R12 S00C01 Tie Mat Ci 0012 - C1
R12 S00C01 Tie Mat Ci 0012 - C1
Hub
Document Title: R12-S00C01– MAT For Bonding Agent for concrete (Nitobond SBR)
Aconex Doc. No. R12-S00C01-TIE-MAT-CI-0012
Revision No. C1
R12-S00C01-
Ref. No. Version C1 Date 06-Mar-2024
TIE-MAT-Cl-0012
Approved
To the Engineer RSG Subcontractor NA
(as applicable)
Material Information
Material Description (One
MATERIAL APPROVAL FOR Bonding Agent for concrete (Nitobond SBR)
item only per Form)
As per Specification R12-S00D04-KAA-SPC-AR-0004 Alternative NA
Drawing Reference Project Drawings BOQ Ref. No.
Manufacturer/Supplier
Contractor’s
06-Mar-2024
Shang Jianzhu
Name Signature Date
Engineer’s - Comments
Comments:
Status Code
RSG-CN-FRM-0011
Rev. 00, 16 Nov 2022 Page 1 of 1
Comments Resolution Sheet - CRS
RSG-DC-FRM-0008
RED_SEA_PROJECT
General Information
Identification of
Reviewer's Reference No. of Doc. or Sign-Off
S/N Comment's Source: Observations|Comments Discipline Assessment Code Response
Name/Oragnization Drwg. (Include Revision) (Open/Closed)
(Title|Page|Clause)
Material Submittal
Prgram: R12
Project: Central Logistics Hub
Project Code: S00C01
Package: Sitewide External Work & Infrastructure
Bonding Agent for Concrete (Nitobond)
Material
RSG-CN-TMP-0007
Revision History
Details of
Rev. Date Prepared By Reviewed By Approved By
Revision
C1 06-Mar-24 For Approval M.Ikram Israr Ahmad Shang Jianzhu
Table of Contents
1 Product Information ................................................................................................................................ 7
2 Statement of Compliance ....................................................................................................................... 8
3 Scope of Works ......................................................................................................................................... 9
4 Specification Compliance Check List ................................................................................................... 10
5 Technical Data Sheet ............................................................................................................................. 11
6 Sample (List / Photos) ............................................................................................................................ 12
7 Test Reports............................................................................................................................................ 12
8 LEED Compliance & Certificates ........................................................................................................... 14
9 Country of Origin – Confirmation Letter ............................................................................................. 15
10 Product Authority Approval ................................................................................................................. 16
11 Draft Warranty ....................................................................................................................................... 17
12 Manufacturer Recommended Spare Parts .......................................................................................... 18
13 Previous Project Approvals ................................................................................................................... 19
14 Trade License.......................................................................................................................................... 20
15 Manufacturer Confirmation of the local Agent .................................................................................. 21
16 Project Reference List ........................................................................................................................... 22
17 Company Profile ..................................................................................................................................... 23
Appendices
Compalince
Sl
Description Not Not Remarks
No Provided
Provided Applicable
1 Statement of Complaince ☐
☒ ☐ ☐
2 Scope of Works ☒ ☐ ☐
3 Specification Complaince Check List ☒ ☐ ☐
4 Technical Data Sheet ☒ ☐ ☐
5 Test Reports ☒ ☐ ☐
6 LEED Complaince ☒ ☐ ☐
7 Country of Origin ☒ ☐ ☐
8 Authority Appovals ☒ ☐ ☐
☐ ☒
9 Draft Warranty ☐
10 Recommended Spare Parts ☐ ☐ ☒
11 Trade Licence ☒ ☐ ☐
12 Project Refrences ☒ ☐ ☐
13 Previous revision comment tracker ☒ ☐ ☐
Above checklist is the minimum requirement, subject to review by the Employer and or Assitants.
Sign
Stamp
Attached Below.
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 12 of 23
CLASSIFICATION: INTERNAL & SENSITIVE
constructive solutions
Technical Submittal
NITOBOND SBR
(Polymer bonding aid and mortar additive)
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 10 of 23
CLASSIFICATION: INTERNAL & SENSITIVE
Project Title: Central Logistics Hub Project Specification Comparison Sheet Date: 29-Jan-2024
Attached Below.
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 10 of 21
Nitobond SBR constructive solutions
Specification clauses Saw cut the extremities of the repair locations to a depth of
at least 10 mm to avoid feather edging and to provide a
Polymer bonding aid and mortar additive square edge. Break out the complete repair area to a
minimum depth of 6 mm up to the sawn edge.
The polymer bonding aid and site-batched mortar shall be
modified by the use of Nitobond SBR, a single component Clean the surface and remove any dust, unsound or
styrene butadiene rubber emulsion. contaminated material, plaster, oil, paint, grease, corrosion
deposits or algae. Where breaking out is not required,
Properties roughen the surface and remove any laitance by light
scabbling or grit blasting.
The results listed below were achieved by assessing the
mechanical properties of a 3:1 sand:cement mortar Oil and grease deposits should be removed by steam
containing Nitobond SBR in the proportions 10 litres per 50 cleaning, detergent scrubbing or the use of a proprietary
kg cement against a 3:1 sand:cement control mortar. The degreaser. The effectiveness of decontamination should
test methods used were in full accordance with BS 6319 at then be assessed by a pull-off test.
28 days – air cured.
