Differential Settlement of Cement FlyAsh Gravel and Cement Soil Compacted Piles
Differential Settlement of Cement FlyAsh Gravel and Cement Soil Compacted Piles
https://doi.org/10.1007/s40098-024-01010-8
TECHNICAL NOTE
13
Vol.:(0123456789)
Indian Geotech J
13
Indian Geotech J
Cement-soil
CFG pile
Soil between the maximum, that is, the puncture of the top of the CFG
pile is 6 mm, and the settlement difference between the
compacted pile piles
0 40
X(m)
seventh CFG pile (observation point 27) and soil between
piles (observation point 29) is 1.5mm. Seven CFG piles
(observation point 3, point 7, point 11, point 15, point 19,
point 23, and point 27) were on different planes along the
4
Y(m)
Soil between piles Cement-soil compacted CFG pile observation
pile length, and the vertical settlement was between 8 and
observation point pile observation point point 4 mm. The maximum settlement of ± 0.000 m surface at the
center line of the embankment is 14 mm, and the settle-
Fig. 4 Top view of piles and soil between piles about the composite ment decreases from 14 to 4.2 mm along the pile body to
foundation
− 15.960 m surface.
13
Indian Geotech J
Table 1 The calculation parameters of CFG pile + cement–soil compacted pile composite foundation model
Name Density (kg/ Elastic Poisson’s Internal fric- Dilatancy Cohesion Lateral Thickness Constitutive
m3) Modulus ratio tion angle angle (°) (kPa) pressure (m) model
(kPa) (°) coefficient
-13.680m plane
0.010 -17.100m plane
0.008
0.006
0.004
0.002
0.000
0 3 6 9 12 15 18 21 24 27 30 33 36 39
Observation point
was carried out separately. According to TB10106 [19] The vertical static load test of the CFG pile and
and TB10751 [20], the requirement of the single pile load cement–soil compacted pile is conducted by using the
test about composite foundation reveals that the vertical slow maintenance load method. For the CFG piles test,
ultimate bearing capacity of a single pile is calculated the designed total test load is 1250 kN; 125 kN is loaded
according to the load value corresponding to the total set- for each time, and after each loading, the cumulative load
tlement of the pile top s = 40 mm. The designed maximum is maintained for two hours, until the maximum load
load of the CFG pile is 1250 kN, and the designed maxi- is reached; finally, the unloading starts step by step, and
mum load of the cement–soil compacted pile is 660 kN. 250 kN is unloaded each time and, after each loading,
13
Indian Geotech J
Settlement (m)
-12.540m plane)
14.820m plane
-15.960m plane
0.008
0.006
0.004
0.002
0 3 6 9 12 15 18 21 24 27 30
Observation point
maintained for one hour, until the unloading is completed. Table 2 Load test of CFG pile (pile number: f6-46)
For the cement–soil compacted pile test, the designed total Number Load (kN) Duration (min) Settlement (mm)
test load is 660 kN; 82 kN is loaded each time, and after each
loading, the cumulative load is maintained for two hours, Level Accumulative Level Accumulative
until the maximum load is reached; finally, the unloading 0 0 0 0 0.00 0.00
starts step by step, and 165 kN is unloaded each time and, 1 125 120 120 0.88 0.88
after each loading, maintained for 1 h, until the unloading 2 250 120 240 1.15 2.03
is completed. 3 375 120 360 1.36 3.39
4 500 120 480 2.07 5.46
Load Test of CFG Pile 5 625 120 600 1.42 6.88
6 750 120 720 2.18 9.06
To make it more simplified, only the loading and unloading 7 875 120 840 2.31 11.37
process of pile f6-46 is given, as shown in Table 2. The field 8 1000 120 960 2.44 13.81
vertical static load test result of CFG piles (numbers: f6-46 9 1125 120 1080 2.79 16.60
pile, g6-46 pile, i6-46 pile, and j6-46 pile) is obtained and 10 1250 120 1200 2.98 19.58
summarized, as shown in Table 3. 11 1000 60 1260 − 0.09 19.49
It can be known from Tables 2 and 3 that when the 12 750 60 1320 − 0.42 19.07
maximum load is 1250 kN, the average maximum settle- 13 500 60 1380 − 0.52 18.55
ment of piles is 19.60 mm, the average residual settlement 14 250 60 1440 − 0.80 17.75
is 16.46 mm after unloading, the average rebound amount 15 0 180 1620 − 1.28 16.47
is 3.15 mm, and the average rebound rate is 16.08%; the set-
Maximum load: 1250 kPa; Maximum settlement: 19.58 mm
tlement of the CFG pile is less than 150 mm, which meets
Maximum rebound: 3.11 mm; Rebound rate:
the requirements for post-construction settlement according
3.11/19.58 × 100% = 15.9%
to TB10035 [21].
Load Test of Cement–Soil Compacted Pile load test results of the 16 cement–soil compacted piles are
obtained and summarized, as shown in Table 5.
Sixteen cement–soil compacted piles at different locations of It can be seen from Table 5 that when the maximum load is
CFG pile + cement–soil compacted pile composite founda- 660.0 kPa, the average maximum settlement is 20.65 mm, the
tion are selected for vertical static load test. To make it more average residual settlement is 17.76 mm after unloading, the
simplified, only the loading and unloading process of piles average rebound amount is 2.89 mm, and the average rebound
a-5 is given, as shown in Table 4. The field vertical static rate is 13.99%; the settlement amount is less than 150 mm,
13
Indian Geotech J
Table 4 Load test of cement–soil compacted pile (pile number: a-5) experimental results, verifying the rationality of the finite
Number Load (kPa) Duration (min) Settlement (mm)
element simulation method.
13
Indian Geotech J
Number Pile number (#) Design value The allowable Maximum Cumulative Residual set- Rebound Rebound rate
of composite bearing capac- load value settlement tlement after amount (mm)
foundation ity of compos- (kPa) (mm) unloading
bearing capac- ite foundation (mm)
ity (kPa) (kPa)
13
Indian Geotech J
17. Cheng XS, Chen JC, Cai XD et al (2021) Dynamic response of CFG 21. TB10035 (2018) Code for design on special railway earth structure.
and cement–soil pile composite foundation in the operation stage. National Railway Administration of the People’s Republic of China,
Geomech Eng 26(4):385–399 Beijing
18. Cheng XS, Liu GN, Gong LJ et al (2020) Mechanical characteris-
tics+ differential settlement of CFG pile and cement–soil compacted Publisher’s Note Springer Nature remains neutral with regard to
pile about composite foundation under train load. Geomech Eng jurisdictional claims in published maps and institutional affiliations.
20(2):155–164
19. TB10106 (2010) Technical code for ground treatment of railway
engineering. Ministry of Railways of the People’s Republic of
China, Beijing
20. TB10751 (2018) Standard for constructional quality acceptance of
high-speed railway subgrade engineering. National Railway Admin-
istration of the People’s Republic of China, Beijing
13