SECTION 06 43 16
WOOD RAILINGS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Wood balustrade railing system
2. Components and accessories
F. [Section 09 91 00 - Painting]
09 05 61-1
1.3 ACTION SUBMITTALS
A. Product Data: Technical data, physical properties and installation instructions for each component.
A. Manufacturer Qualifications:
1. Minimum of 5-years documented experience producing specified materials.
2. Fabricates structural polyurethane balustrades and railing systems.
B. Installer Qualifications:
1. Minimum 5-years documented installation experience of specified materials.
2. Manufacturer approved installer.
E. Mock-Up:
1. Full-size mock up erected at site, to verify color, workmanship and installation details.
2. Complete assembly, color, sheen and model extending a minimum of 5-feet.
3. Must be approved, prior to proceeding with installation of materials.
4. Immediately remove non-conforming work and re-install mockup at the direction of Architect.
4. Approved materials may remain as part of finished installation when approved by Architect.
A. Temperatures above 50°F and humidity less than 50% relative humidity.
C. Store materials are above grade and protected from sun, water, snow and damage prior to installation.
1.8 WARRANTY
A. Installer to warrant installation for a period of 5-years for defects. Repair or replace materials during warranty
period at no cost to Owner.
09 05 61-2
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis of Design: American Porch, LLC. 310 6th Street, Townsend, MT Toll Free: (888) 459-9965
www.americanporch.com; email: [email protected]
2.2 MATERIALS
9. Top Finial:
a. Ball Top: [2-7/8 inch] [3-1/2inch] [5 inch] [7 inch] [8 inch] [9 inch] [10 inch] [12 inch]
b. Decorative:
1. Style: [add manufacturers style number based on catalog]
2. Size: [add height]
3. Base Diameter: [add base size]
2.3 ACCESSORIES
A. Rail Install kit: Manufacturers standard hardware kit for fastening railings to a newel, column or wall.
1. Brackets
2. Screws
09 05 61-3
1. Installation Surface: [Wood Deck] [Concrete]
D. Paint: Primed and finished with exterior grade, commercial paint color as selected by Architect.
2.4 FABRICATION
A. Fit, shape, and assemble components in largest practical sizes, joining components with tightly fitted and
secured joints.
C. Provide components required for anchoring, fastening and maintaining structural requirements.
PART 3 EXECUTION
3.1 EXAMINATION
C. Verify substrates and adjacent surfaces are level and plumb for installation.
1. Do not begin work until construction has progressed to allow installation of materials.
3.2 INSTALLATION
B. Remove contaminates from surfaces and apply paint within 30 days of installation.
1. Verify Architects approved material and color prior to application.
3.3 PROTECTION
A. Protect surface, corners and components from damage prior to Owner occupancy using temporary protection.
END OF SECTION