Saic A 2025
Saic A 2025
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Procedure has been approved & meets the detailed requirements of SAES-A-004,
A2
SAIC-A-2001 (Review Procedure - Pressure Testing) Para. 7.1.1
All required inspection & testing (RT, MT, PT, PWHT, PMI) has been
completed & inspection control sheet has been signed by SA. (ASME 32-SAMSS-004,
A6
VIII, UG-99, Para. A-2) Para 14.1.3
As applicable, an SAEP-1160 Welding Database is reviewed
SAES-A-004
Vents are provided at all high points in the position in which it is to be
B1 Para 7.4.1
tested to purge all possible air during water filling.
All joints and faying surfaces, except those specifically designed and
SAES-W-010,
B4 designated as removable bolted connections, are seal welded by a
Para. 11.15.1
continuous fillet weld (external weep holes are left unwelded).
Weld Summary Record was verified to indicate completion of all weld SAES-W-010,
B5
joints & applicable weld inspection reqmts (visual and NDE). Para. 15.2
32-SAMSS-004,
B6 Post Weld Heat Treatment (PWHT) is complete.
Section 16.3.2
Page 1 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pre-Test Inspection of Pressure Vessels (All Applications,
SAIC-A-2025 15-Dec-09 MECH-
Including In-situ Testing of New Fin Fan Coolers)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Prior to final inspection & pressure test, new vessel internal and external
32-SAMSS-004,
B7 surfaces have been thoroughly cleaned. Any slag, scale, dirt, grit, spatter,
Section 16.2.9
paint, oil, and construction aids are removed.
Vessel Trim (associated piping) receives a strength test except in Utility
services and less when a service test can be conducted. SAES-L-150,
B8
Note: Vessel Trim piping pressure tests are often Para. 5.3
overlooked
Sampling piping systems are pressure tested as an integral part of the
SAES-L-150,
B9 equipment to which it is connected.
Para. 5.3
All welded attachments with telltale holes shall be pneumatically tested at
minimum 35 kPa (5 psi) prior to heat treatment and vessel pressure
32-SAMSS-004,
B10 testing. Telltale holes are OPEN during pressure test.
Section 16.3.3
This is a Bubble Leak test per SAIC-A-2005/A-2021/A-
2023
32-SAMSS-004,
B11 Shellacs, glues, lead, etc.are not applied on gaskets during testing.
Section 16.3.4
Gaskets and bolting materials are as specified on data sheet.
32-SAMSS-004,
B12 Note: Gaskets may be used as service gaskets
Section 16.3.6
if the bolted joint is not disassembled after testing, example: Sumps, etc.
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (30 March, 2005)
2. SAES-A-005, Safety Instruction Sheet, (28 February 2005)
3. SAES-D-008, Repairs, Alterations, and Re-rating of Process Equipment (30 November, 2003)
4. SAES-L-150, Pressure Testing of Plant Piping and Pipelines (16 May 2007)
5. SAEP-1160, Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects. 17 July 2006
6. SAES-W-010, Welding Requirements for Pressure Vessels (14 November 2005)
7. 32-SAMSS-031, Manufacture of Clad Vessels and Heat Exchangers. 31 August, 2003
8. 32-SAMSS-004, Manufacture of Pressure Vessels (30 March, 2005)
9. ASME Section VIII, Division 1 - Rules for Construction of Pressure Vessels (Latest Edition)
10. ASME Section VIII, Division 2 - Rules for Construction of Pressure Vessels, Alternative Rules (Latest Edition)
Page 2 of 3
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pre-Test Inspection of Pressure Vessels (All Applications,
SAIC-A-2025 15-Dec-09 MECH-
Including In-situ Testing of New Fin Fan Coolers)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Name, Initials and Date: Name, Initials and Date:
Page 3 of 3