BOQ For Additional Minor Junctions - 10.11.2024 IE
BOQ For Additional Minor Junctions - 10.11.2024 IE
A B C D E F G H=F X G I
2 Site Clearance
Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 meters, stacking serviceable and unserviceable materials
i 2.05 (ii) A 10 Cum 402.00 817.10 328,474.30
separately, including all labour, usage charges of all machinery, lift, load, unload, transportation etc., complete. etc., complete (Dismantled material to be
transported mechanically).Bituminous courses - By Mechanical Means
Excavation in Soil using Hydraulic Excavator and Tippers with Disposal upto 1000 metres.Excavation for roadwork in soil by hydraulic excavator
including cutting and loading in tippers, trimming bottom and side s lopes, in accordance with requirements of lines, grades and crosssections, and
i 3.06 17 Cum 76.00 4,608.83 350,271.45
transporting to the embankment location , with all lifts and lead upto 1000 m, including all labour, load, unload, usage charges of allmachinery, etc.,
complete.
Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits,transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-2 laid in layers not exceeding 250 mm thick and compacting it by mechanical means after adding
iii 3.18 22 water to its OMC, so as to achieve 97% compaction of maximum dry density and finish the surface to the required camber, grade and cross section etc., Cum 426.00 8,171.00 3,480,847.07
speading, grading by motor grador, consolidation by roller including all lead, lifts, loading, unloading, all labour, usage charges of machinery etc., complete.
(New road formation)
Granular Sub-Base with Close /CoarseGraded Material (Table:- 400-1) By Mix in Place Method
Construction of granular sub-base by providing spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with front
i 4.01 B (v) 33 end loader at OMC and compacting with vibratory roller to achieve the desired density, complete as per clause 401, including protection of edges of GSB Cum 2,228.70 3,268.40 7,284,285.31
layer, cost of all materials, labour, usage charges of all machinery, lighting, guarding, barricading, maintenance of diversion road, loading & unloading all
lead, lifts etc., complete. (Compacted thickness). Grading-V Material (Close graded)
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing,
i 9.01 I-B(i) 129 removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material, including all labour, usage charges of Cum 87.00 3,009.83 261,854.78
machinery, lead, lifts, loading,unloading transporting etc., complete.Ordinary soil - Mechanical Means (Depth upto 3 m)
Laying Reinforced Cement Concrete Pipe NP4 / Prestressed Concrete Pipe on First Class Bedding in SingleRow.Providing & laying Reinforced cement
concrete pipe NP4/ prestressed concrete pipe for culverts on first class bedding of granular material in single row, including fixing collar with with cement
mortar 1 :2, but excluding excation, protection works, backfilling,
ii 9.04 B 132 Metre 7,524.00 630.00 4,740,120.00
concrte and masonry works in headwall and parapetes, including cost of all materials all labour, usage charges of machinery, lead, lifts, loading, unloading
transporting etc., complete.of granular material in single row,including fixing collar with with cement mortar 1 :2, but excluding excation, protection works,
backfilling, concrte and masonry works in headwalland parapetes.900mm Dia
Providing & laying Plain/Reinforced Cement Concrete in open foundation & complete as per drawing & tecnical 2100 pecification for Pipe Culvert complete
as per Drawing and Technical Specifications ,including cost of all materials, formwork,centering, vibrating, compacting,alliabour,usage charges of machinery,
iii 9.06 133 -
lead, lifts,loading, unloading transporting, stacking, curing, finishing the exposed faces etc.,complete. (excluding cost of steel and fabrication charges)PCC
Grade MI5 using batching plant transit mixer & Concrete pump
iv 9.06 A Case-I 133 PCC Grade MI5 using batching plant transit mixer & Concrete pump Cum 5,525.88 114.70 633,841.09
v 9.06 C Case-I 133 RCC Grade M20 using batching plant transit mixer & Concrete pump Cum 6,226.92 968.54 6,030,991.36
vi 9.06 E Case-II 133 RCC Grade M25 using batching plant, transit mixer & Manual Placing Cum 6,977.56 198.45 1,384,696.78
NH SOR 2022-2023 Final Rate Arrived
Chapter
Description Unit after adding lead Qty Amount Remarks
No
Item No. Page No. charges
Supplying, Fitting and Placing un-coated TMT Fe-500 grade bar Reinforcement
in Foundation complete as per Drawing and Technical Specifications. including straightening bar, cutting, bending, hooking binding with approved quality
viii 9.07 134 binding wire,after placing in position, tying, lapping and or welding whereever required ( laps, hooks wastages shall not be measured & paid) incluidng Mt 80,675.23 23.30 1,879,888.49
cost of all materials, fabrication charges, all labour, material, usage chargesof machinery, lead, lifts, loading, unloading,stacking, transporting etc.,
complete.