Page 1
Nitobond SBR
Expose fully any corroded steel in the repair area and 2. Heavy-duty floor screed
remove all loose scale and corrosion deposits. Steel should
be cleaned to a bright condition paying particular attention to 50 kgs Ordinary Portland Cement
the back of exposed steel bars. Grit blasting is 75 kgs 3 mm to 6 mm granite chips
recommended for this process. 75 kgs grade C/M sharp sand
10 litres Nitobond SBR
Where corrosion has occurred due to the presence of 6 litres (approximately) clean water
chlorides, the steel should be high-pressure washed with The screed should be of a semi-dry cohesive
clean water immediately after grit blasting to remove consistency. Recommended thickness 10 mm to 40
corrosion products from pits and imperfections within its mm.
surface.
3. Render
Reinforcing steel priming
50 kgs Ordinary Portland Cement
Apply one full coat of Nitoprime Zincrich to any exposed steel 150 kgs grade C/M sharp sand
reinforcement and allow to dry before continuing. If any 10 litres Nitobond SBR
doubt exists about having achieved an unbroken coating, a 6 litres (approximately) clean water
second application should be made and, again, allowed to The render should be of a semi-dry cohesive
dry before continuing. consistency. Recommended thickness 6 mm to 9 mm.
The substrate should be thoroughly soaked with clean water 50 kgs Ordinary Portland Cement
and any excess removed prior to commencement. A slurry 125 kgs grade C/M sharp sand
primer should be prepared consisting of 1 volume Nitobond 10 litres Nitobond SBR
SBR to 1 volume clean water to 3 volume fresh cement. To 7 litres (approximately) clean water
obtain a smooth consistency, the cement should be blended Water is adjusted to give a firm mortar. For fine joints,
slowly into the premixed liquids. The slurry primer should be use grade M/F sand. Support where necessary until the
stirred frequently during use to offset settlement. mortar is set. Recommended thickness 6 mm to 40
mm.
The slurry primer should be scrubbed well into the surface of
the concrete. Avoid applying too thickly and avoid 'puddling'. Note: The mix designs are based on the use of dry sand
The repair mortar, topping or render must be applied on to and aggregate. Adjustments must be made to the
the wet slurry primer. If the slurry primer dries before water demand relative to the moisture content of the
application of the mortar, it must be removed and the area re- sand and aggregate used. It should also be noted
primed before continuing. that, due to the frequent inconsistencies of site-
stored materials and variable conditions, actual
In exceptional circumstances, e.g. where a substrate/repair results may differ from those published above.
barrier is required or where the substrate is likely to remain
permanently damp, Nitobond EP bonding aid should be used. Weigh the cement, sand and, where required, aggregate
Contract the local Fosroc office for further information. into the mixer and dry blend together for one minutes. With
the machine in operation, add the pre-mixed Nitobond SBR
Mixing and clean water. Continue mixing for 3 minutes to ensure
complete dispersal into the sand and cement. Make any
Care should be taken to ensure that Nitobond SBR mortars small adjustment to the quantity of clean water but do not
are thoroughly mixed. A forced-action mixer is essential. significantly exceed the literage shown above. Additional
Mixing in a suitably sized drum using an approved spiral water should be kept to a minimum. Continue mixing up to
paddle in a slow speed (400/500 rpm) heavy-duty drill is a maximum of 5 minutes until a smooth and fully
acceptable for occasional use. homogeneous consistency is achieved with the required
workability and application properties. It is critical that
A wide range of mix designs is achievable using Nitobond allowance is made for the moisture content of the sand and
SBR. Typical designs are detailed below: aggregate, particularly where they are stored on site.
50 kgs Ordinary Portland Cement For application to all surfaces, Nitobond SBR mortars,
150 kgs grade C/M sharp sand toppings and renders must be well compacted on to the
10 litres Nitobond SBR primed substrate by trowel. It is frequently beneficial to
8 litres (approximately) clean water work a thin layer of the mortar into the slurry primer and
Recommenced thickness 6 mm to 40 mm then build the mortar on to this layer. Exposed steel
reinforcement should be completely encapsulated by the
mortar.
Nitobond SBR mortar repairs are extremely durable and will Coverage and yield
provide excellent protection to the embedded steel
reinforcement within the repaired locations. The surrounding Nitobond SBR: Refer to mix designs
parts of the structure will generally benefit from the Nitobond SBR Approximately 2 to 3 m3 per litre
application of a barrier/decorative coating to limit the advance (as slurry primer):
2
of chlorides and carbon dioxide, thus bringing them up to the Nitoprime Zincrich: 7.4 m per litre
same protective standard as the repair itself. Fosroc Nitobond EP: 10 to 11.5 m2 per pack
recommend the use of the Dekguard range of protective, 2
Nitobond AR: 6 to 8 m per litre
anti-carbonation coatings. These products provide a Concure 90 Clear: 4 to 5 m2 per litre
decorative and uniform appearance as well as protecting
areas of the structure which might otherwise be at risk from
Important note:
Fosroc products are guaranteed against defective materials and manufacture and are sold subject to its standard Conditions
for the Supply of Goods and Services, copies of which may be obtained on request. Whilst Fosroc endeavours to ensure that
any advice, recommendation, specification of information it may give is accurate and correct, it cannot, because it has no direct
or continuous control over where or how its products are applied, accept any liability either directly or indirectly arising from the
use of its products, whether or not in accordance with any advice, specification, recommendation of information given by it.
www.fosroc.com Khamis Mushayt Tel: (017) 250 0469 Fax: (017) 250 0469 NJS Tel: (012) 691 7532 Fax: (012) 682 3625
Registered Office: Industrial Area, Phase 4, Road No. 102, Street No. 82
Page 4 FO SA/NITOBOND SBR/0210/16
Material Submittal
RSG-CN-TMP-0007
Attached Below.
