FIDIC Risk Management in Construction
FIDIC Risk Management in Construction
net/publication/368473064
CITATIONS READS
25 517
3 authors, including:
All content following this page was uploaded by Ahmed Mohammed Abdelalim on 23 February 2024.
2
Professor of Construction Project Management, Faculty of Engineering at Alexandria, Alexandria University,
Alexandria, Egypt
3
Associate professor of construction Engineering and Project Management, faculty of engineering at Mataria, Helwan
University, Cairo, Egypt.
DOI: [Link]
Published Date: 13-February-2023
Abstract: Whereas the construction industry represents a significant proportion of national income in comparison
with other industries, and project management during the construction stage has a very important role through
which most of the project cost is spent out, therefore the project management team has to use the best techniques in
project management to get the best results. Risk Management which requires more time and effort in the
preliminary stage in order to avoid or mitigate risks that may occur during construction, all project stakeholders
are taking responsibility for risks during the construction stage, so it is important to take care of risk management
and allocation between client and contractor according to contractual terms and conditions to achieve the project.
There are many types of contracts that govern the relationship between the contractual parties either locally or
internationally, study proposed FIDIC contracts to govern the relationship during construction. Study proposed risk
management process to Plan Risk Management, Identify Risks, Risk Allocation, Perform Qualitative Risk Analysis,
Perform Quantitative Risk Analysis, Implement Risk Responses, and Monitor. Instead of Plan Risk Management,
Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Implement Risk Responses,
Monitor Risks, as mentioned in PMBOK 6th edition. risk management flow chart for governance during the
construction, and automate project risk management reports and interactive dashboard that demonstrate project
progresses.
Keywords: construction industry, project management team, Risk Management.
1. INTRODUCTION
the urgent need for developing countries to plan, which leads to long-term and short-term goals to meet the increasing
demand for various services and provide a quality of life for citizens, so all organization involved are necessary developed.
Whether it is a government, private or public-private partnership or investment, which includes the development of policies,
methodologies, tools and technologies to achieve the growing demand for the provision of these services, which requires
continuous improvement at all levels, Organizational management, Portfolio management, Program management, and
Project management, to achieve goals and benefits. Increasing demand for the provision of these services, we see a
significant development in the size of Organizational working on project construction from small to medium and large, each
of which operates individually or jointly in the labor market, according to the size of the projects, whether they are small,
medium or large, which are sometimes described as gigantic. In view of the growing increase in the size of projects, which
leads to an increase in the budgets required to achieve these goals, the need for project management arose.
Page | 76
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
In addition, the FIDIC contract was selected to know the obligations and requirements of risk management for each of the
contract parties. The risk management was compared with three of the contracts, namely the construction contract (the red
book), the design and construction of stations contract (yellow book), and the engineering, procurement and construction
contract / turnkey (silver book). In order to find out the commitment of each of the contracting parties in project risk
management and its consequences. And since the construction stage is one of the most important stages where most of the
work is carried out and most of the project budget is spent, the study focused on managing risks during construction, as well
as automating follow-up reports during the work period in order to manage risks efficiently and effectively so that the
project management can take the necessary measures to respond to risks in propar time.
2. RISK MANAGEMENT
Risk management means defining the possibility of risk occurrence, the extent and degree of impact of this risk on the
project in the various stages of project work, and how to prioritize them given that they are in the world of uncertainty - in
the sense of expecting occurrence - and choosing the methods, methodologies and tools that can be used to manage risks in
their interrelated processes in terms of the methodology and policy of the organization to bear Or avoiding the risks and
permissible limits in the various work of the organization since the beginning of the first stage of developing the action plan
for risk management, through the definition of risks, then analyzing the risks, then assessing the risks, planning the response,
applying the response plan when the risk occurs, and monitoring and controlling the processes of risk management, in order
to avoid the problems arising such as the project outside Budget/forecast/estimate/bid, deadline for design, build and
occupancy approvals, or failure to meet required technical standards for quality, function, fitness for purpose, safety and
environmental conservation. Many project management organizations have been interested in developing systems and
standards for risk management, including ISO 31000 issued by the International Standards and Metrology Organization and
Australian and New Zealand [Link]/NZS 4360 Risk Management and Project Risk Analysis and Management Guide
issued by the Project Management Organization of England, Best Practices issued by PMI Project Management Body of
Knowledge 6th edition. In this research, we will discuss a brief definition and comparison of five international risk
management specifications.