1 121+060 LHS 55 7.50 412.50 729.039 728.669 -0.37 1.07 -1.44 20.63 -594.00 206.25 82.50 103.13 412.50 412.50 33.00 412.50 16.50 Village road
2 121+110 RHS 70 5.70 399.00 728.373 728.499 0.126 1.07 -0.944 19.95 -376.66 199.50 79.80 99.75 399.00 399.00 31.92 399.00 15.96 Ashram Road
3 135+170 RHS 55 6.50 357.50 620.264 621.200 0.936 1.07 -0.134 17.88 -47.91 178.75 71.50 89.38 357.50 357.50 28.60 357.50 14.30 For Temple
4 135+450 RHS 55 5.70 313.50 619.120 620.757 1.637 1.07 0.567 15.68 177.75 156.75 62.70 78.38 313.50 313.50 25.08 313.50 12.54 For Temple
5 135+800 LHS 55 5.20 286.00 621.811 622.404 0.593 1.07 -0.477 14.30 -136.42 143.00 57.20 71.50 286.00 286.00 22.88 286.00 11.44 Village road
6 147+235 RHS 81 5.70 461.70 574.117 578.17 4.053 1.07 2.983 23.09 1,377.25 230.85 92.34 115.43 461.70 461.70 36.94 461.70 18.47
7 147+235 LHS 55 5.13 282.32 573.866 578.17 4.304 1.07 3.234 14.12 913.01 141.16 56.46 70.58 282.32 282.32 22.59 282.32 11.29
8 147+770 LHS 55 5.20 286.00 582.701 584.15 1.449 1.07 0.379 14.30 108.39 143.00 57.20 71.50 286.00 286.00 22.88 286.00 11.44
9 147+770 RHS 55 6.20 341.00 582.554 584.15 1.596 1.07 0.526 17.05 179.37 170.50 68.20 85.25 341.00 341.00 27.28 341.00 13.64
10 164+590 LHS 55 5.60 308.00 521.784 523.517 1.733 1.07 0.663 15.40 204.20 154.00 61.60 77.00 308.00 308.00 24.64 308.00 12.32 Village road
11 164+590 RHS 55 5.50 302.50 522.101 523.517 1.416 1.07 0.346 15.13 104.67 151.25 60.50 75.63 302.50 302.50 24.20 302.50 12.10
12 165+890 LHS 55 4.33 238.15 517.766 517.633 -0.133 1.07 -1.203 11.91 -286.49 119.08 47.63 59.54 238.15 238.15 19.05 238.15 9.53 Village road
13 165+890 RHS 55 4.33 238.15 517.402 517.633 0.231 1.07 -0.839 11.91 -199.81 119.08 47.63 59.54 238.15 238.15 19.05 238.15 9.53
14 179+820 LHS 55 5.33 293.15 531.48 532.091 0.611 1.07 -0.459 14.66 -134.56 146.58 58.63 73.29 293.15 293.15 23.45 293.15 11.73 Village road
15 179+820 RHS 55 5.20 286.00 531.318 532.091 0.773 1.07 -0.297 14.30 -84.94 143.00 57.20 71.50 286.00 286.00 22.88 286.00 11.44
16 180+250 LHS 55 4.00 220.00 525.324 529.141 3.817 1.07 2.747 11.00 604.34 110.00 44.00 55.00 220.00 220.00 17.60 220.00 8.80 Village road
17 180+250 RHS 55 8.60 473.00 525.876 529.141 3.265 1.07 2.195 23.65 1,038.23 236.50 94.60 118.25 473.00 473.00 37.84 473.00 18.92
18 183+620 LHS 9.5 3.00 28.50 537.324 538.436 1.112 1.07 0.042 1.43 1.20 14.25 5.70 7.13 28.50 28.50 2.28 28.50 1.14 Village road
19 183+620 RHS 7.5 3.00 22.50 537.451 538.436 0.985 1.07 -0.085 1.13 -1.91 11.25 4.50 5.63 22.50 22.50 1.80 22.50 0.90
