BUILDING TECHNOLOGY 4 ESTIMATES SAMPLES
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
164 views26 pages

BT 4 Estimates SAMPLES

BUILDING TECHNOLOGY 4 ESTIMATES SAMPLES
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 26

NAME: LUCAGBO, JULIE MAE D.

REVELO, JHUNBIE CLAIRE P. 12/17/24


BT ESTIMATES:

FOOTING:
VOLUME OF FOOTING 1= (0.80m) (0.80m) (0.20m) = 0.128 cu. m
FOR 12 FOOTINGS= 12 (0.128 cu. m) = 1.536 cu. m USING CLASS A
MIXTURE; 40 kg
NUMBER OF BAGS OF 40 kg CEMENT= 1.536 cu. m (9.0) = 13.824 or 14 bags

VOLUME OF SAND= 1.536 cu, m (0.50) = 0.768 cu. m or 28.4 or 23 bags


VOLUME OF GRAVEL= 1.536 cu. m (1.0) = 1.536 cu. m or 56.8 or 57 bags

COLUMN:
TOTAL HEIGHT IF COLUMN 1= 5.80m + 0.10m + 0.37m + 1.00m= 7.27 m
VOLUME OF COLUMN 1= (0.20 m) (0.20 m) (7.27 m) = 0.2G08 cu. m
FOR 10 COLUMNS= 10 (0.2908 cu. m) = 2.G08 cu. m
NUMBER OF BAGS OF 40 kg CEMENT= 2.908 cu. m (9.0) = 26.17 or 27 bags VOLUME OF
SAND= 2.908 cu. m (0.50) = 1.454 cu. m or 53.85 or 54 bags VOLUME OF GRAVEL= 2.908 cu.
m (1.0) = 2.G08 cu. m or 107.7 or 108 bags

TO SUMMARIZE:
NUMBER OF BAGS OF 40 kg CEMENT 14 + 27= 41 Bags
VOLUME OF SAND= 0.768 cu. m + 1.454 cu. m= 32.222 cu. m
VOLUME OF GRAVEL= 1.536 cu. m+ 2.908 cu. m = 4.444 cu. m

COMPUTE THE COST:


1 BAG OF CEMENT Php 220- Php 250 41 Bags x Php 250= Php 10,250.00
SAND PER CUBIC METER Php 800 2.222 cu. m x Php 800= Php 1,777.60
GRAVEL PER CUBIC METER Php 1,200 4.444 cu. m x PHP 1,200= Php 5.332.80
MASONRY
Hollow core/cell; 4 Hollow Cells= 0.003 m³/ CHB
Volume of 1 cell= 0.00075 m³

VOLUME OF MORTAR LAYERING: (For 4” thk. CHB) = 0.0125m (0.10m)(0.40m) = 0.0005m³

WALL HEIGHT= 3.90 m; WIDTH= 1.40 m - (0.20 x 2)= 1.00. Therefore 3.90 x 1.00= 3.90 m² (wall area)
NUMBER OF CHB= 3.90 m²/ 0.08 m²= 48.75 pcs or 49 pcs of 4” thk. CHB

MORTAR FOR BLOCK LAYERING= LAYER + FILL= 0.02 + 0.147= 0.167 m³


LAYER= (1.00) (0.10) x 0.0125 m x (15 + 1) = 0.02 m³
FILL= 0.003 m³ (49 pcs of CHB)= 0.147 m³

HORIZONTAL= 1.00/ 0.40= 2.5 pcs VERTICAL= 3.90/ 0.20= 19.5 pcs

MORTAR FOR PLASTERING= (1.00 x 3.90) (1 side) (0.016 m)= 0.0624 m³


VOLUME OF WALL FOOTING= (2.20) (0.20) (0.50)= 0.22 m³
MORTAR= Plastering + block layering = 0.167 + 0.0624= 0.2294 m³

Number of CHB= 49 pcs


Mortar for Block Layering= 0.167 m³
Mortar for Plastering= 0.0624 m³
Volume of Wall Footing= 0.22 m³

Number of 40 kg cement for mortar= 0.2294 (18)= 4.1292 or 5 bags


Volume of sand= 0.22974 (0.5)= 0.1147 m³ or 4.25 or 5 bags
Volume of Gravel= 0.22974 (1)= 0.22974 m³ or 8.49 or 9 bags

FOR WALL FOOTING:


Number of 40 kg cement= 0.22 (9)= 1.98 or 2 bags
Volume of Sand= 0.22 (0.5)= 0.11 m³ or 4.07 or 4 bags
Volume of Gravel= 0.22 (1)= 0.22 m³ or 8.14 or 9 bags

MASONRY REINFORCEMENT
Vertical Bars= 1.65 (width)/ 0.80 m (horizontal spacing)= 2.06 spacing= 2 +1 bar (both ends)
Vertical Bars= 2.80 (height)/ 0.60 m (vertical spacing)= 4.67 spacing= 5 +1 bar (both ends)
Dowel Bars= 0.20 m (exposed) + 0.10m(unexposed)
1 Dowel= 0.30m No. of Dowels= 16 pcs; Dowel Length= 6.00m

For Continuous Mat Bar:= (1.65 + 0.10) (2) (3)= 5.55 m


For Cut Bars= (0.40 m - 0.075 (2) + (0)) ((2.00/ 0.40) + 1)= (0.25) (6)= 1.50m; 1.50m + 5.55m= 7.05m

Vertical Bars= 3 bars (2.80)= 8.40m; Horizontal Bars= 6 bars (1.65)= 9.90m
Dowel Bars= 6.00m WF Bars= 7.05 m Total Bar Length= 31.35m
NOTE: Use 7.50m commercial bar length (less wastage)
No. of 10mm dia bar= 31.35/ 7.50= 4.18 or 5 pcs
TIE WIRES
For every intersection= 6 x 3= 18 intersections; For every dowel splicing= 16 (dowels)
For mat bars intersection= 3 (continuous bars) x 6 (cut bars)= 18 intersections
Total tying points= 18 x 16 x 18= 52 tying points
Total Tie Wires needed: 52 x 0.30= 15.6/ 53 m/kl= 0.29 kls. of tie wires

MASONRY:Summary
Number of CHB= 49 pcs
Mortar for Block Layering= 0.167 m³
Mortar for Plastering= 0.0624 m³
Volume of Wall Footing= 0.22 m³

Number of 40 kg cement for mortar= 0.2294 (18)= 4.1292 or 5 bags


Volume of sand= 0.22974 (0.5)= 0.1147 m³ or 4.25 or 5 bags

FOR WALL FOOTING:


Number of 40 kg cement= 0.22 (9)= 1.98 or 2 bags
Volume of Sand= 0.22 (0.5)= 0.11 m³ or 4.07 or 4 bags
Volume of Gravel= 0.22 (1)= 0.22 m³ or 8.14 or 9 bags

