AWWA C605-2005 - Underground Installation of Polyvinyl Chloride Pressure Pipe and Fittings For Water
AWWA C605-2005 - Underground Installation of Polyvinyl Chloride Pressure Pipe and Fittings For Water
AWWA Standard
Underground Installation
of Polyvinyl Chloride
(PVC) Pressure Pipe and
Fittings for Water
CAUTION NOTICE: The American National Standards Institute (ANSI) approval date on the front cover of this standard
indicates completion of the ANSI approval process. This American National Standard may be revised or withdrawn at
any time. ANSI procedures require that action be taken to reaffirm, revise, or withdraw this standard no later than five
years from the date of publication. Purchasers of American National Standards may receive current information on all
standards by calling or writing the American National Standards Institute, 25 West 43rd Street, Fourth Floor, New York,
NY 10036; (212) 642-4900.
All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means, electronic
or mechanical, including photocopy, recording, or any information or retrieval system, except in the form of brief
excerpts or quotations for review purposes, without the written permission of the publisher.
ii
Committee Personnel
The AWWA Standards Subcommittee on Standard C605, which developed this standard,
had the following personnel at the time:
The AWWA Standards Committee on PVC Pressure Pipe and Fittings, which reviewed and
approved this standard, had the following personnel at the time of approval:
* Liaison, nonvoting
† Alternate
iii
Producer Members
User Members
iv
Contents
All AWWA standards follow the general format indicated subsequently. Some variations from this format
may be found in a particular standard.
SEC. PAGE SEC. PAGE
Foreword 4 Excavation
I Introduction..................................... vii 4.1 Trench Preparation............................ 7
I.A Background...................................... vii 4.2 Trench Construction ......................... 7
I.B History............................................. vii
5 Pipe Installation
I.C Acceptance ....................................... vii
5.1 Material Inspection.......................... 10
II Special Issues..................................... ix
5.2 Precautions ...................................... 10
III Use of This Standard ........................ ix
5.3 Pipe Embedment ............................. 10
III.A Purchaser Options and
5.4 Pipe Laying...................................... 11
Alternatives .................................... ix
5.5 Pipe Joining ..................................... 11
III.B Modification to Standard................... x
5.6 Pipe Bending and Gradual
IV Major Revisions ................................. x
Alignment Change........................ 14
V Comments ......................................... x
5.7 Thrust Restraint............................... 15
Standard 5.8 Backfill............................................. 15
v
SEC. PAGE SEC. PAGE
vi
Foreword
This Foreword is for information only and is not a part of ANSI/AWWA C605.
I. Introduction.
I.A. Background. ANSI/AWWA C605, Standard for Underground Installa-
tion of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water, is offered as a
reference to be used when constructing new water distribution systems and water
transmission pipelines or when making repairs or extensions to existing water
distribution systems and water transmission pipelines. This standard provides
information on pipe handling, trench excavation, pipe installation, appurtenance
placement, and preparation of pipelines for use. It is not intended that this AWWA
standard be used as a contract document; however, it may be used as a reference in
contract documents. This standard represents the consensus of the standards
committee on the recommended practice for the proper installation of polyvinyl
chloride (PVC) pressure water pipe. The standard is not intended to preclude the
manufacture, marketing, purchase, or use of any product, process, or procedure.
I.B. History. This is the second edition of ANSI/AWWA C605. In 1978, the
AWWA Standards Council authorized the AWWA Standards Committee on
Thermoplastic Pressure Pipe to prepare a design and installation manual that would
be followed by an installation standard for PVC pressure pipe. AWWA Manual
M23, PVC Pipe—Design and Installation, was published in 1980. On completion of
the manual, development of this standard began. The first edition was effective July
1, 1995.
In 1988, the AWWA Standards Committee on Thermoplastic Pressure Pipe was
dissolved to allow for the formation of the AWWA Standards Committee on
Polyvinyl Chloride (PVC) Pressure Pipe and Fittings. A new subcommittee was
convened to resume work on the installation standard in 1989. This second edition
of C605 was approved by the AWWA Board of Directors on June 12, 2005.
