Budget Forecast Excel Spreadsheet
Budget Forecast Excel Spreadsheet
Summary
The present report is submitted pursuant to Executive Board decision 2005/36 of 9 September
2005. The progress report provides an update on progress achieved in the implementation of
action to restore the viability of the United Nations Office for Project Services and an update on
the projected 2005 year-ending financial results.
Elements of a decision
The Executive Board may wish to take note of the progress report.
DP/2006/11
Contents
Chapter Page
Introduction...............................................................................................................................
3
I.Status of implementation of Executive Board decision 2005/36..............................................
3
II. Risk assessment and contingency planning during 2006-2007...............................................
4
III. 2005 Estimated year-to-date results and year-end Financial Projections................................
5
Annexes
1. Revised 2006-2007 biennium projections...............................................................................
6
2. Projected 2005 year-end financial results.............................................................................. 7
2
DP/2006/11
Introduction
1. In its second regular session of 2005, the Executive Board requested the
Executive Director of the United Nations Office for Project Services (UNOPS),
through decision 2005/36, to carry out expeditiously a set of reform measures aimed
at restoring the financial viability of the organization. The present report is submitted
to the Executive Board through the Management Coordination Committee (MCC) of
the United Nations Office for Project Services.
centre; (b) rationalization of the European office network into the new UNOPS
headquarters location and consolidation of the UNOPS presence in Africa;
(c) consolidation of the emergency response and disaster preparedness capability;
and (d) implementation, over 2006-2007, of a business process improvement
programme. These measures will lead to a 25 per cent reduction in managerial posts
and an estimated 15 per cent reduction of programme management staff on
completion of the client portfolio rationalization.
8. The costs associated with the relocation, transfer of staff and non-renewal of
contracts component of the overall transition programme are estimated at $6.33
million in 2006 and $1 million in 2007. The transition programme costs will be
absorbed by the grant provided for by the Government of Denmark.
Reducing the fixed-cost base, adjusting portfolio delivery and restoring the
operational reserve
9. During the first quarter of 2006, UNOPS will proceed with a comprehensive
review of its business portfolio aimed at streamlining the delivery of its services;
wherever feasible, service delivery will take place at the country level. This activity
will precede the subsequent rationalization of the high fixed-cost regional client
division structure.
10. The level of delivery under the project portfolio of services is projected to
reach $781 million in 2006 and to level off at $612 million in 2007. The project
portfolio delivery volume is adjusted to reflect the gradual phase-out of current
lower value-added service lines producing marginal to negative returns, in
accordance with the provisions contained in the Executive Board decision 2005/36.
While the impact of the portfolio rationalization is expected to remain modest during
2006, it will accelerate the following year. Hence, projections account for an
estimated 20 per cent downward adjustment for portfolio delivery in 2007.
11. The overall financial performance is expected to improve. All costs for the
transition programme and the relocation are covered under the relocation grant. The
organization will thus generate income of $6.5 million in 2006, and targets a similar
level of income generation in 2007. It is noteworthy that the projected 2007 income
level would be achieved while overall delivery levels are reduced by 20 per cent. The
operational reserve will be replenished accordingly.
Adjusting service pricing and streamlining business processes
12. Activity-based costing pilots will be introduced during 2006 to price service
delivery more accurately, and a new UNOPS pricing policy will be instituted by mid-
2006. Similarly, UNOPS will engage in a revision and adjustment of its most basic
business processes to enhance process efficiency and thus reduce costs.
4
DP/2006/11
(b) If the long-term lease of the current New York premises cannot be
terminated on acceptable terms, UNOPS will make every effort to sublease
available office space for the remaining lease period thus limiting its financial
exposure.
(c) If business managers with delegated authority overspend on administrative
expenditures or do not meet their revenue targets in the first quarter of 2006,
budget authority will be centralized.
(d) Conservative business acquisition ratios underpin the projections to
mitigate, inter alia, possible market volatility or shrinkage.
5
DP/2006/11
Reimbursement expenditures
PeopleSoft/Atlas payment to UNDP 3.50 1.94 0.18 2.12
Reimbursement costs 3.91 2.65 0.24 2.89
Subtotal 7.41 4.59 0.42 5.01
6
DP/2006/11
Administrative expenditures
Salary and benefits 25.29 19.84
General and administrative 18.14 13.56
Subtotal 43.43 33.40
Reimbursement expenditures
PeopleSoft/Atlas payment to UNDP 3.10 3.10
Reimbursement costs 4.79 4.79
Subtotal 7.89 7.89
7
DP/2006/11
8
DP/2006/11
9
DP/2006/11
10
DP/2006/11
11
DP/2006/11
12
DP/2006/11
13
DP/2006/11
—————
14