Page | 77
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Page | 78
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
It is clear from Figure No. (01) that the Australian and New Zealand standards AS/NZS 4360 for risk management and ISO
31000 for the year 2021 and through their operations in risk management they are concerned with the risk management of
the organization and neither of them mentioned what is related to project risk management, and that risk management for
the project in all its stages has been mentioned in the Egyptian code for managing construction projects Code No. 311-
2009, and the guide issued by the Project Management Organization in England issued by (APM association for project
management). It also came in the Project Management Knowledge Guide of the American Project Management Institute,
and chapter eleven was devoted to it.
Since we are in the process of studying the risks during construction of the project, we will address them through the
methodology of the Project Management Knowledge Guide of the PMI#20, because it contains details of project risk
management, and it will be the methodology used until the completion of this study.
Figure No. (03) Example Possibility and Impact matrix with scoring scheme
And the models used in managing the various risks, such as a risk register, periodic reports, the risk response plan, the
alternative plan, follow-up on the reserve, and how to follow up and audit risk management processes.
5.4 Defining project risks
This process is concerned with defining the risks that the project will be exposed to and the details available for each risk
separately. This process results in a project risk register, which includes the definition of the risk, its classification, the
probability of its occurrence, the degree of its impact on any project objectives, what is the strategy used to deal with it and
, and it varies according to the size of the project. The project and its nature, and it also results in a project risk report, which
shows the degree of risk for the project and the data on the sources of the total risks to be dealt with.
5.5 Qualitative assessment of project risks
This process includes the analysis of all the data reached on the risk, especially the probability of occurrence, the timing of
occurrence and the degree of impact. This is done through the risk management team and the participation of stakeholders
through meetings, data collection, data classification and personal interviews. Risks, which are of course reflected in the
quality of risk management in the project, and this data includes, for example, evaluating the quality of risk data in terms
of accuracy and reliability, evaluating the likelihood and impact of risks, strategic impact, evaluating the possibility of
controlling the risk, the possibility of managing it easily, and the time of its occurrence in the [Link] evaluation requires
the skills of a team that has knowledge of this process, or the use of experts if they are unable to do so. In the first place,
the team of workers or experts should have the first priority in front of them is the interest of the project without prejudice
to personal opinions, and this stage results in updating the risk register and updating the hypothesis record. And update
project problem log and risk report.
Page | 81
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Figure No. (04) Example S-Curve from quantitative cost risk analysis
Sensitivity analysis is also used, through which the risks to which the project is exposed are arranged in terms of the greatest
impact on the project objectives and results in a cyclonic chart as shown in Figure No. (05)
Page | 82
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Strategy total
Description of the strategy opportunities
name threats risk
and/or use one of the modern technologies that
reduce the duration and time of the project.
7 Share includes sharing the opportunity with a third
party who shares the benefit accrued from the
opportunity. Examples of the methods used are
yes yes
the establishment of a partnership from a
specialized company, or the appointment of a
subcontractor.
8 Enhance used to try to increase the probability of
occurrence and/or the impact resulting from the
opportunity. The opportunity can be improved
yes yes
by focusing on its causes. One of the methods
used is to increase resources to finish the project
earlier than the original end.
5.8 Decision making
One of the most important benefits that we gain from effective risk management is taking precautionary measures and
formulating the decisions required to be taken before the risk occurs, and thus to formulate good and effective decisions. In
a way that leads to choosing the appropriate and effective decision, and the decisions taken to choose the different response
methods result in several outputs, the most important of which are the required changes to the project management plan,
and the required change in the project documents.
5.9 Project risk response plan implementation
This process is concerned with managing the response that has been chosen and according to what has been planned, to the
expected total or partial risk in order to increase the expected benefit from the opportunities as well as reduce or avoid the
negative effects expected from the threats. In order to ensure the success of the risk response application process, the project
work team, the project manager, and the person responsible for implementing the risk response plan must communicate and
communicate in a dynamic and effective manner, to verify the construction of the response plan as planned.