I.C. Acceptance. In May 1985, the US Environmental Protection Agency
(USEPA) entered into a cooperative agreement with a consortium led by NSF
International (NSF) to develop voluntary third-party consensus standards and a
certification program for direct and indirect drinking water additives. Other members
of the original consortium included the American Water Works Association Research
Foundation (AwwaRF) and the Conference of State Health and Environmental
vii
Managers (COSHEM). The American Water Works Association (AWWA) and the
Association of State Drinking Water Administrators (ASDWA) joined later.
In the United States, authority to regulate products for use in, or in contact with,
drinking water rests with individual states.* Local agencies may choose to impose
requirements more stringent than those required by the state. To evaluate the health
effects of products and drinking water additives from such products, state and local
agencies may use various references, including
1. An advisory program formerly administered by USEPA, Office of Drinking
Water, discontinued on Apr. 7, 1990.
2. Specific policies of the state or local agency.
3. Two standards developed under the direction of NSF, NSF†/ANSI‡ 60,
Drinking Water Treatment Chemicals—Health Effects, and NSF/ANSI 61, Drinking
Water System Components—Health Effects.
4. Other references, including AWWA standards, Food Chemicals Codex, Water
Chemicals Codex,§ and other standards considered appropriate by the state or local
agency.
Various certification organizations may be involved in certifying products in
accordance with NSF/ANSI 61. Individual states or local agencies have authority to
accept or accredit certification organizations within their jurisdiction. Accreditation
of certification organizations may vary from jurisdiction to jurisdiction.
Annex A, “Toxicology Review and Evaluation Procedures,” to NSF/ANSI 61
does not stipulate a maximum allowable level (MAL) of a contaminant for substances
not regulated by a USEPA final maximum contaminant level (MCL). The MALs of
an unspecified list of “unregulated contaminants” are based on toxicity testing
guidelines (noncarcinogens) and risk characterization methodology (carcinogens).
Use of Annex A procedures may not always be identical, depending on the certifier.
*Persons outside the United States should contact the appropriate authority having jurisdiction.
†NSF International, 789 N. Dixboro Road, Ann Arbor, MI 48105.
‡American National Standards Institute, 25 West 43rd Street, Fourth Floor, New York, NY 10036.
§ Both publications available from National Academy of Sciences, 500 Fifth Street N.W.,
Washington, DC 20418.
viii
ANSI/AWWA C605 does not address additives requirements. Users of this
standard should consult the appropriate state or local agency having jurisdiction in
order to
1. Determine additives requirements, including applicable standards.
2. Determine the status of certifications by all parties offering to certify prod-
ucts for contact with, or treatment of, drinking water.
3. Determine current information on product certification.
II. Special Issues. There are no special issues related to this standard.
III. Use of This Standard. It is the responsibility of the user of an AWWA
standard to determine that the products described in that standard are suitable for use
in the particular application being considered.
III.A. Purchaser Options and Alternatives. The following items should be pro-
vided by the purchaser:
1. Standard used—that is, ANSI/AWWA C605, Underground Installation of
Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water, of latest revision.
2. Reference to applicable plans, drawings, specifications, and other contract
documents (all sections).
3. Whether compliance with NSF/ANSI 61, Drinking Water System Compo-
nents—Health Effects, is required, in addition to the requirements of the Safe Drink-
ing Water Act.
4. Details and requirements of state, local, and provincial requirements (Sec. 1.5).
5. Materials inspection and acceptance requirements (Sec. 2.1).
6. Affidavit of compliance (Sec. 2.1).
7. Special provisions for conflicting utilities and responsibility for facilities and
responsibility for the location, relocation, and repair of the conflicting facility or relo-
cation of the pipeline if necessary (Sec. 3.1.3 and Sec. 3.2).
8. Notification requirements (Sec. 3.3).
9. Open trench, trench water, and trench stability requirements (Sec. 4.1).
10. Requirements for the protection of workers and the safety of the general
public (Sec. 4.1.1).
