Hsu 2013
Hsu 2013
Abstract: A cost estimating model is developed for light rail transit (LRT) and bus rapid transit (BRT) systems to better aid transportation
planners and decision makers in the selection process. In evaluating transit systems, cost estimating has always been a major consideration.
Without an applicable cost estimating model or methodology, the decision on the choice between LRT and BRT would cause significant
controversy and difficulty in the early corridor planning stage. The model developed in this paper can be applied to estimate costs and
compare the LRT and BRT systems that operate on various right-of-way categories, alignment configurations, and different given transit
demand volumes. An example and comparative analyses illustrate how the model can be applied in real-world situations. DOI: 10.1061/
(ASCE)TE.1943-5436.0000466. © 2013 American Society of Civil Engineers.
CE Database subject headings: Light rail transit; Buses; Costs.
Author keywords: Light rail transit; Bus Rapid Transit; Cost estimating model.
the most expensive rail tunnels, such as the Silver Line tunnel sec- tem with the lower cost per passenger mile is the preferable and more
tion, with a cost estimated at approximately $500 million per mile cost-effective system.
($310.8 million per km) (Vuchic 2007).
Operating and maintenance (OM) cost is incurred by regular
Development of Cost Estimating Model
operation of the system. Typically, regular costs involved in daily
operations include operating and maintenance costs. The National In this paper, a cost estimating model is developed to estimate
Transit Database (NTD) provides historical data of the OM cost for capital cost, annualized capital cost (depreciation cost), OM cost
public transportation systems. However, most transit agencies nei- and cost per passenger mile to help transportation planners and de-
ther collect nor maintain OM cost for BRT systems or their indi- cision makers select the better mode between LRT and BRT sys-
vidual lines. OM costs of the BRT systems were calculated or tems, in the early corridor planning stage or system analysis. An
estimated by the transit agencies according to the average OM cost accurate cost estimation is difficult to obtain; therefore, the cost
of regular bus service. Transit OM cost is primarily influenced by estimating model is established on a unit cost basis and the standard
fleet size, frequency, passenger capacity and route structure. cost components of both systems will be used to avoid unnecessary
Khistry and Lall (2003) found a faster method to determine transit complications. The unit costs allocated to the cost components of
OM cost through application of unit costs to determine an approxi- capital and OM costs in the cost estimating model were derived
mate cost calculation. It was based on (1) distance-related costs, from high-low unit costs of the historical data of existing systems.
i.e., those related to energy, maintenance, and servicing of Such historical data were obtained from multiple resources, includ-
vehicles, (2) time-related costs, i.e., those related to operating staff ing the FTA, Urban Mass Transportation Administration (UMTA),
wages, and (3) route-related costs, i.e., those related to maintenance Transit Cooperative Research Program (TCRP), General Account-
of roadway, track, signals and stations. ing Office (GAO), and the National Transit Database (NTD), in
The fleet size of the system exerts a significant impact on capital addition to local transit agencies and published papers.
and OM costs. Cost estimations can only be conducted after the
fleet sizes of both LRT and BRT have been calculated. Hsu and
Wu (2008) developed a fleet size model, as shown in Eq. (1), Capital Cost
for determining the number of vehicles required in maximum ser-
vice for both LRT and BRT systems operating under various ROW In accordance with the estimating methodology of the FTA, capital
categories. Factors taken into consideration in the fleet size model cost components of the LRT system are classified into eight cost
include vehicle characteristics, passenger demand volume, ROW categories: guideway, yards and shops, systems, stations, ROW, spe-
configurations, numbers of stations, headway, size of vehicle, cial conditions, vehicles, and soft cost (Table 1). The capital cost
and traffic signal timing at the intersections. structure of the BRT system is dissimilar to that of the LRT because
they utilize different technology. Capital cost components of
tt the BRT system are classified into five cost categories: running
pf½T A þ T B þ T c þ ½2ð2ðmp Þhtp þ ð60 ÞÞg
N¼ ð1Þ way, stops and stations, traffic signal priority, vehicles, and soft cost
Cv α (Table 2). The running way of the BRT system has three types: bus-
way, bus-high occupancy vehicle (HOV) lanes and BRT on arterial
where N = number of vehicles needed in maximum service; T A T B , streets. The BRT system’s construction is somewhat similar in many
and T C = round trip travel time, excluding the dwell time at the stop aspects to freeway or highway construction. The route (guideway for
or station of the vehicle running on the exclusive, reserved, and LRT and running way for BRT) of both systems might operate on
mixed traffic ROW (ROW A, B, and C), respectively, in units of various alignments, which are at-grade, elevated or tunnel structure.