20 183+670 LHS 5 4.00 20.00 539.075 539.686 0.611 1.07 -0.459 1.00 -9.18 10.00 4.00 5.00 20.00 20.00 1.60 20.00 0.80 Village road
21 183+670 RHS 8 4.00 32.00 538.885 539.686 0.801 1.07 -0.269 1.60 -8.61 16.00 6.40 8.00 32.00 32.00 2.56 32.00 1.28
22 186+250 RHS 10 7.00 70.00 528.09 528.621 0.531 1.07 -0.539 3.50 -37.73 35.00 14.00 17.50 70.00 70.00 5.60 70.00 2.80 Temple
23 187+050 RHS 9 3.75 33.75 532.986 534.544 1.558 1.07 0.488 1.69 16.47 16.88 6.75 8.44 33.75 33.75 2.70 33.75 1.35 Village road
24 187+260 RHS 17 4.00 68.00 532.643 535.342 2.699 1.07 1.629 3.40 110.77 34.00 13.60 17.00 68.00 68.00 5.44 68.00 2.72 Village road
25 188+020 RHS 55 6.05 332.75 531.436 532.825 1.389 1.07 0.319 16.64 106.15 166.38 66.55 83.19 332.75 332.75 26.62 332.75 13.31 Temple
26 194+540 LHS 44 3.75 165.00 577.312 578.342 1.03 1.07 -0.04 8.25 -6.60 82.50 33.00 41.25 165.00 165.00 13.20 165.00 6.60 Village road
27 199+260 RHS 25 5.00 125.00 557.221 557.995 0.774 1.07 -0.296 6.25 -37.00 62.50 25.00 31.25 125.00 125.00 10.00 125.00 5.00 Village road
28 199+343 RHS 39 5.00 195.00 557.268 557.901 0.633 1.07 -0.437 9.75 -85.22 97.50 39.00 48.75 195.00 195.00 15.60 195.00 7.80 Village road
29 199+505 RHS 96 5.00 480.00 554.374 557.435 3.061 1.07 1.991 24.00 955.68 240.00 96.00 120.00 480.00 480.00 38.40 480.00 19.20 Village road
30 203+600 LHS 55 5.72 314.60 581.984 584.325 2.341 1.07 1.271 15.73 399.86 157.30 62.92 78.65 314.60 314.60 25.17 314.60 12.58 Major Junction
31 203+600 RHS 55 5.89 323.95 581.479 584.325 2.846 1.07 1.776 16.20 575.34 161.98 64.79 80.99 323.95 323.95 25.92 323.95 12.96 Major Junction
32 215+360 RHS 30 5.00 150.00 565.349 566.063 0.714 1.07 -0.356 7.50 -53.40 75.00 30.00 37.50 150.00 150.00 12.00 150.00 6.00 Village road
33 215+690 RHS 11 6.45 70.95 566.47 567.039 0.569 1.07 -0.501 3.55 -35.55 35.48 14.19 17.74 70.95 70.95 5.68 70.95 2.84
34 216+000 RHS 55 5.85 321.75 570.611 570.867 0.256 1.07 -0.814 16.09 -261.90 160.88 64.35 80.44 321.75 321.75 25.74 321.75 12.87 Village road
35 216+003 LHS 55 5.94 326.59 570.611 570.867 0.256 1.07 -0.814 16.33 -265.84 163.30 65.32 81.65 326.59 326.59 26.13 326.59 13.06 Local Road
36 216+284 RHS 55 4.90 269.50 574.381 575.070 0.689 1.07 -0.381 13.48 -102.68 134.75 53.90 67.38 269.50 269.50 21.56 269.50 10.78 Hospital
37 217+333 RHS 55 8.88 488.13 582.499 582.469 -0.03 1.07 -1.1 24.41 -536.94 244.06 97.63 122.03 488.13 488.13 39.05 488.13 19.53 Village road
38 222+174 RHS 55 9.13 501.88 546.126 547.118 0.992 1.07 -0.078 25.09 -39.15 250.94 100.38 125.47 501.88 501.88 40.15 501.88 20.08 Village road