11. Special provisions for excavation and trenching requirements (Sec. 4.2).
12. Trench width, depth, bottom preparation, rock conditions, previous excava-
tion, blasting, unstable subgrade, dewatering, and excavated material requirements
(Sec. 4.2).
ix
13. Special trench foundations (Sec. 4.2.7).
14. Open trench, trench water, and trench stability requirements (Sec. 4.1).
15. Special embedment materials (Sec. 5.3).
16. Special provisions for testing, including the assignment of responsibility for
providing and conveying water for flushing, testing, disinfection, and provisions for
disposal of disinfection water. Assignment of responsibility for providing equipment
for testing witnessing and required recording of test results (Sec. 7).
17. Special requirements for the method of disinfection, sampling, and analysis
(Sec. 7). (See ANSI/AWWA C651, Standard for Disinfecting Water Mains, of latest
revision.)
18. System design pressure, required test pressure and test duration (Sec. 7.3.5
and Sec. 7.3.4).
III.B. Modification to Standard. Any modification of the provisions, defini-
tions, or terminology in this standard must be provided by the purchaser.
IV. Major Revisions. The revisions made to this edition of ANSI/AWWA
C605 are minor. There are no major revisions.
V. Comments. If you have any comments or questions about this standard,
please call the AWWA Volunteer & Technical Support Group at 303.794.7711, FAX
at 303.795.7603, write to the group at 6666 West Quincy Avenue, Denver, CO
80235-3098, or email at [email protected].
x
ANSI/AWWA C605-05
(Revision of ANSI/AWWA C605-94)
AWWA Standard
Underground Installation of
Polyvinyl Chloride (PVC) Pressure
Pipe and Fittings for Water
SECTION 1: GENERAL
*American National Standards Institute, 25 West 43rd Street, Fourth Floor, New York, NY 10036.
1
2 AWWA C605-05
ASTM F1674—Standard Test Method for Joint Restraint Products for Use with
PVC Pipe.
UNI-B-8*—Recommended Practice for the Direct Tapping of Polyvinyl
Chloride (PVC) Pressure Water Pipe (Nominal Diameters 6–12 Inch).
UNI-PUB-8—Tapping Guide for AWWA C900 Pressure Pipe.
AWWA Manual M17, Installation, Field Testing, and Maintenance of Fire
Hydrants. AWWA, Denver, Colo.
AWWA Manual M23, PVC Pipe—Design and Installation. AWWA, Denver,
Colo.
AWWA Manual M3, Safety Practices for Water Utilities. AWWA, Denver, Colo.
AWWA Manual M12, Simplified Procedures for Water Examination. AWWA,
Denver, Colo.
*Uni-Bell PVC Pipe Association, 2655 Villa Creek Drive, Suite 155, Dallas, TX 75234.
4 AWWA C605-05
traffic and secured to prevent rolling. Bell ends on pipe should be pointed in the
direction of work progress. Caution shall be exercised to minimize the contamination
of pipe interiors and joint components.
SECTION 4: EXCAVATION
Blocking shall not be used to change pipe grade or to intermittently support pipe
across excavated sections. When embedment Type 4 or 5 (See Figure 1) is specified,
bell holes at each joint shall be provided that conform to the shape of the pipe bell.
4.2.4 Rock conditions. Ledge rock, boulders, cobbles, and large stones shall be
removed to provide at least 4 in. (100 mm) of embedment cushion on each side of
and below pipe and appurtenances (see Figure 1). The excavation shall be sufficiently
wide to enable proper placement of the embedment specified by the purchaser. When
excavation is completed, embedment material shall be placed, leveled, and compacted
to provide a proper cushion for the pipe. Such embedment shall be granular material
graded in particle size so that the embedment material supporting the pipe shall be
retained in place under all conditions, including the rapid movement of water through
the pipe embedment and the surrounding material.
4.2.5 Previous excavations. If the trench passes over another pipeline or other
previous excavation, the trench bottom shall (1) be compacted to provide support
equal to that of the undisturbed native soil or (2) conform to specific regulatory
requirements that preclude damage to the existing installed facility.
