
1.1.6. Attachment of Whip lash Arrestor or Equivalent for
hose connections lash arrestor
1.1.7. Grounding and earthing requirements
PAINTING WORKS
1. Use of Pneumatic Tools for Paint Blowing 1.1. Health Hazard / Injury to health 1.1.8. Availability of MSDS and Applied approved
(retouch painting) Inspections BY Third Party Vendor
1.1.9. Wear appropriate PPE as per MSDS Requirements
1.1.10. Only trained or qualified person is allowed for
handling and do the paint work as per MSDS
2. Demobilization 2.1. Work completion; Clutter/Rubbish 2.1.1. Workforce shall be alerted about the work
completion
2.1.2. Good housekeeping practice shall be implemented
throughout the day
2.1.3. Daily Cleaning (collection of spread Garnets)
Prepared by: Supervisor Date: COMMENT :