39 222+187 LHS 55 8.88 488.13 545.901 547.165 1.264 1.07 0.194 24.41 94.70 244.06 97.63 122.03 488.13 488.13 39.05 488.13 19.53 Local Road
40 226+366 LHS 71 6.50 461.50 559.689 561.448 1.759 1.07 0.689 23.08 317.97 230.75 92.30 115.38 461.50 461.50 36.92 461.50 18.46 Village road
41 227+360 RHS 55 5.50 302.50 554.612 554.998 0.386 1.07 -0.684 15.13 -206.91 151.25 60.50 75.63 302.50 302.50 24.20 302.50 12.10 Local Road
42 228+555 LHS 32 5.00 160.00 548.103 550.361 2.258 1.07 1.188 8.00 190.08 80.00 32.00 40.00 160.00 160.00 12.80 160.00 6.40 Local Road
43 229+853 LHS 55 5.99 329.29 548.286 549.47 1.184 1.07 0.114 16.46 37.54 164.64 65.86 82.32 329.29 329.29 26.34 329.29 13.17 Village road
44 231+352 RHS 55 6.26 344.30 546.578 549.324 2.746 1.07 1.676 17.22 577.05 172.15 68.86 86.08 344.30 344.30 27.54 344.30 13.77 Local Road
45 231+370 LHS 55 5.99 329.29 546.822 549.325 2.503 1.07 1.433 16.46 471.87 164.64 65.86 82.32 329.29 329.29 26.34 329.29 13.17 Village road
46 231+370 RHS 55 5.99 329.29 547.01 549.325 2.315 1.07 1.245 16.46 409.96 164.64 65.86 82.32 329.29 329.29 26.34 329.29 13.17
47 235+000 LHS 12 9.50 114.00 542.89 543.16 0.27 1.07 -0.8 5.70 -91.20 57.00 22.80 28.50 114.00 114.00 9.12 114.00 4.56 Kiregeri
48 235+690 LHS 55 5.96 327.91 542.303 545.883 3.58 1.07 2.51 16.40 823.05 163.95 65.58 81.98 327.91 327.91 26.23 327.91 13.12 Village road
49 235+735 RHS 55 5.81 319.55 542.474 545.883 3.409 1.07 2.339 15.98 747.43 159.77 63.91 79.89 319.55 319.55 25.56 319.55 12.78
50 237+504 RHS 55 6.45 354.75 549.334 550.406 1.072 1.07 0.002 17.74 0.71 177.38 70.95 88.69 354.75 354.75 28.38 354.75 14.19 Crusher Road
51 238+185 LHS 13 4.00 52.00 544.384 546.266 1.882 1.07 0.812 2.60 42.22 26.00 10.40 13.00 52.00 52.00 4.16 52.00 2.08 Village road
52 239+783 LHS 10 9.00 90.00 549.746 550.896 1.15 1.07 0.08 4.50 7.20 45.00 18.00 22.50 90.00 90.00 7.20 90.00 3.60 Puradageri
53 239+783 RHS 55 10.00 550.00 550.237 550.896 0.659 1.07 -0.411 27.50 -226.05 275.00 110.00 137.50 550.00 550.00 44.00 550.00 22.00
54 241+295 LHS 15 5.00 75.00 546.674 547.182 0.508 1.07 -0.562 3.75 -42.15 37.50 15.00 18.75 75.00 75.00 6.00 75.00 3.00 Hallur
55 241+300 RHS 11 4.50 49.50 546.515 547.428 0.913 1.07 -0.157 2.48 -7.77 24.75 9.90 12.38 49.50 49.50 3.96 49.50 1.98 Hallur
MINOR JUNCTION QTY/CUM
56 241+947 LHS 12 4.00 48.00 555.898 557.218 1.32 1.07 0.25 2.40 12.00 24.00 9.60 12.00 48.00 48.00 3.84 48.00 1.92 Hallur
57 242+170 LHS 25 6.00 150.00 549.058 552.349 3.291 1.07 2.221 7.50 333.15 75.00 30.00 37.50 150.00 150.00 12.00 150.00 6.00 Petrol Pump
