NAME: LUCAGBO, JULIE MAE D.
REVELO, JHUNBIE CLAIRE P. 12/17/24
BT ESTIMATES:
FOOTING:
VOLUME OF FOOTING 1= (0.80m) (0.80m) (0.20m) = 0.128 cu. m
FOR 12 FOOTINGS= 12 (0.128 cu. m) = 1.536 cu. m USING CLASS A
MIXTURE; 40 kg
NUMBER OF BAGS OF 40 kg CEMENT= 1.536 cu. m (9.0) = 13.824 or 14 bags
VOLUME OF SAND= 1.536 cu, m (0.50) = 0.768 cu. m or 28.4 or 23 bags
VOLUME OF GRAVEL= 1.536 cu. m (1.0) = 1.536 cu. m or 56.8 or 57 bags
COLUMN:
TOTAL HEIGHT IF COLUMN 1= 5.80m + 0.10m + 0.37m + 1.00m= 7.27 m
VOLUME OF COLUMN 1= (0.20 m) (0.20 m) (7.27 m) = 0.2G08 cu. m
FOR 10 COLUMNS= 10 (0.2908 cu. m) = 2.G08 cu. m
NUMBER OF BAGS OF 40 kg CEMENT= 2.908 cu. m (9.0) = 26.17 or 27 bags VOLUME OF
SAND= 2.908 cu. m (0.50) = 1.454 cu. m or 53.85 or 54 bags VOLUME OF GRAVEL= 2.908 cu.
m (1.0) = 2.G08 cu. m or 107.7 or 108 bags
TO SUMMARIZE:
NUMBER OF BAGS OF 40 kg CEMENT 14 + 27= 41 Bags
VOLUME OF SAND= 0.768 cu. m + 1.454 cu. m= 32.222 cu. m
VOLUME OF GRAVEL= 1.536 cu. m+ 2.908 cu. m = 4.444 cu. m
COMPUTE THE COST:
1 BAG OF CEMENT Php 220- Php 250 41 Bags x Php 250= Php 10,250.00
SAND PER CUBIC METER Php 800 2.222 cu. m x Php 800= Php 1,777.60
GRAVEL PER CUBIC METER Php 1,200 4.444 cu. m x PHP 1,200= Php 5.332.80
MASONRY
Hollow core/cell; 4 Hollow Cells= 0.003 m³/ CHB
Volume of 1 cell= 0.00075 m³
VOLUME OF MORTAR LAYERING: (For 4” thk. CHB) = 0.0125m (0.10m)(0.40m) = 0.0005m³
WALL HEIGHT= 3.90 m; WIDTH= 1.40 m - (0.20 x 2)= 1.00. Therefore 3.90 x 1.00= 3.90 m² (wall area)
NUMBER OF CHB= 3.90 m²/ 0.08 m²= 48.75 pcs or 49 pcs of 4” thk. CHB
MORTAR FOR BLOCK LAYERING= LAYER + FILL= 0.02 + 0.147= 0.167 m³
LAYER= (1.00) (0.10) x 0.0125 m x (15 + 1) = 0.02 m³
FILL= 0.003 m³ (49 pcs of CHB)= 0.147 m³
HORIZONTAL= 1.00/ 0.40= 2.5 pcs VERTICAL= 3.90/ 0.20= 19.5 pcs
MORTAR FOR PLASTERING= (1.00 x 3.90) (1 side) (0.016 m)= 0.0624 m³
VOLUME OF WALL FOOTING= (2.20) (0.20) (0.50)= 0.22 m³
MORTAR= Plastering + block layering = 0.167 + 0.0624= 0.2294 m³
Number of CHB= 49 pcs
Mortar for Block Layering= 0.167 m³
Mortar for Plastering= 0.0624 m³
Volume of Wall Footing= 0.22 m³
Number of 40 kg cement for mortar= 0.2294 (18)= 4.1292 or 5 bags
Volume of sand= 0.22974 (0.5)= 0.1147 m³ or 4.25 or 5 bags
Volume of Gravel= 0.22974 (1)= 0.22974 m³ or 8.49 or 9 bags
FOR WALL FOOTING:
Number of 40 kg cement= 0.22 (9)= 1.98 or 2 bags
Volume of Sand= 0.22 (0.5)= 0.11 m³ or 4.07 or 4 bags
Volume of Gravel= 0.22 (1)= 0.22 m³ or 8.14 or 9 bags
MASONRY REINFORCEMENT
Vertical Bars= 1.65 (width)/ 0.80 m (horizontal spacing)= 2.06 spacing= 2 +1 bar (both ends)
Vertical Bars= 2.80 (height)/ 0.60 m (vertical spacing)= 4.67 spacing= 5 +1 bar (both ends)
Dowel Bars= 0.20 m (exposed) + 0.10m(unexposed)
1 Dowel= 0.30m No. of Dowels= 16 pcs; Dowel Length= 6.00m
For Continuous Mat Bar:= (1.65 + 0.10) (2) (3)= 5.55 m
For Cut Bars= (0.40 m - 0.075 (2) + (0)) ((2.00/ 0.40) + 1)= (0.25) (6)= 1.50m; 1.50m + 5.55m= 7.05m
Vertical Bars= 3 bars (2.80)= 8.40m; Horizontal Bars= 6 bars (1.65)= 9.90m
Dowel Bars= 6.00m WF Bars= 7.05 m Total Bar Length= 31.35m
NOTE: Use 7.50m commercial bar length (less wastage)
No. of 10mm dia bar= 31.35/ 7.50= 4.18 or 5 pcs
TIE WIRES
For every intersection= 6 x 3= 18 intersections; For every dowel splicing= 16 (dowels)
For mat bars intersection= 3 (continuous bars) x 6 (cut bars)= 18 intersections
Total tying points= 18 x 16 x 18= 52 tying points
Total Tie Wires needed: 52 x 0.30= 15.6/ 53 m/kl= 0.29 kls. of tie wires
MASONRY:Summary
Number of CHB= 49 pcs
Mortar for Block Layering= 0.167 m³
Mortar for Plastering= 0.0624 m³
Volume of Wall Footing= 0.22 m³
Number of 40 kg cement for mortar= 0.2294 (18)= 4.1292 or 5 bags
Volume of sand= 0.22974 (0.5)= 0.1147 m³ or 4.25 or 5 bags
FOR WALL FOOTING:
Number of 40 kg cement= 0.22 (9)= 1.98 or 2 bags
Volume of Sand= 0.22 (0.5)= 0.11 m³ or 4.07 or 4 bags
Volume of Gravel= 0.22 (1)= 0.22 m³ or 8.14 or 9 bags
No. of 10mm dia bar= 5 pcs
Tie Wire (kgs)= 0.29 kls. Or ⅓ kilo
CONCRETE & STEEL REINFORCEMENT
A. FOOTING:
LENGTH WIDTH DEPTH CONCRETE SET MATBAR
COVER
F1 800 mm 800 mm 30mm 750mm 12 sets 12mm
BOTHWAYS
CONCRETE VOLUME= L x W x D
= (0.80) (0.80) (0.30)
= 0.192 cu. m
= 0.192 cu. m (12 sets)
= 2.304 cu. m
CUT LENGTH= W/L – (Concrete cover) (2) + (hook) (2)
= 0.80 – (0.75) (2) + (0.125) (2)
= 0.9 m
No. of mat pcs = 12 sets (5) (2 both ways)
= 120 pcs of 0.90m No. of cut
length per DRB= 6.00 / 0.90
= 6.67 or 6 pcs
WASTAGE= (excess %) ( cut length )
= ( .67) (0.90 m) = 0.603 or 2,60 per DRB
No. cut length pre DRB= 7.50/0/090 = 8.33 M
WASTAGE= (excess %) (cut length)
= (.33) (0.90)= 0.297 or 0.30 per DRB
F1 CUT LENGTH (CL): 12 PCS @ 0.90M
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(16mm) (m)
6.00 0.90 6.67 6.00 0.60
7.50 8.33 8.00 0.30
NO. OF PCS @ 12mm DIAMETER x 7.50 DRB= 120 pcs / 8pcs