No. of 10mm dia bar= 5 pcs


Tie Wire (kgs)= 0.29 kls. Or ⅓ kilo

CONCRETE & STEEL REINFORCEMENT

A. FOOTING:
LENGTH WIDTH DEPTH CONCRETE SET MATBAR
COVER
F1 800 mm 800 mm 30mm 750mm 12 sets 12mm
BOTHWAYS

CONCRETE VOLUME= L x W x D

= (0.80) (0.80) (0.30)

= 0.192 cu. m

= 0.192 cu. m (12 sets)

= 2.304 cu. m

CUT LENGTH= W/L – (Concrete cover) (2) + (hook) (2)

= 0.80 – (0.75) (2) + (0.125) (2)

= 0.9 m

No. of mat pcs = 12 sets (5) (2 both ways)

= 120 pcs of 0.90m No. of cut


length per DRB= 6.00 / 0.90
= 6.67 or 6 pcs
WASTAGE= (excess %) ( cut length )
= ( .67) (0.90 m) = 0.603 or 2,60 per DRB

No. cut length pre DRB= 7.50/0/090 = 8.33 M

WASTAGE= (excess %) (cut length)

= (.33) (0.90)= 0.297 or 0.30 per DRB

F1 CUT LENGTH (CL): 12 PCS @ 0.90M

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(16mm) (m)
6.00 0.90 6.67 6.00 0.60
7.50 8.33 8.00 0.30

NO. OF PCS @ 12mm DIAMETER x 7.50 DRB= 120 pcs / 8pcs

= 15 pcs of DRB WEIGTH @


12mm DIAMETER x 7.50 DRB= 15 pcs (7.50) (0.888 kg/m)
= 99.9 kgs

TIRE WIRES

= 5 (horizontal) x 5 (vertical)

= 25 intersections

= 12 sets x 25 intersections

= 300 intersections
= 300 tying points x 0.30m

= 90 / 53 m/kl

= 1.698 kg or 1.7 kg of tire wire

SUMMARY:

FOOTING 1 (F-1): @ 12 SETS

Quantity of bar @ 12mm x 7.50 DRB = 15 pcs or 99.9 kgs Quantity


of tire wires = 1.7 kg or 1 ¾ kg
B. COLUMN
C1 @ 7.27m

MAIN VERTICAL BAR CUT LENGTH

VBCL= (7.27M) (-0.075) (concrete cover footing) – (0.012m) (DB) (2) – (0.40) (concrete cover column) +
(0.20) (hook)

VBCL= 7.195 – 0.024 – 0.40 + 0.20

= 6.971 OR 7M
@ 10 sets of C1 @ 7.27 height No. of
VBCL pcs= (10 sets) (4pcs)
= 40pcs of 7.27m

C1 VERTICAL BAR CUT LENGTH (CL)= 40PCS @7.27M

No. of CL per DRB= 7.50 / 7.27

= 1.03

WASTAGE= (excess %) (cut length)

= (0.03) (7.27)

= 0.2181 or 0.22m

No. of pcs @ 12mm diameter x 7.50 DRB= 40 pcs (CL) / 1pc

= 40 pcs of DRB

WEIGTH @ 12mm DIAMETER x 7.50 DRB= 40 (7.50) (0.888 KG/M)

= 239.75 kgs

C1 LATEREAL TIES CUT LENGTH (LTCL)

A (side) 200 – (2) (40) = 120mm or 0.120mm

B (side) 200 – (2) (40) = 120mm or 0.120mm

LTCL= 2 (A (side)) + 2 (B (side)) + 2 (hooks)

= 2(0.120m) + 2 (0.120m) + 2 (0.10m)

= 0.68m
C1 effective Heigth @ GF:

= (3.90M) – (0.075) – (0.012 (2)) – 0.25

= 3.825 – 0.024 – 0.25

= 3.551 M
C1 EFFECTIVE HEIGTH @ 2F= (3.17) – (0.04M) – (0.00M)

= 3.13M

C1 MID-HEIGTH @ DF:

= (3.551M) – (4 (0.05M)) (2) – 6 (0.10) (2)

= 3.551M – 0.4 -1.2

= 1.951 or 2.00m

C1 MID-HEIGTH @ GF LATERAL TIE QUANTITY = 2.00M / 0.20M

= 10PCS

C1 MID-HEIGTH @ 2F = (3.13M) – (4 (0.05)) (2)

= 2.73M

C1 MID-HEIGTH @ 2F LATERAL TIE QUANTITY = 3.17 / 0.15

= 21.13 OR 21 PCS

QUANTITY LATERAL TIES /COLUMN @ GF:

= 1+4+6+10+6+4+1+3

= 35 PCS

QUANTITY LATERAL TIES/ COLUMN @ 2F= 1+4+10+4+1

= 20PCS

10 SETS OF C1 @ 7.27 M HEIGTH

No. of lateral ties (pcs) = (35pcs) + (20pcs) (10 sets)

= 550 pcs of 0.68 m

C1 lateral tie CL: 550 pcs @ 0/68m No. of


CL per DRB = 6.00 / 0.68M
= 8.82 PCS OR 8 PCS
WASTAGE: = (0.03) (0.68M) = 0.02 M

C1 VERTICAL BAR CUT LENGTH (CL): 550 PCS @ 0.68M

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 0.68 8.82 8.00 0.56
7.50 11.03 11.00 0.02

NO. OF PCS @ 12MM DIAMETER x 7.50M PER DRB= 550PCS /11 PCS

= 50 PCS OF DRB

WEIGHT OF 12MM DIAMETER x 7.50M = (50PCS) (7.50) (0.888 KG/M)

= 333 KGS

TIE WIRES:

For every intersection

= 4 (vertical bar) x 55 (lateral ties) = 220 (intersections)

Add: 3 tie points @ hook / vertical bar

= 4 (vertical bar) x 3 (ties points) = 220 + 12

= 232 intersections For


column 1 (c1) sets:
= 10 sets (232 intersections) = 2,320 intersections

TOTAL THE WIRES NEEDED:

= 2,320 (tying points) x 0.30 m

= 696 / 53 m/kl

= 13.13 kgs of tie wires

C1 SUMMARY: @ 10 SETS

Quantity of vertical bar @ 12mm diameter x 7.50 m DRB

= 40 PCS OR 239.75 KGS

Quantity of lateral ties @ 12 mm diameter 7.50m DRB

= 50 PCS OR 333 KGS

Quantity of tie wire

= 13.13 kgs or 13 kgs


C. BEAM
B1: 4 SETS @ 2.50 m
B1 HORIZONTAL MAIN BAR CUT LENGTH (HMBCL): ((2.50m) - ((2)(0.040m)) + ((2)(0.20m))= 2.82m
4 SETS OF B1 @ 2.50m LENGTH
No. of HMBCL= (4 sets) (4 pcs)= 16 pcs of 2.82m

B1 HORT. BAR CUT LENGTH (CL): 16 pcs. @ 2.82m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/2.82m = 3.18 pcs or 3 pcs
WASTAGE = (0.18) (2.82m)= 0.50
Let’s try 7.50m
No. of CL per DRB. = 7.50m/2.82m = 2.66 pcs or 2 pcs
WASTAGE = (0.66) (2.82m)= 1.86

