2019-20-Ce Design of Cabled Stayed Bridge - 05
2019-20-Ce Design of Cabled Stayed Bridge - 05
2016 - 2020
R. G. M College of Engineering and Technology
(Autonomous),
Nandyal 518 501, A. P., INDIA
(Affiliated to J. N. T. University, A. P., INDIA)
(Approved by AICTE, Accredited by N.B.A, NewDelhi, NAAC-A+ Grade)
CERTIFICATE
This is to certify that the Project Report entitled ”DESIGN OF CABLED STAYED
BRIDGE” that is being submitted by
In partial fulfillment of the requirement for the award of B.Tech in Civil Engineering in the
RAJEEV GANDHI MEMORIAL COLLEGE OF ENGINEERING AND TECH-
NOLOGY,Nandyal (Affiliated to J.N.T University, Anantapur) is a bonafide record of confide
work carried out by her under our guidance and supervision. The results embodied in this tech-
nical report have not been submitted to any other university or institute for the award of any
Degree.
i
Dedicated to my beloved parents, and teachers who have worked hard throughout my education.
ii
Acknowledgements
We express deep gratitude to our guides Mr.C.SHASHI KIRAN, M.Tech department of Civil
engineering RGMCET for their guidance, scholarly advice, imparting illuminating ideas, benevolent
attitude, a perennial source of inspiration. He also taught us the time sense, discipline and punctual-
ity, which indeed made us to accomplish this piece of work effectively, efficiently and on time. For all
these, we owe them profusely forever.
We take privilege to express our thanks to the Head of the Department Dr.G.SREENIVASULU M.Tech
(IITK), Ph.D.(IISC) for his continuous help and encouragement.
We are highly grateful to Dr. T. JAYACHANDRAPRASAD, Principal, R.G.M. College of Engineer-
ing and Technology, for his encouragement and inspiration at various points of time in the successful
accomplishment of the project.
We shall remain grateful to Dr. M. SHANTHIRAMUDU, Chairman, R.G.M. College of Engineering
and technology who has been a constant source of inspiration throughout the project work and we
also seek his blessings for a bright future.
We shall remain grateful to Mr.M.SHIVARAM, M.D, R.G.M. College of Engineering and technology
who has been a constant source of inspiration throughout the project work and we also seek his bless-
ings for a bright future.We express our special thanks to the all the teaching and non-teaching staff
members of Civil Engineering Department and college who constantly cooperated in the completion
of the project work.
We thank all those who helped in the completion of this work.
PROJECT ASSOCIATES
R.KARTHIK KUMAR YADAV (16091A0139)
E.CHARAN DEEP CHAND GOUD (16091A0111)
SHAIK MOHAMMED SOHAIL (17095A0119)
L.DAYANANDA (16091A0113)
M.PAVAN SAI (16091A0163)
iii
Abstract
Structural design requires a full understanding and knowledge of all the components comprising
the structure. A cable stayed bridge is a type of bridge in which the deck is hung below cables on
vertical cables. The design of modern cable stayed bridges allows to cover the longer distances than
other type of bridges. The main element of a cable stayed bridge is the cable system. Bridges are
normally designed for live load and other occasional loads. All loading and unloading conditions in
analysis and design are provided as per IRC Codal specification. The design of deck, pylon and cable
are analysis manually.
Cable stayed Bridge having with double lane road is analysed by manually. The results presents in-
cluding moments, axial loads, shear force and displacements. Moreover, moments and shear force at
each cable and at any point within the element can be easily obtained from the manually. This project
examines issues analysis and design calculation in over a structure will safe under all conditions.
