Silo - Tips - A Critical Analysis of Ponte Della Costituzione Venice
Silo - Tips - A Critical Analysis of Ponte Della Costituzione Venice
Abstract: Santiago Calatrava’s Ponte della Costituzione is a steel arched pedestrian bridge built in 2007,
crossing over the Grand Canal in Venice. This paper aims to provide a critical analysis of this modern bridge
built in such a historical City. It will look in detail into the design, aesthetics and construction as well as
including simple calculations to assess how the structure behaves under different loading conditions. The
geology and durability will also be analysed and possible future changes looked at.
Keywords: Ponte della Costituzione, Calatrava, Steel Arch, Pedestrian Bridge, Grand Canal
Figure 6: Elevation
1
Kathryn R. Heath – [email protected]
4 Aesthetics nor does it stand out as the dark red of the steelwork is
The majority of people who visit this bridge think it overshadowed by the deck above.
is a beautiful structure, however there are some who do
not agree, which demonstrates that aesthetics are
subjective. Fritz Leonhardt, a prominent bridge
engineer, gives 10 concepts that should be considered
during bridge design. This paper will look at some of
these concepts in order to better analyse the aesthetics.
The arched form of the bridge demonstrates a clear
structural function, sweeping in a single span from Figure 9: View from embankment
bank to bank, no part of the structure being hidden.
Unlike in the Rialto and Scalzi bridges, the geometry One of the major aesthetic responsibilities for this
of the long span and slenderness at supports may instill bridge is to integrate itself into the environment.
a slight feeling of instability. However the revealed Although it is obviously a modern structure and cannot
steel framework below counteracts this, seen from be mistaken for a traditional Venetian bridge there are
underneath the deck and partly from above through the aspects of the bridge that link it to its surroundings and
glass. The spine-like steel structure shows all the help it to blend in. The Istrian stone used on the deck
structural components and gives a great feeling of and abutments continues as paving on the
stability. embankments of the bridge and surrounding areas. This
stone is a traditional local material that is found
throughout the City. The ‘Venetian Red’ colour of the
structure is reflected in the surrounding red brick
buildings and adds a sense of richness to the bridge. It
also separates the bridge from Calatrava’s other works
where he has always used white for the steelwork.
Perhaps the most extravagant part of the bridge
aesthetically is the bronze handrails that run on top of
Figure 7: Revealed steel structure the glass parapets. These chunky bronze rails give the
feeling of expense and make the bridge seem more of a
Calatrava has designed the proportions of the bridge sculpture. At the ends of the rails where they meet the
so well that it almost looks as though it is floating. The abutments there are engraved connection details. This
glass parapets and dark red structure make the light seems to be Calatrava’s subtle stamp on the bridge as
Istrian stone of the deck really stand out from a the detail is of the crest of the Knights of Calatrava.
distance, making the bridge appear to be an elegant
strip of white stone. This gives the impression the deck
is even more slender than it already is. The lighting
effect at night also adds to this impression as a thin
strip of LEDs run along the base of the glass parapet
forming a line of light. The proportions of the bridge
can also be appreciated when walking over it. The
gradient of the slope means that pedestrians cannot see
what is on the other side and the widening of the deck
in the center opens out to allow people to stop and look
at the surroundings. Figure 10: Crest detail on handrail
1
Kathryn R. Heath – [email protected]
4 Loading 4.3 Live Loading
The bridge is designed for pedestrian loads only. For pedestrian bridges over 36m a factor, k can be
The following section will provide a brief overview of used to estimate the live load.
possible loading conditions in order to better
understand the structure. The assessment was carried k = nominal HA UDL x 10
out using DMRB Part 3 BD21/01 with methods of L+270
analysis taken from BS5400: Part 1. Since BD21/01 is Where,
for short span bridges, it ignores the effects of wind,
temperature and secondary loadings, where these are
looked at BS5400 has been followed.
This gives a value of 0.375 for k and a live load of
4.1 Assessment Loads 1.79kN/m2. This is a very low load for such a crowded
The assessment load (QA) can be found from the bridge and so a load of 4kN/m2 will be assumed. This
following equation: gives a total factored live load of 6kN/m2.
Loading γfl
Dead 1.05
Superimposed Dead
-Surfacing 1.75
-Parapets 1.20
Live 1.5
For loading conditions it will be assumed that the Figure 11: Parapet Loading
bridge has a uniform width.