5.10 Monitoring and controlling project risk management processes
One of the most important processes at all is the process of monitoring and controlling the risk management processes in
the project. During this process, new risks are constantly monitored, re-evaluated, response plans are drawn up, the
construction of response plans is followed up and their effectiveness, and the risks with low probability and impact are
monitored, and are they on the watch list? The same inputs during the planning period, whether the probability of occurrence
and the amount of impact change by increase, then it is planned, or decreased or ended, and it is removed from the watch
list, and during this process the project reserve and the senior management reserve related to the project are followed up, as
well as the allocated resources from the work team, subcontractors and insurance companies, are followed up. And
continuous updating of the risk register. This process results in reports of project risk performance and its impact on project
performance reports, and what this requires in terms of change orders and updating of the project construction management
plan and subsequent updates of project documents, as well as updating the procedures and models of the organization and
the risk segmentation structure.
Page | 84
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
stages. We specifically mention construction in the different contract formulas in the three books (Red, Yellow, and Silver)
according to the nature of the work and the responsibilities that both parties to the contract undertake. I singled out a chapter
for it on the general conditions. (Chapter XVII) entitled Risks and Liability, and it includes six paragraphs, which are
compensation contractor's care of the works And Employer risks and employer risk consequences Intellectual and industrial
property rights and limitation of liability
6.7 Selected FIDIC contracts comparison in terms of allocate risk
By the FIDIC contract, how are these risks distributed between each of employer or Contractor separately during
construction , and what are the risks that employer and contractor share during construction , and according to the type of
contract used to complete the works, the tasks and responsibilities vary, and through researching the references that dealt
with this aspect, it was mentioned in the International Construction Law # 29, which classified the risks and the
consequences of their occurrence, whether it was time, direct costs, indirect costs, or profits during the expected chapters
of the contract. The share of each employer and contractor was distributed according to the red, silver and yellow FIDIC
contracts according to Table No. (03).
Table No. (03) shows a comparison of the risk tolerance of employer and contractor in the FIDIC contract formats
Page | 87
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Thus, this table can be used as a guide in distributing risks between both employer and contractor, and these results in
reducing the periods used to resolve disputes arising from the disagreement in estimating the risk outcomes. The researcher
also suggests adding a process of risk distribution within the risk management processes to effectively complete the process
of risk management governance between the two contracting parties.
Page | 88
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Page | 89
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Page | 90
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
Figure No. (07) Roles and responsibility flow chart Figure No. (08) Programs used
Figure No. (09) Dashboard distribution Flow chart Figure No. (10) dashboard sample
9. CONCLUSION
Through the previous study and comparisons of the attempt to manage risks in construction according to international
standards and best practices, the researcher concluded that for the work to be completed during the project construction
phase with the required quality, the allocated cost, and within the specified period, risk management must be activated and
the requirements of risk management should be integrated into the project contract and the risks of each owner should be
identified. Work and contractor and make the necessary plans to manage them and define the processes of identifying and
evaluating risks during the bidding phase of the project so that there is a future vision for construction before entering it,
and then when starting construction , the expected risks during the phase have been defined in advance and the required
reserve has been put in place to manage them in the event of their occurrence. The researcher recommends a proposal to
add a process to the risk management processes, which is the distribution of risks between each of employer and contractor
and the arrangement of risk management processes to be planning for risk management, risk definition, risk distribution,
qualitative risk analysis, quantitative risk analysis, risk response plan development, and risk application. Responding to
risks and following up on risks, instead of the arrangement included in the Project Management Knowledge Guide chosen
Page | 91
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
for the study, which is planning for risk management, defining risks, conducting a qualitative risk analysis, conducting a
quantitative risk analysis, developing a risk response plan, applying risk response, and following up on risks, and thus it is
practical Distributing risks between both employer and contractor is a proactive step to reduce change orders that occur in
the project as a result of things or events that were not expected by both parties, and thus time, cost and quality are managed
more efficiently than if the risk management had not been pre-distributed, and thus claims are reduced. Financial and
temporal The operations chart presented by the researcher is one of the most important tools for the governance of risk
management operations, which, once activated, shows the tasks and responsibilities of both employer and contractor, and
thus the operations are managed efficiently and effectively. The automation of risk management follow-up reports and
display of results is the final data dashboard (Dashboard) for departments at different levels in different geographical ranges
using Microsoft BI and other programs used which gives real-time data to decision-makers early and contributes to rational
decision-making dealing with project risks.