= 15 pcs of DRB WEIGTH @
12mm DIAMETER x 7.50 DRB= 15 pcs (7.50) (0.888 kg/m)
= 99.9 kgs
TIRE WIRES
= 5 (horizontal) x 5 (vertical)
= 25 intersections
= 12 sets x 25 intersections
= 300 intersections
= 300 tying points x 0.30m
= 90 / 53 m/kl
= 1.698 kg or 1.7 kg of tire wire
SUMMARY:
FOOTING 1 (F-1): @ 12 SETS
Quantity of bar @ 12mm x 7.50 DRB = 15 pcs or 99.9 kgs Quantity
of tire wires = 1.7 kg or 1 ¾ kg
B. COLUMN
C1 @ 7.27m
MAIN VERTICAL BAR CUT LENGTH
VBCL= (7.27M) (-0.075) (concrete cover footing) – (0.012m) (DB) (2) – (0.40) (concrete cover column) +
(0.20) (hook)
VBCL= 7.195 – 0.024 – 0.40 + 0.20
= 6.971 OR 7M
@ 10 sets of C1 @ 7.27 height No. of
VBCL pcs= (10 sets) (4pcs)
= 40pcs of 7.27m
C1 VERTICAL BAR CUT LENGTH (CL)= 40PCS @7.27M
No. of CL per DRB= 7.50 / 7.27
= 1.03
WASTAGE= (excess %) (cut length)
= (0.03) (7.27)
= 0.2181 or 0.22m
No. of pcs @ 12mm diameter x 7.50 DRB= 40 pcs (CL) / 1pc
= 40 pcs of DRB
WEIGTH @ 12mm DIAMETER x 7.50 DRB= 40 (7.50) (0.888 KG/M)
= 239.75 kgs
C1 LATEREAL TIES CUT LENGTH (LTCL)
A (side) 200 – (2) (40) = 120mm or 0.120mm
B (side) 200 – (2) (40) = 120mm or 0.120mm
LTCL= 2 (A (side)) + 2 (B (side)) + 2 (hooks)
= 2(0.120m) + 2 (0.120m) + 2 (0.10m)
= 0.68m
C1 effective Heigth @ GF:
= (3.90M) – (0.075) – (0.012 (2)) – 0.25
= 3.825 – 0.024 – 0.25
= 3.551 M
C1 EFFECTIVE HEIGTH @ 2F= (3.17) – (0.04M) – (0.00M)
= 3.13M
C1 MID-HEIGTH @ DF:
= (3.551M) – (4 (0.05M)) (2) – 6 (0.10) (2)
= 3.551M – 0.4 -1.2
= 1.951 or 2.00m
C1 MID-HEIGTH @ GF LATERAL TIE QUANTITY = 2.00M / 0.20M
= 10PCS
C1 MID-HEIGTH @ 2F = (3.13M) – (4 (0.05)) (2)
= 2.73M
C1 MID-HEIGTH @ 2F LATERAL TIE QUANTITY = 3.17 / 0.15
= 21.13 OR 21 PCS
QUANTITY LATERAL TIES /COLUMN @ GF:
= 1+4+6+10+6+4+1+3
= 35 PCS
QUANTITY LATERAL TIES/ COLUMN @ 2F= 1+4+10+4+1
= 20PCS
10 SETS OF C1 @ 7.27 M HEIGTH
No. of lateral ties (pcs) = (35pcs) + (20pcs) (10 sets)
= 550 pcs of 0.68 m
C1 lateral tie CL: 550 pcs @ 0/68m No. of
CL per DRB = 6.00 / 0.68M
= 8.82 PCS OR 8 PCS
WASTAGE: = (0.03) (0.68M) = 0.02 M
C1 VERTICAL BAR CUT LENGTH (CL): 550 PCS @ 0.68M
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 0.68 8.82 8.00 0.56
7.50 11.03 11.00 0.02
NO. OF PCS @ 12MM DIAMETER x 7.50M PER DRB= 550PCS /11 PCS
= 50 PCS OF DRB
WEIGHT OF 12MM DIAMETER x 7.50M = (50PCS) (7.50) (0.888 KG/M)
= 333 KGS
TIE WIRES:
For every intersection
= 4 (vertical bar) x 55 (lateral ties) = 220 (intersections)
Add: 3 tie points @ hook / vertical bar
= 4 (vertical bar) x 3 (ties points) = 220 + 12
= 232 intersections For
column 1 (c1) sets:
= 10 sets (232 intersections) = 2,320 intersections
TOTAL THE WIRES NEEDED:
= 2,320 (tying points) x 0.30 m
= 696 / 53 m/kl
= 13.13 kgs of tie wires
C1 SUMMARY: @ 10 SETS
Quantity of vertical bar @ 12mm diameter x 7.50 m DRB
= 40 PCS OR 239.75 KGS
Quantity of lateral ties @ 12 mm diameter 7.50m DRB
= 50 PCS OR 333 KGS
Quantity of tie wire
= 13.13 kgs or 13 kgs
C. BEAM
B1: 4 SETS @ 2.50 m
B1 HORIZONTAL MAIN BAR CUT LENGTH (HMBCL): ((2.50m) - ((2)(0.040m)) + ((2)(0.20m))= 2.82m
4 SETS OF B1 @ 2.50m LENGTH
No. of HMBCL= (4 sets) (4 pcs)= 16 pcs of 2.82m
B1 HORT. BAR CUT LENGTH (CL): 16 pcs. @ 2.82m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/2.82m = 3.18 pcs or 3 pcs
WASTAGE = (0.18) (2.82m)= 0.50
Let’s try 7.50m
No. of CL per DRB. = 7.50m/2.82m = 2.66 pcs or 2 pcs
WASTAGE = (0.66) (2.82m)= 1.86
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 2.82 3.18 3.00 0.50
7.50 2.66 2.00 1.86
No. of PCS. @ 12mmø X 6.00m DRB = 16 pcs/ 3 pcs= 5.33 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 12mmø X 6.00m DRB = (6 pcs) (6.00m) (0.888kg/m)= 31.68 kgs
B1 HORIZONTAL MID BAR CUT LENGTH (HMiBCL):
HMiBCL = ((2.50m) - ((2)(0.040m)) + ((2)(0.175m)) = 2.77m
4 SETS OF B1 @ 2.50m LENGTH
No. of HMiBCL= (4 sets) (2 pcs)= 8pcs of 2.77m
B1 HORT. BAR CUT LENGTH (CL): 8 pcs. @ 2.77m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/2.77m = 2.17 pcs or 2 pcs
WASTAGE = (0.17) (2.77m)= 0.47
Let’s try 7.50m
No. of CL per DRB. = 7.50m/2.77m = 2.71 pcs or 2 pcs
WASTAGE = (0.66) (2.77m)= 1.97m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 2.77 2.17 2.00 0.47
7.50 2.71 2.00 1.97
No. of PCS. @ 10mmø X 6.00m DRB = 8 pcs/ 2 pcs= 4 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (4 pcs) (6.00m) (0.616kg/m)=14.78 kgs
B1 STIRRUPS CUT LENGTH (BSCL):
BSCL = 2(A(side)) + 2(B(side)) + 2(hooks)= 2(0.120m) + 2(0.170m) + 2(0.10m)= 0.78m
B1 EFFECTIVE LENGTH @ 2.50m (CONTINUES BEAM):= (2.50m) - (0.40m) – (0.40m)= 1.40m
B1 EFFECTIVE LENGTH @ 3.50m (CONTINUOUS BEAM):= (3.50m) - (0.40) - (0.40)= 2.70m
B1 MID-LENGTH @ 2.50m (CONTINUES BEAM):= (eff. length @ 2.50m) – (spacing @ left & right support)
= (2.50m) – (2(0.05m))(2) – (3(0.10m))(2)= 0.90m
B1 MID-LENGTH STIRRUP QUANTITY @ 2.50m : =0.90/ 0.15 m= 6 pcs.