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 2.82 3.18 3.00 0.50
7.50 2.66 2.00 1.86
No. of PCS. @ 12mmø X 6.00m DRB = 16 pcs/ 3 pcs= 5.33 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 12mmø X 6.00m DRB = (6 pcs) (6.00m) (0.888kg/m)= 31.68 kgs

B1 HORIZONTAL MID BAR CUT LENGTH (HMiBCL):


HMiBCL = ((2.50m) - ((2)(0.040m)) + ((2)(0.175m)) = 2.77m
4 SETS OF B1 @ 2.50m LENGTH
No. of HMiBCL= (4 sets) (2 pcs)= 8pcs of 2.77m

B1 HORT. BAR CUT LENGTH (CL): 8 pcs. @ 2.77m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/2.77m = 2.17 pcs or 2 pcs
WASTAGE = (0.17) (2.77m)= 0.47
Let’s try 7.50m
No. of CL per DRB. = 7.50m/2.77m = 2.71 pcs or 2 pcs
WASTAGE = (0.66) (2.77m)= 1.97m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 2.77 2.17 2.00 0.47
7.50 2.71 2.00 1.97
No. of PCS. @ 10mmø X 6.00m DRB = 8 pcs/ 2 pcs= 4 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (4 pcs) (6.00m) (0.616kg/m)=14.78 kgs
B1 STIRRUPS CUT LENGTH (BSCL):
BSCL = 2(A(side)) + 2(B(side)) + 2(hooks)= 2(0.120m) + 2(0.170m) + 2(0.10m)= 0.78m

B1 EFFECTIVE LENGTH @ 2.50m (CONTINUES BEAM):= (2.50m) - (0.40m) – (0.40m)= 1.40m


B1 EFFECTIVE LENGTH @ 3.50m (CONTINUOUS BEAM):= (3.50m) - (0.40) - (0.40)= 2.70m
B1 MID-LENGTH @ 2.50m (CONTINUES BEAM):= (eff. length @ 2.50m) – (spacing @ left & right support)
= (2.50m) – (2(0.05m))(2) – (3(0.10m))(2)= 0.90m
B1 MID-LENGTH STIRRUP QUANTITY @ 2.50m : =0.90/ 0.15 m= 6 pcs.
B1 MID-LENGTH @ 3.50m (CONTINUOUS BEAM):= (eff. length @ 3.50m) – (spacing @ left & right
support/end)= (3.50m) – (2(0.05m))(2) – (3(0.10m))(2) = 2.70m
B1 MID-LENGTH STIRRUP QUANTITY @ 3.50m : =2.70/ 0.15 m= 18 pcs.

QUANTITY STIRRUPS @ 3.50m (CONTINUES BEAM) : 1 + 2 + 3 + 18 + 3 + 2 + 1= 30 pcs


QUANTITY STIRRUPS @ 2.50m (CONTINUES BEAM) : 1 + 2 + 3 + 6 + 3 + 2 + 1= 18 pcs

4 SETS OF B1 @ 2.50m LENGTH


No. of Beam Stirrups (pcs): ((30 pcs) + (18 pcs)(4 sets)= 102 pcs of 0.78m
B1 STIRRUP CUT LENGTH (CL): 102 pcs. @ 0.78m
Let’s try 6.00m
No. of CL per DRB. =6.00m/ 0.78m = 7.69 pc. or 7 pcs.
WASTAGE = (0.69) (0.78m)= 0.54m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 0.78m = 9.61 pc. or 9 pcs.
WASTAGE = (0.61) (0.78m)= 0.48m

B1 STIRRUP CUT LENGTH (CL): 38 pcs. @ 0.78m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 0.78 7.69 7.00 0.54
7.50 9.61 9.00 0.48
No. of PCS. @ 10mmø X 7.50m DRB = 102 pcs/ 9 pcs= 11.33 pcs or 12 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (12 pcs) (7.50m) (0.616kg/m)=55.44 kgs

TIE WIRES:
For every intersection= 16 (hort. bar) x 102 pcs= 1,632 intersections
ADD: 3 tie pts. @ hook/ vert. Bar: 16 x 3 x 2= 96 intersections; 1,632 + 96= 1,728 intersections
For Footing 1 (F1) sets:= 1 (set) X 1,728 (intersections) =1,728 intersections
Total tie wires needed: 1,728 (tying points) X 0.30m= 518.4/53m / kl= 9.78 kgs. of tie wire

BEAM 1 (B1) SUMMARY: @ 4 SET


QUANTITY OF HORT. BAR @ 12mmø X 6.00m DRB = 16 pcs or 31.68 kgs.
QUANTITY OF MID BAR @ 10mmø X 6.00m DRB = 8 pcs or 14.78 kgs.
QUANTITY OF STIRRUPS @ 10mmø X 7.50m DRB = 102 pcs or 155.44 kgs.
QUANTITY OF Tie wire =9.78 kgs. or 9 ¾ kgs.

D. SLAB
Identify the SLAB perimeter:
SOG EFFECTIVE WIDTH @ (ALONG X-AXIS):= (6.00 - (0.20 + 0.15))= 5.65
SOG EFFECTIVE LENGTH @ (ALONG Y-AXIS):= (5.50- (0.20 + 0.30))= 5.15 m
SOG MAT BAR QUANTITY @ 5.65m (ALONG X-AXIS):= 5.65m/0.60m + 1= 10.42 or 10 pcs
SOG MAT BAR QUANTITY @ 5.15m (ALONG Y-AXIS):= 5.15m/0.60m + 1= 9.58 or 10 pcs
Identify the SOG MAT BAR CUT LENGTH:
Along X: (5.65m + (0.10 +0.075) + (2(0.175))= 6.18m
Along Y: (5.15m + (0.10 +0.075) + (2(0.175))= 5.68m

Summary of SOG MAT BAR CUT LENGTH QUANTITY:


Along X: 10 pcs of 6.18m
Along Y: 10 pcs pf 5.68m

SOG MAT BAR CUT LENGTH (CL): 10 pcs. @ 6.18m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 6.18= 0.97 pc. or 1.00 pc.
WASTAGE = (0) (6.18m)= 0m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 6.18m =1.21 pcs. or 1 pc.
WASTAGE = (0.21) (6.18m)= 1.30m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 6.18 0.97 1.00 0.00
7.50 1.21 1.00 1.30
No. of PCS. @ 10mmø X 6.00m DRB = 10 pcs/ 1 pcs= 10 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (10 pcs) (6.00m) (0.616kg/m)=3.96 kgs

SOG MAT BAR CUT LENGTH (CL): 10 pcs. @ 5.68m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 5.68= 1.05 pc. or 1.00 pc.
WASTAGE = (0.05) (5.68m)= 0.28m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 5.68m =1.32 pcs. or 1 pc.
WASTAGE = (0.32) (5.68m)= 1.82m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 5.68 1.05 1.00 0.28
7.50 1.32 1.00 1.82

No. of PCS. @ 10mmø X 6.00m DRB = 10 pcs/ 1 pcs= 10 pcs of DRB


QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (10 pcs) (6.00m) (0.616kg/m)=3.96 kgs