4.2.6 Blasting. Blasting for excavation shall be permitted only when specified
by the purchaser and when proper precautions have been taken for the protection of
persons and property. Hours permitted for blasting shall be specified by the
purchaser. Damage caused by blasting shall be repaired by the constructor at no
additional expense to the purchaser. Blasting procedures shall conform with
applicable laws, ordinances, and regulations imposed by federal, state, provincial, or
local authorities.
4.2.7 Unstable subgrade. Where an unstable subgrade condition exists that,
in the opinion of the purchaser, cannot support the pipe, an alternative foundation
shall be provided. At the discretion of the purchaser, an additional depth shall be
excavated and refilled to pipe foundation grade with embedment material or special
pipe foundation material in accordance with the purchase documents. Any part of
the trench excavated below grade shall be backfilled to grade and compacted to the
required density. Such embedment material shall have a gradation that inhibits
migration of soil particles.
4.2.8 Dewatering. Where running or standing water occurs in the trench
bottom or where the soil in the trench bottom displays a “quick” tendency, the water
shall be removed by pumps. The trench shall be kept free from water during
installation operations by suitable means, such as well points or pervious underdrain
UNDERGROUND INSTALLATION OF PVC PIPE 9
Type 1 Type 2
Flat-bottomed trench.* Loose embedment. Flat-bottomed trench.* Embedment lightly
E' = 60 psi (340 kPa), K = 0.110 consolidated to centerline of pipe.
E' = 200 psi (1,380 kPa), K = 0.110
Type 3
Pipe bedded in 4 in. (100 mm) minimum of loose
soil.† Embedment lightly consolidated to top of pipe.
E' = 600 psi (2,760 kPa), K = 0.102
Type 4 Type 5
Pipe bedded in sand, gravel, or crushed stone to depth of Pipe embedded in compacted granular material to
1/8 pipe diameter, 4 in. (100 mm) minimum. Embedment centerline of pipe. Compacted granular or select material†
compacted to top of pipe. (Approximately 80 percent to top of pipe. (Approximately 90 percent
Standard Proctor or AASHTO T-99). Standard Proctor or AASHTO T-99).
E' = 1,000 psi (6,900 kPa), K = 0.096 E' = 2,000 psi (13,800 kPa), K = 0.083
NOTE: Required embedment type will depend on the pipe's dimension ratio, internal operating pressure, and external load
and shall be specified by the purchaser (see Sec. 5.3).
*Flat-bottom is defined as undisturbed earth.
†Loose soil or select material is defined as native soil excavated from the trench, free of rocks, foreign materials, and frozen
earth. A soft loose soil bedding will contour to the pipe bottom. Caution must be exercised to ensure proper placement of
embedment material under the haunches of the pipe.
bedding, until the pipe has been installed and backfill placed and compacted to a
sufficient height to prevent pipe flotation. A cover depth of 1.5 pipe diameters will
normally prevent flotation. For pipes having a dimension ratio (DR) greater than
32.5, a cover minimum of 2.0 pipe diameters is recommended.* Soil migration in the
*A 1.5-pipe-diameter cover depth is based on a saturated backfill having a dry density of only 90 lb/ft3
(1,440 kg/m3).
10 AWWA C605-05
pipe zone shall be prevented through the use of geotextile fabric or embedment
material gradation.
4.2.9 Excavated material. Excavated material shall be placed in a manner
that will not obstruct work or endanger personnel or the public. Excavated material
shall not obstruct sidewalks or driveways for extended periods unless provided for in
the contract documents. Hydrants under pressure, valve-pit covers, valve boxes,
curb-stop boxes, fire and police call boxes, or other utility controls shall remain
unobstructed and accessible. Gutters shall remain clear unless other satisfactory
provisions have been made for street drainage. Natural water courses shall not be
obstructed. Surplus excavated material shall be disposed of in a suitable manner.
*Pipe embedment type shall be selected solely on the basis of the pipe stiffness and the anticipated
external load. Internal pipe pressure shall not be included in the embedment selection evaluation.