58 242+920 LHS 40 5.20 208.00 550.735 550.777 0.042 1.07 -1.028 10.40 -213.82 104.00 41.60 52.00 208.00 208.00 16.64 208.00 8.32
59 243+000 LHS 55 6.00 330.00 551.295 552.748 1.453 1.07 0.383 16.50 126.39 165.00 66.00 82.50 330.00 330.00 26.40 330.00 13.20 Village road
60 247+910 RHS 55 5.86 322.30 552.021 552.779 0.758 1.07 -0.312 16.12 -100.70 161.15 64.46 80.58 322.30 322.30 25.78 322.30 12.89 Hanuma Sagar
61 248+066 RHS 55 6.06 333.41 550.128 550.671 0.543 1.07 -0.527 16.67 -175.71 166.71 66.68 83.35 333.41 333.41 26.67 333.41 13.34 Hanuma Sagar
62 248+692 RHS 55 7.00 385.00 549.333 549.929 0.596 1.07 -0.474 19.25 -182.49 192.50 77.00 96.25 385.00 385.00 30.80 385.00 15.40 Village road
63 252+153 LHS 10 5.00 50.00 550.135 550.814 0.679 1.07 -0.391 2.50 -19.55 25.00 10.00 12.50 50.00 50.00 4.00 50.00 2.00 BT Road
Total Qty. 16,342.00 817.10 4,608.83 11,063.99 8,171.00 - - 3,268.40 4,085.50 16,342.01 16,342.01 1,307.36 16,342.01 653.68
ADDITIONAL MINOR JUNCTION
As per Site
CHAINAGE
SI NO SIDE LENGTH WIDTH TOTAL AREA REMARKS
Qty after 5%
Sl.no Item No. Page No. Particulars Nos Length Width Depth Qty Total Qty Unit Remark
Contigency
1 8.13 110 Road Marking 2343.116 Sqm
Logitudinal lines 126 44 0.15 831.6 873.180
Centrel Line 63 33 0.15 311.85 327.442 63
TM03 63 10 0.2 126 132.300 48
63 5 0.2 63 66.150 0.761904761904762
TM04 63 3.6 0.1 22.68 23.814
AM06 63 0.2 2.2 27.72 29.106
63 0.3 1.5 28.35 29.768
63 0.3 1.5 28.35 29.768
AM01 63 0.2 2.2 27.72 29.106
63 0.25 1.2 18.9 19.845
BM04 252 0.75 1.85 349.65 367.133
BM05 378 1.5 0.5 283.5 297.675
126 0.5 0.5 31.5 33.075
Stop Sign 63 0.5 2.05 1.25 80.72 84.755
3 9.01 I-B(i) 129 Excavation for Pipe Cuvert 63 10 2.5 1.82 2866.50 3009.825 3009.825 Cum
4 9.06 A Case-I 133 PCC Below Precast pipe culvert 114.704 Cum
63 10.2 1.7 0.1 109.24 114.704
5 9.06 C Case-I 133 M20 concrete for encasement 968.535225 Cum
63 10 1.5 1.4 1323.00 1389.150
Deduction 63 3.14 0.20 10 400.59 420.615
6 9.06 E Case-II 133 Slab M25 198.450 Cum
63 10 1.5 0.2 189.00 198.450
7 9.07 134 Reinforcement for Encasement Slab 63 0.35 22.19 23.302 23.302 MT
630.000 Rm
8 9.04 B 132 900 mm Pipe 63 10 630
Project: Two Lanning with paved Shoulder of Gadag to Honnali (Km 105.500 to Km 205.290 of SH 57 and Km 215.335 to Km 253.713 of SH 26), 138.2 Km in the State of Karnataka, India on Hybrid Annuity Basis
Concessionaire: M/s Sadbhav Gadag Highway Private Limited
Client: Karnataka State Improvement Project (KSHIP-III)
Independent Engineer: LEA Associates South Asia Pvt. Ltd. EPC Contrctor-Gawar Construction Company