TIE WIRES:
For every intersection= 10 (x-axis) x 10 (y-axis)= 100 intersections
ADD: 3 tie pts. @ hook/ vert. Bar: (10 +10) x 2 x 2= 80 intersections; 100 + 80= 180 intersections
For Slab on Grade (SOG) sets:= 1 (set) X 180 (intersections) =180 intersections
Total tie wires needed: 180 (tying points) X 0.30m= 54/53m / kl=1.02kgs of tie wires

SLAB ON GRADE (SOG) SUMMARY: @ 1 SET


QUANTITY OF SOG MAT BAR @ 10mmø X 6.00m DRB = 20 pcs or 7.92 kgs.
QUANTITY OF Tie wire = 1.02 kgs or 1 kilo
SLAB: SUSPENDED SLAB
Identify the different SLAB perimeter:
S1(A1) EFFECTIVE WIDTH @ (ALONG X-AXIS): =(2.50-(0.20+0.20))= 2.10m
S1(A1) EFFECTIVE LENGTH@ (ALONG Y-AXIS): =(1.30 - (0.00m + 0.20))= 1.10m

CHECK FOR TYPE OF SLAB: =L/ W= 2.50/ 1.30 = 1.92 < 2 “TWO-WAY SLAB”

Identify the BOT. CONT. BAR CUT LENGTH:


Along X:
= (2.50m ) + (0.10m + 0.10m) + (2(0.175m))= 3.05m
Along Y:
= (1.30m ) + (0.10m + 0.10m) + (2(0.175m))= 1.85

S1(A1) BOT. CONT. BAR QUANTITY @ 2.50m (ALONG X-AXIS): =2.50m/ 0.20 + 1= 13.5 or 14 pcs
S1(A1) BOT. CONT. BAR QUANTITY @ 1.30m (ALONG Y-AXIS):= 1.30m/ 0.20 +1 = 2.50 or 3 pcs

Summary of BOT. CONT. BAR CUT LENGTH QUANTITY:


Along X: = 14 pcs. of 3.05m
Along Y: = 3 pcs. of 1.85m

BOT. CONT. BAR CUT LENGTH (CL): 14 pcs. @ 3.05m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 3.05m= 1.96 pc. or 1.00 pc.
WASTAGE = (0.96) (3.05m)= 2.92m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 3.05m =2.45 pcs or 2 pcs
WASTAGE = (0.45) (3.05m)= 1.37m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 3.05 1.96 1.00 2.92
7.50 2.45 2.00 1.37
No. of PCS. @ 10mmø X 7.50m DRB = 14 pcs/ 2 pcs= 7 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (7 pcs) (7.50m) (0.616kg/m)=32.34 kgs

BOT. CONT. BAR CUT LENGTH (CL): 3 pcs. @ 1.85m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.85m= 3.24 pc. or 3.00 pcs.
WASTAGE = (0.24) (1.85m)= 0.44m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.85m =4.05 pcs or 4 pcs
WASTAGE = (0.05) (1.85m)= 0.09m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.85 3.24 3.00 0.44
7.50 4.05 4.00 0.09
No. of PCS. @ 10mmø X 7.50m DRB = 3 pcs/ 4 pcs= 0.75 pcs or 1 pc of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (1 pc) (7.50m) (0.616kg/m)=4.62 kgs

TIE WIRES:
For every intersection= 14 pcs (x-axis) x 3 pcs (y-axis)= 42 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: 14 + 3 x 2 x 2= 68 intersections; 42 + 68= 110 intersections
For Slab-1 (BCBCL) sets:= 1 (set) X 110 (intersections) =110 intersections
Total tie wires needed: 110 (tying points) X 0.30m= 33/53m / kl= 0.62 kgs. of tie wire

S1 (BOT. CONT. BAR) SUMMARY: @ 1 SET


QUANTITY OF SOG MAT BAR @ 10mmø X 7.50m DRB = 8 pcs or 36.96 kgs.
QUANTITY OF Tie wire = 0.62 kgs. or 1 kgs.

Identify the BENT BAR CUT LENGTH:


Along X: = (2.50m ) + (0.10m + 0.10m) + (2(0.175m)) + 0.07m= 3.12m
Along Y: = (1.30m ) + (0.10m + 0.10m) + (2(0.175m)) + 0.07m= 1.92m

S1(A1) BENT BAR QUANTITY @ 2.50m (ALONG X-AXIS): = 2.50/ 2= 1.25 + 1= 7.25 or 7 pcs
S1(A1) BENT BAR QUANTITY @ 1.30m (ALONG Y-AXIS): = 1.30/ 2= 0.65 + 1= 4.25 pcs or 4 pcs

Summary of BOT. CONT. BAR CUT LENGTH QUANTITY:


Along X: = 7 pcs. of 3.12m
Along Y: = 4 pcs. of 1.92m

BOT. CONT. BAR CUT LENGTH (CL): 7 pcs. @ 3.12m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 3.12m= 1.92 pcs. or 1.00 pc.
WASTAGE = (0.92) (3.12m)= 2.87m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 3.15m =2.40 pcs or 2 pcs
WASTAGE = (0.40) (3.12m)= 1.25m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 3.12 1.92 1.00 2.87
7.50 2.40 2.00 1.25
No. of PCS. @ 10mmø X 7.50m DRB = 7 pcs/ 2 pcs= 3.50 pcs or 4 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (4 pc) (7.50m) (0.616kg/m)=18.48 kgs

BOT. CONT. BAR CUT LENGTH (CL): 4 pcs. @ 1.92m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.92m= 3.13 pcs. Or 3.00 pc.
WASTAGE = (0.13) (1.92m)= 0.24m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.92m =3.90 pcs or 3 pcs
WASTAGE = (0.92) (1.92m)= 1.73m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.92 3.13 3.00 0.24
7.50 3.90 3.00 1.73
No. of PCS. @ 10mmø X 6.00m DRB = 4 pcs/ 3 pcs= 1.33 pc or 1 pc of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (1 pc) (6.00m) (0.616kg/m)=3.70 kgs

TIE WIRES:
For every intersection=7 pcs (x-axis) x 4 pcs (y-axis)= 28 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: (7 + 4) x 2 x 2= 44 intersections; 28 + 44= 72 intersections
For Slab-1 (BCBCL) sets:= 1 (set) X 72 (intersections) =72 intersections
Total tie wires needed: 72(tying points) X 0.30m= 21.6/ 53m / kl= 0.40 kgs. of tie wire

S1 (BENT BAR) SUMMARY: @ 1 SET


QUANTITY OF BENT BAR @ 10mmø X 6.00m DRB = 1 pc or 3.70 kgs.
QUANTITY OF BENT BAR @ 10mmø X 7.50m DRB = 4 pcs or 18.48 kgs.
QUANTITY OF Tie wire = 0.40 kgs. or 1⁄2 kgs.