†In very cold installation conditions, the manufacturer or purchaser may permit the constructor to
remove factory-installed gaskets and take them to a heated truck cab or shelter to restore their
flexibility prior to joint assembly. Always check with the pipe and fittings manufacturers before
attempting to remove the gasket because not all factory-installed gaskets are removable.
12 AWWA C605-05
5.5.3.3 Pipe-to-iron fittings. Any of several joint designs that have gaskets
and are manufactured in accordance with ANSI/AWWA C110/A21.10, ANSI/
AWWA C111/A21.11, and ANSI/AWWA C153/A21.53 may be used. For pipe
assembly commonly found with fittings, valves, hydrants, or other appurtenances;
the insertion depths of these joints are significantly less than those of PVC pipe and
fittings. The procedures of Sec. 5.5.1 and Sec. 5.5.2 shall be followed, except the
insertion depths for these joints are generally less than those with PVC pipe or PVC
fittings. Before assembly or insertion, the constructor shall make sure the pipe spigot
end is squarely cut, deburred and given only a slight outer bevel. If the pipe spigot
end has the factory bevel, the factory bevel shall be removed or shortened to ensure
that when assembled, the gasket will be in full contact with the nonbeveled portion
of the pipe outside diameter. Additionally, the published assembly recommendations
of the fitting or appurtenance manufacturer shall be followed. Joints may be either
mechanical or push-on as described in ANSI/AWWA C110/A21.10, ANSI/AWWA
C111/A21.11, or ANSI/AWWA C153/A21.53.
5.5.3.4 Pipe-to-steel fittings. Any of several push-on joint designs that have
gaskets and are manufactured in accordance with ANSI/AWWA C200 may be used.
The procedures of Sec. 5.5.1 and Sec. 5.5.2 shall be followed except the insertion
depths for these joints are generally less than those with PVC pipe or PVC fittings.
Before assembly or insertion the constructor shall make sure the pipe spigot end is
squarely cut, deburred, and given only a slight outer bevel. If the pipe spigot end has
the factory bevel, the factory bevel shall be removed or shortened to ensure that when
assembled, the gasket will be in full contact with the nonbeveled portion of the pipe
outside diameter. Additonally, the published assembly recommendations of the fitting
manufacturer shall be followed.
5.5.4 Field cuts. Circular saws, handsaws, or similar equipment may be used
for cutting PVC pipe. Cuts shall provide a smooth end at right angles to the
longitudinal axis of the pipe. Pipe spigot ends shall be marked and beveled to match
the manufacturer’s insertion line prior to joining with another PVC pipe bell end (see
Sec. 5.5.2).
5.5.4.1 Spigot insertion. Pipe spigot ends are premarked with a circumferen-
tial insertion line. This line references how far the spigot should be inserted into the
adjoining PVC pipe bell. Field-cut pipe spigot ends shall be marked to match the
manufacturer’s insertion line (see Sec. 5.5.1). Pipe-to-pipe joints shall be assembled
14 AWWA C605-05
only to the insertion line. After assembly, the insertion line shall remain visible and
be nearly flush with the lip of the adjoining PVC pipe bell.
5.5.4.2 Mechanical joint. The mechanical joint shall be assembled in
accordance with the fittings manufacturer’s published recommendations. Pipe spigot
bevels may require shortening for use with mechanical joints or fitting joints.
5.8.3 Compaction. Trench backfill that will be under paved surfaces, such as
sidewalks or roads, shall be compacted in layers to the density required by the
governmental agency having jurisdiction over the road or sidewalk. Trench backfill in
locations other than to-be-surfaced areas shall be compacted to a density equivalent
to that of the surrounding soil.
5.8.3.1 Nonsurfaced areas. Trenches in locations other than surfaced areas
shall be compacted to 95 percent standard proctor density in accordance with ASTM
D698.
5.8.3.2 Additional material. Additional backfill material shall be supplied by
the constructor if needed to backfill trenches completely or to fill depressions caused
by subsequent settlement.