Keywords:T-beam, longitudinal girder, cross grider, shear force , bending moments, pylon, cables.
iv
Contents
Abstract iv
1 INTRODUCTION 1
1.1 History of bridges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 History of bridges in India . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.3 Importance of bridges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
3 EXPERIMENTAAL INVESTIGATION 11
3.1 Factored to be considered while designing a Bridge . . . . . . . . . . . . . . . . 11
3.1.1 Topography of the area . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.1.2 Traffic load . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3.2 Design of deck slab . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3.2.1 Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
3.2.2 Permissible Stress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
v
3.2.3 Cross Section of Deck . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
3.2.4 Design of interior slab panels . . . . . . . . . . . . . . . . . . . . . . . . 15
3.2.5 Bending moments(live load):- . . . . . . . . . . . . . . . . . . . . . . . . 15
3.2.6 Bending moment(dead loads) . . . . . . . . . . . . . . . . . . . . . . . . 17
3.2.7 Shear forces(live) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
3.2.8 Shear force (dead) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2.9 Total Design moments and shear . . . . . . . . . . . . . . . . . . . . . . 18
3.2.10 Design of section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
3.2.11 Check for shear . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
3.3 Design of longitudinal girder . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
3.3.1 Determination of Reaction factor: . . . . . . . . . . . . . . . . . . . . . . 19
3.3.2 Dead load from slab for girder . . . . . . . . . . . . . . . . . . . . . . . . 20
3.3.3 Dead load bending moment and shear forces . . . . . . . . . . . . . . . . 21
3.3.4 live load Bending moment and the shear forces . . . . . . . . . . . . . . . 22
3.3.5 Design Bending moment and shear Force . . . . . . . . . . . . . . . . . . 23
3.3.6 Design of sections for maximum B.M and S.F . . . . . . . . . . . . . . . 23
3.4 Design of cross girder . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.5 Design of pylon . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.5.1 Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.5.2 Dead loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.5.3 Live load . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
3.6 Design of cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
5 Conclusion 33
vi
List of Figures
vii
3.19 Reinforcement details of pylon . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.20 cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
viii
List of Tables
ix
Chapter 1
INTRODUCTION
A Bridge is a structure constructed over a canal, river, valley, railway, roadway or any such
obstruction. For the purpose of providing passage to the intended traffic above the obstruction.
In the past, the bridges were mostly built in stone masonry or timber. The present-day bridges
are made in reinforced concrete, pre-stressed concrete, structural steel or a composite construc-
tion of RCC and structural steel.
Bridges having very long spans are built in structural steel or pre-stressed concrete whereas for
moderate spans bridge are constructed in RCC.
1
4000 B.C. arch structures, have been found In Egypt. From the 9th century B.C. early Romans
used the stone arch in bridges.
2
in many cases the capture of strategic structure has had a pronounced effect on the outcome
of the war, bridges have been the center of village or city life. Today the structural engineer
has at his disposal the most powerful analytical tool ever imagined, the digital computer; this
instrument can perform in a matter of minutes a volume of calculations that would have pre-
viously taken years.
3
Chapter 2
This comprises Deck slab, Longitudinal girder, Cross girder, Bearings. This bears the load
passing over it and transmits the forces caused by the same to the substructures.
Bearings: The bearings transmit the load received from the decking on to the substructure and
are provided for distribution of the load evenly over the substructure material which may not
have sufficient bearing strength to bear the superstructure load directly
This comprises piers and abutments, wing walls or returns and their foundation.
PIERS AND ABUTMENTS: These are vertical structures supporting deck/bearing provided
for transmitting the load down to the bed/earth through foundation.
WING WALLS AND RETURNS: These are provided as extension of the abutments to retain
the earth of approach bank which otherwise has a natural angle of repose.
FOUNDATION: This is provided to transmit the load from the piers or abutments and wings
or returns to and evenly distribute the load on to the strata. This is to be provided sufficiently
deep so that it is not affected by the scour caused by the flow in the river and does not get
4
undermined. While the above mentioned are structurally operational parts, for safety hand
rails or parapets, guard rails are curbs are provided over the decking to prevent vehicle or user
from falling into the stream or for the separation of traffic streams.
And these components discussed above, are shown in Fig 2.1
• 2. Suspension bridges
5
2.2.1 Cable stayed bridge
This type of bridge is considered suitable for spans varying from 200m to 600m. The main
components of the girders are:
• 1.Towers
• 3.Deck made from concrete or steel spanning across the stiffened girders.
This type of bridges is considered most suitable for spans varying between 400 to 1200 m. The
below fig 2.3 shows the suspension bridge and the main components of a suspension bridge are
listed below.
