Weekly Management EHSS Walkthrough Report - HCIS Project - 13.11.2024

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views1 page

Weekly Management EHSS Walkthrough Report - HCIS Project - 13.11.2024

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Classification: Internal Use #

HCIS Project Weekly Safety Walkthrough


Attendants:

1 Jihad Albadawi Project Manager (NESMA), Zone-3 (Y)

2 Majed Khan Construction Manager (NESMA), Zone-3 (Y)

3 Khalid Alhejaili Site Engineer, Project (NESMA) • Zone-3 (Y)

5
Afrajuddin Khan

Naeem Bhatti
HSE Manager, Project (NESMA) • Zone-3 (Y)

Project Manager (Expertise) • Zone-3 (Y)


13-Nov-2024
6 Bravin Vinoth Construction Manager (Expertise) • Zone-3 (Y)

7 Ersto Flores Civil Engineer (Expertise) • Zone-3 (Y)

8 Manish Kumar Singh Safety Supervisor (NESMA) Zone-3 (Y)

9 Sultan Al Suhaymi Safety Officer (NESMA) Zone-3 (Y)

10 Mohammad Manzoor Alam Safety Supervisor (Expertise) Zone-3 (Y)

11 Jamshaid Ali Safety Supervisor (NESMA) Zone-3 (Y)

12 Md. Shahbaz Alam Safety Supervisor (Expertise) Zone-3 (Y)

SN Date Project/Location Observation Safe Observations Contractor Action By Status Corrective Action Preventive Action Target date

ECC shall provide the good quality of


Poor quality blanket has fire blanket, fire extinguisher shall be
1 13-Nov-24 Zone-3 Yanbu HCIS - YANBU Poor quality of fire blanket was observed at SFB Gate#2. NESMA ECC Closed 15-Nov-24
been removed from site. approved by ECC HSE prior to mobilize
at site.
NUI EHSS shall ensure the compliance
NUI HSE team instructed
2 13-Nov-24 Zone-3 Yanbu HCIS - YANBU NUI HSE team was observed not wearing red shirt. NESMA ECC Closed to project ITB for safety personnel 14-Nov-24
to wear red shirt.
uniform.
ECC scaffold supervisor was instructed
Scaffold bracing for rest shelter was observed creating Bracing has been to ensure that the bracing shall not
3 13-Nov-24 Zone-3 Yanbu HCIS - YANBU NESMA ECC Closed 13-Nov-24
tripping hazard. modified. exceed the standard overlap and create
any tripping hazard.
Scaffold supervisor was instructed to
Scaffold platform was observed with inadequate anchorage Additional anchorage ensure the availability of adequate
4 13-Nov-24 Zone-3 Yanbu HCIS - YANBU NESMA ECC Open 13-Nov-24
point for carpenter. point has been installed. anchorage point for the work crew as
per their work position as applicable.