5.8.4 Partial backfilling during testing. Newly installed pipelines are normally
tested after backfilling. When the purchaser requires that pressure and leakage testing
be accomplished before completion of backfilling or with pipe joints exposed for
examination, sufficient backfill material shall be placed over the pipe barrel between the
joints to prevent movement, and consideration shall be given to restraining thrust
forces. In particular, pipes connected to restrained-joints, which derive their stability
from the interaction of the pipe and soil, should be backfilled prior to testing.
*PVC pipe classes and sizes outside the range described in (3) and (4) of Sec. 6.4.1.1 shall not be
directly tapped. Only saddle taps are recommended for such pipes (see Sec. 6.4.2).
†When easily practicable, a reduction of line pressure during tapping is suggested.
18 AWWA C605-05
6.4.1.2 Tap spacing. No direct tap shall be made closer than 2 ft (600 mm)
from the ends of the pipe. Multiple taps in a single pipe shall be staggered around the
circumference and at least 18 in. (450 mm) apart when measured along the
longitudinal axis of the pipe.
6.4.1.3 Tapping procedure. The following procedures shall be followed
when making a direct tap:*
1. The tapping machine shall be placed firmly on the pipe in accordance with
recommendations of the machine manufacturer, but not in a way that distorts the pipe.
2. Prior to tapping, the cutter shall be lubricated with a cutting grease
recommended by the cutter manufacturer.
3. Cutting the hole shall require only finger-pull effort, allowing the cutter
to work without forcing it through the pipe wall. Excessive effort indicates that the
cutter is either being advanced too rapidly or that the cutter has become dull. The
number of taps made with a core drill cutter should be limited to the
recommendations published by the cutter manufacturer. The ratchet handle shall be
rotated at least one complete turn for every 1/8 turn of the feed yoke.
4. The feed yoke shall be engaged to cut the first few threads in the pipe
wall. After this, the tapping bit should be self-feeding and the feed yoke can be
disengaged from the boring bar.
5. Tapping to the correct depth is important and should be determined by
performing one or more bench taps in advance. During the bench tap, the operator
should carefully note the position of the top of the threaded feed sleeve relative to the
thrust collar or other datum point, when the corporation stop is correctly inserted.
The “cast-iron” mark on the boring bar is not a reliable indicator of how deep to tap.
6. As the tapping tool is reversed out of the hole, the feed yoke shall be
reengaged or the boring bar held until the tap clears the threads. The bar shall be
released slowly so as not to damage the threads or injure the machine operator.
7. Two spiral wraps of 3-mil PTFE† tape shall be applied clockwise to the
inlet threads on the closed corporation stop. Liquid sealants or other thread
lubricants shall not be used.
*For more information concerning direct tapping, refer to AWWA Manual M23, UNI-B-8, and
UNI-PUB-8.
†Polytetrafluorethylene (Teflon®), nonstick coated.
UNDERGROUND INSTALLATION OF PVC PIPE 19
cutting tool’s feed rate is controlled and accomplished with a feed nut or feed screw
and yoke. The cutting tool should have a minimum of 2 cutting edges and slots to
minimize stress and facilitate easier flow of shavings during the cutting process.
6.4.2.3 Throat depth. The shell-type (hole) cutting tool shall have a throat
depth that exceeds the PVC pipe wall thickness. Twist-drill bits and auger bits shall
be prohibited.
6.4.2.4 Saddle tapping. The following procedures shall be followed when
making a saddle tap:
1. The service clamp or saddle shall be evenly tightened on the pipe. Visible
distortion of the pipe indicates overtightening and shall be prohibited. The inlet side
of the main stop or corporation stop shall be screwed into the saddle threads. The
main-stop valve shall then be opened.
2. The drilling machine shall be attached to the main-stop outlet threads.
3. The boring bar shall be lowered to the main and rotated using finger-pull
pressure on the feed handle. Cutting the hole shall require only finger-pull effort,
allowing the cutter to work without being forced through the pipe wall. The ratchet
handle shall be rotated at least one complete turn for every 1/8 turn of the feed yoke.
4. After the hole has been cut, the cutter should be advanced through the
hole with two or more full turns. The cutter shall then be withdrawn, the main stop
closed, and the drilling machine removed from the pipe. If leakage is observed past
the threads, the main stop should be tightened.