Large Quantity Rates of Rate After
Rate Ananlysis
Project for Changeofof Scope (Gadag-Honnali)
Cement Cement / Current effecting Annexure-A
Rates(As / Steel / Adopted Steel / Rates as Rise/fall in Lead in Total Final Rate
NH SOR 2022-2023 As per Mix Diff, in Cost of Source to Plant Plant
Km to site
(Total (for mix material) Transporti
Haulage
Chapter per NH Bitumen the Bitumen per base rate Material Haulage Transporti Transporti Arrived after
Description Unit Design at Rate Material Lead in Lead - Charges Remark
No Item No. Page No. SOR Requirem Materials per MT as ANNEXUR of finished Requirem Charges on on ng/ Lead adding lead
site (in Rs.) (in Rs.) Km Initial Tonn/
Dharwad ent Req. per SOR E-B item in ent Tonne-KM Charges Charges Charges charges
A B C D E F
2022-2023 G (AsHper I=Min(G,H) 2022-23
J (in K
Rs.) L=K-J M=LxI N=F+M
SOR O P Q R=OxPxQ LeadS of 1 Cum-KM T U=SxT V=R+U W=N+V X
(in Rs.) SOR) (in Rs.) (in Rs.) Km)
2 Site Clearance
Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 meters,
2.05 stacking serviceable and unserviceable materials separately, including all labour, usage charges of all
machinery, lift, load, unload, transportation etc., complete. etc., complete (Dismantled material to be
transported mechanically).
2.05 (ii) A 10 Bituminous courses - By Mechanical Means Cum 402.00 - - - - - - 402.00 - - - - - - - - 402.00
3 EARTHWORK, EROSION CONTROL AND DRAINAGE - - - -
Excavation in Soil using Hydraulic Excavator and Tippers with Disposal upto 1000
metres.Excavation for roadwork in soil by hydraulic excavator including cutting and loading in tippers,
3.06 17 trimming bottom and side s lopes, in accordance with requirements of lines, grades and crosssections, Cum 76.00 - - - - - - 76.00 - - - - - - - - 76.00
and transporting to the embankment location , with all lifts and lead upto 1000 m, including all labour, load,
unload, usage charges of allmachinery, etc., complete.
Road marking with Hot Applied Thermoplastic Compound with Reflectorizing Glass beads on
Bituminous Surface
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass
beads at 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per
8.13 110 Sqm 612.00 - - - - - - 612.00 - - - - - - - - 612.00
IRC:35. The finished surface to be level, uniform and free from streaks and holes, including, barricading,
traffic diversion as per IRC-35,cleaning the surface of dirt, dust and other foriegn matter, demarcation at
site, traffuc control,cost of all materials all labour, lead, lifts, loading, unloading transporting etc., complete.
