No. System Main Equipment Brand/Supplier Origin Delivery Lead Time
1. Digital Transmission System (DTS) 1. SDH Belden OTN Belgium 11 - 12 weeks
2. DC Rectifier Thytron China 8 - 12 weeks
3. UPS & Battery Right Power China 8 - 12 weeks
2. Passenger Information System (PIS) 1. Local Control Unit ASGB Local 8 - 12 weeks
2. Display Unit AGSB Local 8- 12 weeks
3. Public Address System (PA) 1. Main PA Unit R2P Netspire Germany 20 - 24 weeks
2. Speakers TOA Taiwan 20 - 24 weeks
3. Microphone R2P Netspire Germany 20 - 24 weeks
4. Automatic Fare Collection System (AFC) 1. POS NSS IT China 8 - 12 weeks
2. ACG NSS IT China 8 - 12 weeks
3. TVM NSS IT Local 6 - 8 weeks
5. Card Access System (CAS) 1. Door Controller EntryPass Local 8 - 12 weeks
2. Accessories - Reader, etc EntryPass Local 8 - 12 weeks
6. CCTV System 1. Network Video Recorder Bosch Germany 5 - 6 weeks
2. Camera Bosch Germany 5 - 6 weeks
7. PABX System 1. IP Phone Alcatel-Lucent France 8 - 12 weeks
2. Layer 2 Switch HP Aruba USA 4 - 5 weeks
8. ICT System Layer 3 Switch Cisco USA 4 - 5 weeks
9. SCADA 1. Remote Terminal Unit Willowglen Local 8 - 12 weeks
2. Sensors Willowglen Local 8 - 12 weeks