B1 MID-LENGTH @ 3.50m (CONTINUOUS BEAM):= (eff. length @ 3.50m) – (spacing @ left & right
support/end)= (3.50m) – (2(0.05m))(2) – (3(0.10m))(2) = 2.70m
B1 MID-LENGTH STIRRUP QUANTITY @ 3.50m : =2.70/ 0.15 m= 18 pcs.
QUANTITY STIRRUPS @ 3.50m (CONTINUES BEAM) : 1 + 2 + 3 + 18 + 3 + 2 + 1= 30 pcs
QUANTITY STIRRUPS @ 2.50m (CONTINUES BEAM) : 1 + 2 + 3 + 6 + 3 + 2 + 1= 18 pcs
4 SETS OF B1 @ 2.50m LENGTH
No. of Beam Stirrups (pcs): ((30 pcs) + (18 pcs)(4 sets)= 102 pcs of 0.78m
B1 STIRRUP CUT LENGTH (CL): 102 pcs. @ 0.78m
Let’s try 6.00m
No. of CL per DRB. =6.00m/ 0.78m = 7.69 pc. or 7 pcs.
WASTAGE = (0.69) (0.78m)= 0.54m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 0.78m = 9.61 pc. or 9 pcs.
WASTAGE = (0.61) (0.78m)= 0.48m
B1 STIRRUP CUT LENGTH (CL): 38 pcs. @ 0.78m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 0.78 7.69 7.00 0.54
7.50 9.61 9.00 0.48
No. of PCS. @ 10mmø X 7.50m DRB = 102 pcs/ 9 pcs= 11.33 pcs or 12 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (12 pcs) (7.50m) (0.616kg/m)=55.44 kgs
TIE WIRES:
For every intersection= 16 (hort. bar) x 102 pcs= 1,632 intersections
ADD: 3 tie pts. @ hook/ vert. Bar: 16 x 3 x 2= 96 intersections; 1,632 + 96= 1,728 intersections
For Footing 1 (F1) sets:= 1 (set) X 1,728 (intersections) =1,728 intersections
Total tie wires needed: 1,728 (tying points) X 0.30m= 518.4/53m / kl= 9.78 kgs. of tie wire
BEAM 1 (B1) SUMMARY: @ 4 SET
QUANTITY OF HORT. BAR @ 12mmø X 6.00m DRB = 16 pcs or 31.68 kgs.
QUANTITY OF MID BAR @ 10mmø X 6.00m DRB = 8 pcs or 14.78 kgs.
QUANTITY OF STIRRUPS @ 10mmø X 7.50m DRB = 102 pcs or 155.44 kgs.
QUANTITY OF Tie wire =9.78 kgs. or 9 ¾ kgs.
D. SLAB
Identify the SLAB perimeter:
SOG EFFECTIVE WIDTH @ (ALONG X-AXIS):= (6.00 - (0.20 + 0.15))= 5.65
SOG EFFECTIVE LENGTH @ (ALONG Y-AXIS):= (5.50- (0.20 + 0.30))= 5.15 m
SOG MAT BAR QUANTITY @ 5.65m (ALONG X-AXIS):= 5.65m/0.60m + 1= 10.42 or 10 pcs
SOG MAT BAR QUANTITY @ 5.15m (ALONG Y-AXIS):= 5.15m/0.60m + 1= 9.58 or 10 pcs
Identify the SOG MAT BAR CUT LENGTH:
Along X: (5.65m + (0.10 +0.075) + (2(0.175))= 6.18m
Along Y: (5.15m + (0.10 +0.075) + (2(0.175))= 5.68m
Summary of SOG MAT BAR CUT LENGTH QUANTITY:
Along X: 10 pcs of 6.18m
Along Y: 10 pcs pf 5.68m
SOG MAT BAR CUT LENGTH (CL): 10 pcs. @ 6.18m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 6.18= 0.97 pc. or 1.00 pc.
WASTAGE = (0) (6.18m)= 0m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 6.18m =1.21 pcs. or 1 pc.
WASTAGE = (0.21) (6.18m)= 1.30m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 6.18 0.97 1.00 0.00
7.50 1.21 1.00 1.30
No. of PCS. @ 10mmø X 6.00m DRB = 10 pcs/ 1 pcs= 10 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (10 pcs) (6.00m) (0.616kg/m)=3.96 kgs
SOG MAT BAR CUT LENGTH (CL): 10 pcs. @ 5.68m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 5.68= 1.05 pc. or 1.00 pc.
WASTAGE = (0.05) (5.68m)= 0.28m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 5.68m =1.32 pcs. or 1 pc.
WASTAGE = (0.32) (5.68m)= 1.82m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 5.68 1.05 1.00 0.28
7.50 1.32 1.00 1.82
No. of PCS. @ 10mmø X 6.00m DRB = 10 pcs/ 1 pcs= 10 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (10 pcs) (6.00m) (0.616kg/m)=3.96 kgs
TIE WIRES:
For every intersection= 10 (x-axis) x 10 (y-axis)= 100 intersections
ADD: 3 tie pts. @ hook/ vert. Bar: (10 +10) x 2 x 2= 80 intersections; 100 + 80= 180 intersections
For Slab on Grade (SOG) sets:= 1 (set) X 180 (intersections) =180 intersections
Total tie wires needed: 180 (tying points) X 0.30m= 54/53m / kl=1.02kgs of tie wires
SLAB ON GRADE (SOG) SUMMARY: @ 1 SET
QUANTITY OF SOG MAT BAR @ 10mmø X 6.00m DRB = 20 pcs or 7.92 kgs.