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 13 of 21
constructive solutions
NITOBOND SBR satisfies the LEED requirement for SCAQMD VOC limitations and can contribute to earn Indoor
Air Quality Credit 4.2: Low Emitting Materials, which is intended to reduce quantity of indoor air contaminates that
are odorous, potentially irritating and/or harmful to the comfort and well-being of installers and occupants.
Please refer to the MSDS of the above-mentioned product for more details about health and safety.
Best Regards,
For Fosam Company Ltd. (Saudi Fosroc),
________________
Tarek Alwani
Product Segment Manager – Concrete Repair & Grouts
Mobile No.: +966 50 001 2962
“USGBC® and related logo is a trademark owned by the U.S. Green Building Council ® and is used with permission”
Fosam Company Limited
Head Office
telephone: em ail:
PO Box 11081
Jeddah – 21453 +966 (2) 637 5345 [email protected]
Saudi Arabia
C.R. No. 31273 Certificate number IND 93024
Attached Below.
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 18 of 21
SAFETY DATA SHEET
NITOBOND SBR
1.2. Relevant identified uses of the substance or mixture and uses advised against
Identified uses Polymer bonding aid and mortar additive
Pictogram
1/7
NITOBOND SBR
3.2. Mixtures
Composition comments Aqueous dispersion of Copolymer of Styrene and 1, 3 Butadiene
Ingestion If swallowed, drink plenty of water, do NOT induce vomiting. Get immediate medical attention.
Skin contact Wash skin thoroughly with soap and water or use an approved skin cleanser.
Eye contact Flush eyes with clean water for at least 15 minutes keeping eyelids open. If discomfort
persists, consult a physicain.
4.2. Most important symptoms and effects, both acute and delayed
General information No specific symptoms noted.
4.3. Indication of any immediate medical attention and special treatment needed
Notes for the doctor No specific recommendations.
Special protective equipment In the event of fire, wear self-contained breathing apparatus.
for firefighters Use personal protective equipment.
2/7
Revision: 03
NITOBOND SBR
Methods for cleaning up Soak up with inert absorbent or contain and remove by best available means. Gather into
containers.
Protective equipment
Personal protection Use of barrier cream before work will assist subsequent cleansing.
Colour Milky.
Odour Acrylic
3/7
Revision: 03
NITOBOND SBR
10.1. Reactivity
Reactivity There are no known reactivity hazards associated with this product.
Eye contact Vapour or spray in the eyes may cause irritation and smarting.
4/7
Revision: 03
NITOBOND SBR
12.1. Toxicity
Toxicity Not expected to be ecotoxic to fish/daphnia/algae Not expected to be ecotoxic to
fish/daphnia/algae
General The product is not covered by international regulations on the transport of dangerous goods
(IMDG, IATA, ADR/RID).
14.1. UN number
Not applicable.
5/7
Revision: 03
NITOBOND SBR
14.7. Transport in bulk according to Annex II of MARPOL73/78 and the IBC Code
Transport in bulk according to Not applicable.
Annex II of MARPOL 73/78
and the IBC Code
15.1. Safety, health and environmental regulations/legislation specific for the substance or mixture
Guidance Hazard Label Data:-
This product is NOT classified as dangerous for supply
Safety Phrases: Avoid contact with skin and eyes.
In case of contact with eyes, rinse immediately with plenty of water and seek medical
advice.
EC Directives: Dangerous Substances Directive, 67/548/EEC and adaptations.
Dangerous Preparations Directive, 88/379/EEC.
Safety Data Sheets Directive, 91/155/EEC.
Statutory Instruments: Chemicals (Hazard Information and Packaging for Supply)
(Amendment) Regs. 1996 (SI
1092).
Control of Substances Hazardous to Health Regs. 1994 (SI 3246).
Environmental Protection (Duty of Care) Regs. 1991 (SI 2839).
Codes of Practice: Waste Management. The Duty of Care.
The above publications are available from HMSO
General information The data and advice given apply when the product is used for the stated application or
applications. The product is not sold as suitable for any other application. Use of the product
for applications other than as stated in this sheet may give rise to risks not mentioned in this
sheet. The product should not be used other than for the stated application or applications
without seeking advice from Fosam Company ( Fosroc).
If this product has been purchased for supply to a third party for use at work, it is the
purchaser's duty to take all necessary steps to secure that any person handling or using the
product is provided with the information in this sheet.
It is the responsibility and duty of the employer to inform employees and others who may be
affected of any hazards described in this sheet and of any precautions which should be taken.
This sheet does not constitute or substitute for the users own assessment of workplace risk,
as required by other health and safety legislation.
Further copies of this Safety Data Sheet may be obtained from Fosroc Fosam Compamy.
Revision 03
6/7
Revision: 03
NITOBOND SBR
The information on this data sheet represents our current data and is reliable provided that the product is used under the
prescribed conditions and in accordance with the application specified on the packaging and/or in the technical guidance
literature. Any other use of the product which involves using the product in combination with any other product or any other
process is the responsibility of the user.
7/7
constructive solutions
Method Statement
method statement constructive solutions
It is suggested that, for temperatures above 35°C, the following guidelines are adopted as
good working practice:
(i) Store unmixed materials in a cool (preferably temperature controlled) environment, avoiding
exposure to direct sunlight.