• 1.Towers
• 3.Anchorage
6
• 4.Suspenders made up of high tensile steel wires
This is the simplest type of bridge where in the deck slab serves as the main load carrying
member. The slab is supported directly on the embankment or sub structure. This type
of construction is considered suitable for culverts or small bridges up to span of about 8m.
Although the thickness of deck slab is considerable (say up to 600mm), the construction of this
type of bridge work out to be economical because of simple arrangement of reinforcement and
less expensive from work. The solid slab bridge is as shown in fig 2.4
7
2.2.4 Slab and girder or T-beam bridge
This type of bridge is commonly built for spans ranging between 10 to 25m. In this case the
deck slab is supported by longitudinal girders or beams which are cast monolithically with the
slab. The number of longitudinal girders in the bridge depend upon the width of the carriage
way. Because of monolithic construction, the longitudinal girders behave as T-beams and are
designed accordingly as shown in Fig 2.5
This is a continuous type of a bridge suitable for spans between 30 to 60m. In this type
of bridge the structural arrangement of decking consists of combination of supported spans,
cantilevers are suspended spans. In the construction of the bridge the main longitudinal girders
from each end span cantilever out from the next to pier abutments as shown in fig 2.6. The
longitudinal girders of the bridge can be T-beam or hallow box type of construction. Due to
introduction of the hinged joints along the length of the longitudinal girder, this type of bridge
can accommodate small differential settlement of support as well as movement of decking due
to temperature variations.
8
Figure 2.6: Balanced cantilever bridge
It is seen that for long spans, the depth of the longitudinal girders in case of T-beam bridge
becomes excessive and the area of the main reinforcement becomes so large that it becomes
difficult to accommodate the bars in the main girders. This type of bridge consists of a top
slab that is normally wider than the box girder. The box girder consists of vertical webs and
a bottom slab usually as broad as the out width of the girder webs is as shown in fig 2.7. This
type of bridge is considered suitable for spans ranging from 30 to 45.
This type of bridge consists of several parallel longitudinal girders (or solid slab) which are
rigidly connected to the supporting columns or piers. The decking and the supporting sub-
structure are normally cast together monolithically. The below fig 2.8 shows the rigid frame
bridge.
9
Figure 2.7: Box-girder bridge
10
Chapter 3
EXPERIMENTAAL
INVESTIGATION
11
In the above figure the blue line shows the path of the bridge in with there are one obstacles
i.e., Tungabhadra river.
To overcome this difficulty a cable-stayed bridge is constructed between near Kurnool tungab-
hadra river leads to Alampur. It is nearly of 600 meters.
In our project the traffic load is taken as IRC class AA tracked vehicle. The figure 3.2 and
figure 3.3 shows the load for IRC class AA tracked vehicle
12
Figure 3.3: elevation of cable stayed bridge
3.2.1 Data
13
3.2.2 Permissible Stress
σ cb=11.67N/mm
σst=240N/mm
m=280/3*σcb=280/3x11.67=7.99 8
J=1-h/3=1-0.280/3=0.9
n=1/(1+σst/m*σcb)=0.280
Q=0.5*n*J* σcb
=0.5x11.67x2.80x0.9=1.67
m=8 J=0.9 n=0.28 Q=1.47
14
Figure 3.5: Tee beam and slab bridge deck
15
Figure 3.6: position of wheel load for maximum bending moment
16
ML=12.862kN.m
17