Identify the TOP STRAIGHT BAR CUT LENGTH:


Along X:
= (2.50m ) + (0.10m + 0.10m) + (2(0.175m))= 3.05m
Along Y:
= (1.30m ) + (0.10m + 0.10m) + (2(0.175m))= 1.85m

S1(A1) TOP ST. BAR QUANTITY @ 2.50m (ALONG X-AXIS):


= 2.50/ 4= 0.625/ 0.20 + 1= 4.13 or 4 pcs x (2 sides)= 8 pcs
S1(A1) TOP ST. BAR QUANTITY @ 1.30m (ALONG Y-AXIS):
= 1.30/ 4= 0.325/ 0.20 + 1= 2.63 or 3 pcs x (2 sides)= 6 pcs

Summary of TOP STRAIGHT BAR CUT LENGTH QUANTITY:


Along X: = 8 pcs. of 3.05m
Along Y: = 4 pcs. of 1.85m

TOP STRAIGHT BAR CUT LENGTH (CL): 8 pcs. @ 3.05m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 3.05m= 1.96 pcs. Or 1.00 pc.
WASTAGE = (0.96) (3.05m)= 2.93m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 3.05m =2.45 pcs or 2 pcs
WASTAGE = (0.45) (3.05m)= 1.37m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 3.05 1.96 1.00 2.93
7.50 2.45 2.00 1.37
No. of PCS. @ 10mmø X 7.50m DRB = 8 pcs/ 2 pcs= 4 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (4 pc) (7.50m) (0.616kg/m)=18.48 kgs

TOP STRAIGHT BAR CUT LENGTH (CL): 6 pcs. @ 1.85m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.85m= 3.24 pcs. or 3.00 pc.
WASTAGE = (0.34) (1.85m)= 0.44m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.85m = 4.05 pcs or 4 pcs
WASTAGE = (0.05) (1.85m)= 0.09m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.85 3.24 3.00 0.44
7.50 4.05 4.00 0.09
No. of PCS. @ 10mmø X 7.50m DRB = 6 pcs/ 4 pcs= 1.50 pcs of 2 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (2 pc) (7.50m) (0.616kg/m)=9.24 kgs

TIE WIRES:
For every intersection=8 pcs (x-axis) x 6 pcs (y-axis)= 48 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: (8 + 6) x 2 x 2= 56 intersections; 56 + 48= 104 intersections
For Slab-1 (TSBCL) sets:= 1 (set) X 104 (intersections) =104 intersections
Total tie wires needed: 104(tying points) X 0.30m= 31.20/ 53m / kl= 0.59 kgs. of tie wire

S1 (TOP STRAIGHT BAR) SUMMARY: @ 1 SET


QUANTITY OF TOP ST. BAR @ 10mmø X 7.50m DRB = 14 pcs or 27.72 kgs.
QUANTITY OF Tie wire = 0.59 kgs. or 1⁄2 kgs.

Identify the TOP CUT BAR CUT LENGTH:


Along X:
= (2.50m /3) + (0.10m ) + (0.175m)=1.11m
Along X:
= (1.30m /3) + (0.10m ) + (0.175m)=0.71m

S1(A1) TOP ST. BAR QUANTITY @ 2.50m (ALONG X-AXIS):


= 2.50/ 2= 1.25/ 0.20= 6.25 or 6 pcs x (2 sides)= 12 pcs
S1(A1) TOP ST. BAR QUANTITY @ 1.30m (ALONG X-AXIS):
= 1.30/ 2= 0.65/ 0.20= 3.25 or 3 pcs x (2 sides)= 6 pcs

Summary of TOP CUT BAR CUT LENGTH QUANTITY:


Along X: = 12 pcs. of 1.11m
Along Y: = 6 pcs. of 0.71m

TOP CUT BAR CUT LENGTH (CL): 12 pcs. @ 1.11m


Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.11m= 5.41 pcs. or 5.00 pcs.
WASTAGE = (0.41) (1.11m)= 0.46m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.11m = 6.76 pcs or 6 pcs
WASTAGE = (0.76) (1.11m)= 0.84m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.11 5.41 5.00 0.46
7.50 6.76 6.00 0.84
No. of PCS. @ 10mmø X 6.00m DRB = 12 pcs/ 5 pcs= 2.40 pcs or 3 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (3 pc) (6.00m) (0.616kg/m)=11.09 kgs
TOP CUT BAR CUT LENGTH (CL): 6 pcs. @ 0.71m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 0.71m= 8.45 pcs. or 8.00 pcs.
WASTAGE = (0.45) (0.71m)= 0.32m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 0.71m = 10.56 pcs or 10 pcs
WASTAGE = (0.56) (0.71m)= 0.40m

LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE


REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 0.71 8.45 8.00 0.32
7.50 10.56 10.00 0.40
No. of PCS. @ 10mmø X 6.00m DRB = 6 pcs/ 8 pcs= 0.75 pcs or 1 pc of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (1 pc) (6.00m) (0.616kg/m)=3.696 kgs

TIE WIRES:
For every intersection=(12 x 8) (2 sides) (x-axis) + (12 x 8) (2 sides)(y-axis)= 144 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: (12 + 6) x 2 (tie pts) x (end) = 36 intersections; 36 + 144= 180 intersections
For Slab-1 (TSBCL) sets:= 1 (set) X 180 (intersections) =180 intersections
Total tie wires needed: 180(tying points) X 0.30m= 54/ 53m / kl= 1.02 kgs. of tie wire

S1 (TOP CUT BAR) SUMMARY: @ 1 SET


QUANTITY OF TOP ST. BAR @ 10mmø X 6.00m DRB = 4 pcs or 14.76 kgs.
QUANTITY OF Tie wire =1.02 kgs. or 1 kgs.

SUSPENDED SLAB 1(AREA 1) (S1) SUMMARY: @ 1 SET


QUANTITY OF BAR @ 10mmø X 6.00m DRB = 5 pcs or 18.46 kgs.
QUANTITY OF BAR @ 10mmø X 7.50m DRB = 26 pcs or 80.16 kgs.
QUANTITY OF Tie wire = 2.63 kgs. or 2 ½ kgs.

E. STAIRS
PLINTH/STAIR FOOTING
Footing Width 0.90 m
Footing Length 1.10m
Footing Height 0.30m
Footing Col. Width 0.25 m
Footing Col. Height 1.00 m
Concrete Cover 0.075 m

For Vert. Rebars @0.10m O.C (across 1.10m length)


- 12.00 pcs per side
- 24.00 pcs
Vert. Rebar Length
- 1.29 m
- 8.13
Therefore use 3 - 12Ø x 10.5m

For Hor't. Rebars @0.20m O.C (across 1.10m length)


- 6.00 pcs per side
- 12.00 pcs
Hor't. Rebar Length
- 1.025 m
- 5.85 pcs
- 2.05
Therefore use 2 - 10Ø x 6m

For Mat Cut Bars @0.10 O.C


- 12.00 pcs
Mat Cut Bar
- 1.09 m
- 5.51 pcs per cut length
- 2.178
Therefore use 2 - 12Ø x 6m

For Long Temp Bars


- 5.00 pcs
Long Temp Bar Length
- 1.09 m
- 5.85 pcs per cut length
- 0.854167
Therefore use 1 - 12Ø x 6m