(ii) Keep equipment cool, arranging shade protection if necessary. It is especially important to
keep cool those surfaces of the equipment, which will come into direct contact with the material
itself.
(iii) Try to avoid application during the hottest times of the day, arrange temporary shading as
necessary.
(iv) Make sufficient material, plant and labour available to ensure that application is a continuous
process.
(v) Where mixing water is required in the application of a product, it is advised to maintain such
water at a maximum of 20°C
Equipment
It is suggested that the following list of equipment is adopted as a minimum requirement
Protective clothing : Protective overalls
: Good quality gloves, goggles and face mask
Preparation equipment : Marker chalk or pen
: Disc cutter
: Electric/pneumatic breaker or hammer and chisel
: Wire brush
: Proprietary blasting equipment
Mixing equipment : Measuring jug
: Proprietary forced-action mixer
Application equipment : Hand application trowel
: Wooden float
: Steel or plastic finishing float
: Finishing sponge
Fosroc operates a policy to encourage the use, where possible, of registered applicators, since the
long term performance of the materials is dependent upon proper application. For contractors who
wish to apply the materials themselves Fosroc is also able to offer technical assistance and training,
either on-site or at its Training Centre in Jeddah.
Attention to full and proper preparation of the substrate is essential for complete repair
adhesion.
1.1 Mark out the defective area, then saw cut the edge of the repair to a minimum depth of 10 mm,
angling the blade to create an undercut.
1.2 Break out the repair area to remove all contaminated or damaged concrete to a minimum
depth of 10 mm, up to the pre-cut perimeter of the repair.
1.3 Fully expose any corroded reinforcement in the repair area and continue until non corroding
steel is reached - it may be necessary to break out the concrete beyond the original repair area
in order to achieve this. Ensure that a clear gap of at least 20 mm is created behind the rear
face of the steel reinforcement, such that a gloved hand can comfortably reach behind the
bars.
1.4 Oil and grease deposits are best removed by steam cleaning, detergent scrubbing or the use
of a proprietary degreaser. The effectiveness of decontamination should be assessed by a
pull-off test.
1.5 Fully clean the concrete and steel surfaces to remove laitence, the by-products of corrosion
and other contaminants. This is most effectively achieved by the use of proprietary blast media;
with particular attention required to both the rear face of the bars and the edge of the repair.
The steel bars should be cleaned to a uniform bright condition; and the saw cut edge of the
repair should be ‘roughened’ to provide a good mechanical key at the substrate interface.
1.6 Chloride induced corrosion will further require high pressure washing with clean water, after
blasting, to ensure complete removal of the corrosive elements.
2.1 Exposed steel reinforcement, including any replacement reinforcement, should be securely
held in place to avoid movement during application, as this will affect the compaction, build and
bond of the mortar.
2.2 Apply one full, unbroken coat of Nitoprime Zincrich to the steel within 3 hours of cleaning, and
allow drying before continuing. If unsure about continuity of the coating, apply a second coat
and allow drying.
Page 2 of 5
constructive solutions
This can be broadly classified as : (i) standard priming conditions where a standard priming mix
of 1:1:3 of Nitobond SBR : clean fresh water : cement by volume can be used, or (ii) non
standard priming conditions (i.e. where the substrate is contaminated with chlorides or is
immersed) where an epoxy based bonding agent/isolator is required. If in any doubt regarding
the most appropriate primer, contact the local Fosroc office
a) Thoroughly soak with clean water and remove excess, leaving the substrate in “saturated
surface dry” condition.
b) Apply SBR slurry described above by scrubbing into the surface and allow to become tacky
(typically 5 to 10 minutes after application).
c) If the primer is too wet, or has dried, repair mortar will not adhere properly.
c) An unbroken coating of primer must be achieved - apply two coats. Each coat should be
well ‘scrubbed’ into the prepared substrate, the first coat being allowed to gel before
application of the second coat.
d) The primed substrate should then be left for one hour before proceeding with further
application of the repair material.
4.0 Mixing
a) 50 kg Cement
b) 150 kg clean sharp sand C/M
c) 8-10 liters Nitobond SBR
d) 6 Liters clean fresh water (Approximately)
4.2 Use forced action mixer to mix the previous measures, always start with water and 2/3rd of the
required SBR quantity, and add the final 3rd after adding mortar. Always add powder to water
to avoid lumps.
Page 3 of 5
constructive solutions
4.3 It is essential that repair mix is thoroughly mixed and that the temperature of the mixed
material should not be allowed to exceed 300C.
5.0 Application
5.1 Apply the mix to the substrate by trowel or gloved hand, thoroughly compacting onto the
primed substrate, whilst the primer is still tacky. Ensure that mortar is applied around the
exposed steel reinforcement, compacting fully at the rear face.
5.2 Thickness of application should be in accordance with that laid down in the ‘Application
criteria’ section of the current product data sheet.
5.3 If sagging occurs on vertical or overhead faces, the mix must be completely removed. The
substrate must be reprimed and prepared repair mortar then reapplied in layers of reduced
thickness.
6.0 Build-up
6.1 Build-up of the repair mortar is best achieved using a ‘wet on wet’ technique.
6.2 Multiple layers can also be used to achieve the desired thickness and profile; but care must be
taken to ensure consistency of inter-coat bond strength.
6.3 Where multiple layers are to be applied, the surface of intermediate layers should be ‘scratch-
keyed’ and cured with wet hessian. Further applications of fresh prepared repair mortar may
be applied once the intermediate layer has reached its initial set.