QUANTITY OF Tie wire = 1.02 kgs or 1 kilo
SLAB: SUSPENDED SLAB
Identify the different SLAB perimeter:
S1(A1) EFFECTIVE WIDTH @ (ALONG X-AXIS): =(2.50-(0.20+0.20))= 2.10m
S1(A1) EFFECTIVE LENGTH@ (ALONG Y-AXIS): =(1.30 - (0.00m + 0.20))= 1.10m
CHECK FOR TYPE OF SLAB: =L/ W= 2.50/ 1.30 = 1.92 < 2 “TWO-WAY SLAB”
Identify the BOT. CONT. BAR CUT LENGTH:
Along X:
= (2.50m ) + (0.10m + 0.10m) + (2(0.175m))= 3.05m
Along Y:
= (1.30m ) + (0.10m + 0.10m) + (2(0.175m))= 1.85
S1(A1) BOT. CONT. BAR QUANTITY @ 2.50m (ALONG X-AXIS): =2.50m/ 0.20 + 1= 13.5 or 14 pcs
S1(A1) BOT. CONT. BAR QUANTITY @ 1.30m (ALONG Y-AXIS):= 1.30m/ 0.20 +1 = 2.50 or 3 pcs
Summary of BOT. CONT. BAR CUT LENGTH QUANTITY:
Along X: = 14 pcs. of 3.05m
Along Y: = 3 pcs. of 1.85m
BOT. CONT. BAR CUT LENGTH (CL): 14 pcs. @ 3.05m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 3.05m= 1.96 pc. or 1.00 pc.
WASTAGE = (0.96) (3.05m)= 2.92m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 3.05m =2.45 pcs or 2 pcs
WASTAGE = (0.45) (3.05m)= 1.37m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 3.05 1.96 1.00 2.92
7.50 2.45 2.00 1.37
No. of PCS. @ 10mmø X 7.50m DRB = 14 pcs/ 2 pcs= 7 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (7 pcs) (7.50m) (0.616kg/m)=32.34 kgs
BOT. CONT. BAR CUT LENGTH (CL): 3 pcs. @ 1.85m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.85m= 3.24 pc. or 3.00 pcs.
WASTAGE = (0.24) (1.85m)= 0.44m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.85m =4.05 pcs or 4 pcs
WASTAGE = (0.05) (1.85m)= 0.09m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.85 3.24 3.00 0.44
7.50 4.05 4.00 0.09
No. of PCS. @ 10mmø X 7.50m DRB = 3 pcs/ 4 pcs= 0.75 pcs or 1 pc of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (1 pc) (7.50m) (0.616kg/m)=4.62 kgs
TIE WIRES:
For every intersection= 14 pcs (x-axis) x 3 pcs (y-axis)= 42 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: 14 + 3 x 2 x 2= 68 intersections; 42 + 68= 110 intersections
For Slab-1 (BCBCL) sets:= 1 (set) X 110 (intersections) =110 intersections
Total tie wires needed: 110 (tying points) X 0.30m= 33/53m / kl= 0.62 kgs. of tie wire
S1 (BOT. CONT. BAR) SUMMARY: @ 1 SET
QUANTITY OF SOG MAT BAR @ 10mmø X 7.50m DRB = 8 pcs or 36.96 kgs.
QUANTITY OF Tie wire = 0.62 kgs. or 1 kgs.
Identify the BENT BAR CUT LENGTH:
Along X: = (2.50m ) + (0.10m + 0.10m) + (2(0.175m)) + 0.07m= 3.12m
Along Y: = (1.30m ) + (0.10m + 0.10m) + (2(0.175m)) + 0.07m= 1.92m
S1(A1) BENT BAR QUANTITY @ 2.50m (ALONG X-AXIS): = 2.50/ 2= 1.25 + 1= 7.25 or 7 pcs
S1(A1) BENT BAR QUANTITY @ 1.30m (ALONG Y-AXIS): = 1.30/ 2= 0.65 + 1= 4.25 pcs or 4 pcs
Summary of BOT. CONT. BAR CUT LENGTH QUANTITY:
Along X: = 7 pcs. of 3.12m
Along Y: = 4 pcs. of 1.92m
BOT. CONT. BAR CUT LENGTH (CL): 7 pcs. @ 3.12m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 3.12m= 1.92 pcs. or 1.00 pc.
WASTAGE = (0.92) (3.12m)= 2.87m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 3.15m =2.40 pcs or 2 pcs
WASTAGE = (0.40) (3.12m)= 1.25m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 3.12 1.92 1.00 2.87
7.50 2.40 2.00 1.25
No. of PCS. @ 10mmø X 7.50m DRB = 7 pcs/ 2 pcs= 3.50 pcs or 4 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (4 pc) (7.50m) (0.616kg/m)=18.48 kgs
BOT. CONT. BAR CUT LENGTH (CL): 4 pcs. @ 1.92m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.92m= 3.13 pcs. Or 3.00 pc.
WASTAGE = (0.13) (1.92m)= 0.24m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.92m =3.90 pcs or 3 pcs
WASTAGE = (0.92) (1.92m)= 1.73m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.92 3.13 3.00 0.24
7.50 3.90 3.00 1.73
No. of PCS. @ 10mmø X 6.00m DRB = 4 pcs/ 3 pcs= 1.33 pc or 1 pc of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (1 pc) (6.00m) (0.616kg/m)=3.70 kgs
TIE WIRES:
For every intersection=7 pcs (x-axis) x 4 pcs (y-axis)= 28 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: (7 + 4) x 2 x 2= 44 intersections; 28 + 44= 72 intersections
For Slab-1 (BCBCL) sets:= 1 (set) X 72 (intersections) =72 intersections
Total tie wires needed: 72(tying points) X 0.30m= 21.6/ 53m / kl= 0.40 kgs. of tie wire
S1 (BENT BAR) SUMMARY: @ 1 SET
QUANTITY OF BENT BAR @ 10mmø X 6.00m DRB = 1 pc or 3.70 kgs.
QUANTITY OF BENT BAR @ 10mmø X 7.50m DRB = 4 pcs or 18.48 kgs.
QUANTITY OF Tie wire = 0.40 kgs. or 1⁄2 kgs.
Identify the TOP STRAIGHT BAR CUT LENGTH:
Along X:
= (2.50m ) + (0.10m + 0.10m) + (2(0.175m))= 3.05m
Along Y:
= (1.30m ) + (0.10m + 0.10m) + (2(0.175m))= 1.85m
S1(A1) TOP ST. BAR QUANTITY @ 2.50m (ALONG X-AXIS):
= 2.50/ 4= 0.625/ 0.20 + 1= 4.13 or 4 pcs x (2 sides)= 8 pcs
S1(A1) TOP ST. BAR QUANTITY @ 1.30m (ALONG Y-AXIS):
= 1.30/ 4= 0.325/ 0.20 + 1= 2.63 or 3 pcs x (2 sides)= 6 pcs
Summary of TOP STRAIGHT BAR CUT LENGTH QUANTITY:
Along X: = 8 pcs. of 3.05m
Along Y: = 4 pcs. of 1.85m
TOP STRAIGHT BAR CUT LENGTH (CL): 8 pcs. @ 3.05m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 3.05m= 1.96 pcs. Or 1.00 pc.