TOTAL:
Mat Cut bars 2 - 12Ø x 6m
- 10.656 kg
Long Temp bars 1 - 12Ø x 6m
- 5.328 kg
Plinth Vert. bars 3 - 12Ø x 10.5m
- 27.972 kg
Plinth Hor't. Bars 2 - 10Ø x 6m
- 7.392 kg
Note: For 12Ø = 0.888kg/m
For 10Ø = 0.616kg/m

LANDING SLAB
Landing Length 2.2 m
Landing Width 1.1 m
Concrete Cover 0.02 m

For Main Bottom Bars @0.10 O.C


- 12 pcs per
- 36 pcs total for 3 x 1.1m
Length
- 2.126
- 4.233302
- 8.504
Therefore use 9 - 12Ø x 9m

For Hor't. Bottom Bars @0.2 O.C


- 5.5
- 6 pcs
Length (Landing) Length (Floor Level)
- 2.16 1.06
- 3.472222 7.075472
- 1.728 0.848
Therefore use 2 - 10Ø x 7.5m Therefore use 1 - 10Ø x 7.5m

For Main Top Bars @0.10 O.C


- 12 pcs per 1.1m slab
- 36 pcs total for 3 x 1.1m
Length
- 2.126
- 4.233302
- 8.504
Therefore use 9 - 12Ø x 9m

For Hor't. Top Bars @0.2 O.C


- 5.5
- 6 pcs
Length (Landing) Length (Floor Level)
- 2.16 1.06
- 3.472222 7.075472
- 1.728 0.848
Therefore use 2 - 10Ø x 7.5m Therefore use 1 - 10Ø x 7.5m

TOTAL:
Main Bottom bars 9 - 12Ø x 9m
- 71.928 kg
Hor't Bottom bars 3 - 10Ø x 7.5m
- 13.86 kg
Main Top bars 9 - 12Ø x 9m
- 71.928 kg
Hor't Top bars 3 - 10Ø x 7.5m
- 13.86 kg

WAIST SLAB
Waist Length 2.88 m
Stair Width 1.1 m
Concrete Cover 0.02 m

For Main Bottom Bars @0.10 O.C


- 12 pcs
- 24 pcs total (2 flight of stairs)
Length
- 2.88
- 2.083333
- 11.52
Therefore use 12 - 12Ø x 6m

For Hor't. Bottom Temp Bars @0.20 O.C


- 15.4
- 15 pcs
- 30 pcs total (2 flight of stairs)
Length
- 1.06
- 8.490566
- 3.533333
Therefore use 4 - 10Ø x 9m

For Bottom Reinf. Bars (Connecting to Plinth)


- 12 pcs total
Length
- 2.026
- 2.9615
- 4.052
Therefore use 4 - 12Ø x 6m

For Top Bars @0.10 O.C For Hor't. Top Temp Bars @0.20 O.C
- 12 pcs Direct Counting
- 24 pcs total (2 flight of stairs) 17 pcs (1 flight of stairs)
Length 34 pcs total (2 flight of stairs)
2.88 Length
- 2.083333 1.06
- 11.52 7.075472
Therefore use 12 - 12Ø x 6m 4.805333
Therefore use 5 - 10Ø x 7.5m

For Top Reinf. Bars (Connecting to Plinth) For Riser/Tread Cut Bars @0.20 O.C
- 12 pcs total 6.4 pcs per step
Length 48 pcs for 8 steps (1 flight)
- 2.026 96 pcs total
- 2.9615 Length
- 4.052 0.93
Therefore use 4 - 12Ø x 6m 8.064516
11.904
Therefore use 12 - 10Ø x 7.5m

FORMWORKS
A. FOOTINGS

MARK ALONG ALONG Y H REINFORCEME DEPTH TYPE


X NT
mm mm mm SHORT LONG mm
F-1 800 800 300 8-12mmø 8-12mmø 1000 CENTER

F-1 @ 12 Sets= 0.80 x 0.80 x 0.30


Total Area= P x H x Number of sets
P= (a x 2) + (b x 2)
= (0.80 x 2) + (0.8 x 2) + (4 x 0.05)= 3.40m
F-1= 3.4 x 0.30 x 12 sets= 12.24 sqm ← TOTAL AREA
Number of Plywood Needed= 12.24/ (1.2 x 2.4)= 4.25 pcs 50%= 2.125 pcs or 3 pcs

B. COLUMNS
C-1: 0.25 x 0.25 @ 10 sets; C-2: 0.20 x 0.30 @ 2 Sets
hn=3.70; h=3.70m - 3.70/ 3= 2.47m

C-1
P= 2(a + b) + 0.2= 2(0.25 + 0.25) + 0.2= 1.2m
Area= 1.2 x 2.47 x 10 sets= 29.64 sqm

C-2
P= 2(a + b) + 0.2= 2(0.20 + 0.30) + 0.2= 1.2m
Area= 1.2 x 2.47 x 2 sets= 5.928 sqm

TOTAL AREA= 35.568 sqm


Number of Plywood Needed= 35.568/ 2.88= 12.35 pcs x 50%= 6.175 or 6 pcs

BEAM
L= 6 + 6 + 6 + 6 + 5.50 + 5.50 + 5.50= 34.50 sqm; d= 0.3m; b=0.20m; Area= P x L
P= 2(0.30) + 0.20 + 1= 0.90m L=1m
Area= 0.90 x 1= 0.90 sqm/m
Total Area= 34.50 x 0.90 = 31.05 or 31 sqm
Plywood Needed= 31/ 2.88 x 50% = 5.38 or 6 pcs

SLAB: SUSPENDED SLAB


A-1; W= 1.65 m; L= 2.50m
Area= 4.125 sqm
Plywood Needed= 4.125/ 2.88= 1.43 or 2 pcs

A-2; W= 2.60 m; L= 2.50m


Area= 6.50 sqm
Plywood Needed= 6.50/ 2.88= 2.25 or 3 pcs

A-3; W= 1.30 m; L= 2.50m


Area= 3.80 sqm
Plywood Needed= 3.80/ 2.88= 1.32 or 2 pcs

A-4; W= 1.30 m; L= 3.50m


Area= 4.55 sqm
Plywood Needed= 4.55/ 2.88= 1.58 or 2 pcs

A-5; W= 2.60 m; L= 3.50m


Area= 9.10 sqm
Plywood Needed= 9.10/ 2.88= 3.15 or 4 pcs

A-6; W= 1.65 m; L= 3.50m


Area= 5.775 sqm
Plywood Needed= 5.775/ 2.88= 1.99 or 2 pcs

SUMMARY
FOOTING- 3 pcs
COLUMN- 6 pcs
BEAM- 6 pcs
SUSPENDED SLAB- 15 pcs
TOTAL= 30 pcs of 4 ft x 8 ft x ½

SCAFFOLD
Bd. ft.= a x b x l x (pcs) / 12; Number of pcs= Bd. ft. x 12 / a x b x l

A. FOOTING
F-1 (0.80 x 0.80 x 0.30)
4 pcs @ 0.90m, 4 pcs @ 0.80, 12 pcs of 0.20
L-1= 0.90 x 3.28= 2.95 ft. Bd. ft.= 4(2 x 2 x 2.95) / 12= 3.93 bd. ft.
L-2= 0.80 x 3.28= 2.62 ft. Bd. ft.= 4(2 x 2 x 2.62) / 12= 3.50 bd. ft.
L-3= 0.2 x 3.28= 0.67 Bd. ft.= 4(2 x 2 x 0.67) / 12= 2.68 bd. ft.
TOTAL= 10.07 Bd Ft.