7.0 Finishing
7.1 SBR repair mortar is finished by striking off with a straight edge and closing with a steel or
plastic float. Note that water can be drawn to the surface if ‘overworking’ with the float occurs,
and an unsightly finish may result.
7.2 Damp sponges or plastic floats may be used to achieve a desired surface texture, but care
should again be taken not to overwork the surface.
8.0 Curing
8.1 Curing of repaired areas should be carried out as soon as possible after the surface has been
‘closed’, using Concure WB.
8.2 Concure WB should be brush or spray applied as per its current method statement.
Page 4 of 5
constructive solutions
8.3 In adverse conditions (e.g. windy conditions or ambient temperatures greater than 300C),
supplementary curing in the form of polythene sheeting, taped down at the edges, should be
used.
9.0 Cleaning
9.1 SBR Slurry, Concure WB, SBR repair mortar should be removed from tools, equipment and
mixers with clean water immediately after use. Cured material can only be removed by
mechanical means.
9.2 Nitoprime Zincrich and Nitobond EP can only be removed from tools and equipment using
Fosroc Solvent 102.
This method statement is offered by Fosroc as a ‘standard proposal’ for the application of Nitobond
SBR Repair Mortar. It remains the responsibility of the Customer to determine the correct method
for any given application. Where alternative methods are to be used, these must be submitted to
Fosroc for comment, in writing, prior to the commencement of any work.
Page 5 of 5
Material Submittal
RSG-CN-TMP-0007
Test Reports
Attached Below.
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 12 of 21
MTl
Modern Technology laboratory
Construction Materials Laboratory and Engineering Services
SPECIMEN MEASUREMENT
DATE AGE
ID SPECIMEN INFO LOAD{KN) BOND STRENGTH(MPa)
TESTED (DAYS)
BONDING SURFACE
NITOBOND
COATED WITH 04-08-23 28 157.10 25.4
SBR
NITOBOND SBR
TESTED BY CHECKED B
SIGNATURE SIGNATURE
Toi: +DSG , 2 6774340. Fox: +966 1 2 6776253 + q,, 1r "'lvv,rot"" .�� - ..- �,, ,r "lVVE.t""E. • ....A:.JlJ;a
MTl
Modern Technology laboratory
Construction Materials Laboratory and Engineering Services
CONTROL MIX (kg) OPC: 50, SAND: 150, WATER: 18 RELATIVE HUMIDITY(') 51
OPC: 50, SAND: 150, WATER: 8,
NITOBOND SBR MIX(kg) TESTING MACHINE ELE COMPRESSION
NITOBOND SBR: 10
/4�
MTL MANAGEMENT IS NOT RESPONSIBLE OF CUSTOMER SAMPLE 15 DAYS AFTER THE TEST DA\E � � -'
THE TEST REPORT SHALL NOT BE REPRODUCED WITHOUT APPROVAL FROM THE MTL MANAGEM\NT < ->-.:i&..:a"ili
..-:'---.
,",
CONTROL MIX (kg) OPC: 50, SAND: 150, WATER: 18 RELATIVE HUMIDITY('} 51
re·�/4
�-<' \OtOGJ· •,
D SAMPLE PREPARED BY MTL
0
_;
)1 ,
RESULTS RELATE ONLY TO THE SAMPLE AS RECEIVED
MTL MANAGEMENT IS NOT RESPONSIBLE OF CUSTOMER SAMPLE 15 DAYS AFTER THE TEST D g \
THE TEST REPORT SHALL NOT BE REPRODUCED WITHOUT APPROVAL FROM THE MTL MANAGE' NT
\
\,\. ��
Cl
Modem Technology Laboratories
CONTROL MIX (kg) OPC: 50, SAND: 150, WATER: 18 RELATIVE HUMIDITY (')I 51
OPC: 50, SAND: 150, WATER: 8,
NITOBOND SBR MIX(kg) TESTING MACHINE Elf COMPRESSION
NITOBOND SBR: 10
REMARKS
CONTROL MIX (kg) OPC: 50, SAND: 150, WATER: 18 RELATIVE HUMIDITY(% 51
OPC: 50, SAND: 150, WATER: 8,
NITOBOND SBR MIX(kg) TESTING MACHINE WALTER+ BAI
NITOBOND SBR: 10
#'/_J-_ �\_
�
.,""
D SAMPLE PREPARED BY MTL
· £ '""
0 RESULTS RELATE ONLY TO THE SAMPLE AS RECEIVED
g \ 1 )
n
..
I
l"."':":I
MTL MANAGEMENT IS NOT RESPONSIBLE OF CUSTOMER SAMPLE 15 DAYS AFTER c::'\ ,:-,,'";I i....:,;: \/
Ti T Qil.TEI'
THE TEST REPORT SHALL NOT BE REPRODUCED WITHOUT APPROVAL FROM THE MTL � ���ENT-!;..;:;Ji i�n J
. "f. � ,
REMARKS
CONTROL MIX(kg) OPC: 50, SAND: 150, WATER: 18 RELATIVE HUMIDITY (9-c 51
OPC: 50, SAND: 150, WATER: 8,
NITOBOND SBR MIX (kg) TESTING MACHINE WALTER+ BAI
NITOBOND SBR: 10
REMARKS
...