REFERENCES
Books
[1] Michael M. Bissonette, Project Risk Management A Practical Construction Approach, 2016
[2] Ori Schibi, Managing Stakeholder Expectations for Project Success Chapter:8 Managing Risk Effectively: What's
Missing from Current Risk Management Methodologies, 2014
[3] Tom Kendrick, Identifying and Managing Project Risk: Essential Tools for Failure-Proofing Your Project, 2015
[4] Ted Klastorin and Gary Mitchell, Project Management: A Risk-Management Approach, 2020
[5] Roland Wanner, Project Risk Management: The Most Important Methods and Tools for Successful Projects, 2015
[6] Dale Cooper, Pauline Bosnich, Project Risk Management Guidelines: Managing Risk with ISO 31000 and IEC 62198,
2nd Edition, 2014
[7] First Edition, Lukas Klee, International Construction contract Law, 2018
Standers
[8] Project Management Institute, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019
[9] Project Management Institute, Practice Standard for Project Risk Management, 2009
[10] Project Management Institute, A Guide to The Project Management Body of Knowledge (PMBOK® Guide) Sixth
Edition, 2017
[11] American Society of Civil Engineers, Quality in The Construction Project A Guide for Owners, Designers, and
Constructors Third Edition, 2012
[12] International Organization for Standardization (ISO), ISO 31000 - Risk management - Principles and Guidelines, 2021
[13] Office of Statewide Project Management Improvement (OSPMI) Project Risk Management Handbook Second
Edition, Rev. 0, 2007
[14] Egyptian Project Management Committee, Construction Project Management, Egyptian Code, 2009
FIDIC Books
[15] Fidic, FIDIC - Red Book, Conditions of Contract For Construction, For Building and Engineering works Designed
By Employer 2nd edition, 2017
[16] Fidic, FIDIC - Yellow Book Conditions of Contract, For Plant and Design - Build 2nd edition, 2017
[17] Fidic, FIDIC- Silver Book, Conditions of EPC and Turnkey Projects 2nd edition,2017
[18] Fidic, FIDIC-Risk Management Manual 1 st edition, 1997
Papers
[19] Heedae PARK, Kang-Wook LEE, H. David JEONG, and Seung Heon, Effect of Institutional Risks on the
Performance of International Construction Projects, 2014
Page | 92
Research Publish Journals
International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online)
Vol. 10, Issue 2, pp: (76-93), Month: October 2022 - March 2023, Available at: [Link]
[20] Iwona Rybka, Elżbieta Bondar, Department of Environmental Engineering and Geodesy, Wroclaw University of
Environmental and Life Sciences, Planning of the Risk Handling Methods Related to Alterations to Project,
Documentation, 2013
[21] M. MOAZZAMI, R. DEHGHAN and JY RUWANPURA, Department of Civil Engineering, the University of
Calgary, Canada, Contractual Risks in Fast Track Projects, 2011
[22] Ewelina Gajewska, Michaela Ropel, Risk Management Practices in a Construction Project - a case study, 2011
[23] Li Bing, A. Akintoye, PJ Edwards, C. Hardcastle, The allocation of risk in PPP/PFI construction projects in the UK,
2005
[24] Guo Zhanglin, Hu yazhen, Liu Jun'e, The analysis of contractor's risk clause based on the FIDIC construction contract,
2014
[25] Hemanta Doloi, Understanding impacts of time and cost related construction risks on operational performance of PPP
projects, 2012
[26] AACE International Recommended Practice 67R-11, Contract Risk Allocation - As Applied in Engineering,
Procurement, and Construction, 2014
[27] George E. Baram, Project Execution Risks in EPC/Turnkeys Contracts and the Project Manager's Roles and
Responsibilities, 2005
[28] Rashad Zein and Luc Heymans, Quantifying Risks Related to the Execution of Mega Projects, 2012
[29] Hua Zhao1, Yi-lin YIN 2, A Dynamic Mechanism of Risk Allocation of Construction Project from Perspective of
Incomplete Contract Theory: A Theoretical Model, 2011
[30] Ali F. Bakr, Khaled El Hagla, Ayda Nayer Abo Rawash, Heuristic approach for risk assessment modeling: EPCCM
application (Engineer Procure Construct Contract Management), 2012
Other Books
[31] Gamal El-Din Nassar, Claims, Disputes And Arbitration
[32] Gamal El-Din Nassar, Conditions of contract for Construction
Web sites
[33] @RISK manual version 7.5, Palisade Corporation [Link] 2022
[34] Deltek, Inc [Link] 2022
[35] Barbecana, Inc. [Link] 2022
[36] Oracle,Inc [Link] 2022
[37] RiskyProject Professional User Guide, Intaver Institute [Link] 2022