WASTAGE = (0.96) (3.05m)= 2.93m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 3.05m =2.45 pcs or 2 pcs
WASTAGE = (0.45) (3.05m)= 1.37m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 3.05 1.96 1.00 2.93
7.50 2.45 2.00 1.37
No. of PCS. @ 10mmø X 7.50m DRB = 8 pcs/ 2 pcs= 4 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (4 pc) (7.50m) (0.616kg/m)=18.48 kgs
TOP STRAIGHT BAR CUT LENGTH (CL): 6 pcs. @ 1.85m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.85m= 3.24 pcs. or 3.00 pc.
WASTAGE = (0.34) (1.85m)= 0.44m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.85m = 4.05 pcs or 4 pcs
WASTAGE = (0.05) (1.85m)= 0.09m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.85 3.24 3.00 0.44
7.50 4.05 4.00 0.09
No. of PCS. @ 10mmø X 7.50m DRB = 6 pcs/ 4 pcs= 1.50 pcs of 2 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 7.50m DRB = (2 pc) (7.50m) (0.616kg/m)=9.24 kgs
TIE WIRES:
For every intersection=8 pcs (x-axis) x 6 pcs (y-axis)= 48 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: (8 + 6) x 2 x 2= 56 intersections; 56 + 48= 104 intersections
For Slab-1 (TSBCL) sets:= 1 (set) X 104 (intersections) =104 intersections
Total tie wires needed: 104(tying points) X 0.30m= 31.20/ 53m / kl= 0.59 kgs. of tie wire
S1 (TOP STRAIGHT BAR) SUMMARY: @ 1 SET
QUANTITY OF TOP ST. BAR @ 10mmø X 7.50m DRB = 14 pcs or 27.72 kgs.
QUANTITY OF Tie wire = 0.59 kgs. or 1⁄2 kgs.
Identify the TOP CUT BAR CUT LENGTH:
Along X:
= (2.50m /3) + (0.10m ) + (0.175m)=1.11m
Along X:
= (1.30m /3) + (0.10m ) + (0.175m)=0.71m
S1(A1) TOP ST. BAR QUANTITY @ 2.50m (ALONG X-AXIS):
= 2.50/ 2= 1.25/ 0.20= 6.25 or 6 pcs x (2 sides)= 12 pcs
S1(A1) TOP ST. BAR QUANTITY @ 1.30m (ALONG X-AXIS):
= 1.30/ 2= 0.65/ 0.20= 3.25 or 3 pcs x (2 sides)= 6 pcs
Summary of TOP CUT BAR CUT LENGTH QUANTITY:
Along X: = 12 pcs. of 1.11m
Along Y: = 6 pcs. of 0.71m
TOP CUT BAR CUT LENGTH (CL): 12 pcs. @ 1.11m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 1.11m= 5.41 pcs. or 5.00 pcs.
WASTAGE = (0.41) (1.11m)= 0.46m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 1.11m = 6.76 pcs or 6 pcs
WASTAGE = (0.76) (1.11m)= 0.84m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 1.11 5.41 5.00 0.46
7.50 6.76 6.00 0.84
No. of PCS. @ 10mmø X 6.00m DRB = 12 pcs/ 5 pcs= 2.40 pcs or 3 pcs of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (3 pc) (6.00m) (0.616kg/m)=11.09 kgs
TOP CUT BAR CUT LENGTH (CL): 6 pcs. @ 0.71m
Let’s try 6.00m
No. of CL per DRB. = 6.00m/ 0.71m= 8.45 pcs. or 8.00 pcs.
WASTAGE = (0.45) (0.71m)= 0.32m
Let’s try 7.50m
No. of CL per DRB. =7.50m/ 0.71m = 10.56 pcs or 10 pcs
WASTAGE = (0.56) (0.71m)= 0.40m
LENGTH OF CUT LENGTH # OF PCS PRODUCE WASTAGE
REBAR (m) PCS PCS LENGTH
(12mm) (m)
6.00 0.71 8.45 8.00 0.32
7.50 10.56 10.00 0.40
No. of PCS. @ 10mmø X 6.00m DRB = 6 pcs/ 8 pcs= 0.75 pcs or 1 pc of DRB
QUANTITY OF BAR IN WEIGHT (kgs):
WEIGHT @ 10mmø X 6.00m DRB = (1 pc) (6.00m) (0.616kg/m)=3.696 kgs
TIE WIRES:
For every intersection=(12 x 8) (2 sides) (x-axis) + (12 x 8) (2 sides)(y-axis)= 144 intersections
ADD: 2 tie pts. @ hook/ mat. Bar: (12 + 6) x 2 (tie pts) x (end) = 36 intersections; 36 + 144= 180 intersections
For Slab-1 (TSBCL) sets:= 1 (set) X 180 (intersections) =180 intersections
Total tie wires needed: 180(tying points) X 0.30m= 54/ 53m / kl= 1.02 kgs. of tie wire
S1 (TOP CUT BAR) SUMMARY: @ 1 SET
QUANTITY OF TOP ST. BAR @ 10mmø X 6.00m DRB = 4 pcs or 14.76 kgs.
QUANTITY OF Tie wire =1.02 kgs. or 1 kgs.
SUSPENDED SLAB 1(AREA 1) (S1) SUMMARY: @ 1 SET
QUANTITY OF BAR @ 10mmø X 6.00m DRB = 5 pcs or 18.46 kgs.
QUANTITY OF BAR @ 10mmø X 7.50m DRB = 26 pcs or 80.16 kgs.
QUANTITY OF Tie wire = 2.63 kgs. or 2 ½ kgs.