2.5 mm Thick
PCC 1:3:6 in Foundation.Providing & laying Plain cement concrete 1:3: 6 nominal mix in foundation
with crushed stone aggregates 40mm nominal size mechanically mixed,placed in foundation and
9.03 131 Cum 4,737.00 0.260 0.230 0.230 6,100.00 6,250.00 150.00 34.50 4771.50 0.230 45.00 5.60 57.96 8.1875 27.2800 223.36 281.315 5,052.82
compated by vibration including curing, including cost of all materials all labour, usage charges of
machinery, lead, lifts ,loading, unloading transporting etc.,complete.
Large Quantity Rates of Rate After
Rate Ananlysis
Project for Changeofof Scope (Gadag-Honnali)
Cement Cement / Current effecting Annexure-A
Rates(As / Steel / Adopted Steel / Rates as Rise/fall in Lead in Total Final Rate
NH SOR 2022-2023 As per Mix Diff, in Cost of Source to Plant Plant
Km to site
(Total (for mix material) Transporti
Haulage
Chapter per NH Bitumen the Bitumen per base rate Material Haulage Transporti Transporti Arrived after
Description Unit Design at Rate Material Lead in Lead - Charges Remark
No Item No. Page No. SOR Requirem Materials per MT as ANNEXUR of finished Requirem Charges on on ng/ Lead adding lead
site (in Rs.) (in Rs.) Km Initial Tonn/
Dharwad ent Req. per SOR E-B item in ent Tonne-KM Charges Charges Charges charges
A B C D E F
2022-2023 G (AsHper I=Min(G,H) 2022-23
J (in K
Rs.) L=K-J M=LxI N=F+M
SOR O P Q R=OxPxQ LeadS of 1 Cum-KM T U=SxT V=R+U W=N+V X
(in Rs.) SOR) (in Rs.) (in Rs.) Km)
Laying Reinforced Cement Concrete Pipe NP4 / Prestressed Concrete Pipe on First Class Bedding
in SingleRow.Providing & laying Reinforced cement concrete pipe NP4/ prestressed concrete pipe for
culverts on first class bedding of granular material in single row, including fixing collar with with cement
mortar 1 :2, but excluding excation, protection works, backfilling,
9.04 B 132 Metre 10,110.00 - - - - - - 7524.00 - - - - - - - - 7,524.00
concrte and masonry works in headwall and parapetes, including cost of all materials all labour, usage
charges of machinery, lead, lifts, loading, unloading transporting etc., complete.of granular material in
single row,including fixing collar with with cement mortar 1 :2, but excluding excation, protection works,
backfilling, concrte and masonry works in headwalland parapetes.900mm Dia
Providing & laying Plain/Reinforced Cement Concrete in open foundation & complete as per drawing
& tecnical 2100 pecification for Pipe Culvert complete as per Drawing and Technical
Specifications ,including cost of all materials, formwork,centering, vibrating, compacting,alliabour,usage
9.06 133
charges of machinery, lead, lifts,loading, unloading transporting, stacking, curing, finishing the exposed
faces etc.,complete. (excluding cost of steel and fabrication charges)PCC Grade MI5 using batching
plant transit mixer & Concrete pump
9.06 A Case-
133 PCC Grade MI5 using batching plant transit mixer & Concrete pump Cum 5,198.00 0.260 0.275 0.260 6,100.00 6,250.00 150.00 39.00 5237.00 0.260 45.00 5.60 65.52 8.1875 27.2800 223.36 288.875 5,525.88
I
9.06 C Case-
133 RCC Grade M20 using batching plant transit mixer & Concrete pump Cum 5,864.00 0.380 0.347 0.347 6,100.00 6,250.00 150.00 52.08 5916.08 0.347 45.00 5.60 87.49 8.1875 27.2800 223.36 310.842 6,226.92
I
9.06 E
133 RCC Grade M25 using batching plant, transit mixer & Manual Placing Cum ### 0.380 0.347 0.347 6,100.00 6,250.00 150.00 52.08 6890.08 0.347 45.00 5.60 87.49 - - - 87.487 6,977.56
Case-II
Supplying, Fitting and Placing un-coated TMT Fe-500 grade bar Reinforcement
in Foundation complete as per Drawing and Technical Specifications. including straightening bar, cutting,
bending, hooking binding with approved quality binding wire,after placing in position, tying, lapping and or
9.07 134 Mt 86,958.00 1.050 1.050 1.050 68,100.00 61,864.41 (6,235.59) (6,547.37) 80410.63 1.050 45.00 5.60 264.60 - - - 264.600 80,675.23
welding whereever required ( laps, hooks wastages shall not be measured & paid) incluidng cost
of all materials, fabrication charges, all labour, material, usage chargesof machinery, lead, lifts, loading,
unloading,stacking, transporting etc., complete.