6.4.3 Safety precautions. The following safety precautions are always recom-
mended when tapping a pressurized pipe:
1. Personnel on the surface should have a clear understanding of the valve
location(s) and operation necessary to isolate the tapping site in the event of a
problem.
2. At least one worker should remain on the surface (out of the trench)
during the tapping operation.
3. The tapping-machine operator should wear protective goggles and be
provided with a ladder or other appropriate means to exit the trench quickly and
safely.
4. The pipe adjacent to the tap should be covered with a protective blanket.
UNDERGROUND INSTALLATION OF PVC PIPE 21
LD P-
Q = ------------------ (Eq 1)
148,000
Where:
Q = quantity of makeup water, in gallons per hour
L = length of pipe section being tested, in ft
UNDERGROUND INSTALLATION OF PVC PIPE 23
Table 2 Hydrostatic test makeup water allowances per 1,000 ft (305 m) of PVC pipe*—gph †
AWWA C605-05
Avg. Test
Pressure Nominal Pipe Diameter, in. (mm)
psi (kPa) 4 (100) 6 (150) 8 (200) 10 (250) 12 (300) 14 (350) 16 (400) 18 (450) 20 (500) 24 (610) 30 (760) 36 (915) 42 (1,070) 48 (1,220)
300 (2,070) 0.47 0.70 0.94 1.17 1.40 1.64 1.87 2.11 2.34 2.81 3.51 4.21 4.92 5.62
275 (1,900) 0.45 0.67 0.90 1.12 1.34 1.57 1.79 2.02 2.24 2.69 3.36 4.03 4.71 5.38
250 (1,720) 0.43 0.64 0.85 1.07 1.28 1.50 1.71 1.92 2.14 2.56 3.21 3.85 4.49 5.13
225 (1,550) 0.41 0.61 0.81 1.01 1.22 1.42 1.62 1.82 2.03 2.43 3.04 3.65 4.26 4.86
200 (1,380) 0.38 0.57 0.76 0.96 1.15 1.34 1.53 1.72 1.91 2.29 2.87 3.44 4.01 4.59
175 (1,210) 0.36 0.54 0.72 0.89 1.07 1.25 1.43 1.61 1.79 2.15 2.68 3.22 3.75 4.29
150 (1,030) 0.33 0.50 0.66 0.83 0.99 1.16 1.32 1.49 1.66 1.99 2.48 2.98 3.48 3.97
125 (860) 0.30 0.45 0.60 0.76 0.91 1.06 1.21 1.36 1.51 1.81 2.27 2.72 3.17 3.63
100 (690) 0.27 0.41 0.54 0.68 0.81 0.95 1.08 1.22 1.35 1.62 2.03 2.43 2.84 3.24
75 (520) 0.23 0.35 0.47 0.59 0.70 0.82 0.94 1.05 1.17 1.40 1.76 2.11 2.46 2.81
50 (340) 0.19 0.29 0.38 0.48 0.57 0.67 0.76 0.86 0.96 1.15 1.43 1.72 2.01 2.29
*If the pipeline under test contains sections of various diameters, makeup water allowance will be the sum of the test allowance for each size.
†To obtain makeup water allowance in liters per hour, multiply the values in the table by 3.79.
This page intentionally blank.
AWWA is the authoritative resource for knowledge, information, and advocacy to improve the quality and
supply of water in North America and beyond. AWWA is the largest organization of water professionals in the
world. AWWA advances public health, safety, and welfare by uniting the efforts of the full spectrum of the
entire water community. Through our collective strength we become better stewards of water for the greatest
good of the people and the environment.
Hydrostatic testing involves filling the installed PVC pressure pipes with water and applying pressure to check for leaks and structural integrity before the pipeline is put into service . This testing is critical to ensure the integrity and safety of the water distribution system, allowing for identification and rectification of potential issues, such as weak joints or manufacturing defects, that could lead to leaks or pipe failures . This step is essential for compliance with the ANSI/AWWA C605 standard, which emphasizes the importance of verifying the durability of installations prior to use .