E. STAIRS
PLINTH/STAIR FOOTING
Footing Width 0.90 m
Footing Length 1.10m
Footing Height 0.30m
Footing Col. Width 0.25 m
Footing Col. Height 1.00 m
Concrete Cover 0.075 m
For Vert. Rebars @0.10m O.C (across 1.10m length)
- 12.00 pcs per side
- 24.00 pcs
Vert. Rebar Length
- 1.29 m
- 8.13
Therefore use 3 - 12Ø x 10.5m
For Hor't. Rebars @0.20m O.C (across 1.10m length)
- 6.00 pcs per side
- 12.00 pcs
Hor't. Rebar Length
- 1.025 m
- 5.85 pcs
- 2.05
Therefore use 2 - 10Ø x 6m
For Mat Cut Bars @0.10 O.C
- 12.00 pcs
Mat Cut Bar
- 1.09 m
- 5.51 pcs per cut length
- 2.178
Therefore use 2 - 12Ø x 6m
For Long Temp Bars
- 5.00 pcs
Long Temp Bar Length
- 1.09 m
- 5.85 pcs per cut length
- 0.854167
Therefore use 1 - 12Ø x 6m
TOTAL:
Mat Cut bars 2 - 12Ø x 6m
- 10.656 kg
Long Temp bars 1 - 12Ø x 6m
- 5.328 kg
Plinth Vert. bars 3 - 12Ø x 10.5m
- 27.972 kg
Plinth Hor't. Bars 2 - 10Ø x 6m
- 7.392 kg
Note: For 12Ø = 0.888kg/m
For 10Ø = 0.616kg/m
LANDING SLAB
Landing Length 2.2 m
Landing Width 1.1 m
Concrete Cover 0.02 m
For Main Bottom Bars @0.10 O.C
- 12 pcs per
- 36 pcs total for 3 x 1.1m
Length
- 2.126
- 4.233302
- 8.504
Therefore use 9 - 12Ø x 9m
For Hor't. Bottom Bars @0.2 O.C
- 5.5
- 6 pcs
Length (Landing) Length (Floor Level)
- 2.16 1.06
- 3.472222 7.075472
- 1.728 0.848
Therefore use 2 - 10Ø x 7.5m Therefore use 1 - 10Ø x 7.5m
For Main Top Bars @0.10 O.C
- 12 pcs per 1.1m slab
- 36 pcs total for 3 x 1.1m
Length
- 2.126
- 4.233302
- 8.504
Therefore use 9 - 12Ø x 9m
For Hor't. Top Bars @0.2 O.C
- 5.5
- 6 pcs
Length (Landing) Length (Floor Level)
- 2.16 1.06
- 3.472222 7.075472
- 1.728 0.848
Therefore use 2 - 10Ø x 7.5m Therefore use 1 - 10Ø x 7.5m
TOTAL:
Main Bottom bars 9 - 12Ø x 9m
- 71.928 kg
Hor't Bottom bars 3 - 10Ø x 7.5m
- 13.86 kg
Main Top bars 9 - 12Ø x 9m
- 71.928 kg
Hor't Top bars 3 - 10Ø x 7.5m
- 13.86 kg
WAIST SLAB
Waist Length 2.88 m
Stair Width 1.1 m
Concrete Cover 0.02 m
For Main Bottom Bars @0.10 O.C
- 12 pcs
- 24 pcs total (2 flight of stairs)
Length
- 2.88
- 2.083333
- 11.52
Therefore use 12 - 12Ø x 6m
For Hor't. Bottom Temp Bars @0.20 O.C
- 15.4
- 15 pcs
- 30 pcs total (2 flight of stairs)
Length
- 1.06
- 8.490566
- 3.533333
Therefore use 4 - 10Ø x 9m
For Bottom Reinf. Bars (Connecting to Plinth)
- 12 pcs total
Length
- 2.026
- 2.9615
- 4.052
Therefore use 4 - 12Ø x 6m
For Top Bars @0.10 O.C For Hor't. Top Temp Bars @0.20 O.C
- 12 pcs Direct Counting
- 24 pcs total (2 flight of stairs) 17 pcs (1 flight of stairs)
Length 34 pcs total (2 flight of stairs)
2.88 Length
- 2.083333 1.06
- 11.52 7.075472
Therefore use 12 - 12Ø x 6m 4.805333
Therefore use 5 - 10Ø x 7.5m
For Top Reinf. Bars (Connecting to Plinth) For Riser/Tread Cut Bars @0.20 O.C
- 12 pcs total 6.4 pcs per step
Length 48 pcs for 8 steps (1 flight)
- 2.026 96 pcs total
- 2.9615 Length
- 4.052 0.93
Therefore use 4 - 12Ø x 6m 8.064516
11.904
Therefore use 12 - 10Ø x 7.5m
FORMWORKS
A. FOOTINGS
MARK ALONG ALONG Y H REINFORCEME DEPTH TYPE
X NT
mm mm mm SHORT LONG mm
F-1 800 800 300 8-12mmø 8-12mmø 1000 CENTER
F-1 @ 12 Sets= 0.80 x 0.80 x 0.30
Total Area= P x H x Number of sets
P= (a x 2) + (b x 2)
= (0.80 x 2) + (0.8 x 2) + (4 x 0.05)= 3.40m
F-1= 3.4 x 0.30 x 12 sets= 12.24 sqm ← TOTAL AREA
Number of Plywood Needed= 12.24/ (1.2 x 2.4)= 4.25 pcs 50%= 2.125 pcs or 3 pcs
B. COLUMNS
C-1: 0.25 x 0.25 @ 10 sets; C-2: 0.20 x 0.30 @ 2 Sets
hn=3.70; h=3.70m - 3.70/ 3= 2.47m
C-1
P= 2(a + b) + 0.2= 2(0.25 + 0.25) + 0.2= 1.2m
Area= 1.2 x 2.47 x 10 sets= 29.64 sqm
C-2
P= 2(a + b) + 0.2= 2(0.20 + 0.30) + 0.2= 1.2m
Area= 1.2 x 2.47 x 2 sets= 5.928 sqm
TOTAL AREA= 35.568 sqm
Number of Plywood Needed= 35.568/ 2.88= 12.35 pcs x 50%= 6.175 or 6 pcs
BEAM
L= 6 + 6 + 6 + 6 + 5.50 + 5.50 + 5.50= 34.50 sqm; d= 0.3m; b=0.20m; Area= P x L
P= 2(0.30) + 0.20 + 1= 0.90m L=1m
Area= 0.90 x 1= 0.90 sqm/m
Total Area= 34.50 x 0.90 = 31.05 or 31 sqm
Plywood Needed= 31/ 2.88 x 50% = 5.38 or 6 pcs
SLAB: SUSPENDED SLAB
A-1; W= 1.65 m; L= 2.50m
Area= 4.125 sqm
Plywood Needed= 4.125/ 2.88= 1.43 or 2 pcs
A-2; W= 2.60 m; L= 2.50m
Area= 6.50 sqm
Plywood Needed= 6.50/ 2.88= 2.25 or 3 pcs
A-3; W= 1.30 m; L= 2.50m
Area= 3.80 sqm
Plywood Needed= 3.80/ 2.88= 1.32 or 2 pcs
A-4; W= 1.30 m; L= 3.50m
Area= 4.55 sqm
Plywood Needed= 4.55/ 2.88= 1.58 or 2 pcs
A-5; W= 2.60 m; L= 3.50m
Area= 9.10 sqm
Plywood Needed= 9.10/ 2.88= 3.15 or 4 pcs
A-6; W= 1.65 m; L= 3.50m
Area= 5.775 sqm
Plywood Needed= 5.775/ 2.88= 1.99 or 2 pcs
SUMMARY
FOOTING- 3 pcs
COLUMN- 6 pcs
BEAM- 6 pcs
SUSPENDED SLAB- 15 pcs
TOTAL= 30 pcs of 4 ft x 8 ft x ½
SCAFFOLD
Bd. ft.= a x b x l x (pcs) / 12; Number of pcs= Bd. ft. x 12 / a x b x l
A. FOOTING
F-1 (0.80 x 0.80 x 0.30)
4 pcs @ 0.90m, 4 pcs @ 0.80, 12 pcs of 0.20
L-1= 0.90 x 3.28= 2.95 ft. Bd. ft.= 4(2 x 2 x 2.95) / 12= 3.93 bd. ft.