The assessment load effects (SA) uses a further (Factored load = 11.34kNm)
safety factor (γf3) to take into account possible
inaccurate assessment. In this particular case it could Due to the stepped nature of the bridge it is not
compensate for inaccuracies in dimensions and steel accessible by cars and so no secondary live loads will
section properties, as many will be assumed. be taken into account.
1
Kathryn R. Heath – [email protected]
Vd = Sg Vs best aesthetic effect. The final shape was decided upon
after extensive Finite Element modeling to understand
The site hourly mean wind speed can be found from better the effects of loading, temperature and seismic
the equation: effects. The structure was also pre-assembled offsite
and static loading tests were carried out.
Vs = Vb Sp Sa Sd
Sg = Sb Tg Sh’
Pt = qA1CD
Pv = qA3CD
1
Kathryn R. Heath – [email protected]
dimensions of the triangle are 1.4m breadth and 0.8m
depth and the I-value is approximately 10.94 x 10-3m4.
5.4 Temperature
The effect of temperature needs to be considered as
it may cause the steel structure to expand or contract,
which will affect the internal stresses.
Figure 16: Case 2 - worst loading case The difference in temperatures between the bridge
deck and the steel structure should not cause any
problems, as they are not structurally reliant on each
other.
The temperature can range from –25oC to +40oC in
Venice. As this is a pedestrian bridge and has an
assumed design life of 1 in 50 years we can add +/-2 oC
to these values. This gives a temperature difference of
61oC. Using a coefficient of expansion (α) of 12x10-6
for steel the following equation can be used to find the
possible change in length (e) for the central triangular
girder:
1
Kathryn R. Heath – [email protected]
an overestimate as when considering the cross section 6 Geology and Foundations
of the deck the secondary arch was not taken into The Island of Venice is situated in an enclosed
consideration. This secondary arch would reduce the lagoon and as such has great difficulties with
overall bending stress and so the effects of temperature increasing water levels and settlements of structures.
may not be problematic.
1
Kathryn R. Heath – [email protected]
an arch. This would mean high bending stresses being 6 Construction
generated which it is not designed to cope with. One of the most important considerations in the
The solution to this problem was to set up a erection of the bridge was the possible disruption
permanent jacking system in the bridge and a caused on site. In such a busy area with lots of traffic
permanent monitoring system, which continuously on the Canal, any prolonged construction works could
measures the displacements of the foundations. If a cause huge problems. In order to cause the least impact
displacement of over 20mm is recorded on both sides possible the steelwork was prefabricated offsite and the
of the canal then the hydraulic jacks will be used to erection of the bridge took place over a few days with
bring the bridge back to its original shape. The jacks the Canal traffic being stopped for only two nights.
are installed permanently in the bridge between the The first step in construction which took place in
abutment and steel structure, which is extended into the January 2007 was preparing the foundations. This
abutment. When needed it pushes the extended steel included strengthening the ground due to poor soil
out so that the shape of the arch is restored. conditions. The piles were then driven into the ground
and substantial reinforcement assembled before
pouring the concrete. Once the abutments were finally
constructed the steel structure could be brought onto
site.
The arch was prefabricated in three parts, these
Figure 20: Horizontal displacement of foundations consisted of two side sections and a central span. All
the steel was fabricated at a site on the edge of the
lagoon so that it could be easily transported by barge.
1
Kathryn R. Heath – [email protected]
around 60m long and around 270tonnes. Transporting arch was loaded with its worst case loading condition -
it along the Canal took a long time, as it had to asymmetrical loading to test for deflections.
navigate its way carefully around the bends.
Once on site the barge had to perform a careful Figure 27: Load testing on assembled structure
rotation so that the section was placed in the right
direction. Due to the limited width of the Canal, it had The last stage in construction included the paving of
to be transported the wrong way round to navigate the the deck and installation of the parapets, handrails and
corners. Finally in the correct position, the hydraulic LED lighting. Finally, after almost a year since the
jacks lifted the structure until it was above the two side first sections were installed, the bridge was opened to
segments before lowering it into place. The sections the public.
were then quickly welded together. Once welded the
temporary supports could be removed as the bridge
7 Durability and Vandalism
was self-supporting.
