Clinker Silo MOS (2)
Clinker Silo MOS (2)
Method of Statement
Farakka Line-II Expansion Project
Introduction:
The Farakka project involves the erection of a clinker silo roof with a total weight of 220
tons. The roof structure will be assembled at ground level, comprising 18 rafters, 90 tie
beams, 120 bracing, and 287 purlins. The primary purpose of this assembly method is
to minimize erection time and significantly reduce the risk associated with working at
heights.
This innovative approach to major erection will be implemented for the first time in
ACC, Ambuja, and Adani projects (AAA)
Below is the figure showing structural overview of Clinker silo and top roof girder.
Figure 1: Structural overview: Clinker silo top roof girder and radial girders
Site assembly Plan: As per site assessment all the structures will be assemble in ground
level as per convenience. We have identified the location for rafter assembly and crane
movement as per below sketch.
Installation of Structure:
Erection weights are below:
Design Consideration: Designing and assembling a clinker silo roof at ground level before
erecting it at a height of +32.40 M involves several critical considerations to ensure
safety, structural integrity, and efficiency. Here are the key factors to keep in mind:
By considering above factors, we can ensure a successful and safe assembly and
erection of the clinker silo roof at the specified height.
Roof erection:
As per below sketch, dome structure (159 T) will be placed on RCC wall in single lift by
600 Ton crane with the combination of 54 M (Main boom) and 30 M (Luffing Boom) at
32.40 M level.
1. Dome erection:
As per above sketch, 18 no rafter (160 T) will be assembled at the ground level with ring
platform and erected. It will be placed on 18 no base plate arranged at silo RCC wall at
32.40 m level, which will be locked at 4 fixed bearing from all the direction. After this
placement, balance tie and bracing will be fixed.
2. Equipment erection:
After placing the dome, the bag filter, fan and BC03 head drive will be erected upon ring
platform @44.00 m level.
Counterweight
Crane Counterweight - 160MT and Super lift counterweight - 250MT
3. Penthouse erection:
As per below sketch, Penthouse assemble at ground level to minimize the WAH hazards,
It weight 50 Ton will be placed on ring beam by 600 Ton crane with the combination of
54 M (Main boom) and 30 M (Luffing Boom) at 44.00 m level after completion of all rafter
and bracing.