hours; p = passengers per hour per direction (pphpd); tt = layover Tables 1 and 2 contain a list of various cost components, high-
and recovery time (min); tp = passenger boarding/alighting time low ranges of the unit costs for each cost component, and their re-
(h/passenger); h = headway (in units of hours); m = number of spective economic lifetime. By using the cost allocation technique,
loading areas per stop for BRT (m ¼ 1 for an LRT system); the LRT and BRT capital cost can be calculated through Eqs. (2)
Cv = seats per vehicle; and α = loading factor. and (3), as follows:
1
CLRT ¼ ½ðG1 U g1 þG2 U g2 þG3 U g3 þU s þU r þU sp ÞL
Problem 1−U so
þðU y þU v ÞN L þðG1 U stL1 þG2 U stL2 þG3 U stL3 ÞS ð2Þ
Most previous cost models and system comparisons do not take both
capital and OM costs into consideration. However, cost comparisons where CLRT = LRT capital cost in millions of dollars; Gi = structure
among different modes should be examined on the basis of total costs, percentage (grade, elevated, and tunnel at i ¼ 1, 2, and 3,
including capital and OM costs, because the provision of transit respectively); L = route length (in units of miles); S = number
service incurs both types of costs. Because of different planning of stops and stations); N L = number of LRT vehicles; U so = soft
and complicated operation scenarios, it is necessary to develop a cost cost (assuming 10% of the total project cost); U gi = LRT guideway
þ G3 U R3 Þ þ ðU t S þ U vB N B Þ þ SðG1 U stB1 into Eqs. (2) and (3), respectively. Therefore, the capital cost of
LRT and BRT can be estimated through Eqs. (4) and (5), as
þ G2 U stB2 þ G3 U stB3 Þ ð3Þ follows:
CLRT=high ¼ 1.1½ð8.6G1 þ 21G2 þ 60G3 þ 17.8ÞL þ ð3.3ÞN L þ ð3.6G1 þ 3.6G2 þ 33G3 ÞS
ð4Þ
CLRT=low ¼ 1.1½ð2.9G1 þ 2.9G2 þ 45G3 þ 3.7ÞL þ ð1.1ÞN L þ ð0.2G1 þ 3.6G2 þ 8G3 ÞS
CBRT=high ¼ 1.1½2Lð2.7G11 þ 2.7G12 þ 9.4G13 þ 27.6G2 þ 96.6G3 Þ þ ð0.04S þ 1.5N B Þ þ Sð3.6G1 þ 3.6G2 þ 33G3 Þ
ð5Þ
CBRT=low ¼ 1.1½2Lð0.01G11 þ 2.3G12 þ 6G13 þ 11G2 þ 55.2G3 Þ þ ð0.01S þ 0.3N B Þ þ Sð0.2G1 þ 3.6G2 þ 8G3 Þ
For the purpose of making a cost comparison between LRT and recovery factor is applied for each cost component in the cost esti-
BRT systems, the capital costs should be annualized to calculate mating model. The annual capital recovery factors have been deter-
the total annual costs, which are the sum of annualized capital cost mined based on an FTA-prescribed 7% interest rate (PBQD 2001) to
(depreciation cost) and annual OM cost. The capital costs are annual- construct the annualized capital cost. The LRT and BRT annualized
ized to represent depreciation and interest changes. An annual capital capital costs can be calculated through Eqs. (6) and (7), respectively,
as follows:
Table 1. Cost Components of LRT Capital Cost
Table 2. Cost Components of BRT Capital Cost
Unit cost
(millions Lifetime Unit cost
Components Unit of dollars) (years) (millions Lifetime
Components Unit of dollars) (years)
Guideway
At-grade $/Mile High 8.6 30 Running way
Low 2.9 At-grade