Effective width of slab=k*(1-x/L)+bw
Breadth of cross girder = 30cm =300mm=0.3m
Clear length of the span = L=4-0.3=3.7m
Clear breadth of the span =B=2.5-0.3=2.2m
B/L=3.7/2.2=1.68
From IRC 21-2000 pg.no-53, k=2.52
Effective width of the slab-=[2.52*0.705(1-0.705/2.2)+3.6+(2*0.08)]=5m
Load perimeter width =350/5=70kN
Shear force =70(2.2-0.705)/2.2=47.60kN
Factored shear force = (1.25*47.60) = 59.50kN
18
Longer span:
Effective depth for longspan using 10mm diameter bar
175-8-5=162mm
Ast=400mm
Spacing s=196.04mm
Adopt 10mm diameter bar with spacing 20mmc/c
19
Figure 3.9: Transverse position IRC Class AA tracked vehicle
W1 = 0.5w
RA=(1.107*0.5w)=0.5596kN
RB=(0.667*0.5w)=0.333w
20
Deck slab =(0.2*1.10*24) = 5.28 kN.m
Kerb = (0.5*0.6*1*24) = 7.2kN.m
Total dead load =(2*15.116)+(6.56*5.3)=65kN.m
It is assumed that the dead load is shared equally by all girders Dead load /girder=65/3=21.66m
Depth of the girder is assumed as 1200mm (100mm for every meter of the span)
Depth of rib = 1.0m
Width = 0.3m
Weight of the rib/m=(1*0.3*1*24)=7.2kN.m
Weight of cross girder = 7.2 kN/m
Reaction of the main girder = (7.2*2.5)=18kN
Reaction from deck slab on each girder =21.66kN.m
Total dead load /m on the girder = (21.66+7.2) = 28.86kN.m
Maximum B.M at centre of span is obtained in figure
RA+RB=28.86X12+18X2=382.82kN
RA=191.41kN RB=191.41KN
Max. BM due to udl = 191.4*6-28.56*6*3= 634.38kN.M
moment max=191.41*6-18*4=1076.45-634.38= 442.08kN.M
Dead load shear at support = 191.41kN
21
3.3.4 live load Bending moment and the shear forces
RA=RB=700kN,RA=350kN,RB=350kN
B.M = RA * 6-700*1.8*(1.8/2)= 966kN.m
B.M including impact and reaction factor for
Outer girder = 9.66* 1.1 *0.5536=733.194 kN.m
Interior girder 966* 1.1*0.33 =350.067 kN.m
for estimating the maximum live load shear in the girder ,the IRC class AA loads are placed is
shown in fig
reaction of w2 on girder B =(350*0.45)/2.5=63
22
reaction of w2 on the girder A = (350*2.05)/2.5=287kN
Total load on girder B = (350+63)=413kN
Max. reaction in girder B=(413*10.2)/12=351.05kN
Max. reaction in girder B=287*10.2/12=243.95kN
Max. live load shear with impact factor is
Inner girder = (351.01*1.1)=386.155kN
Outer girder=(243.95*1.1)=268.34kN
Mmax= 1175.274kN.m
Vmax=577.56kN
The beams id designed as tee-section assuming an effective depth,d=1250mm
Approximate lever arm = (1250-(200/2))= 1150mm
Ast=[1175.2*106 /(200*150)]= 5109.5mm
Provide 16 bars of 32mm diameter HYSD bars in four rows
Provide 32mm diameter bars
Maximize of bars not to exceed 32mm diameters as per IRC :21-1987
Nominal shear stress Tv=(V/bd)=(577.5.56*106 /300*1250)=1.540n/mm Hence safe
Assuming 2 bars of 32mm diameter to be bent up at support section,shear resisted by the
bentup bars is given by
Vs=(σsv.Asv.sinα)=[(200*2*804*1)/(1000*20 .5)]=227kN
Shear resisted by vertical stirrups is computed as balance shear =(557.56-227)=350.56kN
Using 10mm diameter ,4 legged stirrups,spacing
23
Sv=[ σsv.Ast.d/v]
=[(200*4*79*1250)/350.56*106]
=225mm
Provide 10mm diameter 4 legged stirrups at 150mm centres
24
Figure 3.15: position of live load for maximum B.M in cross girder
25
Figure 3.16: Reinforcement details of T-beam and deck slab
26
3.5 Design of pylon
3.5.1 Data
27
Factored axial load on each pylon,Pu=1.5 * 39806.44 = 59709.66kN
Pu = [0.45fck(0.99Ag)+(0.67-0.4fy-0.4fck)0.01Ag]
59709.66 * 103 = [0.445*0.99Ag+(0.67-0.4(500)-0.4(45))0.01Ag]
Ag=15628272.08mm2
p p
Diameterofthepylon= Area(Ag) ∗ 4/Π= (15628272.08 ∗ 4)/π=4460.77=4500mm