•
P.O.Box: 4869 Jeddah 21412 rttlr ,o= EAH ,y.v, �
ACCREDITED
Tel: +966 12 6774340, Fax: +966 12 6776253 ISO 17025
;.;* 'If •rr�•·w�•
constructive solutions
Job References
Job References for Nitobond SBR
Sorted by ascending Project Category and ascending Project Date
Project Title Sector Segment Main Contructor Country Quantity Units Date
JIZAN REFINERY Industrial Oil & Gas Various Saudi Arabia 22,000 Litres 2016
Institutional & HOUSE OF SKILL EST. -
NATIONAL GUARD - TABOUK Buildings Saudi Arabia 9,000 Litres 2016
Public Buildings TABOUK
Institutional & SAUDI BINLADIN GROUP
MAKKAH HARAM EXPANTION Buildings Saudi Arabia 13,000 Litres 2015
Public Buildings ABCD -
Institutional & HOUSE OF SKILL EST. -
NATIONAL GUARD - TABOUK Buildings Saudi Arabia 12,000 Litres 2015
Public Buildings TABOUK
SAUDI ARCHIRODON
JSTPP - JEDDAH Utilities Power Saudi Arabia 12,500 Litres 2014
LIMITED -
Public &
BANKERS Buildings Institutional 0 Jordan 11,500 m2 2014
Buildings
DISI PROJECT Utilities Water 0 Jordan 62,000 m2 2014
AL MARAIE HO Buildings Commerical Hashem Saudi Arabia 30 drum 2014
ARAFAT-MINA(AL MASHAER) RAIL WAY Transport Rail CHINA RAIL WAY CO. Saudi Arabia 3,700 Litre(s) 2010
ARAFAT-MINA RAIL WAY Transport Rail CHINA RAIL WAY CO. Saudi Arabia 3,750 Litre(s) 2010
1 - 7 HIGH STREET Buildings Commerical Robertson Construction Scotland 300 Litres 2010
Public &
CLACKMANNANSHIRE SCHOOLS - ALVA
Buildings Institutional Ogilvie Construction Scotland 25 Litres 2009
ACADEMY
Buildings
AL TARF PUMP STATION Utilities Water Civil Works Company Saudi Arabia 1 Units 2009
CENTRAL CONTAINER TERMINAL Transport Marine Al futtaim Carallion UAE 50 Units 2008
SWC Saudi Arabia 24 Pails 2008
AL-BASHIER HOSPITAL REHABILITATION Institutional
Buildings M.A Abu Aishe Jordan 5 25 Ltr
PHASE 2&3 Public & 2008
Buildings
AL ITTIHAD MALL Buildings Commerical Al Sahel Contracting UAE 20 drum 2008
Public & 2007
AL Naboodah Cont -
CANAL POINT HOSPITAL Buildings Institutional UAE 4,000 Litre(s)
Building Division
Buildings
CONTAINER CENTRAL TERMINAL Transport Marine Al Futtaim UAE 6 200 L Drum 2007
Public & 2007
CITY OF ARABIA INFRASTRUCTURE &
Buildings Institutional Kier UAE 4 25ltr
ROADS
Buildings
Public & 2006
United Engineers
COLLEGE OF TECHNOLOGY Buildings Institutional Qatar 2,500 Litre(s)
Malaysia-Berhard
Buildings
DAMMAM STP Utilities Water C.W.C. Saudi Arabia 24 Pails 2006
Power Oil, Gas, Thai Nishimatsu 2006
BLCP POWER PLANT Utilities Thailand 20 Pails
Coal Construction Co., Ltd.
CLUSTER BUILDINGS, ASAB Buildings Residential Al Geemi & Ptnrs UAE 1,400 Litre(s) 2006
National Transport and 2006
5 NO. RES/COMM BUILDINGS Buildings Commerical Contracting Company UAE 600 Litre(s)
(NTCC)
Nael & Bin Harmal 2006
ADSS CONTRACT 308/1, LIWA PROJECT Utilities Water UAE 500 Litre(s)
Hydroexport Est
Public & 2005
Chongqing Kindly
CHONGQING BA SHU HIGH SCHOOL Buildings Institutional China 6 drum
Waterproofing Co.
Buildings
Public & 2005
Chongqing Kindly
CHONGQING NAN KAI HIGH SCHOOL Buildings Institutional China 18 drum
Waterproofing Co.