Elevated $/Mile High 21.0 30 Arterial $/Lane Mile High 0.27
Low 2.9 Low 0.009
Subway $/Mile High 60.0 100 Busway $/Lane Mile High 2.7 30
Low 45.0 Low 2.3
Yards and shops $Shop/Vehicle High 0.9 30 HOV $/Lane Mile High 9.4
Low 0.2 Low 6.0
System $/Mile High 6.2 30 Elevateda $/Lane Mile High 27.6 30
Low 1.3 (Exclusive busway) Low 11.0
Stationa $/Station High 3.6 30 Subway $/Lane Mile High 96.6 100
Low 0.2 (Exclusive busway) Low 55.2
Vehicle $/Vehicle High 2.4 30 Stop, stationb $/Stop High 3.6 30
Low 0.9 Low 0.2
Right-of-way $/Mile High 2.7 100 Traffic signal priority $/Intersection High 0.04 10
Low 1.1 Low 0.008
Special condition $/Mile High 8.9 0 Vehicle $/Vehicle High 1.5 12
Low 1.3 Low 0.3
Project soft cost 10–40% of total Project soft cost 15% of total
project cost (miscellaneous) project cost
Note: Data sources are the following: (1) cost of guideway, system, special Note: Data sources are the following: running way cost (Diaz et al. 2004;
conditions (Schneck 1991). Year 1990 costs will be escalated to year 2000 Levinson et al. 2003); traffic signal priority cost (Diaz et al. 2004; de Garmo
using 1.32 escalation rate. 1 mile = 1.609 kms. (2) cost of yards and shops, 2000), vehicle cost (Levinson et al. 2003). 1 mile = 1.609 km. Costs are in
station, systems, vehicle (FTA 1992). Year 1994 costs will be escalated to year 2000 U.S. dollars.
a
year 2000 using 1.16 escalation rate. (3) project soft cost (PFQD 2001; These facilities can be a major highway (Diaz et al. 2004).
b
Schneck 1991). The stop and station cost of BRT assumes the same as LRT system. Each
a
Each elevated station costs $3.6 million; tunnel station costs between elevated station costs $3.6 million; tunnel station costs between $8 million
$8 million to $33 million, average $21 million (Schneck 1991). Year 1990 and $33 million, average $21 million (Schneck 1991). Year 1990 costs are
costs are escalated to year 2000 using 1.32 escalation rate. escalated to year 2000 using 1.45 escalation rate.
The NTD provides historical data of the OM cost of public trans- where OM = operating and maintenance cost (in millions of dol-
portation systems. Fourteen LRT systems were examined and the lars); x1 = dollars per vehicle-mile; x2 = dollars per vehicle-hour;
data were collected. The existing data of BRT systems are limited. x3 = dollars per route-mile for LRT or dollars per vehicle for
For this reason, BRT systems examined and selected in this re- BRT; x4 = roundtrip travel time (in units of hours); x5 = peak head-
search were based on available data. Data from most existing sys- way (in units of hours); x6 = operating time (in units of hours);
tems were applied to develop the cost estimating model; the data of x7 = cars per train for LRT or buses per stop or station for
the remaining systems proceeded through a validation process to BRT; and x8 = route length (in units of miles) for LRT or vehicles
illustrate how the developed cost estimating model could be applied required in maximum service (in units of number of vehicles)
in the future. for BRT.