Area of Steel=0.01*Ag=0.01*(Π*(4500)2̂)/4=159043.1281 mm2
28
3.6 Design of cable
According to plan, a total 96 cables are provided
For each pylon side cables are=12
The type of cable used is freyssinet for Values from BS 5896:1980 Spacing of cables = 12m
Calculation of loads from 12m span
Self weight of deck slab = 501.12kN
Self weight of longitudinal girder = 311.04kN
Self weight of cross girder = 129.6kN
Self weight of kerbs = 51.84kN
Self weight of railing = 57.6kN
Self weight of Wearing coarse = 158.4kN
Total dead load for 12m span = 1209.6kN
8.7RA=(350x1.15 )+(35 x3.2)+(350x3.2)+(350x5.5)+(350x7.55)
Therefore RA = 700kN and RB=700kN (only for live load)
RA=0.5(1209.6) = 604.8kN(only for dead load)
RB=0.5(1209.6)= 604.8kN(only for dead load)
Total reaction ,R=700+604.8 = 1304.8kN
P = R/Sinα
α = tan( − 1) ((90-12)/(150-6))
P = 1304.8/(Sin(274926.75)) = 2795.449kN
Using 7 mm diameter high tensile wire initially stressed to 1200N/mm2
Force in each wire = 150/2 * 1200/1304.8 = 68.97kN
No of strands in each Cable = 2795.449/68.97 = 40.53 41
29
Figure 3.20: cables
30
Chapter 4
4.1 Results
31
4.1.4 Pylon
4.1.5 Cables
32
Chapter 5
Conclusion
It has been demonstrated that the design of cable stayed bridge generally requires the contri-
bution of several technical professional , each with their own expert knowledge , in order to
achieve the best possible solutions to the various aspects that the cable stayed bridge should
satisfy.It is of fundamental importance that the project manager for a bridge project always
keeps in mind all ascepts of project , their interconnection and any situation where they conflict
in the future.We should be involved in all major decision taken about the global project , which
could influence the conception or design of the cable stayed bridge.
33
References
1. I.R.C:6-2000, Standard Specifications and Code of Practice for Bridges, Section ii, Loads
and Stresses (Fourth Revision), Indian Roads Congress, New Delhi,2000,pp. 1-61.
2. Raina, V.K., Concrete Bridge Practice, Analysis, Design and Economics, Tata McGraw Hill
Publishing Co. Ltd., New Delhi, 1991, pp. 9-25.
3.IRC: 6-2000, Standard Specifications and Code of Practice for Road Bridges Section ii, Loads
and Stresses (Fourth revision), Indian Roads Congress, New Delhi, 2000, pp. 1-61.
4. Krishna Raju, N., Limit State design for Structural Concrete, proceedings of the Institution
of Engineers (India), Vol. 51, Jan. 1971, pp. 138-143.
5. IRC: 21-2000, Standard Specification & Code of Practice for Road Bridges, Section-ii, Ce-
ment Concrete (Plain and Reinforced), (Third revision), the Indian Roads Congress, New Delhi,
2000,
6. Courbon, J., Application de la resistance des Materiaux au calculdes Fonts, Dunod Publi-
cations, Paris, 1950.
7. Sarkar. S, Kapla, M.S; Prasada Rao, A.S and Chhauda, J.N., Handbook for Prestressed
Concrete Bridges, Structural Engineering Research Centre Publication, Roorke (U.P), 1969,
pp. 15-23.
8.IRC:83-1982, Standard Specifications and Code of Practice for Road Bridges, Section ix,
Bearings, Part-1: Metallic Bearings, Indian Roads Congress, 1982, pp. 1-27.
9.IS: 1076-1967, Indian Standard Specifications on Preferred Numbers, Indian Standard Insti-
tution, New Delhi, 1967.
10.Raina, V.K., Concrete Bridges Practice, Analysis, Design & Economics, Tata McGraw Hill
Publishing Co. Ltd., New Delhi, 1991, pp. 138-178.
11.IRC: 6-1966, Standard Specifications and Code of Practice for Road Bridges, Section ii-
Loads & Stresses, Indian Roads Congress, New Delhi, 1997,
34