BOQ OF FACTORY SHED AT MD MOTORS
AREA 769.2 SQM
Plinth HT 0.75 MTR
SR.NO. DESCRIPTION OF ITEMS QTY. RATE UNIT AMOUNT
A UP TO PLINTH
1 EXCAVATION WORK
Earth work in excavation below existing ground level in foundations, trenches, in all class
of soil / murrrum except rock up to a depth of 1.50 mtrs. Including shoring, strutting,
dewatering, and disposing off the un useful soil outside the plot boundary complete as
directed by Engineer IN charge.
a ( upto 1.50 )
Do--- as above in depth 0 mtrs. To 1.50 mtrs. 230.13 175 CUM 40273.23
b ( upto 3.00 )
Do--- as above in depth 1.50 mtrs. To 3.00 mtrs. 40.99 195 CUM 7993.44
2 BACK FILLING WORK
Filling in foundation & in Plinth with selected(Non Expansive) earth spread in layers of
150 to 230 mm thickness to achieve required level and slope / gradient and compacted
to 95% of proctor density and leveling finally as per the instruction of Engineer-In-Charge
inclusive cost of soil, transportation and all taxes and royalties .
a Available excavated good earth 232.04 95 CUM 22044.27
b Earth brought from outer side for Plinth filling 813.97 425 CUM 345935.20
3 Metalling [ 63-90 mm ]
Providing and laying metal (size 63mm x 90mm) in a layer of 175mm each well
compacted with power roller without damaging foundation filling voids with quarry dust,
watering, ramming, compacting if required for edges and corners use plate compactor 106.20 1950 CUM 207092.16
etc. complete as directed by Engineer In charge.
4 PLAIN CEMENT CONCRETE [M10-1:3:6]
Providing and laying cement concrete in foundation and plinth M:10 [Site mix] and
curing complete including cost of formwork as directed by Engineer In charge.
Total Qty. for Metal concrete(PCC) 66.94 4750 CUM 317979.27
5 RCC work [ in M20 Grade ]
Providing and laying controlled reinforced Cement Concrete of M20 grade with
20mm down size graded crushed stone aggregate including scaffolding, opening,
recesses, chamfering, finishing top surfaces vibrating, machine mixing tamping, curing
(excluding centering and shuttering) etc. complete as per the specifications,
drawings and instruction of Engineer - in- charge (excluding cost of reinforcement) for
all elements of concrete
a Total Qty. for RCC footings 26.33 6300 CUM 165903.05
b Total qty. for RCC columns (Pedestal ) 7.43 6300 CUM 46777.50
c Total Qty. for RCC groundbeams 12.26 6300 CUM 77241.84
d Total Qty. for RCC plinth beam 0.00 6300 CUM 0.00
e Total Qty. for copping beams 2.72 6300 CUM 17164.85
6 BRICK MASONARY WORK
Providing and constructing Conventional Brick masonry in CM 1:6 (1 Cement and 6
Coarse sand) upto plinth with conventional size bricks having minimum crushing
strength of 35 Kg / Sq. Cm. including scaffolding, racking out joints, curing, watering etc.,
complete as directed by Engineer IN charge.
a Total qty. of brick work upto P.L. (230 mm thick) (1:6) proportion 9.05 5800 CUM 52507.57
7 REINFORCEMENT STEEL FE 500
Providing & Supplying & fixing in position High yield deformed bar Reinforcement
confirming to IS – 1139 or cold Twisted bars, TOR steel / TMT / or Equivalent
Reinforcement bars confirming to IS – 1786 for RCC construction including transporting
(i.e. loading & unloading) the steel from store/issue points to site of works including
unloading from Trucks/Trailers, cleaning, de coiling, cutting, bending to required shape 5.33 79000 MT 421082.56
and lengths as per detailed drawing, binding with 16 SWG black soft annealed binding
wire, placing with proper cover block, support chairs, overlap, spacers, etc. complete in
all respect as directed by Engineer IN charge in foundation and up to Plinth level.
8 SHUTTERING
Providing and erecting in position form work with plate shuttering materials of
approved quality for all type of concrete elements vertical, horizontal or inclined
including scaffolding, stagging, fasteners,locking ,Ties at respective levels necessary nails,
wires, locking pins,Guggus etc keeping in position till concrete is laid and members have 249.79 450 SQM 112405.50
acquired required strength, removal thereafter, applying shuttering oil etc. complete as
directed by Engineer-in-Charge.
9 RCC Tremix Flooring [M:20]
Providing and laying conventional cement concrete M-20, 150 mm thick in alternate
panels for flooring. Panels shall be formed by MS channel 100 mm depth on all four sides
and bolted adequately to make the panel size as required. Entire concrete mass shall be
vibrated with screed vibrators and levelled etc ,including the cost of form work but 88.50 6300 CUM 557555.83
excluding cost of reinforcement, and curing by pounding the surface of concrete,
complete as directed by Engineer IN charge..
10 TRIMIX WORK-Final finisihing work
Extra for using "Tremix system " (vacuum dewatering system and smooth finishing and
after that smooth finish with power trowel) in flooring.etc complete incl.all cost and as 708.01 85 SQM 60180.63
per instruction of Engg Incharge .