Table 3 lists the breakdown of the OM costs of nine existing The roundtrip travel time, x4 , in Eq. (8) can be replaced by the
LRT systems and seven existing bus systems. Most of the data re- product of the number of vehicles required in maximum service (N)
ported by transit agencies to the NTD do not separate BRT buses and peak headway (h) divided by cars per train of LRT or buses per
from regular buses in the system. Consequently, the BRT OM costs stop of BRT (n). Three hundred equivalent working days in a year
are derived from the operating expenses of regular bus systems. The and 20 operating hours per day of transit systems are used as a
cities selected for the seven existing bus systems in Table 3 feature default value. Three peak hours each in the day and evening are
both regular bus and BRT services, because accounting of the BRT applied. Off-peak headway is twice the time of peak headway.
OM cost is more consistent. The components of LRT and BRT/bus Therefore, the annual OM cost for LRT and BRT can be expressed
OM costs are similar, which can be broken down into vehicle as in Eq. (9), as follows:
Table 3. Breakdown of the OM Costs of the Selected LRT and Bus Systems
System Vehicle General Vehicle Non-vehicle
System City operationa operation administration maintenance maintenance Total
LRT Sacramento 40.7 8,091,248 4,306,463 4,819,471 2,111,784 19,328,966
Salt Lake City 29.6 3,834,812 458,701 1,589,763 1,476,417 7,359,693
San Diegob 96.6 14,220,561 7,454,215 6,098,982 4,380,931 32,154,689
Dallas 40.8 12,314,721 7,945,759 5,482,530 7,112,018 32,855,028
Baltimore 57.6 13,750,555 2,706,672 5,315,633 6,962,551 28,735,411
Portland 64.9 11,949,492 9,495,758 9,836,077 10,059,334 41,340,661
St. Louis 34.0 8,701,097 2,479,112 3,762,139 4,648,018 19,590,366
Denver 28.0 4,369,476 2,217,512 2,536,271 2,056,867 11,180,126
Buffalo 12.4 5,963,005 1,756,469 3,247,109 3,549,432 14,516,015
Average percentage 40 21 19 20 100
BRT Seattle 892 151,902,827 26,470,045 46,341,860 19,268,839 243,983,571
San Jose 427 85,661,821 53,304,424 36,029,440 7,300,665 182,296,350
Los Angeles 1,888 346,252,299 112,586,578 157,160,824 21,680,487 637,680,188
Pittsburgh 848 102,988,809 23,749,931 43,436,807 11,219,354 181,394,901
Dallas 441 64,701,387 37,390,858 26,760,162 7,713,013 136,565,420
Denver 639 83,047,498 33,865,201 40,694,718 12,751,070 170,358,487
Miami 530 92,197,192 18,479,944 32,122,633 8,055,418 150,855,187
Average percentage 53 22 19 6 100
Note: Compiled year 2000 data from NTD. 1 mile = 1.609 km. Costs are in year 2000 U.S. dollars.
a
System operation for LRT = rail-total directional route miles, system operation for BRT = vehicles operated in maximum service.
b
Many of the administration costs are not included in the San Diego LRT system (Watkins 2003).
and x3 = dollars per route-mile of LRT or dollars per vehicle where CP = annualized capital cost (in millions of dollars); OM =
of BRT. operating and maintenance cost (in millions of dollars); P =
x1 , x2 , and x3 can be calculated by applying the historical data in passengers per peak hour per direction (pphpd); T adj = adjusted
Table 3. The calculation results of these three unit costs of the OM operating time (in units of hours); and T = operating time (in units
cost are presented in Table 4. The high and low values of x1 , x2 , and of hours).