Addional item Rates which are not found in SOR-2022-23 -
Rate Analysis
( Sub Grade of Rate - - - -
50% & Granular Sub Granular Shoulder (50% GSB Materials &50% SG Materials) Cum 1,281.50 - - - - - - 1281.50 - - - - 8.1875 11.20 91.7000 91.700 1,373.20
Base of Rate 50%)
ANNEXURE - B
Revised Material Rates
Prevail Market Rates (As per
Rate Considered in
Sl. No Description of Materials Unit Superintending Engineer, NH Remarks
SOR 2022-23
Circle Bangalore. Dharward)
1 2 3 4 5 6
1 VG-10 Bitumen (80/100 Grade) Bulk MT 50,652 48,818 M-076
2 VG-30 Bitumen (60/70 Grade) Bulk MT 51,370 48,384 M-075
3 VG-40 Bitumen (30/400 Grade) Bulk MT 54,760 51,118 M-074
4 Crumb Rubber Modified Bitumen-55 Grade Bulk MT 53,795 42,750 M-078 B
5 Rapid Setting Emulsion of packed (R/C drums) RS-1 MT 46,080 44,446 M-078
6 Slow Setting Emulsion of packed (R/C drums) SS1 MT 87,628 48,393 M-078 A
7 TMT Steel (Thermo Mechanically Treated) FE-500 MT 68,100 61,864 M-083
8 Corrosion resistant Structural Steel MT 76,270 64,407 M-088
9 Cement MT 6,100 6,250 M-081
Lead details
1 Bitumen Km. 309.00 From Source to Plant Lead chart Sheet Attached
2 Cement Km. 45.00 From Source to Plant The Cement & Steel Leads shall not added separately however, it
is inclusive of all leads, lifts and loading & unloading charges as
3 Steel Km. 45.00 From Source to Site per mentioned in point no-20 in general notes of SOR-2022-23.
4 Other Items ( Mix Materials) Km 40.00 From Plant to Site Lead chart Sheet Attached
Materials
a Bitumen MT - 5.6
b Cement MT - 5.6
c Unit MT - 5.6
2 Mixed Materials (plant to Site)
a GSB CUM 2.00 11.2
b WMM CUM 2.00 27.2
c DBM CUM 2.30 12.88
d BC CUM 2.35 13.16
e Cement Concrete for all grades CUM 2.20 27.28
Lead Chart
Lead Chart From source to Plant(i.e; Bitumen) Lead Chart From source to Plant (i.e; Cement & Steel)
Lead Chart From Plant to Site (i.e;Concrete,Granular Sub Base, Wet Mix Macadam & Bituminous Works)
Existing Road
Cement
Steel
46
Existing Road
310 46 46 46 41.00
Itagi Ranebennur
Itagi Camp 161+850 RHS Itagi
MRPL Kuthethoor,Mangalore 161+850 RHS Itagi Camp 168+215 Varada Bridge ROB Ch 202+000
Camp
0.050
4 Dist. Bar 9.92 12 150 10 9.972 99.72