Area= 1.26 sqm


Bd Ft.= 10.07 bd. ft.
Constant (m)= 10.07 bd. ft./ 1.26 sqm= 7.99 bd.ft./ sqm
Total Area.= 15.3 sqm
Total Bd. ft.= 7.99 bd.Ft x 15.3 sqm= 122.247 bd. Ft. x 50%= 61.1235 bd.ft.
Number of pcs= 61.1235 x 12/ 2 x 2 x 8= 22.92 pcs or 23 pcs

B. COLUMN
2”x3”x10’
8pcs.-2”x3”x10’ (8pcs x 2” x 3” x 10ft.)/12= 40 bd.ft. TOTAL: 56.71 bd.ft.
6pcs.-2”x3”x0.49’ (6pcs x 2” x 3” x 0.49ft.)/12=1.47 bd.ft.
6pcs.-2”x3”x0.82’ (6pcs x 2” x 3” x 0.82ft.)/12= 2.46 bd.ft.
12pcs.-2”x3”x2.13’ (12pcs x 2” x 3” x 2.13ft.)/12= 12.78 bd.ft.

Total Bd. ft.= 56.71 x 12 x 50%= 340.26 bd.ft.


Number of pcs= 340.26 x 12/ 2” x 3” x 10’= 4083.12/ 60= 68.05 or 68 pcs

C. BEAM
12 Bd. ft./lm L=34.50m
Bd.ft= 12 x 34.50 x 50%= 207 Bd.ft
Number of pcs= 207 x 12/ 2 x 3 x 10= 2484/ 60= 41.4 or 45 pcs
45 pcs of 2” x 3” x 8’ FORM LUMBER

D. SLAB
2 x 3 x 12 FOR VERTICAL SUPPORT
2 x 3 x 8 FOR HORIZONTAL BRACE AND DIAGONAL BRACE

4pcs.-2 x 3 x 12’ FOR VERTICAL SUPPORT


12pcs.-2 x 2 x 8’ FOR HORIZONTAL BRACE
8pcs.-2 x 2 x 8’ FOR DIAGONAL BRACE

VERTICAL SUPPORT= 4 x 12 x 50%= 24 pcs


HORIZONTAL SUPPORT = 12 x 12 x 50%= 72 pcs
DIAGONAL SUPPORT= 8 x 12 x 50%= 48 pcs

L=34.50m 2” x 3” x 10’ VERTICAL SUPPORT 2” x 2” x 8’ HORIZONTAL SUPPORT


Vertical Support= 34.50/ 1= 34.50 or 35 pcs of 2” x 3” x 10’
Horizontal Support= (34.50 x 3)/ 2.4= 43.13 or 44 pcs of 2” x “ 2” x 8’

SUSPENDED SLAB:
W=1.65m L=2.50m
Area= 1.65m x 2.50m= 41.13 sqm
Bd.ft.= 41.13 x 6.1= 250.90 Bd. ft 2” x 3” x 10’
Number of pcs= 250.90 x 12/ 2 x 3 x 10= 50.18 or 51 pcs

EARTHWORKS
A. EXCAVATION
FOOTING
V= L x W x H
L= 0.80 + 0.25 + 0.25= 1.3m W= 0.80 + 0.25 + 0.25= 1.3m H= 1.00 + 0.10= 1.10m
V= 1.30 x 1.30 x 1.10 = 1.859 cu.m
Vtotal= 1.859 x 12 sets= 22.31 cu.m

WALL FOOTING
NOTE: Based on our Foundation Plan
Total Length L= 19.95 m
L=19.95 m W= 0.40m x 0.10 x 0.10= 0.60 H=0.70m
V= 19.95 m x 0.60 x 0.70= 8.379 cu.m
Vtotal= 22.31 cu.m + 8.379cu.m= 30.69 cu.m

B. GRADING AND COMPACTION


FOOTING
Area of F-1= 1.50 x 1.50 x 12 sets= 27 sqm
SLAB ON GRADE
Area SOG= 6.00m x 5.50m= 33 sqm
WALL FOOTING
Area WF-1= 19.95 X 0.60= 11.9 sqm
TOTAL AREA= 27 + 33 + 11.97= 71.97 sqm

C. GRAVEL BEDDING
F-1, V= 1.50 x 1.50 x 0.13 x 12 sets= 3.51 cu.m
Length of Wall Footing @ G. L “A”= 4.35 m
Length of Wall Footing @ G. L “B”= 4.75 m
Length of Wall Footing @ G. L “C”= 4.35 m
Length of Wall Footing @ G. L “1”= 5.20 m
Length of Wall Footing @ G. L “2”= 5.20 m
Length of Wall Footing @ G. L “3”= 5.20 m
Length of Wall Footing @ G. L “4”= 5.20 m
TOTAL LENGTH=34.25m

FOOTING
F-1, V= 1.50 x 1.50 x 0.13 x 12 sets= 3.51 cu.m
WALL FOOTING
WF-1, V= 34.25 x 0.60 x 5.50 x 0.13= 2.6715 cu.m
SLAB ON GRADE
SOG, V= 6.00 x 5.50 x 0.13= 4.29 cu.m
TOTAL VOLUME OF GRAVEL G-1
V= VF-1 + VWF-1+ VSOG= 3.51 + 2.6715+ 4.29= 10.47 cu.m
D. SOIL POSITIONING
Area= 6.00m x 5.50m= 33 sqm

E. BACKFILLING AND COMPACTION


NOTE: Based on our Floorplan; Toilet: 0.225 - (0.10 + 0.10)= 0.025m,Fill with the height of 25mm
All of the area except the carport= 0.25 - (0.10 + 0.10)= 0.05m, Fill with the height of 50mm
Vcut= 3.90 x 4.00 x 0.05= 0.78 cu.m
Vfill= 2.00 x 1.30 x 0.025= 0.065 cu.m
Excess Volume from excavated soil
Vexcess= 0.78 + 15.28= 16.06 cu.m

EXCAVATION: 53 cu.m
BACKFILLING AND COMPACTION 16.91 cu.m
Total Excavated Soil= 53 + 0.065 -16.06= 37.01 cu.m

EARTHWORKS: Summary
● EXCAVATION 53 cu.m
● BACKFILLING AND COMPACTION 16.91 cu.m
● GRADING AND COMPACTION 71.97 sqm
● GRAVEL BEDDING 10.47 cu.m
● SOIL POSITIONING 33 sqm

ROOFING WORKS
A. ROOF FRAMING
Vertical Length of Roof Truss= 8.20 x 3= 24.60 m
Quantity of Bars(pcs)= 24.60m/6.00m= 4.10 or 4 pcs