[38] RiskyProject Professional Lite Guide, Intaver Institute [Link] 2022
[39] RiskyProject Professional Enterprise Guide, Intaver Institute [Link] 2022
[40] Safran Risk manual, Safran Software Solutions [Link] 2022
[41] Vose Software web site [Link] 2022
[42] [Link] 2022
[43] [Link] 2022
[44] [Link] 2022
[45] [Link] 2022
[46] [Link] 2022
[47] [Link] 2022
Page | 93
Research Publish Journals
The fixed price feature of the FIDIC Silver Book influences risk distribution by transferring more financial risk to the contractor. Since the price is predetermined, the contractor assumes greater responsibility for managing unforeseen costs that could arise during construction, potentially leading to a more cautious approach in managing resources and schedules .
The AS/NZS 4360 standards focus on organizational risk management rather than project-specific risks, as noted in the source document. In contrast, the Egyptian code for managing construction projects explicitly addresses risk management across all stages of a project, making it more relevant for construction industry applications where detailed project risk management is crucial .
The FIDIC Yellow Book's approach of sharing risks between employers and contractors can be effective as it encourages collaboration and mutual accountability. This shared risk structure aims to balance responsibilities and incentivizes both parties to work together to mitigate risks, potentially enhancing efficiency in project execution. However, effectiveness largely depends on clear communication and cooperation among the parties involved .
Key elements of a risk management plan during construction include risk identification, risk analysis, and risk response planning. These elements are crucial because they provide a structured approach to anticipate, mitigate, and control risks, ensuring the project stays on track and within budget, thus reducing the likelihood of unforeseen complications that could derail project success .
The Project Management Institute's Project Management Knowledge Guide adopts a detailed methodology for managing risks during the construction stages. It involves a step-by-step process: defining risks, conducting risk analysis and assessment, planning responses, implementing the response plan, and continuously monitoring and controlling risk processes. This comprehensive methodology ensures that all potential risks are addressed systematically throughout the construction phase .
Neglecting proper risk management procedures during construction projects can lead to significant negative outcomes, including delays in project timelines, budget overruns, compromised quality, and increased likelihood of conflicts among stakeholders. This oversight may also result in missed opportunities for early risk mitigation, affecting overall project success and stakeholder satisfaction .
Continuous improvement is emphasized in risk management methodologies to ensure they remain dynamic, responsive to changes, and comprehensive. This approach facilitates predictable outcomes and addresses evolving project demands, thereby enhancing the likelihood of project success in terms of timely completion, budget adherence, and quality assurance .
The primary objective of risk management during the construction phase is to efficiently and effectively respond to risks to ensure the project is completed within its allocated time and budget, and meets quality standards. This involves continuous management of all project inputs to achieve maximum efficiency during construction .
The Egyptian code for managing construction projects ensures risk management inclusion at all project stages by providing a framework that addresses risk considerations from design through to handover. By detailing specific methodologies and procedures, the code integrates risk management into the project's lifecycle, thereby enhancing preparedness and responsiveness to potential risks .
FIDIC contract forms address construction risks by clearly defining and allocating responsibilities and duties among project participants through structured contract terms. These contracts allocate risks between employers and contractors by specifying which party is responsible for managing certain risks, thus minimizing ambiguity and potential disputes during the project lifecycle .