Buildings
Public & 2005
United Engineers
COLLEGE OF TECHNOLOGY-QATAR PH.2 Buildings Institutional Qatar 2,500 Litre(s)
Malaysia-Berhard
Buildings
ALAB MARINE - CALCINING & BLENDING Cement & 2005
Industrial Global Bahrain Bahrain 4,500 Litre(s)
SILOS EXTERNAL COATING Concrete
Square 2004
AMBEDKAR BRIDGE Transport Road -- India 2,500
Metre(s)
Vaishnavi Waterproofing Square 2004
AIRFORCE STATION Transport Airports India 570
and Construction Metre(s)
India Guniting 2004
CHENNAI AIRPORT Transport Airports India 1,000 Litre(s)
Corporation
DIRAH AL-JAZIRA Buildings Residential Al-Mabani Saudi Arabia 625 Litre(s) 2003
Amec-Hong Kong 2002
CC202, YUEN LONG & LONG PING STATION Transport Rail Hong Kong 33,400 Kg
Construction
DAMASCUS GATE RESORT Buildings Commerical Eng. Fayz Adhami Syria 8,000 Litre(s) 2002
Public & 2002
CASTELÃO STADIUM Buildings Institutional Cinzel Brazil 940 Litre(s)
Buildings
BANDERANIAKE INTERNATIONAL AIRPORT Transport Airports K.D.A. Weerasinghe Sri Lanka 300 Litre(s) 2002
Public & 2002
AL MASSOOD TOWER Buildings Institutional al hamad contr. co UAE 25 25 Litre
Buildings
COPENHAGEN METRO Transport Rail COMET Denmark 245 Litre(s) 2001
CARREFOUR AL AIN Buildings Commerical DIPLOMAT UAE 14,000 Ltr 2001
ARAB BANK - NEW HEADQUARTERS Buildings Commerical Medgulf Construction Qatar 400 Litre(s) 2001
Public & 2001
AL AHLI HOSPITAL Buildings Institutional Contraco Qatar 275 Litre(s)
Buildings
DONG HU HAO TING Buildings Residential Unknown China 6,225 Kilogram(s) 2001
COMM. BLDG FOR H.H.CROWN PRINCE W- Group 3 Engineers 2001
Buildings Commerical UAE 2,400 Litre(s)
10/C-62 Contractors
BASELINE ROAD IMPROVEMENT Transport Road Kumagi - Gumi Sri Lanka 150 Litre(s) 2000
BOLE INTERNATIONAL AIRPORT Transport Airports M.A.Al-Kharafi & Sons Ethiopia 1,450 Litre(s) 2000
AL-RAJHI TOWERS Buildings Commerical Al-Zaidi Contracting Saudi Arabia 7,500 Litre(s) 2000
The No.2 Subsidiary 2000
DA-YA GULF NUCLEAR POWER STATION Utilities Power Nuclear Department of China China 399 oL
Construction Co
6 TOWER BLOCKS Buildings Residential McAlpine UK 12,000 Litres 1999
Public & 1999
CROFT WARD Buildings Institutional Unknown UK 0 Unknown
Buildings
EASTON STREET CARPARK Transport Road Concrete Repairs Ltd UK 2,000 Litres 1999
Material Submittal
RSG-CN-TMP-0007
Attached Below.
RSG-CN-TMP-0007
Rev. 01, Oct. 01, 2022 Page 20 of 21
constructive solutions
Case Histories
CASE STUDY
Constructive solutions
Project Name
Developing rainwater
Micro-Tunnels
Qassim - Saudi Arabia
CLIENT
Ministry of Water and Electricity
CONTRACTOR
Thrustboring Construction Company
SECTOR
UGC – “Micro – tunneling”
DATE
March 2016
PRODUCTS
Conbextra AGB
Supercast PVC
Nitobond SBR
BACKGROUND Nitocote ET550
Saudi Arabia had witnessed heavy rainfall which caused problems to the current under- Nitoproof 10
designed rainwater channels across its cities. Qassim region is especially prone to
flooding since the average annual rainfall is calculated to exceed other regions, as
illustrated in figure 1. As a mitigation action the ministry of water and electricity began
developing new rainwater culverts and micro-tunnels around the region including
Buraydah and Unaizah.
THE PROJECT
Rainwater tunnels stretching across different parts of Qassim to accommodate the
rainfall and prevent future floods. Thrustboring Construction Company, a trenchless
technology company, had been given the job to build underground tunnels using tunnel
boring machines – TBMs. This method will limit the disturbance of the surrounding
environment and present high advance rates.
FOSROC’S SOLUTION
TCC - Thrustboring Construction Compnay (the contractor) needed a company which
could provide them with materials that can be durable, trusted and available with the
required technical and site support at all times. Map of Saudi Arabia showing the
Fosroc has introduced the right solutions throughout the project execution which distribution of annual rainfall for a 50
included sodium bentonite (Conbextra AGB), a product that provides annulus grouting for year period (1950-2000) based on rain
the TBM ,lubrication and stabilizes the soil. Fosroc’s construction materials were also used gauge observations. The circulations
indicate the location radar observations.
for the construction of the launching and receiving shafts as shown in figure 2, like
“Supercast PVC Waterstops”. The waterstops were designed to provide an integral sealing
system for the construction joints of the cast in-situ shafts. Another critical part of
construction is to protect the concrete from chlorides and sulphate ions, this was
accomplished by coating the shafts with “Nitoproof 10”, a bitumen emulsion which acts as
a damp-proof membrane and vapour seal for concrete and masonry.
THE BENEFITS
The availability and quality of the products both with the continuous service provided,
allowed the project to stay on schedule and proved the extent of Fosroc’s involvement.
Lowering the launching shaft into the ground Building a supporting wall for the Pressure jacks of the TBM
Assembling the pressure jacks Pressure jacks pushing the concrete segments while
the TBM is advancing through the ground
Constructive solutions
Project Name
King Khalid Military College
Podium at National Guard
CUSTOMER
Al Khayyam International
Contracting Co.
SECTOR
Infra-Structure
DATE
May – September 2015
PRODUCTS
Renderoc HS Xtra
Nitobond SBR
Renderoc FC
Nitocote EPU
THE PROJECT
Project calls for the construction King Khalid Military College Podium, will be an attractive
land mark composite structure of concrete and steel with wooden external decoration,
and to be used for military shows, training and other official events. The project located at
Khashm Al Aan area east of Riyadh with a total build up area of 3,000 SM, and a contract
value of US 12million dollars. Main contractor is M/s Al Khayyam International Contracting
Company was awarded this project in early of May 2014.