L-2= 0.80 x 3.28= 2.62 ft. Bd. ft.= 4(2 x 2 x 2.62) / 12= 3.50 bd. ft.
L-3= 0.2 x 3.28= 0.67 Bd. ft.= 4(2 x 2 x 0.67) / 12= 2.68 bd. ft.
TOTAL= 10.07 Bd Ft.
Area= 1.26 sqm
Bd Ft.= 10.07 bd. ft.
Constant (m)= 10.07 bd. ft./ 1.26 sqm= 7.99 bd.ft./ sqm
Total Area.= 15.3 sqm
Total Bd. ft.= 7.99 bd.Ft x 15.3 sqm= 122.247 bd. Ft. x 50%= 61.1235 bd.ft.
Number of pcs= 61.1235 x 12/ 2 x 2 x 8= 22.92 pcs or 23 pcs
B. COLUMN
2”x3”x10’
8pcs.-2”x3”x10’ (8pcs x 2” x 3” x 10ft.)/12= 40 bd.ft. TOTAL: 56.71 bd.ft.
6pcs.-2”x3”x0.49’ (6pcs x 2” x 3” x 0.49ft.)/12=1.47 bd.ft.
6pcs.-2”x3”x0.82’ (6pcs x 2” x 3” x 0.82ft.)/12= 2.46 bd.ft.
12pcs.-2”x3”x2.13’ (12pcs x 2” x 3” x 2.13ft.)/12= 12.78 bd.ft.
Total Bd. ft.= 56.71 x 12 x 50%= 340.26 bd.ft.
Number of pcs= 340.26 x 12/ 2” x 3” x 10’= 4083.12/ 60= 68.05 or 68 pcs
C. BEAM
12 Bd. ft./lm L=34.50m
Bd.ft= 12 x 34.50 x 50%= 207 Bd.ft
Number of pcs= 207 x 12/ 2 x 3 x 10= 2484/ 60= 41.4 or 45 pcs
45 pcs of 2” x 3” x 8’ FORM LUMBER
D. SLAB
2 x 3 x 12 FOR VERTICAL SUPPORT
2 x 3 x 8 FOR HORIZONTAL BRACE AND DIAGONAL BRACE
4pcs.-2 x 3 x 12’ FOR VERTICAL SUPPORT
12pcs.-2 x 2 x 8’ FOR HORIZONTAL BRACE
8pcs.-2 x 2 x 8’ FOR DIAGONAL BRACE
VERTICAL SUPPORT= 4 x 12 x 50%= 24 pcs
HORIZONTAL SUPPORT = 12 x 12 x 50%= 72 pcs
DIAGONAL SUPPORT= 8 x 12 x 50%= 48 pcs
L=34.50m 2” x 3” x 10’ VERTICAL SUPPORT 2” x 2” x 8’ HORIZONTAL SUPPORT
Vertical Support= 34.50/ 1= 34.50 or 35 pcs of 2” x 3” x 10’
Horizontal Support= (34.50 x 3)/ 2.4= 43.13 or 44 pcs of 2” x “ 2” x 8’
SUSPENDED SLAB:
W=1.65m L=2.50m
Area= 1.65m x 2.50m= 41.13 sqm
Bd.ft.= 41.13 x 6.1= 250.90 Bd. ft 2” x 3” x 10’
Number of pcs= 250.90 x 12/ 2 x 3 x 10= 50.18 or 51 pcs
EARTHWORKS
A. EXCAVATION
FOOTING
V= L x W x H
L= 0.80 + 0.25 + 0.25= 1.3m W= 0.80 + 0.25 + 0.25= 1.3m H= 1.00 + 0.10= 1.10m
V= 1.30 x 1.30 x 1.10 = 1.859 cu.m
Vtotal= 1.859 x 12 sets= 22.31 cu.m
WALL FOOTING
NOTE: Based on our Foundation Plan
Total Length L= 19.95 m
L=19.95 m W= 0.40m x 0.10 x 0.10= 0.60 H=0.70m
V= 19.95 m x 0.60 x 0.70= 8.379 cu.m
Vtotal= 22.31 cu.m + 8.379cu.m= 30.69 cu.m
B. GRADING AND COMPACTION
FOOTING
Area of F-1= 1.50 x 1.50 x 12 sets= 27 sqm
SLAB ON GRADE
Area SOG= 6.00m x 5.50m= 33 sqm
WALL FOOTING
Area WF-1= 19.95 X 0.60= 11.9 sqm
TOTAL AREA= 27 + 33 + 11.97= 71.97 sqm
C. GRAVEL BEDDING
F-1, V= 1.50 x 1.50 x 0.13 x 12 sets= 3.51 cu.m
Length of Wall Footing @ G. L “A”= 4.35 m
Length of Wall Footing @ G. L “B”= 4.75 m
Length of Wall Footing @ G. L “C”= 4.35 m
Length of Wall Footing @ G. L “1”= 5.20 m
Length of Wall Footing @ G. L “2”= 5.20 m
Length of Wall Footing @ G. L “3”= 5.20 m
Length of Wall Footing @ G. L “4”= 5.20 m
TOTAL LENGTH=34.25m
FOOTING
F-1, V= 1.50 x 1.50 x 0.13 x 12 sets= 3.51 cu.m
WALL FOOTING
WF-1, V= 34.25 x 0.60 x 5.50 x 0.13= 2.6715 cu.m
SLAB ON GRADE
SOG, V= 6.00 x 5.50 x 0.13= 4.29 cu.m
TOTAL VOLUME OF GRAVEL G-1
V= VF-1 + VWF-1+ VSOG= 3.51 + 2.6715+ 4.29= 10.47 cu.m
D. SOIL POSITIONING
Area= 6.00m x 5.50m= 33 sqm
E. BACKFILLING AND COMPACTION
NOTE: Based on our Floorplan; Toilet: 0.225 - (0.10 + 0.10)= 0.025m,Fill with the height of 25mm
All of the area except the carport= 0.25 - (0.10 + 0.10)= 0.05m, Fill with the height of 50mm
Vcut= 3.90 x 4.00 x 0.05= 0.78 cu.m
Vfill= 2.00 x 1.30 x 0.025= 0.065 cu.m
Excess Volume from excavated soil
Vexcess= 0.78 + 15.28= 16.06 cu.m
EXCAVATION: 53 cu.m
BACKFILLING AND COMPACTION 16.91 cu.m
Total Excavated Soil= 53 + 0.065 -16.06= 37.01 cu.m
EARTHWORKS: Summary
● EXCAVATION 53 cu.m
● BACKFILLING AND COMPACTION 16.91 cu.m
● GRADING AND COMPACTION 71.97 sqm
● GRAVEL BEDDING 10.47 cu.m
● SOIL POSITIONING 33 sqm
ROOFING WORKS
A. ROOF FRAMING
Vertical Length of Roof Truss= 8.20 x 3= 24.60 m
Quantity of Bars(pcs)= 24.60m/6.00m= 4.10 or 4 pcs
PURLINS LENGTH= 8.65 x 10 (pcs)= 86.5
Quantity of Bars(pcs)= 86.5/6.00m= 14.42 or 15 pcs
Length of Fascia Frame= (8.65 x 2 (sides)) + (8.20 x 2 (side))= 33.70m
Quantity of Bars(pcs)= 33.7/6.00m= 5.61 or 6 pcs
B. ROOFING MATERIALS
Wave Type Roof- Effective width 1-½ /2 lap= 950mm (approx.)