x3 in Table 4 are input to Eq. (9). Therefore, the high-low annual
OM costs of LRT and BRT systems can be estimated as follows in
Eqs. (10) and (11): Model Verification
model with the existing capital costs of the selected LRT and BRT The difference between existing and estimated capital costs is
systems are listed in Table 5. In Table 5, the existing capital cost of relatively minor.
each selected system falls between the high and low cost ranges
of the estimated costs. The average capital cost estimated from
the cost estimating model is close to the existing capital cost of OM Cost
each selected LRT or BRT system. The differences between the
existing capital cost and the average estimated capital cost of each Route mile (L), number of vehicles (N), peak headway (h), cars per
system are from 0.5–25%. The average difference is 15.5%. train (n) of the LRT system, and buses per stop or per station (n)
Low 4.6
Average 8.2 N ¼ 16
route mile ¼ 8.3
vehicle-mile ¼ 540; 518
vehicle-hour ¼ 45; 312
Boston 89.1 High 111.3 n ¼ 1.9
Low 46.0 h ¼ 2.6 min −12
Average 78.6 N ¼ 154
route mile ¼ 51
vehicle-mile ¼ 6; 334; 450
vehicle-hour ¼ 422; 297
Baltimore 28.7 High 40.0 n ¼ 2.45
Low 13.9 h ¼ 13 min −6
Average 27.0 N ¼ 40
route mile ¼ 57.6
vehicle-mile ¼ 2; 770; 769
vehicle-hour ¼ 174; 408
Cleveland 15.9 High 23.6 n ¼ 1.9 1
Low 8.4 h ¼ 9.2 min
Average 16.0 N ¼ 25
route mile ¼ 30.8
vehicle-mile ¼ 1; 158; 015
vehicle-hour ¼ 76; 173
Los Angeles 61.4 High 77.9 n ¼ 1.65
Low 29.0 h ¼ 5.0 min −13
Average 53.4 N ¼ 51
route mile ¼ 82.4
vehicle-mile ¼ 4; 709; 915
vehicle-hour ¼ 205; 207
BRT Seattle 6.6 High 8.6 n ¼ 2.5 2
Low 4.8 h ¼ 3 min
Average 6.7 N ¼ 25b
route mile ¼ 2.1
Los Angeles 32.7 High 47.4 n ¼ 1.0 11
(Wilshire-Whittier) Low 25.1 h ¼ 2 min
Average 36.3 N ¼ 90b
route mile ¼ 26
Los Angeles 12.5 High 15.0 n ¼ 1.0
(Ventura metro bus) Low 8.0 h ¼ 4 min −8
Average 11.5 N ¼ 29b
route mile ¼ 16
Pittsburgh (east) High 44.7 n ¼ 3.0
Low 23.8 h ¼ 1.7 min
Average 34.2 N ¼ 86b
route mile ¼ 6.8
43.0a 8c
Pittsburgh (south) High 16.1 n ¼ 2.0
Low 8.8 h ¼ 4 min
Average 12.4 N ¼ 37b
route mile ¼ 4.3
Note: Data of the selected BRT systems is from Levinson et al. (2003), n = cars per train of LRT or buses per stop or station of BRT, h = headway, and
N = number of vehicles required. 1 mile = 1.609 km. Costs are in year 2000 U.S. dollars.
a
OM cost in Pittsburgh is estimated as 43,000 average weekday trips × $0.15 per passenger mile × 11.1 route length × 2 × 300 day per year = $43 million
(de Garmo 2000).
b
Applying equation (1) to estimate N, number of vehicles required.
c
8% ¼ ðð34.2 þ 12.4Þ − 43Þ=43.