11 Groove cutting
Providing and constructing groove cutting of size 5mm x 50mm deep for floor , including
saw cutting of concrete floors / pavement to the required depth, filling the same with 384.60 140 RMT 53844.00
polysulpide, etc. complete.as per instruction of Engg in charge.
12 Expansion Joint
Providing and filling expansion joint 25 mm wide in concrete floor, beams, chhajja,
a columns etc. with impregnated tiki tar sheet as directed by Engineer In charge. As per R/O 320 SQM
drg
13 Foundation Bolt Fixing
Labour charges for Positioning Foundation Bolts in the pedastals maintaining all the line
& level , confirming from the responsible Engineer etc as per detailed drawing, to keep 120.00 150 NOS 18000.00
the bolts in position as required ,etc. complete as directed by Engineer In Charge.
14 GP2 Grouting
Filling the gap between RCC column, base plate and floor with GP2 Grout of M45 I S I
grout to consume shall confirm to company Equavalient of SIKA make / Fair mate / Dr.
fixit etc. as per I S Specification including the all the over head expesnes and the edges 0.14 60000 CUM 8100.00
shall be shampered etc completed as directed by Engineer Incharge.
A ABOVE PLINTH TO 3 MTR HEIGHT
15 RCC work [ in M20 Grade ]
Providing and laying controlled reinforced Cement Concrete of M20 grade with
20mm down size graded crushed stone aggregate including scaffolding, opening,
recesses, chamfering, finishing top surfaces vibrating, machine mixing tamping, curing
(excluding centering and shuttering) etc. complete as per the specifications,
drawings and instruction of Engineer - in- charge (excluding cost of reinforcement) for
all elements of concrete
a RCC COLUMNS 4.86 6300 CUM 30618.00
b RCC Copping beam 4.33 6300 CUM 27261.39
16 BRICK MASONARY WORK
Providing and constructing Conventional Brick masonry in CM 1:6 (1 Cement and 6
Coarse sand) above plinth and upto ground floor slab level with conventional size bricks
having minimum crushing strength of 35 Kg / Sq. Cm. including scaffolding, racking out
joints, curing, watering etc., complete as directed by Engineer IN charge.
a Total qty. of brick work above P.L. (230 mm thick) (1:6) propoprtion 28.29 5800 CUM 164074.00
b Partition wall above P.L (115 mm thick) (1:4) propoprtion R/O SQM
17 Inside Single coat Smooth Plaster
Providing and applying 12mm thk. Smooth cement plaster in CM 1:4 (1:Cement and
4:Coarse sand) to walls, beams, column, drain, bends, moulds, making grooves, pattas on
all brick and RCC surfaces including raking joints, scaffolding, curing finishing smooth ,
above plinth to all level above plinth. The plaster shall be rubbed with "Iron Plate' till the 176.47 350 SQM 61763.03
surface shows cement paste in line level including scaffolding ,curing etc., complete as
directed by Engineer IN charge. and the RCC surface shall be chipped etc.
18 Outside Double coat Sand faced Plaster OR Mala Plaster
Providing and applying 20 mm th. double coat sandfaced or mala cement plaster on any
surface, consisting of 12 mm thick backing coat in CM 1:3 with water proofing compound
(1:Cement and 3:Coarse sand) & 8 mm thick finishing coat in CM 1:1 with water proofing
compound (Q 200ml /bag as dosage)(1:Cement and 1:Coarse sand) to walls, beams,
column, drain, bends, moulds, making grooves, pattas and all brick and RCC surfaces
including raking joints, scaffolding, curing finishing.The plaster surface shall have rough 232.95 385 SQM 89687.67
finish by using sponge on all types of surfaces in line level and including all scaffolding
and curing & level at all level above plinth and upto ground floor level complete as
directed by Engineer IN charge
19 REINFORCEMENT STEEL FE 500
Providing & Supplying & fixing in position High yield deformed bar Reinforcement
confirming to IS – 1139 or cold Twisted bars, TOR steel / TMT / or Equivalent
Reinforcement bars confirming to IS – 1786 for RCC construction including transporting
(i.e. loading & unloading) the steel from store/issue points to site of works including
unloading from Trucks/Trailers, cleaning, de coiling, cutting, bending to required shape 1.27 79000 MT 100492.03
and lengths as per detailed drawing, binding with 16 SWG black soft annealed binding
wire, placing with proper cover block, support chairs, overlap, spacers, etc. complete in
all respect as directed by Engineer IN charge in above plinth to upto GF slab level.
20 SHUTTERING
Providing and erecting in position form work with steel props, shuttering and boxing
using plate shuttering materials of approved quality for all type of concrete elements
vertical, horizontal or inclined including scaffolding, stagging, fasteners,locking ,Ties at
respective levels necessary nails, wires, locking pins,Guggus etc keeping in position till 85.77 450 SQM 38596.95
concrete is laid and members have acquired required strength, removal thereafter,
applying shuttering oil etc. complete as directed by Engineer-in-Charge.