Horizontal Effective Width= 8.65m
Horizontal Roofing Sheet Quantity= 8.65/ 0.95= 9.11 or 10 pcs
Vertical Effective Width= 8.20m
Vertical Roofing Sheet Quantity= 8.20/ 0.95= 9.11 or 10 pcs
C. ROOFING ACCESSORIES
GUTTER
Horizontal Roofing Accessories quantity= 8.65 + 0.10 (end lapping) + 0.10 (end lapping)
= 8.85/ 2.30 (effective width)= 3.84 or 4 pcs
Vertical Roofing Accessories quantity= 8.20 + 0.10 (end lapping) + 0.10 (end lapping)
= 8.40/ 2.30 (effective width)= 3.65 or 4 pcs
BUBBLE INSULATIONS
Horizontal Bubble insulations quantity= 8.65 + 0.30 (side lapping) + 0.30 (side lapping)
= 9.25/ 0.70 (effective width)= 13.21 or 14 pcs
Vertical Bubble insulations quantity= 8.20 + 0.30 (side lapping) + 0.30 (side lapping)
= 8.80/ 0.70 (effective width)= 12.57 or 13 pcs
D. ROOFING CONSUMABLES
Purlins Total Length= 8.65 x 10 pcs= 86.5 m or 87m
Tekscrew Quantity= 87 x 4 pcs = 348 pcs
TILEWORKS
TILEWORKS: AREA METHOD
TILE AREA= 0.6 x 0.6 = 0.36 sqm
QUANTITY= 9.38 sqm / 0.36 sqm= 26.05 pcs
AREA= 2.571 x 3.649 = 9.38 sqm
TILEWORKS: PERIMETER METHOD
L= 2.571 m; W= 3.671 m
Q1= 2.571/ 0.6= 4.285 pcs ; Q2= 3.649 / 0.6= 6.08 pcs
QUANTITY= 4.285 x 6.08= 26.05 pcs
AREA METHOD
L= 2.556 m ; W= 3.671 m
AREA = 2.556 x 3.671= 9.38 sqm
tTILE AREA= 0.6 x 0.6 = 0.36 sqm
QUANTITY= 9.38 / 0.36= 26.05 pcs
PERIMETER METHOD:
Q1= 2.556 / 0.6= 4.26 m ; Q2= 3.671 / 0.6= 6.118333
[email protected]= 0.556 x 0.6 = 0.3336 m ; [email protected]= 0.671 / 0.6= 1.1183
THEREFORE: 4 x 6= 24 pcs
TOTAL= 24 +13= 37 pcs
TILES ADHESIVES: 60 x 60 GLOSSY FINISH
AREA= 9.38 + 4.49 + 1.36 + 5.36= 20.59 sqm
# of bags= 20.59 / 2.6= 7.919 say 8 bags
# of bags= 20.59 x 0.30 kgs= 6.177 kgs / 2 kgs
= 3.0885 or 3 bags
N DP (volume)= 20.59 x 0.05= 1.0295 cu.m
THEREFORE: Cement (bags)= 1.0295 cu.m x 9.00
= 9.26 or 10 bags
Sand (bags)= 1.029 cu.m or 0.75
= 0.772 or 1 cu.m
PAINTING WORKS
PAINTING WORKS
Exterior Walls= 145.812 sqm + 3.487 sqm= 149.299 sqm (acrytex)
Interior Walls= 96.49 sqm (latex)
Corner Walls= 3.487 sqm
EXTERIOR WALLS
Materials Needed Coverage Area Area Quantity
1.) Masonry Neutralizer B-44 20 sqm/ 4.25 liters 149.299 sqm 1.87 ltrs.
2.) Acrytex Primer B-1705
● First Coat 25 sqm/ 4 liters 149.299 sqm 23.89 ltrs.
● Second Coat 30 sqm/ 4 liters 149.299 sqm 19.91 ltrs
3.) Acrytex Cast B-1711 25 sqm/ 4 liters 149.299 sqm 23.89 ltrs.
4.) Acrytex Top Coat
● First Coat 25 sqm/ 4 liters 149.299 sqm 23.89 ltrs.
● Second Coat 30 sqm/ 4 liters 149.299 sqm 19.91 ltrs
5.) Thinning Solvent
(Acrytex Reducer B-1750)
● Acrytex Cast B-1711 1:4 5.97 ltrs
● Acrytex Primer B-1705 1:4 4.98 ltrs
● Acrytex Top Coat 1:4 4.98 ltrs
INTERIOR WALLS
Materials Needed Coverage Area Area Quantity
1.) Masonry Neutralizer B-44 20 sqm/ 4.25 liters 96.49 sqm 1.21 ltrs.
2.) Flat Latex B-701 (Primer)
● First Coat 25 sqm/ 4 liters 96.49 sqm 15.44 ltrs.
● Second Coat 30 sqm/ 4 liters 96.49 sqm 12.87 ltrs
3.) Masonry Putty B-7311 25 sqm/ 4 liters 96.49 sqm 15.44 ltrs.
4.) Flat Latex
● First Coat 25 sqm/ 4 liters 96.49 sqm 15.44 ltrs.
● Second Coat 30 sqm/ 4 liters 96.49 sqm 12.87 ltrs
NOTE: MASONRY NEUTRALIZER
1 PART OF B-44: 16 PART OF WATER
EXTERIOR WALLS
Materials Needed Packaging Area Quantity
1.) Masonry Neutralizer 1 gal or 3.785 ltrs 149.299 sqm 1.87 ltrs. 0.49 gal 1 gal
B-44
2.) Acrytex Primer B-1705 4 ltrs and 16 ltrs
● First Coat 149.299 sqm 23.89 ltrs. 2.74 pail 3 pail
1.34 gal 2 gal
● Second Coat 149.299 sqm 19.91 ltrs
3.) Acrytex Cast B-1711 4 ltrs and 16 ltrs 149.299 sqm 23.89 ltrs. 5.97 gal 6 gal
4.) Acrytex Top Coat 4 ltrs and 16 ltrs
● First Coat 149.299 sqm 23.89 ltrs. 2.74 pail 3 pail
● Second Coat 149.299 sqm 19.91 ltrs 1.34 gal 2 gal
5.) Thinning Solvent 4 ltrs and 16 ltrs
(Acrytex Reducer
B-1750)
● Acrytex Cast 5.97 ltrs 3.96 gal 4 gal
B-1711
● Acrytex Primer 4.98 ltrs
B-1705
● Acrytex Top Coat 4.98 ltrs
PLUMBING WORKS