Table 7. Cost Estimating Model Results of the LRT and BRT Systems
LRT-1 LRT-2 BRT-1 BRT-2 (articulated bus)
Input Route length (mi) 14.6
Passenger demand (pphpd) 3,400
Number of stops and stations 16
Operating hour (h) 20
ROW (%) ROW A: 68; ROW B: 0; ROW C: 32
Alignment (%) at grade: 97; elevated:3
Vehicle passenger capacity
Passengers per vehicle 190 250 45 67
Seats per vehicle 68 190 50 74
Peak headway (min) 10 10 3 3
Output Number of vehicles requireda 42 31 118 74
Capital cost (millions of dollars) 509.1 477.0 311.0 257.0
Millions of dollars per mile 34.8 32.7 21.3 17.6
OM cost (millions of dollars) 27.0 21.6 62.4 38.4
Depreciation cost (millions of dollars)b 29.6 27.1 31.2 24.1
Total annual costs (millions of dollars)c 56.5 48.6 93.6 62.5
Dollars per passenger mile 0.146 0.125 0.242 0.162
Note: Year 2000 costs are escalated to year 2010 using 1.26 escalation rate. 1 mile = 1.609 km. Costs are in year 2010 U.S. dollars.
a
Number of vehicle required is estimated by applying Eq. (1).
b
Depreciation cost = annualized capital cost.
c
Total annual costs = depreciation cost + OM cost.
Table 10. Capital and OM Costs with Respect to Variables in the Cost
Capital and OM costs with Respect to Route Length Estimating Model: Row Configuration
The capital and OM costs with respect to route length in Table 8 ROW (%) Capital cost OM cost
show that the capital cost of BRT is less expensive than that of LRT Fleet size (millions of (millions of
at the same route length. In other words, the cost estimated from the System A B C (vehicles) dollars per mile) dollars)
developed model indicates that the construction of BRT is less ex- LRT 100 0 0 37 31.5 23.8
pensive than that of LRT. On a per unit distance basis, the longer the 40 50 10 40 32.0 24.6
route length, the lower the cost for both LRT and BRT systems; 20 60 20 41 32.4 25.0
however, as the route length increases, the OM cost increases. With 5 65 30 43 32.7 25.4
longer route length, the O&M cost of the BRT is much higher than 5 95 0 40 32.1 24.6
that of the LRT. BRT 100 0 0 94 18.0 52.6
40 50 10 108 19.1 55.8
20 60 20 116 19.8 57.7
Capital and OM costs with Respect to Alignment 5 65 30 124 20.4 59.5
5 95 0 108 19.1 55.7
Configuration
Note: Passenger demand volume = 3,400 pphpd; route length = 14.6 mi;
With respect to alignment configuration of LRT guideway or BRT number of stations and stops = 16; LRT ¼ 68 seats/vehicle, 2.8 passengers/
running way in Table 9, the capital costs of both LRT and BRT seat; BRT ¼ 50 seats/vehicle, 0.9 passengers/seat; 1 mile = 1.609 km. costs
systems will increase greatly if the system is to be elevated or are in year 2009 U.S. dollars.
put underground, especially in the case of tunneling. The capital
cost of the BRT is more expensive than that of the LRT if there
is a portion of elevated or tunnel alignment. The OM costs of Capital and OM costs with Respect to ROW
BRT systems are more expensive than those of LRT systems. How- Configuration
ever, the OM cost will not change no matter how the alignment More or less exclusive ROW will significantly affect the number of
configuration may change. vehicles required and costs. With respect to ROW configuration,
the capital and OM costs of LRT and BRT in Table 10 operating
Table 8. Capital and OM Costs with Respect to Variables in the Cost on a non-exclusive ROW feature higher capital and OM costs than
Estimating Model: Route Length those operating on an exclusive ROW. LRT vehicles exhibit larger
size vehicles and can carry more passengers than bus vehicles.
Route Capital cost (millions of OM Cost (millions
System length (mi) dollars per mile) of dollars)
With the same passenger demand volume and route length, the
differences of capital or OM costs of the BRT that operating on
LRT 5 47.1 12.9 a non-exclusive ROW and an exclusive ROW are greater than those
10 35.8 19.1 of the LRT. The OM cost of BRT depends primarily on ROW
15 32.1 25.4
configuration.