The ANSI/AWWA C605 standard provides guidelines for the underground installation of polyvinyl chloride (PVC) pressure pipes used in water distribution systems and transmission pipelines. It covers procedures such as trench excavation, pipe installation, and hydrostatic testing to ensure proper functionality and safety . While the standard is not a contract document, it can be referenced in contracts to provide a consensus on industry best practices for constructing and maintaining water systems. The standard encourages optional features and modifications by users to address specific project needs .
The ANSI/AWWA C605 standard outlines specific guidelines for the handling and storage of PVC pressure pipes to prevent damage prior to installation. Pipes must be stored safely and stably to avoid warping or bending . During handling, careful techniques are required to prevent scratching, gouging, or otherwise compromising the pipe surface. Clean handling practices are emphasized to maintain pipe cleanliness and prevent contamination that could affect joint integrity during installation . Following these guidelines helps ensure the pipes remain in optimal condition until they are installed, contributing to the overall reliability of the pipeline system.
Trench construction recommendations in the ANSI/AWWA C605 standard, such as maintaining a minimum clear width to accommodate compaction equipment and ensuring proper trench depth for adequate pipe support, enhance the stability and performance of PVC pressure pipes . Proper preparation of the trench bottom provides uniform support, preventing damage and misalignment, while recommendations against using blocking improve long-term structural integrity. These guidelines ensure the longevity and reliability of pipe installations by addressing potential issues like pipe floating and stress concentration .
For trench embedment in PVC pipe installations, materials should be granular and adequately graded to provide a stable cushion around the pipe. The trench should be wide enough to accommodate compaction equipment, and embedment should prevent movement under conditions like rapid water flow . Rock, boulders, or large stones must be removed to provide at least 4 inches of embedment on all sides, and a stable trench bottom is crucial to support the weight of the pipe without shifting . These conditions ensure uniformity and stability of the installed pipe, preventing stress or damage during service.
AWWA standard disclaimers, which acknowledge that the standards provide a baseline rather than exhaustive specifications, are significant because they allow for adaptability in diverse project conditions . These disclaimers make it clear that while the standards represent industry consensus on best practices, they do not preclude users from implementing additional measures or modifications tailored to specific site conditions or technical requirements. This flexibility is important for industry practitioners in regions where standard conditions differ, ensuring that PVC pipe installations can meet unique performance and regulatory expectations while maintaining safety and effectiveness .
Direct tapping for PVC pressure pipes requires compliance with several criteria: approval by the purchaser, taps no larger than 1 inch, and pipes meeting ANSI/AWWA C900 standards with a maximum DR of 18 . The tapping procedure involves using specialized tools that drill and tap threads into the pipe wall while ensuring the core remains intact to prevent debris. An appropriate cutting lubricant is necessary to avoid undue force on the pipe during the tapping process. These requirements prevent pipe distortion and ensure the integrity of the pipe system while maintaining operational safety .
The procedures for joining PVC pressure pipes involve cleaning the sealing surfaces, using approved lubricants, and correctly assembling the joints with factory-installed elastomeric gaskets to ensure a secure seal . These steps prevent leakage and contamination, maintaining the integrity of the pipeline. Gaskets must be compatible with the other joint components, and the use of proper joining equipment is crucial to avoid damaging the pipe and fittings. These precautions are critical for preventing infiltration and exfiltration, which could compromise the system's performance and water quality .
The revisions made to the latest edition of ANSI/AWWA C605 are considered minor, with no significant changes reported in the document. The revisions primarily include updates to ensure the standard remains relevant and accurate based on current industry practices and technological advancements .
The AWWA plays a crucial role in standardizing PVC pressure pipe installation through the development and maintenance of comprehensive guidelines like ANSI/AWWA C605. By fostering a consensus among industry stakeholders, the AWWA ensures that these standards reflect best practices and technological advancements, promoting quality assurance and consistency across water distribution systems . Its efforts have significantly impacted the water supply industry by enabling safer, more efficient installations, minimizing risks associated with improper installations, and enhancing the reliability of water infrastructure .