21 PAINTING WORK (FROM INSIDE)
Providing and applying Two coats of Acrylic distemper [ Water base ]of approved brand
& make , with one two coats of Brila putti--Or J k Putti over the distemper of approved
shade of color on wall and all other surfaces to give an even and smooth painted surface
over and including a priming coat after thoroughly cleaning the walls by water,
scaffolding and brushing to remove all dirt and remains of loose materials, mortar 176.47 195 SQM 34410.83
droppings & other foreign matter and preparing the surface even and sand papered
smooth complete, up to all level above plinth complete as directed by Engineer In
Charge.(INNER SIDE)
22 PAINTING WORK (FROM OUTSIDE)
Providing and applying two or more coats, of "Apex weather proof exterior emulsion
paint" (Asian paint make) of approved shade to give good and even shade over plaster,
brick / concrete surfaces at all levels as per instructions of the engineers-in-charge 232.95 195 SQM 45426.23
including scaffolding, cleaning, washing the surface etc. complete at all levels.
23 Alluminum Windows & Ventilation -
Providing, febricating and fixing in position aluminum windows and ventilator
using :Jindal / BANCO " make aluminum sections with approved colour anodizing ( 15
microns ). Supplying and fixing 5mm thick plane glass.. SAINT GOBAIN /MODIGAURD
/ASAHI including sealing the gap between frame & plaster with SILICON SELEANT of -
approved make , all fixtures and fastening, fittings such as hinges, handles, tower bolts
(concealed) etc. all as per drawing / manufacturing specification & direction of Engineer
in charge.
a DO above but for Two track -(two glass shutter windows using following sections :) 12.600 4000.00 SQM 50,400.00
Bottom frame - 61.2X31X 1.5mm thick @ 0.905 Kg/m. -
Top & side frame -61.2X31X 1.5 mm thick @ 0.781 Kg/m. -
Shutter top and bottom frame - 40.00 x 18.5 x 1.5 thick @ 0.530 Kg/m. -
Shutter Handle side vertical frame - 40.00 x 18.5 x 1.5mm @ 0.530 Kg/m -
Shutter interloking frame - 40.00 x 18.5 x 1.5mm thick @ 0.629 Kg/m. -
24 ROLLING SHUTTER
Providing and fixing in position interlocking Rolling Shutters of approved make of 18
gauge, 75mm wide, cold rolled, MS lathe interlocked including top cover, spring, axles,
a guide rails, tees, iron pulleys, bearings, handles, holding down bolts embedded in C.C. 132.00 0 SQM 0.00
(1:2:4) including two coats of synthetic enamel paint over a coat of primer etc. complete
as directed.
TOTAL AMOUNT FOR CIVIL WORK AS PER FINALAZATION 3174811.03
383.59
TOTAL AMOUNT FOR CIVIL WORK ( ROUND OFF) AS PER FINALAZATION 3173000.00
25 STRUCTURAL STEEL WORK WITH SHEETS
Providing and labour charges for straightening, cutting, cleaning, fabricating, erecting,
placing in position and connecting M.S. Str.l work fabricated from rolled steel sections,
plates, angles, channels, rounds, flats, RHS etc. in roof trusses, Column, beams, gantry
girders, bracings,catwalk for false ceiling, platforms, pipe trestles, stairs, monorails,
a cleats, protection angles, brackets, hangers, purlins, tie runners, sag rods with 19.00 105000 MT 1995000.00
threading, triangular frames for louvers, cable trays, rain water & other utilities pipe
supports, ladders with or without cage, canopy, etc. including transport, loading and
unloading as and when required, cutting, wastage, welding with welding rods (shop &
site) bolting, wherever necessary including cleaning etc. complete.
26 PAINTING FOR STRUCTURAL STEEL
Painting with one coat of red oxide premier before erection and two coats of synthatic
enamel paint of approved shade after erection to Fabricated structure in position various 19.00 8000 MT 152000.00
insert like edge angels channels ,plates etc complete.
27 POLYCARBONATE SHEET
Providing and Fixing in polycarbonate sheet of 1.5m thick in precoated sheet roofing for
1150 SQM 0.00
lighting etc.including necessary scaffolding ,fixtures and as directed.
28 TURBO VENTILATOR
Providing and fixing turbo ventilators on roof with necessary fixtures to avoid leakage
along with all safety measures etc. complete as per drawing, specification and instructed 8.00 8000 NOS 64000.00
by Engineer In-charge.
29 DOWN TAKE PIPE..110 mm dia
Providing and fixing in positional PVC Rain Water Pipe of Prince or Supreme
Manufacture,jointing with suitable adhensive as per manufacturer specification with all 96.00 700 RMT 67200.00
special likes bends ,shoes,M.S. Clamps etc. complete.
TOTAL COST FOR STRUCTURAL STEEL WORK 2278200
TOTAL AMOUNT FOR CIVIL WORK ( ROUND OFF) AS PER FINALAZATION 3173000
TOTAL AMOUNT CIVIL AND STRUCTURAL WORK 5453011