PURLINS LENGTH= 8.65 x 10 (pcs)= 86.5


Quantity of Bars(pcs)= 86.5/6.00m= 14.42 or 15 pcs

Length of Fascia Frame= (8.65 x 2 (sides)) + (8.20 x 2 (side))= 33.70m


Quantity of Bars(pcs)= 33.7/6.00m= 5.61 or 6 pcs

B. ROOFING MATERIALS
Wave Type Roof- Effective width 1-½ /2 lap= 950mm (approx.)
Horizontal Effective Width= 8.65m
Horizontal Roofing Sheet Quantity= 8.65/ 0.95= 9.11 or 10 pcs

Vertical Effective Width= 8.20m


Vertical Roofing Sheet Quantity= 8.20/ 0.95= 9.11 or 10 pcs

C. ROOFING ACCESSORIES
GUTTER
Horizontal Roofing Accessories quantity= 8.65 + 0.10 (end lapping) + 0.10 (end lapping)
= 8.85/ 2.30 (effective width)= 3.84 or 4 pcs
Vertical Roofing Accessories quantity= 8.20 + 0.10 (end lapping) + 0.10 (end lapping)
= 8.40/ 2.30 (effective width)= 3.65 or 4 pcs
BUBBLE INSULATIONS
Horizontal Bubble insulations quantity= 8.65 + 0.30 (side lapping) + 0.30 (side lapping)
= 9.25/ 0.70 (effective width)= 13.21 or 14 pcs
Vertical Bubble insulations quantity= 8.20 + 0.30 (side lapping) + 0.30 (side lapping)
= 8.80/ 0.70 (effective width)= 12.57 or 13 pcs
D. ROOFING CONSUMABLES
Purlins Total Length= 8.65 x 10 pcs= 86.5 m or 87m
Tekscrew Quantity= 87 x 4 pcs = 348 pcs
TILEWORKS
TILEWORKS: AREA METHOD

TILE AREA= 0.6 x 0.6 = 0.36 sqm

QUANTITY= 9.38 sqm / 0.36 sqm= 26.05 pcs

AREA= 2.571 x 3.649 = 9.38 sqm

TILEWORKS: PERIMETER METHOD

L= 2.571 m; W= 3.671 m

Q1= 2.571/ 0.6= 4.285 pcs ; Q2= 3.649 / 0.6= 6.08 pcs
QUANTITY= 4.285 x 6.08= 26.05 pcs

AREA METHOD

L= 2.556 m ; W= 3.671 m
AREA = 2.556 x 3.671= 9.38 sqm
tTILE AREA= 0.6 x 0.6 = 0.36 sqm
QUANTITY= 9.38 / 0.36= 26.05 pcs

PERIMETER METHOD:
Q1= 2.556 / 0.6= 4.26 m ; Q2= 3.671 / 0.6= 6.118333
[email protected]= 0.556 x 0.6 = 0.3336 m ; [email protected]= 0.671 / 0.6= 1.1183
THEREFORE: 4 x 6= 24 pcs
TOTAL= 24 +13= 37 pcs
TILES ADHESIVES: 60 x 60 GLOSSY FINISH

AREA= 9.38 + 4.49 + 1.36 + 5.36= 20.59 sqm


# of bags= 20.59 / 2.6= 7.919 say 8 bags
# of bags= 20.59 x 0.30 kgs= 6.177 kgs / 2 kgs
= 3.0885 or 3 bags
N DP (volume)= 20.59 x 0.05= 1.0295 cu.m
THEREFORE: Cement (bags)= 1.0295 cu.m x 9.00
= 9.26 or 10 bags
Sand (bags)= 1.029 cu.m or 0.75
= 0.772 or 1 cu.m

PAINTING WORKS
PAINTING WORKS
Exterior Walls= 145.812 sqm + 3.487 sqm= 149.299 sqm (acrytex)
Interior Walls= 96.49 sqm (latex)
Corner Walls= 3.487 sqm
EXTERIOR WALLS
Materials Needed Coverage Area Area Quantity

1.) Masonry Neutralizer B-44 20 sqm/ 4.25 liters 149.299 sqm 1.87 ltrs.

2.) Acrytex Primer B-1705

● First Coat 25 sqm/ 4 liters 149.299 sqm 23.89 ltrs.

● Second Coat 30 sqm/ 4 liters 149.299 sqm 19.91 ltrs

3.) Acrytex Cast B-1711 25 sqm/ 4 liters 149.299 sqm 23.89 ltrs.

4.) Acrytex Top Coat

● First Coat 25 sqm/ 4 liters 149.299 sqm 23.89 ltrs.

● Second Coat 30 sqm/ 4 liters 149.299 sqm 19.91 ltrs

5.) Thinning Solvent

(Acrytex Reducer B-1750)

● Acrytex Cast B-1711 1:4 5.97 ltrs

● Acrytex Primer B-1705 1:4 4.98 ltrs

● Acrytex Top Coat 1:4 4.98 ltrs


INTERIOR WALLS

Materials Needed Coverage Area Area Quantity

1.) Masonry Neutralizer B-44 20 sqm/ 4.25 liters 96.49 sqm 1.21 ltrs.

2.) Flat Latex B-701 (Primer)

● First Coat 25 sqm/ 4 liters 96.49 sqm 15.44 ltrs.

● Second Coat 30 sqm/ 4 liters 96.49 sqm 12.87 ltrs

3.) Masonry Putty B-7311 25 sqm/ 4 liters 96.49 sqm 15.44 ltrs.

4.) Flat Latex

● First Coat 25 sqm/ 4 liters 96.49 sqm 15.44 ltrs.

● Second Coat 30 sqm/ 4 liters 96.49 sqm 12.87 ltrs


NOTE: MASONRY NEUTRALIZER
1 PART OF B-44: 16 PART OF WATER

EXTERIOR WALLS

Materials Needed Packaging Area Quantity

1.) Masonry Neutralizer 1 gal or 3.785 ltrs 149.299 sqm 1.87 ltrs. 0.49 gal 1 gal
B-44

2.) Acrytex Primer B-1705 4 ltrs and 16 ltrs

● First Coat 149.299 sqm 23.89 ltrs. 2.74 pail 3 pail


1.34 gal 2 gal
● Second Coat 149.299 sqm 19.91 ltrs

3.) Acrytex Cast B-1711 4 ltrs and 16 ltrs 149.299 sqm 23.89 ltrs. 5.97 gal 6 gal

4.) Acrytex Top Coat 4 ltrs and 16 ltrs

● First Coat 149.299 sqm 23.89 ltrs. 2.74 pail 3 pail

● Second Coat 149.299 sqm 19.91 ltrs 1.34 gal 2 gal

5.) Thinning Solvent 4 ltrs and 16 ltrs

(Acrytex Reducer
B-1750)

● Acrytex Cast 5.97 ltrs 3.96 gal 4 gal


B-1711

● Acrytex Primer 4.98 ltrs


B-1705

● Acrytex Top Coat 4.98 ltrs


PLUMBING WORKS