Without end restraints the central section would be Durability is of great importance to this structure as
subject to very high bending stresses as it would it was built to be a landmark bridge which will
behave as a beam rather than an arch. The section was hopefully remain standing for many years to come, as
not designed to cope with these high stresses and the the Rialto, Accademia and Scalzi bridges have.
solution to this problem was to use tensioning cables An area of concern for this bridge in particular is the
along the length of the arch. corrosive properties of salt water on the steel structure.
Although none of the steel is in constant contact with
the water there will be some splashing and perhaps
flooding throughout its lifetime. It is assumed that a
suitable coating will have been used to protect against
this happening and will be easily reapplied if needed.
As all the steel work is exposed and the decking is
laid directly on top, it is not expected that there will be
any problems with maintenance as all parts of the
bridge seem to be easily accessible. If the bridge did
have to be closed for a period of time it would not be
catastrophic as the Scalzi bridge provides an alternative
crossing point and is not far away.
Vandalism does not seem to have been an issue for
the bridge so far. In an area which is almost always
crowded it is unlikely that any vandalism would be
carried out.
8 Future Changes
Figure 26: Tensioning cables
One of the great subjects of controversy
surrounding this bridge when it was first built was its
Three cables were used in total and were tensioned lack of disabled access. On the one hand, was the
all the way through construction until all the segments design and vision of the bridge more important than
had been welded together, at which point they were de- making it accessible for everyone? Or on the other
tensioned. The assembly of the steel structure took two hand, as Venice has over 400 stepped bridges that
days in total, causing minimum disruption to the local don’t provide for disabled users why should this one be
canal traffic. any different? Calatrava says that he provided designs
with access but the Council of Venice preferred this
The next stage before adding the decking was to do one and ultimately the final decision was up to them.
load testing to confirm the strength of the arch. The However, due to the number of complaints received the
1
Kathryn R. Heath – [email protected]
council decided they should incorporate a lift into the
design. This was meant to be implemented soon after
the opening of the bridge but does not seem to have
been carried out yet. Figure [28] shows the final
design, which should soon be in use. It consists of an
eggshaped capsule that rises from the banking onto the
side of the bridge, attaching itself to a set of rails which
will be incorporated into the framework.
References
[1] Zordan., T, Briseghella, B., Siviero, E., 2010. The
Fourth Bridge over the Grand Canal in Venice,
from idea to analysis and construction, Structural
Engineering International 1/2010
Figure 28: Egg-shaped capsule
[2] Tzonis, A., Caso Donadei, R., 2005 Calatrava
Bridges Thames and Hudson
10 Conclusion [3] BS5400-2:2006 Steel, Concrete and Composite
Throughout this paper the aesthetics, design and Bridges-Part 2: Specification for loads BSI
other important aspects of this bridge have been looked [4] Part 3 BD21/01 The Assessment of Highway
at and analysed. To arrive at the final design this Bridges and Structures DMRB
bridge had to overcome several hurdles including weak [5] Chajes, M., 2002. Load Rating of Arch Bridges
ground conditions, delays in construction and University of Delaware
escalating costs. [6] Citta di Venizia The works for assembling the
As shown in the analysis, there may be ways in fourth Bridge on the Grand Canal 2008
which the design could have been made more efficient www.commune.venizia.it
however it does provide a solution to the large [7] Romaro, G., Romaro, C., Ziero, L., 2007 The New
horizontal thrusts generated which have caused Footbridge in Venice technical presentation SAIE
problems in so many other Venetian bridge designs in 2007 exhibition
the past. It has also proven through extensive testing [8] Wright, H 2008. Calatrava Bridge Venice
that the structure works efficiently under the worst Blueprint Magazine Issue 271
loading cases and so really there is no reason to change [9] My Forecast, 2010. Almanac: Historical
the design and compromise on aesthetics. Information www.myforecast.com
What ultimately defines this bridge are its
surroundings and location in such a historical City,
which seems to have dictated almost every design
decision, from the arched shape to the paving on the
deck.
In conclusion, this elegant structure described by
Calatrava as a ‘carpet of light’ and the ‘most beautiful
bridge he has every created’ aims to provide a balance
between the old and the new and does so very
successfully. It is a shame that the controversy
surrounding its implementation has overshadowed its
overall design and that it has not received more
recognition. Hopefully over time the locals will come
to appreciate the design more and it will become
globally recognized as a landmark feature of Venice.
1
Kathryn R. Heath – [email protected]