QA-105-005 2/27/2023
BATTERY CHARGER AND BATTERIES ITR-B
REPORT NUMBER: QA-105 INSPECTION DATE:
PROJECT DESCRIPTION: SYSTEM & SUBSYSTEM:
CONTRACTOR PROJECT AREA:
CLIENT PROJECT REFERENCE: SKID NUMBER:
CLIENT: INSPECTION PERFORMED BY:
EQUIPMENT DESCRIPTION:
TAG NUMBER: TEMP-TAG-016 CONTACTOR SIZE:
EQUIPMENT DESCRIPTION: RATING: VOLTS AMPS KVA
CELL VOLTAGE: NO. OF CELLS:
DRAWING NO: TYPE:
SERIAL NO: CALIBRATION EXPIRY DATE:
PRE-COMMISSIONING CHECKS
CONFIRMED
SN INSPECTION TEST DESCRIPTION
YES NO NA
PRIOR TO COMMISSIONING TAKING PLACE, REFER TO VENDOR MANUAL AND RECOMMENDED TEST
1
PROCEDURES.
2 VISUALLY INSPECT EQUIPMENT FOR DAMAGE.
3 ENSURE ALL EQUIPMENT IS CLEAN AND FREE FROM DUST, AND PRESERVATION MATERIALS REMOVED.
4 CONFIRM ALL MANUFACTURERS SETTINGS ARE CORRECT, (FUSES, TIMERS ETC).
5 CONFIRM BATTERIES ARE CONNECTED AND DC BREAKER IS IN THE OFF POSITION
6 CONFIRM BATTERY TEMPERATURE SENSOR IS CORRECTLY INSTALLED.
CHECK AND RECORD FEEDER CABLE CONTINUITY AND INSULATION RESISTANCES :
7
CHARGER 1 OHMS CHARGER 2 OHMS ACH OHMS
8 CHECK AND RECORD CHARGER TO VESSEL GROUND RESISTANCES. OHMS
CONFIRM DISTRIBUTION CIRCUIT BREAKERS ARE ISOLATED IN ACCORDANCE WITH THE PROJECT PERMIT
9
TO WORK PROCEDURE.
WITH CHARGER INCOMING SUPPLY CIRCUIT BREAKERS IN THE OFF POSITION , ENERGIZE SUPPLIES TO
BOTH CHARGERS AND CONFIRM CORRECT PHASE ROTATION AND VOLTAGE
10
CHARGER 1: L1-L2 V L2-L3 V L1-L3 V PHASING
CHARGER 2: L1-L2 V L2-L3 V L1-L3 V PHASING
11 CHECK AND RECORD GROUND LOOP IMPEDANCE (GF PROTECTION NOT PROVIDED) OHMS
12 ENERGIZE ANTI CONDENSATION HEATERS CONFIRM CORRECT POLARITY AND VOLTAGE
IN ACCORDANCE WITH THE MANUFACTURERS TEST PROCEDURE ENERGIZE CHARGER 1 AND 2 AND
13
CONFIRM CORRECT OUTPUT POLARITY WITH BATTERIES PRIOR TO COMMENCING BATTERY CHARGING.
IN ACCORDANCE WITH THE MANUFACTURERS TEST PROCEDURE PROVE OPERATION OF THE FOLLOWING:
(ADDITIONAL TESTS TO BE RECORDED IN REMARKS) CHARGER 1 CHARGER 2
AC POWER AVAILABLE LED
AC BREAKER CLOSED LED
DC BREAKER CLOSED LED
OVER TEMPERATURE ALARM / INDICATION
14 OVERLOAD ALARM /INDICATION
DC UNDER VOLTAGE ALARM / INDICATION
AC BREAKER SHUNT TRIP AND DISABLE KEY SWITCH
OPERATION
GROUND FAULT
BATTERY ALARM
TRIP AND DISABLE KEY SWITCH OPERATION
COMMON FAULT ALARM
CONSTRUCTION EQUIPMENT USED (IF APPLICABLE)
EQUIPMENT DESCRIPTION SERIAL NUMBER
COMMENTS
ACTION REQUIRED
NON-CONFORMANCE REPORT: RED-LINE REVISION REQUIRED:
VERIFIED BY CONTRACTOR PERSONNEL
NAME: COMPANY: SIGNATURE:
DATE: POSITION:
VERIFIED BY OTHER
NAME: COMPANY: SIGNATURE:
DATE: POSITION:
4 of 5
QA-105-005 2/27/2023
BATTERY CHARGER AND BATTERIES ITR-B
REPORT NUMBER: QA-105 INSPECTION DATE:
PROJECT DESCRIPTION: SYSTEM & SUBSYSTEM:
CONTRACTOR PROJECT AREA:
CLIENT PROJECT REFERENCE: SKID NUMBER:
CLIENT: INSPECTION PERFORMED BY:
EQUIPMENT DESCRIPTION:
TAG NUMBER: TEMP-TAG-016 CONTACTOR SIZE:
EQUIPMENT DESCRIPTION: RATING: VOLTS AMPS KVA
CELL VOLTAGE: NO. OF CELLS:
DRAWING NO: TYPE:
SERIAL NO: CALIBRATION EXPIRY DATE:
PRE-COMMISSIONING CHECKS
CONFIRMED
SN INSPECTION TEST DESCRIPTION
YES NO NA
IN ACCORDANCE WITH THE MANUFACTURERS TEST PROCEDURE PROVE OPERATION OF THE FOLLOWING:
(ADDITIONAL TESTS TO BE RECORDED IN REMARKS) CHARGER 1 CHARGER 2
PROVE OPERATION OF EXTERNAL TRIPS AND ALARMS, F&G,
15
ESD ETC.
WITH BATTERIES ON CHARGE CONFIRM THE FOLLOWING IS IN
COMPLIANCE WITH MANUFACTURERS TEST RECORDS.
16
FLOAT CHARGING CURRENT
FLOAT CHARGING VOLTAGE
FULLY CHARGE BATTERY BANK AND CHECK FULLY CHARGED
TERMINAL VOLTAGE. MONITOR BATTERY TEMPERATURE,
17
TERMINATE TEST IF TEMPERATURE EXCEEDS
MANUFACTURERS
TERMINAL VOLTAGESPECIFICATION.
= VDC
VDC
PERFORM A BATTERY DISCHARGE TEST
IN ACCORDANCE WITH BATTERY MANUFACTURER
INSTRUCTIONS AND PROJECT SPECIFICATIONS.
RECORD RESULTS BELOW
18 TERMINAL VOLTAGE BEFORE DISCHARGE
TERMINAL VOLTAGE AFTER DISCHARGE
RECHARGE BATTERY BANK AND RECORD
FULLY CHARGED TERMINAL VOLTAGE VDC
CONSTRUCTION EQUIPMENT USED (IF APPLICABLE)
EQUIPMENT DESCRIPTION SERIAL NUMBER
COMMENTS
ACTION REQUIRED
NON-CONFORMANCE REPORT: RED-LINE REVISION REQUIRED:
VERIFIED BY CONTRACTOR PERSONNEL
NAME: COMPANY: SIGNATURE:
DATE: POSITION:
VERIFIED BY OTHER
NAME: COMPANY: SIGNATURE:
DATE: POSITION:
5 of 5