20 30.2 31.6
25 29.1 37.6
BRT 5 32.0 26.8
10 22.7 42.8 Conclusions
15 19.6 58.9
20 18.0 74.9 Choosing between LRT and BRT systems is often controversial and
25 17.1 91.0 not an easy task for transportation planners. In evaluating transit
Note: Passenger demand volume = 3,400 pphpd; number of stations and systems, cost estimating has always been a major consideration.
stops = 16; LRT ¼ 68 seats/vehicle, 2.8 passengers/seat; BRT ¼ 50 seats/ In this paper, a cost estimating model is developed to estimate
vehicle, 0.9 passengers/seat; 1 mile = 1.609 km; costs are in year 2009 capital cost, annualized capital cost (depreciation cost), OM cost
U.S. dollars. and cost per passenger mile for LRT and BRT systems, to aid
modifications, unknown environmental and engineering condi- Hsu, L. R., and Wu, J. W. (2008). “A fleet size model for light rail and
tions, construction schedule, and price inflation. Given that accu- bus rapid transit systems.” Transportation Research Record 2063,
rate values are difficult to obtain, the high and low cost ranges of Transportation Research Board, Washington, DC, 34–42.
cost components are applied to provide more reasonable estimates. Khisty, C. J., and Lall, B. K. (2003). Transportation engineering, Prentice-
The average cost derived from calculation of the cost estimating Hall, Englewood Cliffs, NJ.
model can be used for the systems’ comparison process. The sys- Levinson, H., et al. (2003). TCRP Report 90, National Research
tem with the lower cost per passenger mile is the preferable and Council, Transportation Research Board, Washington, DC.
more cost-effective system. Li, J., and Wachs, M. (2000). “A test of inter-modal performance measures
As a simplified planning tool for evaluation and comparison, the for transit investment decisions.” Transportation, 27(3), 243–267.
cost estimating model can be used for evaluation and comparison to Parsons Brinckerhoff Quade & Douglas (PBQD), Inc. (2001). “Technical
distinguish which system would be a better mode for the respective memorandum: Capital cost estimating methodology-north/southeast
area, so long as the passenger demand volume is given. Beyond corridor study alternative analysis/draft environmental impact state-
ment.” Rep. Prepared for Jacksonville Transportation Authority and
LRT and BRT systems, the cost estimating model could be applied
Florida Department of Transportation, Jacksonville, FL.
extensively to various public transportation systems by changing
Schneck, D. C., Amodei, R. M., and Ferreri, M. G. (1991). “Light rail
the variables and unit costs in the process of cost estimating. transit capacity cost study.” Report, U.S. Department of Transportation,
Urban Mass Transportation Administration, Washington, DC.
United States General Accounting Office (USGAO). (2001). “Mass
References
transit-bus rapid transit shows promise.” Report No. GAO-01-984,
Biehler, A. D. (1989). “Exclusive busways versus light rail transit-a com- Washington, DC.
parison of new fixed- guideway systems.” Transportation Research Vuchic, V. R. (2005). Urban transit: Operations, planning, and economics,
Board Special Report, Washington, DC, 89–97. Wiley, Hoboken, NJ.
de Garmo, F. A. (2000). “Bus rapid transit-a feasibility study for Austin, Vuchic, V. R. (2007). Urban transit systems and technology, Wiley,
Texas.” Thesis, Univ. of Texas at Austin, Austin, TX. Hoboken, NJ.
Diaz, R. B., et al. (2004). “Characteristics of bus rapid transit for Watkins, K. E. (2003). “A comparison of bus rapid transit and light rail
decision-making.” Federal Transit Administration Project No. FTA- transit in ten north American cities.” Thesis, Dept. of Civil Engineering,
VA-26-7222-2004.1, Washington, DC. Univ. of Connecticut, Storrs, CT.