Fosroc Products
THE SOLUTION
During the concrete works, poor workmanship led to major problems in concrete in both
Structural & Non-Structural problems, challenges were to provide a solution that
assuring the monolithic concrete repair system and to provide the required structural
repair along with the cosmetic one, with long lasting solution that is matching the
expected serviceability period of the structure. Our Solution was to provide the Renderoc
HS Xtra along with the polymer based bonding agent Nitobond SBR, which gives high
strength with very low permeability that provides proper protection for reinforcement
steel. On the other hand Renderoc FC was used for cosmetic and non-structural repair.
Application Works
THE BENEFITS
Project was executed and the required service was delivered to both of the client and the
contractor in addition to meet the required job quality and surface finishing as per KSA
and international standards
constructive solutions
Wadi Hali Water
Treatment Plant
Qunfuda - Saudi Arabia
CUSTOMER
Ministry of Water & Electricity
SECTOR
Water Utilities
DATE
2009 - 2015
PRODUCTS
Fosroc Polyurea WPE
Nitocote EPSW
Supercast PVC waterstop
Nitomortar TC2000
Nitobond SBR
Thioflex 600
Renderoc FC , TG
THE PROJECT
Wadi Hali Water Treatment Plant is designed to serve western region of Saudi Arabia. Its main
objective is to treat and waste water, hence, producing a treated to water to be used for other
purposes. The plant is considered one of the biggest waste water treatment plants in Saudi Arabia.
The Dam is 384 mLength, 71m width at the base & 8m width at the top crest.
The construction process is in the final stage, handled by Al-Ruwaite Contracting Company. And the
owner is Saudi ministry of water and electricity.
Construction stage
THE SOLUTION
Fosroc team approached the contractor from the project start and provided full assistant to
achieve the required specifications. Fosroc products contributed efficiently and performed
satisfactory from the early stage till the finishing, starting with the waterproofing using Supercast
waterstop, rendering using more 50 tons Renderoc range and Nitomortar TC2000, and finishing
with more than 65 tons of high quality coating products FOSROC Polyurea & Nitocote EPSW. During
the project Fosroc team provided full technical assistant in educating and training contractor’s
team to apply products properly and satisfactory.
- The client was satisfied for FOSROC team’s continuous support during products’
application
- The client was satisfied from having the same source providing all construction chemical
solutions.
- Contractors required was fulfilled through a cost-effective and up to standard solutions
constructive solutions
RAHEJA IT SEZ
HYDERABAD
CUSTOMER
Raheja IT SEZ
SECTOR
Commercial
DATE
October 2015
PRODUCTS
Nitoproof 600
BrushBond
Nitobond SBR
THE PROJECT
Mind space is all about creating a new age philosophy to live & work in INDIA. It is the
perfect confluence of intelligent work spaces, state-of-the-art infrastructure, 360 degrees
support facilities and life style amenities. All seamlessly integrated within one complex to
create a single business environment for hi-technology companies. The project is
designed with the podium slab which is completely used for landscaping which enhances
the aesthetics, Green building concept & Eco friendly. Here the challenge is the podium
slab with landscaping stays uninterruptedly contact with water for 24Hrs a day, 7 days in
a week & 365 days in a year, under the podium, provision for car parking has been Ariel view of Podium after
provided. In order to protect their podium slab from leaks & other snags they need to application of Nitoproof 600
have a robustic water proofing solution for the protection of their podium.
THE SOLUTION
Fosroc has met the client with the tailor made solution against their requirement which is
very helpful for the client to distinguish & judge the solution and to proceed further.
Fosroc proposed Nitoproof 600 for podium waterproofing which is having exceptional
product features and advantages of its own in terms of elongation, crack bridging,
flexibility and permeability. Fosroc has supported and clarified the doubts of the client in
terms of product usage and application and maintained a good rapport with the client.
Application of Nitoproof 600
Client has gratified with Fosroc product technically even though Fosroc proposal is
commercially greater at comparison with the competitors, Fosroc has bagged the order
& proved once again its gigantic presence in terms of technicality in the market.
THE BENEFITS
Nitoproof 600, single component cold applied hence it is seamless & made application
very easy, escaping the risk of torching in case of APP membrane. Fully bonded to the
substrate where lateral movement of water is not possible which most important benefit
Front view of the Project
for the client. The system is having 620% of elongation and flexibility and having excellent
crack bridging properties and made his podium slab complete leak proof & water tight.
constructive solutions
Victory Valley
Gurgaon
Haryana
Client – IREO
Contractor – Larsen &
Toubro Ltd, Construction
DATE- YEAR 2012 -2014
PRODUCTS
CONPLAST SP430
CONCURE LP90(M)
REEBOL
NITOBOND EP
NITOBOND SBR
CEBEX 100
COLPOR 200
THE PROJECT
IREO is the first and the largest private equity fund dedicated to the Indian real estate
sector with a fund size of US $2 billion.IREO has a diversified portfolio of high quality
projects spread across approximately 3,000 acres of owned land.
IREO Victory Valley is an iconic high rise housing project in Gurgaon. With the tallest of
it’s three high-rise towers being a stunning 51 floors tall.
THE BENEFITS
Fosroc’s prompt response, technical support and material availability on time helped the
customer to stay on his schedule without any delay, as the schedule was very tight.
Moreover, the customer is fully assured that after Fosroc’s solution. Fosroc solution and
technical services also gave customer great satisfaction and confidence.
Project view
T:+91 80 42521900 F: +91 80 23551510 E: [email protected]
Address: Sapthagiri Place, No.38, Floor 12 Cross, CBI Road, Ganganagar North Bangalore 560024, India
www.fosroc.com